|
---|
Category:Inspection Plan
MONTHYEARIR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 IR 05000220/20230052023-08-31031 August 2023 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2023005 and 05000410/2023005) ML23090A1242023-04-0505 April 2023 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000220/2023011 and 05000410/2023011 IR 05000220/20220062023-03-0101 March 2023 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2022006 and 05000410/2022006) IR 05000220/20220052022-08-31031 August 2022 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2022005 and 05000410/2022005) IR 05000220/20210062022-03-0202 March 2022 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2021006 and 05000410/2021006) IR 05000220/20210052021-09-0101 September 2021 Updated Inspection Plan for the Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2021005 and 05000410/2021005) ML21088A2682021-03-30030 March 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000220/20200062021-03-0303 March 2021 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2020006 and 05000410/2020006) IR 05000220/20190062020-03-0303 March 2020 Annual Assessment Letter for the Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2019006 and 05000410/2019006) ML19344D0232019-12-0909 December 2019 Ti 2515/194 Inspection Documentation Request IR 05000220/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000220/2019005 and 05000410/2019005) IR 05000220/20180062019-03-0404 March 2019 Annual Assessment Letter for the Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2018006 and 05000410/2018006) ML18348A5322018-12-13013 December 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000220/2019403 and 05000410/2019403 IR 05000220/20180052018-08-28028 August 2018 LLC, Units 1 and 2 Updated Inspection Plan: Inspection Report 05000220/2018005 and 05000410/2018005 IR 05000220/20170062018-02-28028 February 2018 Annual Assessment Letter for Nine Mile Point Nuclear Station LLC, Units 1 and 2 (Report 05000220/2017006 and 05000410/2017006, Report 05000220/2017402 and 05000410/2017402, and Report 05000220/2017501 and 05000410/2017501) IR 05000220/20170052017-08-28028 August 2017 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 - Inspection Report 05000220/2017005 and 05000410/2017005 IR 05000220/20160062017-03-0101 March 2017 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2016006 and 05000410/2016006) IR 05000220/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, Report 05000220/2016005 and 05000410/2016005 IR 05000220/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2015006 and 05000410/2015006) IR 05000220/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220/2015005 and 05000410/2015005) ML15084A3432015-03-25025 March 2015 Notification of Conduct Triennial Fire Protection Baseline Inspection IR 05000220/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220/2014001 and 05000410/2014001)(w/Inspection Plan) IR 05000220/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220-14-006 and 05000410-14-006) IR 05000220/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220/2013001 and 05000410/2013001)(w/Inspection Plan) IR 05000220/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Nine Mile Point Nuclear Station Units 1 and 2 (Report 05000220-13-006 and 05000410-13-006) IR 05000220/20120012013-03-0404 March 2013 Annual Assessment Letter for Nine Mile Point Nuclear Station Units 1 & 2 (Report 05000220/2012001 and 05000410/2012001) ML12244A3272012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Nine Mile Point Nuclear Station Units 1 and 2 IR 05000220/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000220/2011001 and 05000440/2011001) ML1124207972011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Nine Mile Point Nuclear Station Units 1 and 2 IR 05000220/20100012011-03-0404 March 2011 Annual Assessment Letter for Nine Mile Point Nuclear Station (Report 05000220/2010001 and 05000410/2010001 ML1024401282010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Nine Mile Point Nuclear Station IR 05000041/20100102010-03-0303 March 2010 Annual Assessment Letter - Nine Mile Point IR 05000220-10-001 & 050004110-10-001) ML1006205312010-03-0303 March 2010 Annual Assessment Letter - Nine Mile Point IR 05000220-10-001 & 050004110-10-001) ML0924403112009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Nine Mile Point Nuclear Station, Dated 09/01/09 IR 05000220/20090012009-03-0404 March 2009 IR 05000220-09-001 and 05000410-09-001, Nine Mile Point Nuclear Station, LLC, Annual Assessment Letter, Dated March 4, 2009 IR 05000220/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Nine Mile Point, (IR 050000220-08-001 and 05000410-08-001) ML0806100122008-03-0303 March 2008 2007 Annual Assessment Letter EOC 2007 ROP8 - Nine Mile Point (05000220-08-001, 05000410-08-001) ML0734709612007-12-13013 December 2007 ROP8 - Nine Mile Point - Change to Inspection Plan, 12/13/07 ML0724309152007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Nine Mile Point Nuclear Station IR 05000220/20070012007-03-0202 March 2007 Annual Assessment Letter - Nine Mile Point Nuclear Station (Report 05000220-07-001 and 05000410-07-001) ML0624305022006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Nine Mile Point Nuclear Station ML0606202732006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Nine Mile Point Nuclear Station (Report 05-220/2006001 and 05-410/2006001) ML0524206882005-08-30030 August 2005 Mid-Cycle Performance Review and Inspection Plan - Nine Mile Point Nuclear Station IR 05000220/20050012005-03-0202 March 2005 Annual Assessment Letter - Nine Mile Point (Report 05000220/2005001 and 05000410/2005001)) ML0424406052004-08-30030 August 2004 2004 Nine Mile Point Mid-Cycle Performance Review and Inspection Plan ML0306202032003-03-0303 March 2003 2003 Annual Assessment Letter - Nine Mile Point Nuclear Station ML0223501892002-08-23023 August 2002 2002 Mid-Cycle Performance Review and Inspection Plan - Nine Mile Point Nuclear Station IR 05000220/20020012002-03-0404 March 2002 2002 Annual Assessment Letter - Nine Mile Point Nuclear Station (Report 50-220/02-01 and 50-410/02-01) 2024-08-29
[Table view] Category:Inspection Report
MONTHYEARIR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 IR 05000220/20234022023-11-28028 November 2023 Security Baseline Inspection Report 05000220/2023402 and 05000410/2023402 IR 05000220/20234202023-11-0101 November 2023 Security Baseline Inspection Report 05000220/2023420 and 05000410/2023420 IR 05000220/20230032023-10-25025 October 2023 Integrated Inspection Report 05000220/2023003 and 05000410/2023003 IR 05000220/20235012023-10-17017 October 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000220/2023501 and 05000410/2023501 IR 05000220/20230112023-10-16016 October 2023 Comprehensive Engineering Team Inspection Report 05000220/2023011 and 05000410/2023011 IR 05000220/20233032023-09-20020 September 2023 Retake Operator Licensing Examination Report 05000220/2023303 IR 05000220/20230052023-08-31031 August 2023 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2023005 and 05000410/2023005) IR 05000220/20234012023-08-0808 August 2023 Cyber Security Inspection Report 05000220/2023401 and 05000410/2023401 (Cover Letter Only) IR 05000220/20230022023-08-0101 August 2023 Integrated Inspection Report 05000220/2023002 and 05000410/2023002 IR 05000220/20230102023-06-29029 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000220/2023010 and 05000410/2023010 IR 05000410/20233022023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000410/2023302 IR 05000220/20230012023-05-0505 May 2023 Integrated Inspection Report 05000220/2023001 and 05000410/2023001 IR 05000220/20233012023-03-29029 March 2023 Initial Operator Licensing Examination Report 05000220/2023301 IR 05000220/20220062023-03-0101 March 2023 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2022006 and 05000410/2022006) IR 05000220/20220042023-01-23023 January 2023 Integrated Inspection Report 05000220/2022004 and 05000410/2022004 IR 05000220/20220102022-11-22022 November 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000220/2022010 and 05000410/2022010 IR 05000220/20220032022-11-0404 November 2022 Integrated Inspection Report 05000220/2022003 and 05000410/2022003 IR 05000220/20220052022-08-31031 August 2022 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2022005 and 05000410/2022005) IR 05000220/20224012022-08-30030 August 2022 Security Baseline Inspection Report 05000220/2022401 and 05000410/2022401 IR 05000220/20220022022-08-0808 August 2022 Integrated Inspection Report 05000220/2022002 and 05000410/2022002 and Independent Spent Fuel Storage Installation Report 07201036/2022001 IR 05000220/20210042022-05-19019 May 2022 Reissued Integrated Inspection Report 05000220/2021004 and 05000410/2021004 IR 05000220/20220012022-04-29029 April 2022 Integrated Inspection Report 05000220/2022001 and 05000410/2022001 IR 05000220/20210062022-03-0202 March 2022 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2021006 and 05000410/2021006) ML22026A3502022-01-26026 January 2022 Integrated Inspection Report 05000220/2021004 and 05000410/2021004 IR 05000220/20210122022-01-10010 January 2022 Biennial Problem Identification and Resolution Inspection Report 05000220/2021012 and 05000410/2021012 IR 05000220/20210032021-11-0909 November 2021 Integrated Inspection Report 05000220/2021003 and 05000410/2021003 and Independent Spent Fuel Storage Installation Report 07201036/2021001 IR 05000220/20215012021-10-14014 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000220/2021501 and 05000410/2021501 IR 05000220/20210052021-09-0101 September 2021 Updated Inspection Plan for the Nine Mile Point Nuclear Station, Units 1 and 2 (Reports 05000220/2021005 and 05000410/2021005) IR 05000220/20214012021-09-0101 September 2021 Material Control and Accounting Program Inspection Report 05000220/2021401 and 05000410/2021401 (Letter Only) IR 05000220/20210102021-08-24024 August 2021 Triennial Fire Protection Inspection Report 05000220/2021010 and 05000410/2021010 IR 05000220/20210022021-08-10010 August 2021 Integrated Inspection Report 05000220/2021002 and 05000410/2021002 and Independent Spent Fuel Storage Installation Report 07201036/2021002 IR 05000220/20214022021-06-22022 June 2021 Security Baseline Inspection Report 05000220/2021402 and 05000410/2021402 IR 05000410/20213022021-05-12012 May 2021 Initial Operator Licensing Examination Report 05000410/2021302 IR 05000220/20210012021-05-0505 May 2021 Integrated Inspection Report 05000220/2021001 and 05000410/2021001 IR 05000220/20210112021-05-0404 May 2021 Temporary Instruction 2515/194 Inspection Report 05000220/2021011 and 05000410/2021011 IR 05000220/20200062021-03-0303 March 2021 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2020006 and 05000410/2020006) IR 05000220/20200042021-02-11011 February 2021 Integrated Inspection Report 05000220/2020004 and 05000410/2020004 and Independent Spent Fuel Storage Installation Report 07201036/202004 IR 05000220/20203012021-01-25025 January 2021 Initial Operator Licensing Examination Report 05000220/2020301 ML20343A0112020-12-0909 December 2020 Security Inspection Report Cover Letter 05000220/2020420 and 05000410/2020420 IR 05000220/20204202020-12-0909 December 2020 Security Inspection Report 05000220/2020420 and 05000410/2020420 2020 Report IR 05000220/20200102020-11-24024 November 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000220/2020010 and 05000410/2020010 2024-08-05
[Table view] Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds NMP2L2880, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 2024-09-04
[Table view] |
Text
ust 28, 2019
SUBJECT:
NINE MILE POINT NUCLEAR STATION UNITS 1 AND 2 UPDATED INSPECTION PLAN (INSPECTION REPORTS 05000220/2019005 AND 05000410/2019005)
Dear Mr. Hanson:
The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for Nine Mile Point Nuclear Power Station, Units 1 and 2. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In addition to normal baseline inspections, the NRC will be performing Inspection Procedure (IP) 71003, Post Approval Site Inspection For License Renewal, for Nine Mile Point Unit 1, IP 60855.1, Operation of an ISFSI Independent Spent Fuel Storage Installation at Operating Plants, and plans to conduct inspections per Temporary Instruction (TI) 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems, and TI 2515/193, Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions, at your facility during the period.
You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (610) 337-5120 with any questions you have regarding this letter.
Sincerely,
/RA/
Erin E. Carfang, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-220, 50-410 License Nos. DPR-63, NPF-69 Enclosure:
Nine Mile Point Inspection Plan cc: Distribution via ListServ
ML19233A261 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME SHaney ECarfang DATE 8/21/19 8/26/19
IP 22 Inspection Activity Plan Report Nine Mile Point 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count ISFSI OPERATIONAL INSPECTION 2 1, 2 07/08/2019 07/12/2019 IP 60855 001001 Operation Of An ISFSI 1, 2 07/08/2019 07/12/2019 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Heat Sink 1 1, 2 08/04/2019 08/10/2019 IP 71111.07T 000700 Heat Sink Performance PI&R BIENNIAL 4 1, 2 08/12/2019 08/16/2019 IP 71152B 000747 Problem Identification and Resolution 1, 2 08/26/2019 08/30/2019 IP 71152B 000747 Problem Identification and Resolution RAD SAFETY 01,02,03,04 1 1, 2 08/26/2019 08/30/2019 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 08/26/2019 08/30/2019 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 08/26/2019 08/30/2019 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 08/26/2019 08/30/2019 IP 71124.04 000728 Occupational Dose Assessment 1, 2 08/26/2019 08/30/2019 IP 71151 000746 Performance Indicator Verification RAD SAFETY REMP 1 1, 2 09/16/2019 09/20/2019 IP 71124.07 000731 Radiological Environmental Monitoring Program 1, 2 09/16/2019 09/20/2019 IP 71151 000746 Performance Indicator Verification TI-193 Hardened Containment Vent 3 1, 2 09/23/2019 09/27/2019 TI 2515/193 000511 Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions NMP EP EXERCISE INSPECTION 5 1, 2 10/07/2019 10/11/2019 IP 71114.01 000716 Exercise Evaluation 1, 2 10/07/2019 10/11/2019 IP 71151 001397 Performance Indicator Verification NMP2 REQUAL INSP W/ P/F RESULTS 2 1, 2 10/20/2019 10/25/2019 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance EQ PROGRAM 3 1, 2 10/21/2019 10/25/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
This report does not include INPO and OUTAGE activities. Page 1 of 4 This report shows only on-site and announced inspection procedures.
8/21/2019 2:48:20 PM
IP 22 Inspection Activity Plan Report Nine Mile Point 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count EQ PROGRAM 3 1, 2 11/04/2019 11/08/2019 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
NMP2 INITIAL OL EXAM 4 2 11/10/2019 11/16/2019 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2 12/08/2019 12/21/2019 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
TI-194 Open Phase Condition Inspection-NMP 2 1, 2 11/18/2019 11/22/2019 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)
NMP UNIT 1 - LICENSE RENEWAL PHASE 4 3 1 12/08/2019 12/14/2019 IP 71003 000687 Post-Approval Site Inspection for License Renewal Rad Safety Refuel 1 1, 2 03/02/2020 03/06/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/02/2020 03/06/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 03/02/2020 03/06/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/02/2020 03/06/2020 IP 71124.04 000728 Occupational Dose Assessment ISI - UNIT 2 1 2 03/09/2020 03/13/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Rad Safety RETS 1 1, 2 05/18/2020 05/22/2020 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 05/18/2020 05/22/2020 IP 71151 000746 Performance Indicator Verification Access Control, Equipment Testing and Maintenance, Training 3 1, 2 06/01/2020 06/05/2020 IP 71130.02 000734 Access Control 1, 2 06/01/2020 06/05/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 06/01/2020 06/05/2020 IP 71130.07 000739 Security Training 1, 2 06/01/2020 06/05/2020 IP 71151 001338 Performance Indicator Verification Rad Safety Inspection 1 1, 2 06/08/2020 06/12/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 06/08/2020 06/12/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. Page 2 of 4 This report shows only on-site and announced inspection procedures.
8/21/2019 2:48:20 PM
IP 22 Inspection Activity Plan Report Nine Mile Point 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Rad Safety Inspection 1 1, 2 06/08/2020 06/12/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 06/08/2020 06/12/2020 IP 71124.04 000728 Occupational Dose Assessment NMP EP PROGRAM INSPECTION 1 1, 2 07/13/2020 07/17/2020 IP 71114.02 000717 Alert and Notification System Testing 1, 2 07/13/2020 07/17/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 07/13/2020 07/17/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 07/13/2020 07/17/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 07/13/2020 07/17/2020 IP 71151 001397 Performance Indicator Verification Radwaste 1 1, 2 07/27/2020 07/31/2020 IP 71124.08 000732 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation Rad Safety Instruments 1 1, 2 08/02/2020 08/07/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation Rad Safety Inspection 1 1, 2 10/05/2020 10/09/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 10/05/2020 10/09/2020 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 10/05/2020 10/09/2020 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/05/2020 10/09/2020 IP 71124.04 000728 Occupational Dose Assessment 1, 2 10/05/2020 10/09/2020 IP 71151 000746 Performance Indicator Verification DESIGN BASIS ASSURANCE INSPECTION - TEAMS 7 1, 2 10/19/2020 10/23/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
1, 2 11/02/2020 11/06/2020 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
NMP1 INITIAL OL EXAM 4 1 11/01/2020 11/07/2020 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1 11/29/2020 12/12/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
NMP1 Requal Inspecton with P/F Results 2 1 11/15/2020 11/21/2020 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance 1 11/15/2020 11/21/2020 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance This report does not include INPO and OUTAGE activities. Page 3 of 4 This report shows only on-site and announced inspection procedures.
8/21/2019 2:48:20 PM
IP 22 Inspection Activity Plan Report Nine Mile Point 07/01/2019 - 06/30/2021 Unit Start End Activity CAC Title Staff Count Rad Safety Inspection 1 1, 2 03/29/2021 04/02/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/29/2021 04/02/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 03/29/2021 04/02/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/29/2021 04/02/2021 IP 71124.04 000728 Occupational Dose Assessment INSERVICE INSPECTION 1 1 04/04/2021 04/10/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Access Control, Protective Strategy, TSR 4 1, 2 05/24/2021 05/28/2021 IP 71130.02 000734 Access Control 1, 2 05/24/2021 05/28/2021 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 05/24/2021 05/28/2021 IP 71130.14 000743 Review of Power Reactor Target Sets 1, 2 05/24/2021 05/28/2021 IP 71151 001338 Performance Indicator Verification MATERIAL CONTROL AND ACCOUNTABILITY 1 1, 2 06/06/2021 06/12/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)
Rad Safety Inspection 1 1, 2 06/07/2021 06/11/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 06/07/2021 06/11/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 06/07/2021 06/11/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 06/07/2021 06/11/2021 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 4 of 4 This report shows only on-site and announced inspection procedures.
8/21/2019 2:48:20 PM