IR 05000416/1978011

From kanterella
Jump to navigation Jump to search
IE Inspec Rept 50-416/78-11 on 780811 During Which 1 Item of Noncompliance Was Noted:Failure to Control Curing Temp on Concrete Test Cylinders
ML19248C484
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 08/10/1978
From: Harris J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19248C477 List:
References
50-417-78-11, NUDOCS 7809270282
Download: ML19248C484 (8)


Text

.

UNITED sT ATEs

>* * E Gg NUCLEAR REGULATORY COMMIS510N f

o, R E GION 11

  • y, ( [,g O,

101 M AntET T A sT RE ET, N.W.

,

?-*-

<

c ATL ANT A GEORGI A 30303

[

o

%,,... f Report No.: 50-416/78-11, 50-417/78-11 Docket No.:

50-416 and 50-417 License No.:

CPPR-118 and CPPR-119 Category:

A2, A2 Licensee: Mississippi Power and Light Company P. O. Box 1640 l

Jackson, Mississippi 39205 l'

Facility Name:

Grand Gulf Nuclear Station, Units 1 and 2 Inspection at: Grand Gulf, Mississippi Inspection Conducted: June 28-30, 1978 i

Inspectors:

J. R. Harris h/J[f Reviewed by:

g g Date

'. C. Bryant, L ief

.ngineering upport Section No. 1 Reactor Construction and Engineering Support Branch

-

Inspection Summary Inspection on June 28-30, 1978 (Report No. 50-416/78-11 and 50-417/78-11)

Areas Inspected: Previously identified item; structural concrete {Dait 2);

anchor bolt installations (Unit 1). The inspection involved 21 inspector-hours on site by one NRC inspector.

Results: Of the three areas inspected, no apparent items of noncompliance or deviations were identified in two areas; one apparent item of noncompliance (infraction -

failure to control curing temperature on concrete test cylinders paragraph 4) was identified in one area.

(

1 0 3 2

,..,7 J809DOML

(

RII Rpt. Nos. 50-416/78-11 and 50-417/78-11 I-1

/

f /p[ff DETAILS I Prepared by:_

w John R.'Har rs, Civil ngineer/_

Date

_

[ Engineering S'ipport Section No.

Geologist

Reactor Construction and Engineering Support Branch Dates of Inspection:

June 28-30, 1978 Reviewed by:

g(M-g [p f

,

.J. E Bryan Chief Date Engineering Support Section No. 1 Reactor Construction and Engineering Support Branch 1.

Persons Contacted Mississippi Power and Light. Company (MP&L)

a.

  • T. E. Reaves, Manager of Quality Assurance (QA)

P. W. Sly, QA Field Supervisor

  • J.

C. Fuller, Piping QA Representative

  • W. M. Garner, Civil QA Representative b.

Contractor Organizations Bechtel Power Corporation (Bechtel)

  • R. L. Scott, Project QA Manager
  • D. W. Strohman, QA Engineer
  • J.

H. McCarthy, Project Field Quality Control Engineer J. R. Jordon, Batch Plant and Concrete Testing Laboratory Inspector E. W. Jessemer, Lead Civil QC Engineer B. Poppell, Field Engineer, Civil M. Robinson, Assistant Project Field QC Engineer A. Lentencourt, QA Engineer J. Temen, Electrical QC Engineer h. Hindershot, General Foreman (Electrical)

  • Attended exit interview.

"!.

Licensee Actions on Previous Inspect ion Findings (Closed) Unresolved Item (417/78-08-01):

Unusual variation in slump (

and air test data for concrete pour number Q2 T-21-W-21093.

1032 lj

(

~

IfN R11 Rpt. Nos. 50-416/78-11 and 50-417/78-11 I-2 dlL s-F.xamination of licensee records and discussions with responsible engineers and testing personnel indicated testing and work related equipment has been reinspected and recalibrated, testing personnel were knowledgeable and certified in areas of responsibility and that work activities are continuously inspected by QC personnel and periodically observed by QA personnel.

The inspector has no further questions regarding this item.

3.

Unresolved Items Unresolved items are matters about which more information is required in order to ascertain whether they are acceptable items, items of

noncompliance, or deviations.

Two unresolved items diclosed during l

the inspection are discussed in paragraph 5.

4.

Independent Inspection The inspector examined the following areas:

General inspectice of the site and engning vork activities, a.

b.

Installation of cinch anchors, and controls for cutting of reinforcing steel in the Unit 1 Auxiliary building, Work activities at the soils and concret laboratory.

c.

Observation of work activities at the concrete laboratory disclosed the following noncompliance:

Specification number 964-C-191.0 and referenced ASTM Standard C 31-69 require that concrete test cylinders made in the field be stored under conditions that maintain the temperature in the range of 60 to 80 degrees Fahrenheit.

Contrary to the above requirement, during the inspectica test cylinder sets 2650 A-D, 2651 A-D, 2652 A-D, 2653 A-D and 2654 were on the floor of the concrete lab exposed to full sun and an ambient temperature of 99 degrees Fahrenheit. The situation occurred as a result of the roof and sides at the laboratory recently having been removed to repair damage caused by a tornado on April 17, 1978.

When the inspector pointed out the nonconforming curing condition, the licensee issued NCR number 2733 and took ic. mediate steps to correct the matter.

Failure to perform test activities as required by documented I

instructions is contrary to Criterion V of Appendix B to 10 CFR 50 and was identified to the licensee as Inf raction 417/78-11-01.

I t

I 1032 x7

.

I RI.I Rpt. Nos. 50-416/78-11

'g g

i and 50-417/78-11 1-3 J

-

- di6 5.

Containment (Structural Concrete I) - Review of Quality Records, Unit 2 A follow-on inspection was made of quality records on pour number Q2T21-W-210937.0A in the Unit 2 Auxiliary building basemat. Acceptance criteria examined by the inspector appear in the following documents:

a.

PSAR, Sect ion 3.8.1. 7.5 b.

FSAR, Section 3.8.1.6.5 c.

Specification 9645-C-191.0, Revision 13, Materials Testing

!

Services d.

Specification 9645-C-103.0, Revision 17, Form, Place, Finish and Cure Concrete, e.

Specification 9645-C-101.0, Revision 14, Furnish and Deliver I.

Concrete, f.

"peci fi cat ion 9645-C-115.0, Inst all Reinforcing Mechanical Splices, g.

Specification 9645-C-112.0, Placement of Reinforcing Steel, h.

QCI 9.1, Concrete Inspection Activities, i.

QCI 9.1.7, Inspection of Reinforcing Mechanical Splices,

Records examined included:

a.

Certification records of Pittsburg Testing Laboratory (PT&L) and Bechtel inspectors, b.

Certification records of ten Cadweld inspectors, c.

Cadweld daily inspection and test frequency logs and tensile strength data, d.

Cadweld location drawings, FSK-C-1062,1063,1068,1070 and 1216, e.

WPIR Q 2T-21-W-21093 which contained batch tickets, cylinder breaks, concrete mix reports, preplacement and placement reports, in process test data and concrete yield work sheets. _

(

l t

l 1032 JO

.

R11 Rpt. Nos. 50-416/78-11 and 50-417/78-11 I-4 Examination of the above documents and discussions with responsible MP&L and Bechtel personnel disclosed the following unresolved items:

Acceptance Criteria on Air Temperature and Slump at Batch Plant a.

Acceptance criteria for in process tests on air temperature and slump performed at the batch plant on punped concrete do not appear to be clearly defined in the specifications. Discussions with QC and QA personnel indicated that the specifications are not being interpreted uniformly. This was identified to the licensee as Unresolved Item 417/78-11-02.

I b.

Frequency of In process Correlation Testing, Pump.ed Concrete Examination of records indicated the location and f requency of sampling for testing of air, temperature and slump were not in accord with the PSAR. Discussions with MP&L and Bechtel personnel indicated changes in the location and frequency of sampling were based on correlation tests, engineering evaluation and changes in (

the cur rent ANSI Standard N45.2.5 - 1978. They indicated their specification in ese and FS?R currently at NRR, which was scheduled for docketing en June 30, 1976, reflected their 1, resent mode of testing.

The licensee indicated his mode of operation, change, and basis for changes that have occurred to date are as follows:

(1) PSAR, December 1974 - August 1977 Sample and test at point of placement every 50 yards for slump and temperature and every 100 yards for air and test cylinders.

(2) FSAR, August 1977 i February 1978 (Change reflected in FSAR based on correlat a testing and engineering evaluation during operations 1. ween December 74 - August 77)

Sample at batch plant every 50 yards for slump and temperature and every 100 yards for air and cylinders. Make correlation tests every 200 yards at point of placement for air, temperature and slump; working limits at point of placement.

(3)

Specification 9645-C-191.0, Revision 13, February 1978 to j

July 7, 1978 (change based on engineering evaluation of operations to date and ANSI standard N45.2.5 - 1978).

1032

.:1

.

(

RII Rpt. Nos. 50-416/78-11 and 50-417/78-11 I-5 at batch plant eve ry 50 yards for slump and Sample Make temperature and every 100 yards for air and cylinders.

correlation tests for air, temperature and slump every 500 yards at point of placement; working limits at point of placement.

Subsequent examination of the FSAR and ANSI Standard N45.2.5 -

1978 at Region 11 indicated the licensee's current mode of in-process testing appeared to be a deviation from the FSAR and ANSI Standard N45.2.5-19 78.

The licensee was notified on July 5, 1978 of NRC's concern regarding the mode of in process testing.

On July 7, 1978, per l

telephone conversation with Region II IE, the licensee agreed to

return to the mode of operation stated in the FSAR and as discussed in paragraph Sb(2) (appears to agree with ANSI N45.2.5-1978).

Following several phone conversations with NRR, Headquarters 1E, f

and responsible personnel at MP&L and Bechtel, the licensee was noti fied per t elephone on July IS,1978 t hat the matt er rega rding frequency of in process correlation testing would be an unresolved item pending RII IE review of the licensee's justification for deviating from the PSAR, FSAR, and ANSI Standard N45.2.5, 1978.

This is unresolved item 417/78-11-03.

Containment (Ctructural Concrete II) - Review of Quality Records 1 6.

Unit 2 The inspector examined quality records on pour numbers Q2M22-W-23243WXA(A), Q2M22-W-23243WXA(B) and Q2M22-W-23243WXA(C) in the A, B and C rings of the Containment Building. Acceptance criteria examined Records by the inspector are the same as those listed in paragraph 5.

examined included:

Certification of PT&L and Bechtel QC inspectors, a.

b.

Certification records of ten Cadweld inspectors, c.

Cadweld daily inspection and test frequency logs and tensile strength data, t

.

1032

.:2

.

l

.

.

RII Rpt. Nos. 50-416/78-11 I-6 and 50-417/78-11 d.

Cadweld location drawings FSK-C-1199, 1115, 1118, 1112, 1111, 1121 and 1110, Work package and inspection report numbers Q2M22-W-2343W concrete mix

.

Q2M22-W-23243WXA(B) which contained batch t e.

data and concrete yield sheets, f.

NCR number 2695.

Records on correlation testing indicate the frequency of correlation Unresolved Item tests are not in accord with the FSAR as discussed in I

l 417/78-11-03, paragraph 5.

(Structural Concrete II) - Observation o' Work and e

7.

Containment Work Activities, Unit 2 The inspector observed partial placement of pour number Q2M22-

~

23243WXA(C) in _he C ring of the containment building.

Acceptance the saae as t. hose listed in criteria examined by the inspector are paragraph 5.

Examination of Cadweld records indicated Forms were tight and clean.

required by specifications.

rebar placement and splicing was as indicated by the signed preinspection Placeme..t activities pertainine to delivery time, piping, free inspection was Preplacement fall, layer thickness and c.,nsolida i o conformed to specifications.

form.

Activities were continu-usly monitored by QC personnel.

indicated proper mixes were being An examination of the batch plantdelivered to the specified sit accurate batch plant records were being generated.

Post placement examination of records indicated samples for h batch plant temperature, slump and air were taken every 50 ya h

i t of placement.

The above records indicate the frequency of correlation tests are no 417/78-11-03, in accord with the FSAR as discussed in Unresolved Item paragraph 5.

(u 1032 s]]

.

.

~

.

RII Tpt. Nos. 50-416/78-11 I-7 and 50-417/78-11 8.

Exit Interview The inspector met with licensee representatives denoted in paragraph 1 30, 1978. The licensee was at the conclusion of the inspection on June f

apprised of the scope of the inspection which included examination o l

work performance, quality records and QA implementation on structura The licensee anchor bolts and a previously identified i,em.

item of noncompliance discussed in paragraph 4 and concrete, acknowledged the the unresol,ed item discussed in paragraph Sa and indicated measures would be taken to resolve the items.

The licensee was notified by telephone of the second unresolved item as i

discussed in paragraph 5b.

l

(

l 1032 Ji

.

=

...

eI j.. MISSISSIPPI POWER & LIGHT COMPANY

'

[

A

.. lLu72

.

liciping Build Mississippi P. O.

B O X 1G 4 0. J A C K S O N. MISSISSIPPI 39205

-

'

e ooverre occ...csr Sept e:aber 20, 1978 g

ff

/c- ' <

.s.-s C 31-r /

9m

-

.

U. S. !;uclear Regulatory Commission Region 11 101 Parietta Street, Suite 3100 Atlanta, Georgia 30303

.

Attention:

Mr. J.

P. O'Reilly, Director Gentleme n :

I SUBJECT: Grand Gulf Nuci nr Station

'

File 0272/0494/15521 Units 1 and 2 R11:

JJB 50-416, 417/78-12 IE Inspection Report of (

July 18 through July 21, 1978

  • MQEC 7E/156*

AEO;-78/75 In response to your letter of August 29, 1978, transmit tir.g IE Inspection Report of the July 18 through July 21, 1978 inspection, we find no proprietary data contained therein.

Yours truly, f

W

.

y J. P. McCaughy, Jr.

Director of Power Production JRF:dwe cc:

Mr. N. L. Stacpley Mr. R. B. McGehee Mr. T. B. Conner Dr. Ernst Volgenau, Director Division of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D. C.

20555 (

..

,

AFv4bOM

.

h ft

  1. % 9 9 P b

, h 9

$ to C U C 9 A FM

' '

w W

'%