IR 05000220/2019013

From kanterella
Jump to navigation Jump to search
Temporary Instruction 2515/193 Inspection Report 05000220/2019013 and 05000410/2019013
ML19295E729
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 10/21/2019
From: Marc Ferdas
NRC/RGN-I/DRP/PB7
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Ferdas M
References
IR 2019013
Download: ML19295E729 (8)


Text

October 21, 2019

SUBJECT:

NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 - TEMPORARY INSTRUCTION 2515/193 INSPECTION REPORT 05000220/2019013 AND 05000410/2019013

Dear Mr. Hanson:

On September 26, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Nine Mile Point Nuclear Station, Units 1 and 2 and discussed the results of this inspection with Mr. Todd Tierney, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Marc S. Ferdas, Team Leader Technical Support and Assessment Team Division of Reactor Projects

Docket Nos. 05000220 and 05000410 License Nos. DPR-63 and NPF-69

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000220 and 05000410

License Numbers:

DPR-63 and NPF-69

Report Numbers:

05000220/2019013 and 05000410/2019013

Enterprise Identifier: I-2019-013-0013

Licensee:

Exelon Generation Company, LLC

Facility:

Nine Mile Point Nuclear Station, Units 1 and 2

Location:

Oswego, NY

Inspection Dates:

September 23, 2019 to September 26, 2019

Inspectors:

S. Haney, Senior Project Engineer

C. Cahill, Senior Reactor Analyst

K. Mangan, Senior Reactor Inspector

Approved By:

Marc S. Ferdas, Team Leader

Technical Support and Assessment Team

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Temporary Instruction 2515/193 inspection at Nine Mile Point Nuclear Station, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

2515/193 - Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions

Inspection of the Implementation of EA-13-109: Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation under Severe Accident Conditions (1 Sample)

(1) Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the reliable hardened containment wetwell vent as described in the plant specific submittals and the associated safety evaluations (ADAMS Accession Nos. ML18355A737 - Unit 1 and ML18255A121 - Unit 2), and determined that the licensee was in compliance with NRC Order EA-13-109 Phase 1, Reliable, Severe Accident Capable Wetwell Venting System (ADAMS Accession No. ML13143A321).

The inspectors verified that the licensee satisfactorily:

Installed the hardened containment vent system (HCVS) to meet the performance objectives outlined in Section A.1.1 of Attachment 2 to the Order EA-13-109;

Installed the HCVS system with the design features specified in Section A.1.2 of Attachment 2 to the Order EA-13-109;

Designed the HCVS to meet the quality standards described in Section A.2 of 2 to the Order EA-13-109;

Developed and implemented adequate maintenance and testing of HCVS equipment to ensure their availability and capability;

Developed and issued procedures to safely operate the HCVS using normal power supplies during extended loss of alternating current power (ELAP) and a postulated severe accident scenario, and integrated the procedures into existing plant procedures; and

Trained their staff to assure personnel can proficiently operate the HCVS.

Based on samples selected for review, the inspectors verified that the licensee satisfactorily implemented appropriate elements of the reliable wetwell venting strategy as described in the plant specific submittals and the associated safety evaluation (ADAMS Accession Nos. ML18355A737 - Unit 1 and ML18255A121 - Unit 2) and determined that the licensee was in compliance with NRC Order EA-13-109 Phase 2, Reliable, Severe Accident Capable Drywell (or alternative strategy) Venting System (ADAMS Accession No. ML13143A321).

The inspectors verified that the licensee satisfactorily developed a strategy making it unlikely that the licensee would need to vent from the containment drywell that includes the following:

Implemented the severe accident water addition (SAWA)/severe accident water management (SAWM) systems as defined, and fulfilled functional requirements for installed and portable equipment.

Installed and/or identified the previously-installed instrumentation necessary to implement SAWM.

Developed and implemented adequate maintenance and testing of SAWA/SAWM equipment to ensure availability and capability.

Developed and issued procedures to safely operate the SAWA/SAWM during an ELAP and during postulated severe accident scenario, and integrated their procedures into their existing plant procedures such that entry into and exiting from the procedures are clear when using existing plant procedures.

Trained their staff to assure personnel can proficiently operate the HCVS during an ELAP and accident scenario.

The inspectors verified that any noncompliance with requirements and standards identified during the inspection were entered into the licensee's corrective action program.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On September 26, 2019, the inspectors presented the Temporary Instruction 2515/193 inspection results to Mr. Todd Tierney, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2515/193

Calculations

A.10.1-P-051

Nitrogen Requirement for Operation of the HCVS Valves

S14-54HX019

Spent Fuel Pool Heat Up During Severe Accident Resulting

from an ELAP Event

S22.4-

201.13M002

HCVS Valve Motive Gas Supply Sizing

Corrective Action

Documents

AR 04137905

AR 04241162

AR 04274864

AR 04275007

Engineering

Changes

ECP-13-000086

ECP-17-000279

Miscellaneous

CC-NM-118-1003

Nine Mile Point Nuclear Station Unit 1, Final Integrated Plan

Document - Mitigating Strategies NRC Order EA-12-049

CC-NM-118-1004

Nine Mile Point Nuclear Station Unit 2, Final Integrated Plan

Document - Mitigating Strategies NRC Order EA-12-049

CC-NM-118-1005

Final Integrated Plan HCVS Order EA-13-109 for Nine Mile

Point Nuclear Power Station - Unit 1 (NMP1)

CC-NM-118-1006

Final Integrated Plan HCVS Order EA-13-109 for Nine Mile

Point Nuclear Power Station - Unit 2 (NMP2)

N-NM-EP-FLEX-

TECH

FLEX Related ERO Technical Training

Report QR-

351024565-1

Qualification Report for Absolyte GP VRLA Battery and A12B

Series Battery Charger

VENRPT-15-

000013

Seismic Qualification Summary for Hardened Containment

Vent Components

Procedures

CC-NM-118

Site Implementation of Diverse and Flexible Coping

Strategies (FLEX) and Spent Fuel Pool Instrumentation

Program

CC-NM-118-101

Beyond Design Basis Administrative Controls

00400

EP-AA-124-F-03

FLEX Communications Equipment Testing and Inventorying

of the Site and Site-Specific EOF Fixed and Portable Satellite

System

C

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

N1-DRP-FLEX-

ELEC

Emergency Damage Repair - BDB/FLEX Generator

Deployment Strategy

00400

N1-DRP-FLEX-

MECH

Emergency Damage Repair - BDB/FLEX Plump Deployment

Strategy

00700

N1-EOP-4.1

Primary Containment Venting

200.01

N1-PM-M5

Monthly Checklist

00501

N2-DRP-FLEX-

ELEC

Emergency Damage Repair - BDB/FLEX Generator

Deployment Strategy

00300

N2-DRP-FLEX-

MECH

Emergency Damage Repair - BDB/FLEX Plump Deployment

Strategy

00500

N2-EOP-6.21

Containment Venting

N2-PM-M008

Monthly Checklist

01300

S-DRP-COMM

BDBEE Communication Procedure

Self-Assessments AR 04249579

Work Orders

C93470077

C93632926

C93659488

C93660043

C93660263

C93671603

C93675035

C93689483