Security Baseline Inspection Report 05000443/2025401
ML25167A195
Person / Time
Site: Seabrook 
Issue date: 06/16/2025
From: Brice Bickett
Division of Operating Reactors
To: Coffey B
NextEra Energy
References
IR 2025401
Download: ML25167A195 (1)


Text

June 16, 2025

SUBJECT:

SEABROOK STATION - SECURITY BASELINE INSPECTION REPORT 05000443/2025401

Dear Bob Coffey:

On June 5, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Seabrook Station and discussed the results of this inspection with David Sluszka, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Brice A. Bickett, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety & Security

Docket No. 05000443 License No. NPF-86

Enclosure:

As stated

Inspection Report

Docket Number:

05000443

License Number:

NPF-86

Report Number:

05000443/2025401

Enterprise Identifier: I-2025-401-0020

Licensee:

NextEra Energy Inc.

Facility:

Seabrook Station

Location:

Seabrook, NH

Inspection Dates:

June 02, 2025 to June 05, 2025

Inspectors:

K. Hussar, Senior Physical Security Inspector

C. Davis, Physical Security Inspector

J. Edwards, Physical Security Inspector

S. McCarver, Physical Security Inspector

Approved By:

Brice A. Bickett, Chief

Security, Emergency Preparedness and Incident Response Branch

Division of Radiological Safety & Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Seabrook Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.02 - Access Control

The inspectors evaluated the access control program through completion of the following

===inspection elements:

Access Control===

(1)

  • Tier I: All Requirements
  • Tier II: 11 Requirements (02.06 a - d, 02.07 a, 02.08 a, b, d - g)
  • Tier III: 1 Requirement (02.09)

71130.05 - Protective Strategy Evaluation

The inspectors evaluated the licensee's protective strategy through completion of the following procedure elements:

Protective Strategy Evaluation (2 Samples)

(1)

  • Tier I: All Requirements
  • Tier II: All Requirements
  • Tier III: All Requirements (2)
  • The inspectors evaluated the Security Performance Evaluation Program.

71130.09 - Security Plan Changes

The inspectors evaluated the security plan changes through completion of the following procedure elements:

Security Plan Changes (1 Partial)

(1)

(Partial)

The opportunity to apply this procedure was not available in accordance with IMC 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specifically, the licensee has not initiated a physical security plan change in accordance with 10 CFR 50.54(p)(2) since the last performance of this IP.

71130.14 - Review of Power Reactor Target Sets

The inspectors evaluated the Security Target Set Program. The following elements were

===evaluated:

Review of Power Reactor Target Sets===

(1) Requirements (9): 03.01 a.; 03.02 a - e; 03.04 a, b; 03.05 a

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)

=

(1) October 01, 2024, through March 31,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On June 5, 2025, the inspectors presented the security baseline inspection results to David Sluszka, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71130.02

Corrective Action

Documents

2502636

2504363

2514553

2503133

2505142

2506606

2506674

2506675

Procedures

GN1315.01

Issue/Control and Inventory of Keys and Cores

Revision 5

GN1337.01

Operation and Testing of Contraband Detection Equipment

Revision 28

SY-AA-102-1021

Conduct of Personnel Searches

Revision 18

SY-AA-102-1022

Vehicle and Material Searches

Revision 16

71130.05

Calculations

FPL SB030-

CALC-001

Summary Evaluation of DBT Threats - VBS

Revision 0

Corrective Action

Documents

Resulting from

Inspection

2516879

Procedures

GN 1316.01

Tactical Response Basis

Revision 23

GN 1316.03

Tactical Response

Revision 15

GN1322.04

Post / Patrol Routine Duties

Revision 31

71130.14

Corrective Action

Documents

Resulting from

Inspection

2516684

Miscellaneous

Seabrook Target Sets (SGI)

Revision 03

Procedures

SY-AA-102-1036

Target Set Development, Identification, and Maintenance

Revision 9

71151

Corrective Action

Documents

2508310

2510945

2512015

Procedures

LI-AA-100-10003

NRC Performance Indicator

Revision 6