|
---|
Category:Inspection Report
MONTHYEARIR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 IR 05000400/20243012024-02-21021 February 2024 – NRC Operator Licensing Examination Approval 05000400/2024301 IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML22355A5062022-12-23023 December 2022 404 Cyber Notification and RFI Letter IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 IR 05000400/20220052022-08-24024 August 2022 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2022005) IR 05000400/20224032022-08-23023 August 2022 Security Baseline Inspection Report 05000400/2022403 IR 05000400/20220022022-08-0505 August 2022 Integrated Inspection Report 05000400/2022002 IR 05000400/20220112022-07-20020 July 2022 Biennial Problem Identification and Resolution Inspection Report 05000400 2022011 IR 05000400/20224022022-06-30030 June 2022 Material Control and Accounting Program Inspection Report 05000400/2022402 (OUO Removed) IR 05000400/20220102022-06-13013 June 2022 Design Basis Assurance Inspection (Programs) Inspection Report 05000400/2022010 IR 05000400/20220012022-05-0404 May 2022 Integrated Inspection Report 05000400/2022001 IR 05000400/20224012022-03-24024 March 2022 Security Baseline Inspection Report 05000400/2022401 IR 05000400/20210062022-03-0202 March 2022 Annual Assessment Letter for Shearon Harris Nuclear Power Plant (Report No. 05000400/2021006) IR 05000400/20210042022-02-0404 February 2022 Integrated Inspection Report 05000400/2021004 IR 05000400/20210112022-01-24024 January 2022 Triennial Fire Protection Inspection Report 05000400/2021011 IR 05000400/20210102021-12-28028 December 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000400/2021010 IR 05000400/20214202021-12-0707 December 2021 Security Inspection Report 05000400/2021420 IR 05000400/20210032021-11-10010 November 2021 Integrated Inspection Report 05000400/2021003 IR 05000400/20210052021-08-26026 August 2021 Updated Inspection Plan for Shearon Harris Nuclear Power Plant (Report 05000400/2021005) IR 05000400/20210022021-08-0202 August 2021 Integrated Inspection Report 05000400/2021002 IR 05000400/20213012021-05-18018 May 2021 NRC Operator License Examination Report 05000400/2021301 IR 05000400/20210012021-04-29029 April 2021 Integrated Inspection Report 05000400/2021001 IR 05000400/20200062021-03-0303 March 2021 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2020006 IR 05000400/20200042021-01-27027 January 2021 Integrated Inspection Report 05000400/2020004 IR 05000400/20203012021-01-0808 January 2021 301 Exam Report 05000400/2020301 IR 05000335/20204012021-01-0505 January 2021 Security Baseline Inspection Report 05000335/2020401 and 05000389/2020401 IR 05000400/20200102020-12-14014 December 2020 Design Basis Assurance Inspection (Teams) Inspection Report 05000400/2020010 IR 05000400/20200112020-12-0202 December 2020 Biennial Problem Identification and Resolution Inspection Report 05000400/2020011 IR 05000400/20204052020-11-0606 November 2020 Security Baseline Inspection Report 05000400/2020405 IR 05000400/20200032020-11-0606 November 2020 Integrated Inspection Report 05000400/2020003 IR 05000400/20204032020-10-30030 October 2020 Security Baseline Inspection Report 05000400/2020403 2024-09-10
[Table view] Category:Letter
MONTHYEARML24290A1102024-10-24024 October 2024 Notification of Licensed Operator Initial Examination 05000400/2025301 05000400/LER-2024-001-01, Automatic Reactor Trip Due to Main Generator Lock-Out2024-10-23023 October 2024 Automatic Reactor Trip Due to Main Generator Lock-Out IR 05000400/20240112024-09-10010 September 2024 NRC Inspection Report 05000400/2024011 IR 05000400/20240052024-08-26026 August 2024 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400-2024005) Rev 1 ML24059A4252024-08-14014 August 2024 Issuance of Amendment No. 202 Regarding Alignment of Certain Technical Specifications with Improved Standard Technical Specifications ML24213A0522024-08-0202 August 2024 Issuance of Amendment No. 201 to Extend Completion Time of Inoperable Reactor Coolant System Accumulator Using Consolidated Line Item Improvement Process ML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter IR 05000400/20240022024-07-29029 July 2024 – Integrated Inspection Report 05000400/2024002 05000400/LER-2024-001, Automatic Reactor Trip Due to Main Generator Lock-Out2024-07-22022 July 2024 Automatic Reactor Trip Due to Main Generator Lock-Out ML24183A0972024-07-12012 July 2024 ISFSI; Catawba 1, 2 & ISFSI; McGuire 1, 2 & ISFSI; Oconee 1, 2, 3 & ISFSI; Shearon Harris 1; H. B. Robinson 2 & ISFSI; and Radioactive Package Shipping Under 10 CFR 71 (71-266 & 71-345) – Review of QA Program Changes EPID L-2024-LLQ-0002 IR 05000400/20243022024-06-27027 June 2024 – NRC Operator Licensing Examination Approval 05000400/2024302 IR 05000400/20244012024-06-25025 June 2024 – Security Baseline Inspection Report05000400/2024401 ML24162A1372024-06-24024 June 2024 – Regulatory Audit Summary Related to the Review of Exemption Request from Certain Requirements in 10 CFR 50.55a(h)(2)(EPID L-2024-LLE-00040) ML24136A1382024-05-20020 May 2024 – Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2024011) and Request for Information (RFI) ML24116A2592024-05-14014 May 2024 Staff Evaluation Related to Aging Management Plan and Inspection Plan for Reactor Vessel Internals ML24127A1592024-05-0808 May 2024 – Notification of Licensed Operator Initial Examination 05000400/2024302 IR 05000400/20240012024-05-0505 May 2024 Integrated Inspection Report 05000400/2024001 ML24100A0912024-04-10010 April 2024 Operator License Examination Report ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) IR 05000400/20230062024-02-28028 February 2024 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2023006 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000400/20243012024-02-21021 February 2024 – NRC Operator Licensing Examination Approval 05000400/2024301 IR 05000400/20230042024-01-30030 January 2024 Integrated Inspection Report 05000400/2023004 ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230032023-11-0909 November 2023 Integrated Inspection Report 05000400/2023003 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23234A1702023-10-0303 October 2023 Issuance of Amendment No. 199 Regarding Administrative Changes to the Renewed Facility Operating License and Technical Specifications ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000400/20230052023-08-23023 August 2023 Updated Inspection Plan for Shearon Harris Nuclear Power Plant, Unit 1 (Report 05000400/2023005) ML23234A2542023-08-22022 August 2023 RQ Inspection Notification Letter IR 05000400/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000400/2023402 IR 05000400/20230022023-07-24024 July 2023 Integrated Inspection Report 05000400/2023002 IR 05000400/20234402023-07-17017 July 2023 Special Inspection Report 05000400/2023440 and Preliminary Greater than Green Finding and Apparent Violation Cover Letter IR 05000400/20230012023-05-10010 May 2023 Integrated Inspection Report 05000400 2023001 IR 05000400/20234042023-05-0404 May 2023 Cyber Security Inspection Report 05000400/2023404 ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML23118A1392023-04-28028 April 2023 Submittal of Updated Final Safety Analysis Report (Amendment 65), Technical Specification Bases Revision, Report of Changes Pursuant to 10 CFR 50.59 and Summary of Commitment Changes IR 05000400/20234032023-04-0505 April 2023 Security Baseline Inspection Report 05000400/2023403 IR 05000400/20230102023-03-15015 March 2023 Comprehensive Engineering Team Inspection (CETI) Inspection Report 05000400/2023010 ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000400/20220062023-03-0101 March 2023 Annual Assessment Letter for Shearon Harris Nuclear Power Plant - NRC Inspection Report 05000400/2022006 ML23033A5272023-02-0808 February 2023 Correction of Typographical Errors Incurred During Issuance of License Amendment No. 196 IR 05000400/20220042023-02-0707 February 2023 Integrated Inspection Report 05000400/2022004 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000400/20220032022-11-10010 November 2022 Integrated Inspection Report 05000400/2022003 IR 05000400/20223012022-11-0202 November 2022 NRC Operator License Examination Report 05000400/2022301 2024-09-10
[Table view] |
Inspection Report - Harris - 2006008 |
---|
|
|
Text
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT- NRC EMERGENCY PREPAREDNESS INSPECTION REPORT 50-400/2006008
Dear Mr. Gannon:
On April 3-7, 2006, the US Nuclear Regulatory Commission (NRC) completed an inspection at your Harris Plant. The enclosed inspection report documents the inspection findings, which were discussed on April 3-7, 2006, with Mr. Edward Wills and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection no findings of significance were identified. However, a licensee identified violation which was determined to be of very low significance is listed in the report. The NRC is treating the violation as a non-cited violation (NCV) consistent with Section VI.A of the NRC Enforcement Policy because of the very low significance of the violation and because it is centered into your corrective action program. If you contest this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator Region II; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at Shearon Harris Nuclear Power Plant.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publically Available Records (PARS)
component of NRCs document system (ADAMS). To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be
CP&L 2 placed in the PDR and PARS without redaction. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Brian R. Bonser, Chief Plant Support Branch 2 Division of Reactor Safety Docket Nos.: 50-400 License Nos: NPF-83
Enclosure:
Inspection Report 05000400/2006008 w/Attachment: Supplemental Information
REGION II==
Docket Nos.: 50-400 License Nos.: NPF-63 Report No: 05000400/2006008 Licensee: Progress Energy Facility: Shearon Harris Nuclear Power Plant Location: 5421 Shearon Harris Road New Hill, NC 27562-9998 Dates: April 3-7, 2006 Inspectors: Lee Miller, Senior Emergency Preparedness Inspector (Section 1EP2, 1EP3,1EP4, 1EP5, 4OA1)
Approved by: Brian R. Bonser, Chief Plant Support Branch 2 Division of Reactor Safety Enclosure
SUMMARY OF FINDINGS
IR No. 05000400/2006008; 04/03/2006 - 04/07/2006; Harris Nuclear Power Plant; Emergency
Preparedness The report covered a one week announced inspection be a regional senior emergency preparedness inspector. The significance of most findings is indicated by their color (Green,
White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after the NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUNREG-1649, Reactor Oversight Process, Revision 3, dated July 2000.
NRC-Identified and Self-Revealing Findings
Cornerstone: Emergency Preparedness
No findings of significance were identified.
Licensee-Identified Violations
.
Violations of very low safety significance, which were identified by the licensee have been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. These violations and corrective actions are listed in Section 4OA7 of this report.
REPORT DETAILS
REACTOR SAFETY
Cornerstone: Emergency Preparedness
1EP2 Alert and Notification System Testing
a. Inspection Scope
The inspectors evaluated the adequacy of licensee methods for testing the alert and notification system in accordance with NRC Inspection Procedure 71114, Attachment 02, Alert and Notification System (ANS) Testing. The applicable planning standard 10 CFR Part 50.47(b)(5) and its related 10 CFR Part 50, Appendix E, Section IV.D requirements were used as reference criteria. The criteria contained in NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants, Revision 1, was also used as references.
The inspectors reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
1EP3 Emergency Response Organization (ERO) Augmentation
a. Inspection Scope
The inspectors reviewed the ERO augmentation staffing requirements and the process for notifying the ERO to ensure the readiness of key staff for responding to an event and timely facility activation. The results of the 03/14/2006 unannounced off-hours augmentation drill was reviewed. The inspectors conducted a review of the backup notification systems. The qualification records of key position ERO personnel was reviewed to ensure all ERO qualifications were current. A sample of problems identified from augmentation drills or system tests performed since the last inspection were reviewed to assess the effectiveness of corrective actions.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, 03, Emergency Response Organization (ERO) Augmentation Testing.
The applicable planning standard, 10 CFR 50.47(b)(2) and its related 10 CFR 50, Appendix E requirements were used as reference criteria.
The inspectors reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
1EP4 Emergency Action Level (EAL) and Emergency Plan Changes
a. Inspection Scope
The inspectors evaluated the associated 10 CFR 50.54(q) reviews associated with non-administrative emergency plan, implementing procedures and EAL changes. The revision 50 of the Emergency Plan covered the period from 03/22/2005 to 04/07/2006.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, 01, Emergency Action Level and Emergency Plan Changes. The applicable planning standard, 10 CFR 50.47(b)(4) and its related 10 CFR 50, Appendix E requirements were used as reference criteria. The criteria contained in NUMARC/NESP-007, Methodology for Development of Emergency Action Levels, Revision 2, Regulatory Guide 1.101 were also used as references.
The inspectors reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
1EP5 Correction of Emergency Preparedness Weaknesses and Deficiencies
a. Inspection Scope
The inspectors reviewed the corrective actions identified through the EP program to determine the significance of the issues and to determine if repeat problems were occurring. The facilitys self-assessments and audits were reviewed to assess the licensees ability to be self-critical, thus avoiding complacency and degradation of their EP program. In addition, inspectors review licensees self-assessments and audits to assess the completeness and effectiveness of all EP-related corrective actions.
The inspection was conducted in accordance with NRC Inspection Procedure 71114, 05, Correction of Emergency Preparedness Weaknesses and Deficiencies. The applicable planning standard, 10 CFR 50.47(b)(14) and its related 10 CFR 50, Appendix E requirements were used as reference criteria.
The inspectors reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
OTHER ACTIVITIES
4OA1 Performance Indicator (PI) Verification
a. Inspection Scope
The inspectors reviewed the licensees procedure for developing the data for the Emergency Preparedness PIs which are:
- (1) Drill and Exercise Performance (DEP);
- (2) ERO Drill Participation; and
- (3) ANS Reliability. The inspectors examined data reported to the NRC for the period 01/01/2005 to 12/31/2005. Procedural guidance for reporting PI information and records used by the licensee to identify potential PI occurrences were also reviewed. The inspectors verified the accuracy of the PI for ERO drill and exercise performance through review of a sample of drill and event records. The inspectors reviewed selected training records to verify the accuracy of the PI for ERO drill participation for personnel assigned to key positions in the ERO. The inspectors verified the accuracy of the PI for alert and notification system reliability through review of a sample of the licensees records of periodic system tests.
The inspection was conducted in accordance with NRC Inspection Procedure 71151, Performance Indicator Verification. The applicable planning standard, 10 CFR 50.9 and NEI 99-02, Revision 3, Regulatory Assessment Performance Indicator Guidelines, were used as reference criteria. This inspection activity represents three samples on an annual basis.
The inspectors reviewed various documents which are listed in the Attachment to this report.
b. Findings
No findings of significance were identified.
4OA6 Meetings, including Exit
On April 7, 2006, the inspector presented the inspection results to Mr. E. Willis, Manager
- Operations, and other members of his staff acknowledged the findings. The team lead stated that additional information would be accepted and reviewed. The inspectors confirmed that proprietary information was not provided or taken during the inspection.
4OA7 Licensee-Identified Violations
The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements which meet the criteria of Section VI of the NRC Enforcement Policy, NUREG-1600, for being dispositioned as an NCV.
10CFR50.47(b)(5) requires in part that the public alert and notification system meets the design requirements of FEMA-REP-10 or is compliant with FEMA approved Alert and Notification System (ANS) design report and supporting FEMA approval letter.
Contrary to this, on January 24, 2006, during a review of the Harris Plant tone alert radio database, it was discovered that 92 addresses in the 5 mile radius of the Harris Nuclear Plant did not have tone alert radios. This was identified in the licensees Corrective Action Program, Action Request Number: 182074, tone alert radios not in all residences as required by the E Plan. This finding is of very low safety significance because the licensee demonstrated that all of the 92 addresses could be notified with backup route alerting within 45 minutes and the licensee took prompt action to deliver tone alert radios to the 92 homes. The last radio was delivered on February 1, 2006.
ATTACHMENT: Supplemental Information
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee personnel
- E. Wills, Manager Operations
- P. Fulford, Manager - Nuclear Assessment
- D. Corlett, Supervisor - Licensing/Regulatory Programs
- T. Pilo, Emergency Preparedness Supervisor
- M. Janus, Lead Assessor - Nuclear Assessment
- J. Dills, Maintenance - Superintendent
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Openned None Openned and
Closed
None
Closed
None Attachment
LIST OF DOCUMENTS REVIEWED