IR 05000397/1979002
| ML17272A354 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 02/16/1979 |
| From: | Carlson J, Johnson P, Sternberg K NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | |
| Shared Package | |
| ML17272A353 | List: |
| References | |
| 50-397-79-02, 50-397-79-2, NUDOCS 7903300349 | |
| Download: ML17272A354 (8) | |
Text
U, S.
NUCLEAR REGULATORY COl'INISSION OFFICE OF INSPECTION AND ENFORCEMENT REGION Y R 9
. ~gtl-997 79-Ilt Docket No.
50-397 License No.
CPPR-93 Safeguards Group Licensee:
llashinqton Public Power Su
S stem P. 0.
Box 968 Richland, llashington 99352 Facility Name:
Mashington Nuclear Project No.
(MNP.-2)
Inspection at:
MNP-2 Site, Benton County, Washington Inspection onducted:
January 30 - February 1, 1979 Inspectors:
.
H. John ea or Inspector
g J
D.
Ca lson, Reactor Inspector Date Signed
"Approved By:
'Summary:
>8
D. M. Sternberg, Chief; Reactor Project Section 1, Reactor Operations and-Nuclear Support Branch r
'Ins ection on Januar 30 - Februar 1, 1979 Re ort No. 50-397/79-02 A~ltd:
R I, dt
RI f
p tf I tftg, quality assurance for preoperational testing, and resolution of comments on-overall preoperational test program (see Report No. 50-397/78-08).
The inspection involved 39 inspector hours onsite by two.NRC inspectors.
Results:
No deviations or items of noncompliance were identified.
> S 0 3 3 0 0 3gcI IE:V Form 219. (2)
~ '
I i'~
DETAILS 1.
Per sons Contacted
- J. D. Martin, Startup and Operations Manager
- D. L. Howard, WPPSS Operational gA Manager
- A. M. Sastry, Project gA Manager
- J. R. Holder, Assistant Superintendent
- G. K. Afflerbach, Supervising Test Engineer
- J. F. Peters, Startup Administrative Supervisor
- R. L. Corcoran, Principal Operations Engineer
- R. 0. Hurd, Principal Test Engineer J.
W. Hedges, Maintenance Supervisor
- S. L. Washington, Operational OA Engineer R. D. Davidson, Training Coordinator The inspectors also talked with other licensee personnel, including test engineers and plant operators.
- Present at Exit Interview.
2.
0 erational Staffi~n The inspector reviewed the qualifications for the remainder of the operations staff (see Report No. 78-13) except for the Plant Superintendent, who has not been appoin'ted, and staff welders, who are being qualified at the present time.
gualifcations of the staff wer e reviewed against ANSI N18.1 for minimum education and experience.
Additional staff review will be performed when plant
.staffing and training are completed.
No deviations or items of noncompliance were identified.
3.
gualit Assurance For Preo erational Testin The inspector reviewed implementation of portions of the guality Assurance Program applicable to preoperational testing (see Report No. 78-08 for program review).
Due to schedule slippage, little preoperational testing has been performed.
It was noted that an operational gA audit schedule for 1979 had not been issued.
The licensee committed in the exit interview to prepare an audit
'schedule for 1979.
No deviations or items of noncompliance were identifie.
Overall Prep erational Test Pro ram Review This inspection included followup on the inspection findings discussed in Inspection Report No. 78-08, as follows:
(78-08-01, Closed)
Review of test categor ies:
The licensee had reviewed system lineup and acceptance tests to determine whether any were within the scope of preoperational testing as defined by Regulatory Guide 1.68.
The inspector determined from review of the Preoperational Test Index that a number of procedures had been r edesignated Preoperational Test Procedures (POTPs).
(78-08-02, Open) Interfaces with test personnel:
The interface between test and operating personnel, particularly between the test erigineer and the shift supervisor,'ill be defined in a pending revision to Section 8.6 of the Test and Startup Program Manual (TSPM}.
(78-08-03, Open) Test organization changes:
The applicant stated that an update to the FSAR was in progress.
(78-08-04, Closed)
Pre-test procedure review:
The applicant had revised Test and Startup Instruction (TSI) Section 8 to describe the timing of preperformahce review of approved pre-operational test procedures (POTPs) consistent with Section 14.2.4.1.1 of the FSAR; (78-08-05, Open) Briefing of test personnel:
The applicant was incorporating pre-test briefing requirements into a pend-ing revision of TSPM; Section 8.6.1.
- (78-08-06, Open) Test interruptions:
Documentation of test interruptions will be discussed in a pending revision of TSPM, Section 8.6.8.
(78-08-07, Open) Resolution of problems:
The applicant was planning a revision to TSP-9 of the TSPM, which will define a test result not satisfying acceptance criteria to be a
deficiency.
TSP-9 would then require the item to be docu-mented and resolved on a Startup Problem Report form.
(78-08-08, Open) Distribution control:
The applicant had established procedures defining document control measures to be applied to prints, equipment manuals, and test procedures; however, the related'procedure (TSI 8.1, Paragraph 4.3) treated only the master copy of approved POTPs, and did not define what distribution of'OTPs is to be made and what controls are to be applied to that distribution.
The applicant stated that dis-tribution of POTP's would be included in the procedur (78-08-09, Closed)
Jumper contro1:
The applicant had revised TSI 13.1 to require mechanical jumpers, strainers, and other t'emporary conditions not specifically installed and removed in accordance with an approved procedure to be caution tagged in accordance with TSI 10.1.
The format of flushing procedures was also noted to provide control of temporary mechanical system attachments, with signatures required to verify installation and removal.
(78-08-10, Closed) Cleanliness of plant systems:
Neasures to control cleanliness of plant systems during the preopera-tional test phase were included in the facility's flushing program instructions and were incorporated by reference into TSI 12.1.
During review of the followup items discussed above, the inspector noted that Section 8.5.3 of the TSPN calls for the Startup Program Hanager to approve performance of preoperational test procedures,
whereas Section 14.2.4.1.1 of the FSAR requires this approval to be given by the Test Working Group.
The applicant also indicated an intent to delegate this authority to the Supervising Test Engineer.
The inspector expressed no concern about the licensee's intent so long as the FSAR is revised accordingly.
The applicant stated that the FSAR and TSPM would be made consistent with one another.
(79-02-01)
No deviations or items of noncompliance. were identified.
5.
Exit Inter view The inspectors met with 1JPPSS representatives (denoted in Paragraph 1)
on February 1, 1979.
The scope of the inspectioh was discussed as identified in Paragraphs 2, 3, and 4.
During the interview, the applicant confirmed that a copy of all approved preoperational test procedures (POTPs) will be forwarded to the inspectors,