IR 05000400/1992022
| ML18010A808 | |
| Person / Time | |
|---|---|
| Site: | Harris |
| Issue date: | 09/30/1992 |
| From: | Blake J, Kleinsorge W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML18010A807 | List: |
| References | |
| 50-400-92-22, GL-89-08, GL-89-8, IEIN-88-048, IEIN-88-48, IEIN-91-031, IEIN-91-31, NUDOCS 9210140053 | |
| Download: ML18010A808 (13) | |
Text
~y,8 REGII, P0 nO
I qP
+**++
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTASTREET, N.W.
ATLANTA,GEORGIA 30323 Report Nos.:
50-400/22 Licensee:
Carolina Power and Light Company P. 0.
Box 1551 Raleigh, NC 27602 Docket Nos.:
50-400 Facility Name:
Inspection n
License Nos.:
'NPF-63 September-25, 1992 Inspector:
W nsorge P
a t I spec ate Signed Appro d by:
j J.J.
B k
, Chief Materials and Process Section Engineering Branch Division of Reactor Safety ate igned SUMMARY Scope:
'This routine, announced inspection was conducted in the area of
, Inservice Inspection (ISI).
In addition the following areas
.were examined:
Followup on NRC Generic Letter (GL) 89-08
"Erosion/Corrosion-Induced Pipe Wall Thinning";
NRC Information Notices (IN):
88-48 "Licensee Report of Defective Refurbished Valves" and 91-31 "Nonconforming Magnetic Particle (14AM)
Prepared Bath."
Results:
In each of the areas examined the inspector discovered that nondestructive test (NDE) examiners were conduct'ing conservative examinations in accordance with the appropriate test procedure.
NDE procedures were also noted to be very detailed, well organized and technically effective in implementing the applicable code requirements.
Supervisors, engineers, and NDE examiners contacted during this inspection were very knowledgeable in their areas of responsibility.
9210140053 921006 PDR ADOCK 05000400
It appears that the licensee has established an effective program to 'maintain high energy carbon steel piping systems within.
acceptable.wall thickness limits.
The licensee has taken appropriate actions, in response to IN Nos.
88-48 and 91-31, although the actions taken with respect to IN 88-48 were not well documente REPORT DETAILS Persons Contacted, Licensee Employees
- E ~
- J
- R.
- L
- C
- C
- M.
- L
- D
- T
- J
- J
- C
- C
- L
- W.
- G
- G
- E
- L Black, Nondestructive Examination (NDE) Unit Collins, Manager, Operations Connolly, Quality Assurance (QA) Engineer Costello, NED-HESS Gibson, Manager, Programs and Procedures Hinnant, General Manager, Harris Plant Hamby, Project Specialist Regulatory Compliance Lee, NED-HESS Meleg, Project Specialist-NDE Services Morton, Manager, Maintenance Moyer, Manager, Project Assessment Nevill; Manager, Technical Support Osman, Principal NDE Specialist-NDE Service Unit Olexik, Manager, Regulatory Compliance Rowell, Project Engineer-Nuclear Engineering-Seyler, Assistant to Site Manager Tucker, Specialist Technicial Support Vaughn, Vice President, Harris Nuclear Project Willett, Manager, Outages and Modifications Woods, Manager System Engineers Other licensee employees contacted during this inspection included craftsmen, engineers, technicians, and administrative personnel.
NRC Resident Inspector(s)
- J. Tedrow, Senior Resident Inspector (SRI)
- M. Shannon, Resident Inspector (RI)
- Attended exit interview Inservice Inspection (ISI)
The inspector reviewed documents and records, and observed activities, as indicated below, to determine whether ISI was being conducted -in accordance with applicable procedures, regulatory requirements, and licensee commitments.
The applicable code for ISI, for the plant is the American Society of Mechanical Engineers Boiler and Pressure Vessel (ASME BRPV)
Code,Section XI, 1983 Edition with Addenda through Summer 1983 (83S83)
.
The plant has completed the fourth fuel cycle, and is in the second outage of the second 40 month period, of the first ten year ISI interval
(I1,P2,02).
The plant received its operating license January 12, 1987 and commenced commercial operations on May 2,
1987.
The licensee has contracted with Nuclear Energy Services Inc (NES) to perform liquid penetrant (PT),
magnetic particle (MT), and ultrasonic (UT) examinations under the umbrella of the NES Quality Assurance (QA)
program.
a
~
ISI Program Review, (73051)
The inspector reviewed the following documents relating to the ISI program to determine whether the plan had been approved by the licensee and to assure that proce-dures and plans had been established for the applicable activities.
Documents were reviewed for technicial content.
Documents Reviewed ZD Revision Title NES-83A5462 NES-80A9003 CPEcL (RO)
(R13)
Quality Assurance program Plan For Inspection Related Services For Carolina Power And Light NES Document Control Inservice Inspection Program Plan-First Interval CPEcL (R1)
Inspection Checklist Report Welds For Outage 1-2-4 b.
Review of NDE Procedures, (73052)
The inspector reviewed the procedures listed below to determine whether these procedures were consistent with regulatory requirements and licensee commitments.
The procedures were also reviewed for technical content.
ID Procedures Reviewed Revision Title NES-83A6113 (R1)
Magnetic Particle Examination for Shearon Harris Nuclear Power Plant
Documents Reviewed Cont.
ID Revision
~Title NES-83A0281 (R2,AD3)
Liquid Penetrant Examination (Color Contrast, Solvent Removable)
NES-83A6013
(R1,FC1)
Ultrasonic Examination of Piping Systems for Shearon Harris Nuclear Power Plant NES-83A0291 NES-83A0283 (R3)
(R1)
Visual Examination Procedure for Nuclear Power Systems and Related Components.
PSI/ISI Examination Areas and Volumes NES-80A9068 (R9)
Procedure for Certifying Nondestructive Examination Personnel NES-80A9084 (R6)
NES-80A9052 (R9)
NES-80A9054 (R5)
NES-80A9055 (R5)
Nondestructive Examination Procedure Qualification Ultrasonic Instrument Linearity Verification Calibration of Magnetic Par'ticle Examination Equipment Calibration of Thermometers Relative to the review above the inspector noted the following:
NES visual examination procedure 83A0291, R3 does not make provisions to assure the inclusion of an audio or video statement, on video tapes, indicating inspection type and the identification of the item being examined.
Observation of Work and Work Activities, (73753)
The inspector observed work activities, reviewed certification records of NDE equipment and materials, and reviewed NDE personnel qualifications for personnel who had been utilized in the ISI examinations during this outage.
The observations and reviews conducted by the inspector are documented belo Activities Observed Liquid Penetrant Examination (PT)
The inspector observed PT examinations of piping welds listed below.
The inspector performed an independent evaluation of the indications obtained to confirm the NDE examiner's evaluation.
Liquid Penetrant Examinations Observed Weld No.
1-CT-12-5-SW-1 1-CT-SW-ES 1-CT-SW-ESA System Containment Spray Containment Spray Containment Spray The inspector reviewed the certification documentation for penetrant Batch No.90H03K, developer Batch No.
92E02K and cleaner Batch No 92C02K.-
The inspector reviewed the certification, qualification, and visual acuity documentation for PT-II examiners DM and JKM, and PT-III SL.
The examinations were performed satisfactorily, Magnetic Particle (MT) Examination The inspector observed the MT examination of the weld listed below.
The inspector performed an independent evaluation of the indications obtained to confirm the NDE examiner's evaluation.
Magnetic Particle Examinations Observed Weld No.
1-FW-SW-A3 System Feedwater The inspector reviewed the certification documentation for Red MT powder Batch No.
SSL063, yoke 415 and
Lbs. test weight No.SRO-MT-001.
The inspector reviewed the certification, qualification, and visual acuity documentation for MT-II examiners VG, SL and TJA.
The examination was performed satisfactoril Ultrasonic (UT) Examination The inspector observed the UT examination of the welds listed.below.
The inspector performed an independent evaluation of the indications obtained to confirm the NDE examiner's evaluation.
Ultrasonic Examinations Observed Weld No.
1-FW-39-3-SW-1 1-FW-39-4-SW-1 System Feedwater Feedwater The'inspector reviewed the certification documentation for the following:
Calibration Block No. UT-30-1; Rompas Block No. 87-4879; Ultrasonic Instrument Nos.
27276-3409 and 27276-3784; transducer Nos.
K150022 and B25120; and ultrasonic coupelent batch Nos.
9092.
The inspector reviewed the certification, qualification, and visual acuity documentation for UT-II examiners VG and SS and UT-III examiners SL and EMB.
(CPEcL).
The examinations were performed satisfactorily.
Data Review and Evaluation Unit 1 (73755)
The inspector also reviewed completed ultrasonic data of welds where recordable indications had been detected to determined if the indications were properly interpreted and dispositioned.
The inspector also reviewed baseline data of the welds to determine whether the indications were previously recorded and if so, were there any noticeable differences in the recorded information.
Records for the following welds were reviewed:
Examination Records Examined Weld No.
1-MS-SW B4 1-MS-SW-B5 1-MS-SW-B35 System Main Steam Main Steam Main Steam The inspector reviewed the last audit conducted in the area of ISI which was included in the Audit Report No.
QAA/0022-90-04 dated 10/19/90,
"Harris Nuclear Project Maintenance Program".
In addition the inspector reviewed the surveillance reports for NDE activities conducted during Refueling Outage 3.
The licensee conducted 19 MT,
PT and
UT examinations during
RF03 but only conducted 10 UT surveillances.
As plants age the importance of surface inspections increases because of the increased likelihood of component failure by fatigue.
the licensee should consider conducting some surveillances in the surface examination area.
Within the areas examined, no violations or deviations were identified.
Followup (92701)
a
~
NRC Generic Letter (GL) 89-08:
"Erosion/Corrosion-Induced Pipe Wall Thinning" This GL requested licensees to provide assurances that a long term Erosion/Corrosion (E/C) monitoring program, has been established to ensure that E/C does not lead to degradation of carbon steel piping in single and two phase high energy piping systems.
The licensee has established an E/C inspection program which uses the CHECMATE EPRI (Electric Power Research Institute) computer'rogram, industry experience, and previous inspection data as predictive tools for determining and prioritizing inspection locations.
The licensee's CHECMATE electronic model for the seven chosen piping systems is complete.
Currently the licensee is not using the T-Dat portion of the CHECKMATE program.
The program is implemented by CPEL procedure ISI-107,
"HNP Flow Accelerated Corrosion (FAC) Monitoring Program".
The inspector reviewed the licensee's program, examined marked grids, observed data collection, interviewed licensee personnel and reviewed inspection data and calculations to evaluate the licensee's E/C program.
Observations/Findings The inspection sample is selected on an outage by outage basis, based on the data from previous outages.
The licensee has tested approximately 350 test locations.
Of these, 155 have been inspected more than once.
During this outage, RFO4, the licensee intends to test 182 locations.
As a result of the Erosion
/Corrosion Program the licensee has replaced
fitting Documents Reviewed ID Revision CP&L-ISI-107 (R3)
CP&L-ISI-107 (R4)
CP&L-NDEP-427 (RO)
CP&L-.NDEP-1012 (RO)
.Title I
SHNPP Erosion/Corrosion Program HNP Flow Accelerated Corrosion (FAC) Monitoring Program Digital Ultrasonic Thickness Measurement (Panametrics Model 26DL Plus)
For Erosion/Corrosion Detection and Monitoring'ridding Of Components For Erosion/Corrosion The gridding layout scheme used by the licensee is consistent with the EPRI CHECMATE recommendations with the following exceptions:
P Approximately 10% to 15~ of the total test locations on elbows were established prior to the EPRI recommendations and differ in that they have uniform square blocks vice trapezoidal blocks.
The licensee intends to maintain that scheme for those fittings to assure trending continuity.
.Procedure ISI-107 makes no special provisions for diffusers and expanding elbows.
EPRI CHECMATE manual Appendix A, recommends that an area of two pipe diameters upstream of those fittings be tested.
This recomendation is based on EPRI test data which indicates that E/C can occur upstream of diffusers and expanding elbows..
ISI-107, R3, paragraph Nos. 3.6 and 5.5.1 require contractor to perform applicable ultrasonic examinations in accordance with the. requirements of Attachment 6.6.
Attachment 6.6 addresses the technique requirements for the Panametrics Model 26 DL thickness gauge.
The licensee is currently using the Panametrics Model 26DL Plus in accordance with procedure NDEP-427.
Although the Panametrics Model 26DL Plus is an improvement and its accompanying procedure NDEP-427 has been approved by a CP&L UT Level III, the licensee failed to make any administrative provisions authorizing the use of NDEP-427.
The above is corrected in ISI-107 R4, which was issued expeditiously
after the inspector discussed. this matter with the licensee.
'Not withstanding the above,'t appears that the licensee has established an effective program to maintain high energy carbon steel piping systems within'ode allowable wall thickness limits; b.
NRC Information Notice (IN) 88-48:
"Licensee Report of Defective Refurbished Valves" In this IN and the two associated supplements, the staff discussed a problem identified by Pacific Gas and Electri.c Company (PGEE)
when a counterfeit valve was installed in a non-safety related (NSR) system.
The licensee (PGRE) believed the valve was manufactured by Heniy Vogt Company.
The licensee performed a record review and determined that;they had'ot bought any refurbished SR or NSR valves from the listed suppliers.
It should be noted that this information was obtained by interviews with licensee personnel, as the licensee had not documented well their actions in regards to thi's issue.
The licensee indicated that they would amend their package to better address this issue.
The licensee has taken appropriate action in response to this IN.
C.
NRC Information Notice (IN) 91-31:
"Nonconforming Magnetic Particle (14AM) Prepared Bath" This IN transmitted a Magnaflux Notice which recalled three batches of 14AM MT aerosol prepared bath, and included a warning for six others.
The licensee reviewed their records and determined that the Harris site has never received any of the material identified in the IN.
The licensee has taken appropriate action in response to this IN.
In the areas inspected, no violations or deviations were identifie Cl
Exit Interview The inspection scope and results were summarized on September 25, 1992, with those persons indicated in paragraph 1.
The inspector described the areas inspected.
Although reviewed during this inspection, proprietary information is not contained in this report.
Dissenting comments were not received from the licensee.
Acronyms and Initialisms ASME BEcPV CPEcL E/C EPRI FAC GL ID ISI IN MT NDE NES No.
NPF NRC NSR P.E.
RFO RI SR SRI UT American Society of Mechanical Engineers Boiler and Pressure Vessel Carolina Power and Light Erosion/Corrosion Electric Power Research Institute Flow Accelerated Corrosion NRC Generic Letter Identification Inservice Inspection NRC Information Notice Magnetic Particle Nondestructive Examination Nuclear Energy Services Number Nuclear Power Facility Nuclear Regulatory Commission Non Safety-Related Professional Engineer Pacific Gas and Electric Company Liquid Penetrant Quality Assurance Revision Refueling Outage Resident Inspector Safety Related Senior Resident Inspector Ultrasonic