IR 05000413/1979003

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-413/79-03 & 50-414/79-03 on 790206-09.No Noncompliance Noted.Major Areas inspected:safety-related Components,Steel Structures,Supports & Concrete Expansion Anchors
ML19270F957
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 03/07/1979
From: Bryant J, Compton R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19270F951 List:
References
50-413-79-03, 50-413-79-3, 50-414-79-03, 50-414-79-3, NUDOCS 7904090289
Download: ML19270F957 (6)


Text

~

.

g

UNITED STATES

  1. p >8 880 9'o,,

NUCLEAR REGULATORY COMMISSION

8 n

REClON11

,t 101 M ARIETT A STRE ET. N.W.

ATLANTA. oEORGIA 30303 os.,...../

Report Nos.:

50-413/79-3 and 50-414/79-3 Licensee: Duke Power Company Post Office Box 33189 Charlotte, North Carolina 28242 Facility Name:

Catawba Nuclear Station, Units 1 and 2 Docket Nos.: 50-413 and 50-414 License Nos.: CPPR-116 and CPPR-117 Inspection at Catawba site near Charlotte, North Carolina Inspecto l

3[lf7)

zw _

,

m, R. M. Compton \\

Dat6 Signed

[Date[ Signed Approved by:_

ryant ection Chief, RCESB

'

SUMMARY Inspection on February 6-9, 1979 Areas Inspected This routine, unannounced inspection involved 26 inspector-hours on-site in the areas of safety-related components, safety-related steel structures and supports and concrete expansion anchors.

Results Of the areas inspected, no apparent items of noncompliance or deviations were identified.

7 9 0 4 0 9 0 2 E'l

'.

.

DETAILS 1.

Persons Contacted

.

Licensee Employees

  • D. C. Beam, Project Manager
  • D. L. Freeze, Project Engineer
  • R. A. Morgan, Senior QA Engineer
  • J. W. Willis, QA Engineer
  • S. W. Dressler, Senior Technical Support Engineer
  • C. L. Ray, Design Engineer
  • L. R. Davison, QC Engineer T. Weir, Technical Support Engineer W. I. Reardon, Technical Support Engineer Other Organizations G. H. Eriksen, QA Engineer, Bahnson/Envirotech
  • Attended exit interview.

2.

Exit Interview The inspection scope and findings were summarized on February 9,1979 with those persons indicated in Paragraph 1 above.

3.

Licensee Action on Previous Inspection Findings Not inspected.

4.

Unresolved Items Unresolved items were not identified during this inspection.

5.

Independent Inspection A general examination of safety-related equipment installation was made in the Auxiliary Building and in the Unit 1 Containment Building.

In place storage conditions, installation of piping and component supports and piping fabrication and installation were observe *

,

.

!

-2-An examination was made of the following documents concerning the installation and inspection of concrete expansion anchors for pipe supports, HVAC and electrical equipment:

DPC QA Procedures M-15, M-18, M-41, M-52

-

DPC Construction Procedures (CP)-ll5 and 301

-

DPC Specifications CNS-Il96.02-00-0000 and CNS-1211.00-05

-

-

Draft Bahnson/Envirotech procedure for inspection of expansion anchors for HVAC work.

Inspection requirements were discussed with QC inspectors and QA en-gineers involved in the various activities utilizing concrete expansion anchors. The following two areas that require further procedural clarification were identified. At present, the above documents contain no acceptance criteria for gaps between base plates and walls caused by irregularities in the concrete surfaces.

A draft change to specifica-tion CNS-Il96.02-00-0000 to address gaps is under review by site QA personnel and was examined by the inspector.

Secondly, the need for sufficient load testing or torque checking of installed expansion anchors was discussed with the licensee. This inspection is not con-sistently addressed ty the existing procedures governing anchor in-stallation for the various safety-related applications; HVAC, piping and electrical supporte. Clarification of these two areas has been identified as Inspector Follow-Up Item 413/79-03-01.

QC inspection of anchor bolt installations for pipe and HVAC supports has not yet begun.

No deviations or items of noncompliance were identified.

6.

Safety-Related Structures (Structural Steel Supports)-

Observation of Work and Work Activities (Unit 1)_

The containment spray heat exchanger foundation was examined for com-pliance with configuration, location, dimensional and material require-ments of DPC drawings CN-1220-43, Revision 3, and CN-1224-2, Revision 13.

Additional acceptance criteria for this item are contained in PSAR Sections 3.8 and 17, QA Procedures M-18 and M-21 and Construction Procedures 22 and 23.

Grouting of floor anchors and installation inspection had not yet been accomplished on this structure.

No deviations or items of noncompliance were identifie *

.

.

-3-7.

Safety-Related Components-Observation of Work and Work Activities (Unit 1)

Containment spray pump casings 1A and IB were examined for proper

-

installation, in-place storage and protection. These casings had been set on their support columns, but the pump supports had not been com-pleted and pump internals had not been installed.

Installation and storage and maintenance requirements are contained in the following documents:

Bingham /Willamette Company Drawing H-406, Revision E

-

-

DPC drawings CN 1201.05-126; CN 1221-1, Revision 10; CN 1220-21, Revision 4; CN 1200-1.1, Revision 5; CN 1221-1Aa; 1438.31-18B DPC Specification CNS-1121.00-1, Revision 3

-

Construction Procedures 117 and 137

-

-

QA Procedures P-3, M-5, M-9, M-10, M-21 and M-30 Installation and inspection requirements were discussed with the re-sponsible construction engineer and QA personnel.

No deviations or items of noncompliance were identified.

8.

Safety-Related Components-Review of Quality Records (Unit 1)

The inspector examined quality records for containment spray pump casings IA and IB and the four steam generators.

The following containment spray pump records were examined for com-pliance with QA Procedure P-1 and the documents listed in paragraph 7 above:

Form P-3A, Serial M-112, " Equipment Special Storage and Main-

-

tenance Inspection"

-

Form P-3B, " Storage and Maintenance Requirement Change Notice" Form M-9B, " Equipment Release Document for the Installation of

-

Rotating and Non-Rotating Equipment" Form 9-D, " Process Control Sheet for Installation of Rotating and

-

Non-Rotating Equipment"

,

.

J-4-Form M-10A's, " Process Control and Inspection of Torque to Bolts

-

and Studs", for pump hold down bolts ar' foundation anchor bolts Form P-1A, " Receiving Inspection Information Report"

-

.

Bingham /Williamette Certification of Complianca

-

ASME Code Data Reports

-

-

Form H-30A, "NDE Inspection Record" for support column top plate UT.

Three plates had not yet been UT'd after fabrication.

Form M-21A, " Field Weld Check-Off-List (Structural Steel)" for support column assembly CSI-I Form M-5A, " Structural Grouting Inspections"

-

During this review, it was noted that no inspections were required by the M-9 forms to verify that the pump support assemblies (col imns and lateral restraints) met drawing requirements as to location, size, configuration, material size and type, etc.

These inspections are not specified in the procedures governing the site fabrication of these supports either. Documents covering installation of RHR pumps with identical supports also lacked this inspection requirement. Most steel structures and supports are installed per QA Procedure M-18, "Inspec-tion of Structural Steel Erection", which requires QC inspection for location, size, orientation, material size and type, etc. The require-ments of M-18 had not been invoked for these pump supports.

Licensee personnel are evaluating the need for procedural changes.

Because fabrication, installation and inspection of these pump supports are not complete, this question concerning inspection requirements is identi-fied as Inspector Follow-Up Item 413/79-03-02.

The following steam generator quality records were examined:

Form CP-183A's

-

Form M-30A for NDT of lifting gear shackles

-

Form M-9B's for SG installation, lower lateral support instal-

-

lation and suport column embedment installation Form M-10A's for SG to support column upper clevis bolts and for

-

column embedment hold down nuts Variation Notices 2288, 2800, 2836, 2909

-

',

.

.

-5-The following documents were examined to determine installation and inspection requirements;

-

DPC Drawing CN 1070-12, Revision 4, " Steam Generator Lower Support-Plan and Details" DPC Drawing CN 1070-11, Revision 2, " Steam Generator Lower

-

Support-Plan"

-

DPC Drawing CN 1070-9, Revision 3, " Steam Generator and Reactor Coolant Pump Support Columns Plan" DPC Drawing CN 1070-10, Revision 8, " Steam Generator and Reactor

-

Coolant Pump Support Columns-Plan and Details"

-

DPC Drawing CN 1070-2, Revision 7, " Steam Generator and Reactor Coolant Pump Column Embeds"

-

CP-183, Revision 0, "NSSS Vessel Installation"

-

QA Procedures M-9 and M-10 Steam Generator upper lateral supports have not yet been installed.

No deviations or items of noncompliance were identified.