IR 05000369/2021004

From kanterella
Jump to navigation Jump to search
Mcguire Nuclear Station - Integrated Inspection Report 05000369/2021004 and 05000370/2021004
ML22026A344
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 01/26/2022
From: Eric Stamm
NRC/RGN-II/DRP/RPB1
To: Teresa Ray
Duke Energy Carolinas
References
IR 2021004
Download: ML22026A344 (11)


Text

January 26, 2022

SUBJECT:

MCGUIRE NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000369/2021004 AND 05000370/2021004

Dear Mr. Ray:

On December 31, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at McGuire Nuclear Station. On January 18, 2022, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Eric J. Stamm, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 05000369 and 05000370 License Nos. NPF-9 and NPF-17

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000369 and 05000370

License Numbers:

NPF-9 and NPF-17

Report Numbers:

05000369/2021004 and 05000370/2021004

Enterprise Identifier:

I-2021-004-0011

Licensee:

Duke Energy Carolinas, LLC

Facility:

McGuire Nuclear Station

Location:

Huntersville, North Carolina

Inspection Dates:

October 1, 2021 to December 31, 2021

Inspectors:

A. Hutto, Senior Resident Inspector

C. Scott, Resident Inspector

N. Peterka, Fuel Facility Inspector

M. Meeks, Senior Operations Engineer

Approved By:

Eric J. Stamm, Chief

Reactor Projects Branch 1

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at McGuire Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 operated at or near 100 percent rated thermal power (RTP) for the entire inspection period.

Unit 2 began the inspection period shut down for a scheduled refueling outage. The unit was brought on-line on October 11, 2021, and returned to 100 percent RTP on October 15, 2021, and remained at or near 100 percent RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, conducted routine reviews using IP 71152, Problem Identification and Resolution, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated that flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on October 18, 2021.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)1A diesel generator, on October 12, 2021 (2)1A motor driven auxiliary feedwater system, on October 28, 2021

(3) Unit 1/2 channel "D" vital AC and DC instrument power, on November 4, 2021

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the Unit 1 service water system, on December 14, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Shutdown safety facility (fire area SSF) on December 13, 2021
(2) Emergency supplemental power supply (fire area YRD) on December 13, 2021
(3) Unit 1 cable spread room on December 14, 2021
(4) Units 1 and 2 main control room on December 20, 2021

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Units 1 and 2 diesel generator rooms

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 2B component cooling water heat exchanger

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) Annual Review of Licensee Requalification Examination Results: On November 8, 2021, the facility licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), Requalification Requirements, of the NRCs Operators Licenses. During the week of December 13, 2021, the inspectors performed an in-office review of the overall pass/fail results of the individual operating examinations and the crew simulator operating examinations in accordance with Inspection Procedure (IP) 71111.11, Licensed Operator Requalification Program. These results were compared to the thresholds established in Section 03.03, Requalification Examination Results, of IP 71111.11.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during Unit 2 reactor startup following refueling outage M2R27, on October 10, 2021.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated Cold Crew Exam - 3, involving a failed pressurizer power operated relief valve, a loss of condenser vacuum, a turbine trip, a failed reactor coolant pump, and a small break loss of coolant accident, on October 20, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Nuclear condition report (NCR) 2397076, inadequate quantity of hydrogen igniters to complete scope of work

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Equipment protection plan for Unit 2 spent fuel pool cooling time to 200 degrees Fahrenheit, on October 14, 2021
(2) Equipment protection plan for "B" control room air handling unit bearing failure, on October 26, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) NCR 2401165, 2D reactor coolant flow, 2NCFT5090, issues during M2R27, on October 19, 2021
(2) NCR 2404495, "B" control room air handling unit (0VCAH0002) start pushbutton stuck out, on November 9, 2021
(3) NCR 2405373, gas present during emergency core cooling system venting of 2ND-121, on November 16, 2021
(4) NCR 2405536, standby shutdown facility (SSF) fuel oil tank showed presence of water, on November 30, 2021
(5) NCR 2407993, Unit 2 reactor coolant system core exit thermocouple at location J02 reading less than Tcold, on December 15, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) TT/2/A/9700/414, "Diesel Load Sequencer 2B Cutler-Hammer Relay Replacement Functional Verification," following sequencer circuit modifications, on October 1, 2021
(2) PT/0/A/4150/028, "Initial Criticality and Zero Power Physics Test," following core reload, on October 13, 2021
(3) OP/0/A/6450/011, "Control Area Ventilation/Chilled Water System," following replacement of "B" control room air handler unit bearing, on October 27, 2021
(4) PT/0/A/4200/002, "SSF Operability Test," following SSF diesel preventive maintenance (PM), on November 26, 2021

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated Unit 2 refueling outage M2R27 activities from October 1, 2021, to October 15, 2021.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Ice Condenser Testing (IP Section 03.01)

(1) PT/0/A/4200/018, "Ice Bed Analysis," on October 7,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1 (October 1, 2020 through September 30, 2021)
(2) Unit 2 (October 1, 2020 through September 30, 2021)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (October 1, 2020 through September 30, 2021)
(2) Unit 2 (October 1, 2020 through September 30, 2021)

71152 - Problem Identification and Resolution (PI&R)

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in equipment reliability that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) NCR 2408566, 1VNHGH021/1-MCA-VN-H021: Investigate/repair snubber

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On January 18, 2022, the inspectors presented the integrated inspection results to Tom Ray and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

AP/0/A/5500/044

Plant Flooding

Drawings

MCFD-1592-

01.01

Flow Diagram of Auxiliary Feedwater System (CA)

OP/1/A/6250/002

Auxiliary Feedwater System

OP/1/A/6400/006

A

Nuclear Service Water System Valve Checklists

71111.04

Procedures

OP/2/A/6350/002

A

Diesel Generator

Calculations

MCC-1535.00-00-

00-0106

MNS Fire PRA Summary Report Calculation

CSD-MNS-PFP-

AB-0767-001

Auxiliary Building Elev. 767

Fire Plans

CSD-MNS-PFP-

SRV-0739-001

Service Building Elevation 739 Pre-fire Plan

71111.05

Procedures

AD-EG-ALL-1520

Transient Combustible Control

71111.06

Procedures

AP/0/A/5500/044

Plant Flooding

NDE Reports

MG-NDE-ET-002

2KCHX006 Eddy Current Inspection Results

71111.07A

Work Orders

WO 20440813

PM-2KCHX0006-(2B) Clean/Inspect/Eddy Current Test

71111.11Q

Procedures

AD-OP-ALL-1000

Conduct of Operations

AD-EG-ALL-1204

Single Point Vulnerability Identification, Elimination and

Mitigation

AD-EG-ALL-1206

Equipment Reliability Classification

AD-EG-ALL-1209

System, Component, and Program Health Reports and

Notebooks

AD-EG-ALL-1210

Maintenance Rule Program

71111.12

Procedures

AD-EG-ALL-1211

System Performance Monitoring and Trending

71111.13

Procedures

AD-OP-ALL-0201

Protected Equipment

AD-EG-ALL-1211

System Performance Monitoring and Trending

AD-OP-ALL-0102

Operability Decision Making

71111.15

Procedures

AD-OP-ALL-0105

Operability Determinations and Functionality Assessment

71111.19

Procedures

AD-EG-ALL-1155

Post Modification Testing

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

OP/0/A/6450/011

Control Area Ventilation / Chilled Water System

71111.22

Procedures

AD-WC-ALL-0250

Work Implementation and Completion

AD-LS-ALL-0004

NRC Performance Indicators and Monthly Operating Report

71151

Procedures

AD-PI-ALL-0100

Corrective Action Program

AD-LS-ALL-0006

Notification/Reportability Evaluation

AD-PI-ALL-0100

Corrective Action Program

71152

Procedures

AD-PI-ALL-0105

Effectiveness Reviews