IR 05000400/2012403

From kanterella
Jump to navigation Jump to search
IR 05000400-12-403, 7/19/2012, Shearon Harris Nuclear Power Plant, Cover Letter
ML12228A731
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 08/15/2012
From: Binoy Desai
NRC/RGN-II/DRS/PSB2
To: Hamrick G
Progress Energy Carolinas, Progress Energy Co
References
IR-12-403
Download: ML12228A731 (4)


Text

August 15, 2012

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - NRC SECURITY INSPECTION REPORT 05000400/2012403

Dear Mr. Hamrick:

On July 19, 2012, the U. S. Nuclear Regulatory Commission (NRC) completed a security baseline inspection at your Shearon Harris Nuclear Power Plant, Unit 1. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed report documents the inspection results, which were discussed with you and other members of your staff.

This inspection examined activities conducted under your license as they relate to security, and compliance with the Commission=s rules and regulations, and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

One finding of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process) was identified during this inspection. The deficiency was corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site. The finding did not have a cross-cutting aspect. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2, of the NRC Enforcement Policy because of the very low safety significance of the violation, and because it was entered into your corrective actions program. If you contest this non-cited violation, you should provide a response within 30 days of the date of this inspection report, with the basis of your denial, to the Nuclear Regulatory Commission, Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Shearon Harris Nuclear Station. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system, ADAMS.

ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.

In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, mark your entire response ASecurity Related Information-Withhold Under 10 CFR 2.390" and follow the instructions for withholding in 10 CFR 2.390 (b)(1).

Sincerely,

/RA/

Binoy A. Desai, Chief Plant Support Branch 2 Division of Reactor Safety

Docket No.

50-400 License No. NPF-63

Enclosure:

Inspection Report 05000400/2012403 w/Attachment Supp. Info. (OUO)

cc w/encl: (See page 3)

ML1222A731 X SUNSI REVIEW COMPLETE X FORM 665 ATTACHED OFFICE RII: DRS RII: DRS RII: DRS RII: DRS RII: DRS RII: DRS RII: DRP SIGNATURE RA/JG RA/JS RA/JW RA/AT RA/RP RA/BD RA/RM NAME J. Graham J. Shehee J. Wallo A. True R. Patterson B. Desai R. Musser DATE 08/15/2012 08/09/2012 08/18/2012 08/14/2012 08/08/2012 08/09/2012 08/14/2012 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO cc w/Encl:

George Vice President Carolina Power and Light Company Shearon Harris Nuclear Power Plant P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

Ernest J. Kapopoulos Jr.

Plant General Manager Carolina Power and Light Company Shearon Harris Nuclear Power Plant 5413 Shearon Harris Road New Hill, NC 27562

R. Keith Holbrook Manager, Support Services Shearon Harris Nuclear Power Plant 5413 Shearon Harris Road New Hill, NC 27562

David H. Corlett Supervisor Licensing/Regulatory Programs Progress Energy P.O. Box 165, Mail Code: Zone 1 New Hill, NC 27562-0165

Joseph W. Donahue Vice President Nuclear Oversight Progress Energy TPP-15 100 E. Davie Street Raleigh, NC 27601

Edward T. O'Neil Director Nuclear Protective Svc. and Emergency Preparedness Progress Energy TPP-15 100 East Davie Street Raleigh, NC 27601

Terrence E. Slake Manager Nuclear Plant Security Shearon Harris Nuclear Power Plant 5413 Shearon Harris Road New Hill, NC 27562