IR 05000354/2019011

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000354/2019011
ML19127A094
Person / Time
Site: Hope Creek PSEG icon.png
Issue date: 05/06/2019
From: Christopher Cahill
Engineering Region 1 Branch 2
To: Sena P
Public Service Enterprise Group
References
IR 2019011
Download: ML19127A094 (21)


Text

May 6, 2019

SUBJECT:

HOPE CREEK GENERATING STATION -TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000354/2019011

Dear Mr. Sena:

On March 29, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Hope Creek Generating Station and discussed the results of this inspection with Paul Davison, Vice President - Engineering and other members of your staff. The results of this inspection are documented in the enclosed report.

NRC inspectors documented two findings of very low safety significance (Green) in this report.

These findings involved violations of NRC requirements.

The inspectors documented a licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violations or significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC resident inspector at Hope Creek.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; and the NRC resident inspector at Hope Creek.

P Sena

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Christopher G. Cahill, Chief Engineering Branch 2 Division of Reactor Safety

Docket No.: 50-354 License No.: NPF-57

Enclosure:

Inspection Report 05000354/2019011

Inspection Report

Docket Number:

05000354

License Number:

NPF-57

Report Number:

05000354/2019011

Enterprise Identifier: I-2019-011-0014

Licensee:

PSEG Nuclear, LLC

Facility:

Hope Creek Generating Station

Location:

Hancocks Bridge, NJ 08038

Inspection Dates:

March 11, 2019, to March 29, 2019

Inspectors:

J. Patel, Senior Reactor Inspector (Team Leader)

D. Kern, Senior Reactor Inspector

J. Rady, Reactor Inspector

D. Werkheiser, Senior Reactor Inspector

Approved By:

Christopher G. Cahill, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Triennial Fire Protection inspection at Hope Creek Generating Station in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.

Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. Findings and violations being considered in the NRCs assessment are summarized in the table below.

Licensee-identified non-cited violations are documented in report sections: 71111.05T.

List of Findings and Violations

Failure to Protect Automatic Start Capability of Fire Pumps Due to Fire Damage Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000354/2019011-01 Open/Closed None (NPP)71111.05T The inspectors identified a finding of very low safety significance (Green), involving a non-cited violation (NCV) of Hope Creek Generating Station (HCGS) Operating License Condition 2.C.(7) for failure to implement and maintain in effect all provisions of the approved Fire Protection Program (FPP). Specifically, PSEG did not adequately protect the automatic start capability of the motor driven and diesel driven fire pumps as described in the HCGS FPP (Updated Final Safety Analysis Reports (UFSAR) 9.5.1) due to the effects of a fire.

Inadequate Procedural Guidance to Perform Time Critical Actions Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems Green NCV 05000354/2019011-02 Open/Closed

[P.2] - Evaluation 71111.05T The inspectors identified a finding of very low safety significance (Green) involving a non-cited violation (NCV) of Hope Creek Generating Station (HCGS) License Condition 2.C.(7) for failure to implement and maintain in effect all provisions of the approved Fire Protection Program (FPP), in that procedures for shutting down the plant in response to a fire that requires main control room evacuation were not adequate. Specifically, the alternate (remote) post-fire shutdown procedures and supporting master list of time critical actions were not accurate or adequate to secure in a timely manner high pressure coolant injection (HPCI) to prevent overfilling of the reactor vessel following a spurious fire-induced start of HPCI pump and failed reactor water high-level automatic shutdown of HPCI.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.05T - Fire Protection Fire Protection Inspection Requirements (IP Section 02.02)

The inspectors evaluated fire protection program implementation in the following selected areas and/or fire zones, including analyzed electrical circuits:

(1) CD 35, Control Equipment Room Mezzanine
(2) AB1, Electrical Access Area, Division I
(3) RB1, Reactor Building, Division I
  • Room 4112, HPCI Electrical Equipment Room
  • Room 4309, SACS Heat Exchanger and Pump Room
(4) CD71, Class 1E Inverter Room

Analyzed Circuits:

  • EG-BP210, Safety Auxiliary Cooling System Pump B
  • BD-FIC-4158, RCIC Pump Flow Controller
  • SB-TE-3647J-2, Suppression Pool Indicator and Transmitter

B.5.b Inspection Activities (IP Section 02.03) (1 Sample)

The inspectors evaluated the following B.5.b Mitigating Strategies:

  • Manually Open Containment Vent Lines
  • Inject Water into the Drywell

INSPECTION RESULTS

Licensee-Identified Non-Cited Violation 71111.05T This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a Non-Cited Violation, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: HCGS License Condition 2.C.(7), in part, requires PSEG to implement and maintain in effect all provisions of the approved fire protection program as described in the UFSAR and as approved by the NRC as in the Safety Evaluation Report dated October 1984.

UFSAR Section 9.5.1.6, Standard Review Plan (SRP) Review, stated that HCGS has implemented the requirements of Branch Technical Position CMEB 9.5-1 Revision 2, dated July 1981 per NUREG 0800 (SRP 9.5.1, Revision 3) in the development of the fire protection program. Branch Technical Position CMEB 9.5-1, Section C.4.h, Corrective Action, required that measures be established to ensure that conditions adverse to fire protection are promptly identified, reported, and corrected.

Contrary to the above, from April 4, 2016, until December 4, 2018, PSEG did not promptly correct a condition adverse to fire protection associated with an issue previously documented as NCV 05000354/2016007-01, Inadequate Testing of Emergency Diesel Generator (EDG)

Takeover Switches and Remote Shutdown Panel (RSP) Transfer/Isolation Relays.

Specifically, the corrective actions created by PSEG to address this NCV did not fully resolve the identified performance deficiency of not adequately verifying or demonstrating that the EDG normal-emergency takeover switches and RSP transfer/isolation relays would perform their intended function. Therefore, the previously NRC-identified condition adverse to fire protection was not corrected and compliance was not restored.

Significance: Green.

The inspectors assessed this finding in accordance with the NRC IMC 0609, Significance Determination Process, Appendix F, Fire Protection Significance Process. In Appendix F, the inspectors answered NO to step 1.4.7-C because this finding did not adversely affect the ability to reach and maintain hot shutdown conditions using the credited safe shutdown success path. Subsequently, PSEG adequately tested EDG takeover switches and RSP transfer/isolation relays and demonstrated reasonable expectation of functionality of these switches. Therefore, based on these aspects, the finding is determined to be of very low safety significance (Green).

Corrective Action Reference: Notification 20803353

Failure to Protect Automatic Start Capability of Fire Pumps Due to Fire Damage Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000354/2019011-01 Open/Closed

None (NPP)71111.05T The inspectors identified a finding of very low safety significance (Green), involving a non-cited violation (NCV) of Hope Creek Generating Station (HCGS) Operating License Condition 2.C.(7) for failure to implement and maintain in effect all provisions of the approved Fire Protection Program (FPP). Specifically, PSEG did not adequately protect the automatic start capability of the motor driven and diesel driven fire pumps as described in the HCGS FPP (Updated Final Safety Analysis Reports (UFSAR) 9.5.1) due to the effects of a fire.

Description:

The UFSAR Section 9.5.1.2.3.2, Pumps, stated that the electric motor driven fire pump starts automatically at 110 psig of fire water system header pressure. If it fails to start or cannot meet the water flow demand, the diesel driven fire pump starts automatically when the fire water system header pressure drops to 100 psig. The fire pumps continue to operate until manually stopped at the local pump control panel. Both fire pumps can be manually started remotely from the main control room or locally within the fire pump house.

The inspectors reviewed the circuit analysis of Hope Creek's electric motor driven and diesel driven fire pumps. The inspectors noted that Hope Creek has a capability to remotely start any of the two fire pumps using the switches located in the main control room. The inspectors performed a review of cable routing associated with remote start circuits and determined that the cables associated with remote start circuit of the fire pumps could be damaged by a fire occurring in the areas between the main control room and the fire pump house, through which cables are routed. The inspectors determined that a short-to-ground fault on the remote start cables could result in a loss of capability of both fire pumps to automatically start, continue to run if already auto-started on low fire water header pressure, or to manually start from the main control room. The cables for both fire pumps are routed through three fire areas (Fire areas CD35, CD46, and AB3) in close proximity to each other.

Therefore, both pumps remote start circuit cables could be exposed to potential damage by a single fire. Fire Area CD35, Control Equipment Room Mezzanine, credits a backup manual water deluge system and water hose stations for suppression. Fire Area CD46, Main Control Room, credits water hose stations for suppression. Fire Area AB3, Auxiliary Building Radwaste Area, credits an automatic water suppression system. The inspectors determined if both pumps' cables were damaged due to an exposure fire, then no water would be available for fire suppression in these fire areas until at least one fire pump was manually started at the fire pump house. Cable damage to the motor driven fire pump would render its operation unavailable until adequate repairs were implemented. However, the inspectors determined that the diesel driven fire pump could be started manually at the local control panel.

Corrective Action: PSEG placed this issue into the corrective action program and implemented compensatory measures by issuing Hope Creek standing order 2019-20. The Standing order directs Hope Creek to utilize procedure HC.FP-EO.ZZ-0001, Fire and Medical Emergency Response Manual Hope Creek Control Room Fire Response, upon notification of a confirmed fire in those three fire areas to dispatch an operator to the fire pump house to monitor and/or start the diesel driven fire pump.

Corrective Action Reference: Notification 20823038

Performance Assessment:

Performance Deficiency: The inspectors determined that failure to protect the automatic start capability of fire pumps due to fire damage and ensure a reliable fire protection water supply for the fixed and manual fire suppression systems credited as part of the fire protection program was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Protection Against External Factors attribute of the Mitigating Systems cornerstone. The finding adversely affected the Mitigating System cornerstone objective to ensure the availability, reliability, and capability of systems that respond to fire events to prevent undesirable consequences. Specifically, failure to protect the automatic start capability of fire pumps affected the defense-in-depth barriers of the FPP to rapidly suppress fire that occurs in the plant areas. If fire is not suppressed in a timely manner could result in a damage to the safe shutdown systems and could challenge the plant operations.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Using Appendix F, Attachment 1, Fire Protection SDP Phase 1 Worksheet, the inspectors assigned the category to fire water supply. Using Appendix F, Attachment 2, Degradation Rating Guidance the inspectors assigned a LOW degradation to the performance deficiency because there would be adequate fire water capacity for fixed and manual fire suppression after the nuclear equipment operator is dispatched to manually start a diesel driven fire pump at the local control panel. Therefore, based on these aspects, the finding is determined to be of very low safety significance (Green).

Cross-cutting Aspect: Not Present Performance. No cross cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: HCGS License Condition 2.C.(7), in part, requires PSEG to implement and maintain in effect all provisions of the approved fire protection program as described in the UFSAR and as approved by the NRC. Hope Creeks' FPP is described in the UFSAR Section 9.5.1, Fire Protection Program. UFSAR Section 9.5.1.2.3.2, Pumps, stated that the electric motor driven fire pump starts automatically at 110 psig. If it fails to start or cannot meet the water flow demand, the diesel engine driven fire pump starts automatically when the system pressure drops to 100 psig. Contrary to the above, as of March 28, 2019, PSEG had not protected the automatic start capability of the fire pumps due to fire damage and ensure a reliable fire protection water supply for the fixed and manual fire suppression systems credited as part of the fire protection program.

Enforcement Action: This violation is being treated as an Non-Cited Violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Procedural Guidance to Perform Time Critical Actions Cornerstone Significance Cross-cutting Aspect Report Section Mitigating Systems

Green NCV 05000354/2019011-02 Open/Closed

[P.2] -

Evaluation 71111.05T The inspectors identified a finding of very low safety significance (Green) involving a non-cited violation (NCV) of Hope Creek Generating Station (HCGS) License Condition 2.C.(7) for failure to implement and maintain in effect all provisions of the approved Fire Protection Program (FPP), in that procedures for shutting down the plant in response to a fire that requires main control room evacuation were not adequate. Specifically, the alternate (remote) post-fire shutdown procedures and supporting master list of time critical actions were not accurate or adequate to secure in a timely manner high pressure coolant injection (HPCI)to prevent overfilling of the reactor vessel following a spurious fire-induced start of HPCI pump and failed reactor water high-level automatic shutdown of HPCI.

Description:

HCGS's thermal hydraulic analysis BJ-0024, Failure of the High-level HPCI Turbine Trip, Revision 2, analyzed a scenario for a fire in the main control room that causes HPCI to malfunction so that the HPCI high-level trip is disabled with or without a spurious start of HPCI. For a fire in the main control room, operators would evacuate the control room and transfer the controls of the required equipment at the remote shutdown panel (RSP). If HPCI is no longer required, and if necessary, operators perform a manual action at the Class 1E switchgear room to open the 1AD417-10 breaker to induce a HPCI trip. While operators are transiting from the main control room to the RSP room and from the RSP room to the Class 1E switchgear room, HPCI injection would continue to fill the reactor vessel. The analysis determined that for the worst-case scenario, water would enter the steam lines at 4 minutes and 10 seconds. If HPCI is not promptly secured, it will overfill the reactor vessel and water would enter the main steam lines which would adversely impact the reactor core isolation cooling (RCIC) turbine driven pump. For the alternate safe shutdown method, RCIC is the only credited system for inventory control function. The analysis showed that if RCIC is not operating and if HPCI is secured within 10 minutes, then there is adequate time for the RCIC steam line to drain prior to being required for inventory control.

The inspectors walked down procedures with PSEG to evaluate their response to a fire that would require control room evacuation (HC.OP-AB.FIRE-0001, Fire - Spurious Operations, Revision 2), evaluate main control room evacuation and transfer of control to the RSP (HC.OP-AB.HVAC-0002, Control Room Environment, Revision 10), and complete remote shutdown and cooldown from the RSP (HC.OP-IO.ZZ-0008, Shutdown From Outside Control Room, Revision 37). Also, the inspectors compared time-critical actions (TCAs) documented in Hope Creeks master list HC-OP-102-106, Hope Creek's Master List of Time Critical and Time Sensitive Operator Activities, Revision 4, to the referenced procedures that were walked down.

The inspectors questioned the applicability and timeliness of TCA-9 and TCA-10, where each required actions to secure HPCI to prevent reactor vessel overfill, since TCA-10 included additional actions to establish control at the RSP and spanned across different procedures.

The inspectors also noted that the expected performance time for TCA-9 and TCA-10 were the same (5 minutes) in Table 1 of OP-HC-102-106, though TCA-10 included more actions.

These actions include

(1) scramming the reactor from the reactor protections system (RPS)breakers,
(2) closing main steam line isolation valves from the RPS panel,
(3) verifying reactor scram from lower relay room, and
(4) trip/secure HPCI to prevent overfill. The expected performance time of 5 minutes did not appear to be consistent with what was observed by the inspectors during the walkdown.

The inspectors reviewed PSEGs evaluation and response in notification 20723308 regarding a previous time critical action concern during the 2016 NRC fire protection inspection. A revalidation of actions by PSEG under order 80107159, operations 25 and 26, documented a time to secure HPCI to be approximately 5 minutes and 7 seconds but did not account for diagnosis time of HPCI fire-damage spurious operation. After discussions with PSEG, the inspectors observed an additional ad-hoc timed walkdown of control room evacuation procedures HC.OP-AB.HVAC-0002 and HC.OP-IO.ZZ-0008 to identify the approximate time to evacuate the control room and diagnosis spurious operation of HPCI. PSEG recorded 5 minutes and 2 seconds on March 15, 2019. The addition of the time to evacuate the control room and diagnosis spurious operation of HPCI (5 min 2 sec), and the time to secure HPCI (5 min 7 sec) did not completely bound the expected performance time of TCA-10 (10 min 9 sec). This approximation exceeded the 10 minute maximum allowed time for TCA-10 and provided reasonable doubt that TCA-10 would be reliably completed in the required time based on the existing procedures and guidance.

Corrective Action: PSEG reviewed the issue and agreed there are errors in the TCA procedure OP-HC-102-106 and that the TCA and alternate post-fire safe shutdown procedures need to be revised to clarify required actions and priorities. PSEG issued Hope Creek standing order 2019-17 to require each crew to tabletop HC.OP-AB.HVAC-0002, Condition C, control room evacuation, to prioritize actions to prevent HPCI overfill. Other corrective actions are to evaluate affected time-critical actions and revise related procedures.

Corrective Action References: Notifications 20820914, 20821021, and 20821328.

Performance Assessment:

Performance Deficiency: The inspectors determined that PSEGs failure to provide adequate procedural guidance for post-fire safe shutdown was a performance deficiency that was reasonably within PSEGs ability to foresee and prevent.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Mitigating Systems cornerstone. The finding affected the Mitigating Systems cornerstone objective of ensuring the reliability and availability of the RCIC system under postulated fire safe shutdown conditions. The finding is also similar to IMC 0612, Appendix E, Example 3.k, where there was a reasonable doubt on the operability of RCIC system because inadequate procedure guidance could result in overfill of the reactor vessel, and water would enter the main steam lines which would impact RCIC turbine driven pump.

Significance: The inspectors assessed the significance of the finding using Appendix F, Fire Protection and Post - Fire Safe Shutdown SDP. Using Appendix F, Attachment 1, Fire Protection SDP Phase 1 Worksheet, the inspectors assigned the category to post-fire safe shutdown. Using Appendix F, Attachment 2, Degradation Rating Guidance the inspectors assigned a LOW degradation to the performance deficiency because the identified procedure inadequacies were compensated by operator training and familiarity, such that it would not affect the ability to reach and maintain a stable hot shutdown conditions. Therefore, based on these aspects, the finding is determined to be of very low significance (Green).

Cross-cutting Aspect: P.2 - Evaluation: The organization thoroughly evaluates issues to ensure that resolutions address causes and extent of conditions commensurate with their safety significance. Specifically, PSEG's evaluation of time critical actions under notification 20723308 and order 80107159, operations 25 and 26, was not thorough, in that it did not consider the diagnosis time of HPCI fire-damage spurious operation in the performance time of the TCA 9 and 10.

Enforcement:

Violation: License Condition 2.C(7) for HCGS states in part that, PSEG Nuclear LLC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report. Updated Final Safety Analysis Report, Appendix 9A states in part that, Procedures are in effect to implement this [alternate shutdown] capability. Contrary to the above, until March 15, 2019, when Hope Creek standing order 2019-017 was issued as a temporary compensatory measure, PSEG failed to provide adequate procedural guidance for post-fire safe shutdown in that the alternate (remote) post-fire shutdown procedures and supporting master list of time critical actions were not accurate or adequate to timely secure HPCI to prevent overfilling of the reactor vessel following a spurious fire-induced start of HPCI pump and failed reactor water high-level automatic shutdown of HPCI.

Enforcement Action: This violation is being treated as an Non-Cited Violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On March 29, 2019, the inspector presented the inspection results to Paul Davison, Vice President - Engineering and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05T Calculations

11-0028

Reactor Building Flood Calculation for Elevation 102

11-0092

Reactor Building Flood Calculation for Elevation 54/ and 77

19-0018

Maximum Flood Levels in Control/Diesel Generator Areas

431856

Hope Creek Generating Station Safe Shutdown Analysis

Reports for Fire Areas RB1, RB2, AB1, CD20, CD71, and

CD82

70143136-0410

Time Critical Operator Action Validation to Secure HPCI per

HC.OP-IO.ZZ-0008, Attachment 9

3/4/13

70185264-10-80

Evaluation of Securing HPCI as a Time Critical Action and

Procedure HC.OP-AB.FIRE-0001

2/22/19

80107159-25

Re-Validation of HPCI Time Critical Actions

3/17/18

BJ-0024

Failure of High Level Turbine Trip

E-26

Breaker and Fuse Coordination for Appendix R Systems

E-7.4

Class 1E 4.16kV System Protective Relay Settings

E-7.7

Class 1E 480V System Protective Relaying

H-1-KC-FEE-

1582

Gypsum Board Wall and Fire Dampers 262D2 and 263D2

H-1-KC-FEE-

1889

Carbon Dioxide System 1C10 Preop Test Review Room

5403

H-1-ZZ-SEE-

278-1

Evaluation of Gypsum Board Fire Barrier between Rooms

5301 and 5339

H-1-ZZ-SEE-0279 Evaluation of Gypsum Board Fire Barrier Rooms 5237 and

207

PM652-0066

Vendor Calculation for Control Equipment Room Mezzanine,

System 1C10

Corrective Action

Documents

20442810

20452227

20452335

20722147

20723341

20723357

20723901

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20723902

20803353

20804672

20804674

20804675

20804990

20813283

20818156

Corrective Action

Documents

Resulting from

Inspection

20722174

20723308

20723338

20819997

20820010

20820020

20820080

20820082

20820083

20820301

20820551

20820565

20820601

20820606

20820689

20820690

20820691

20820707

20820812

20820879

20820895

20820913

20820914

20820915

20820924

20820926

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

20820927

20821021

20821328

20821331

20821703

20821704

20822786

20822823

20822848

20823038

20823433

Drawings

E-0001-0

Single Line Station Diagram

E-0005-0

Single Line Meter and Relay Diagram 4.16kV Station Power

System

E-0006-1, Sht. 1

Single Line Meter and Relay Diagram 4.16kV Class 1E

Power System

E-0006-1, Sht. 2

Single Line Meter and Relay Diagram 4.16kV Class 1E

Power System

E-0013-0, Sht. 2

Single Line Meter and Relay Diagram 480V Units

E-0084-0

Electrical Schematic Diagram Class 1E 4.16kV Station

Power System

E-0086-0

Electrical Schematic Diagram Class 1E 4.16kV Station

Power System

E-6067-0, Sht. 4

Electrical Schematic Diagram Solenoid Pilot Valves

E-6084-0, Sht. 7

Electrical Schematic Diagram RCIC Main Steam Supply

Valve

J-0399-0, Sht. 13

Remote Shutdown Control Panels 10C399 Instrument and

Control Section

J-0399-0, Sht. 3

Remote Shutdown Control Panels 10C399 Instrument and

Control Section

J-0399-0, Sht. 4

Remote Shutdown Control Panels 10C399 Instrument and

Control Section

J-4041-0, Sht. 3

Loop Diagram for Nuclear Boiler Suppression Pool

Temperature Recorder on Remote Shutdown Panel

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

J-4049-0, Sht. 2

RCIC Pump Turbine Control

M-11-1, Sht. 1

Safety Auxiliary Cooling System Reactor Building

M-22-0, Sht. 1

Fire Protection Fire-Water Permanent & Temporary Fire

Pump House

M-22-0, Sht. 2

Fire Protection Fire-Water Permanent & Temporary Fire

Pump House

M-22-0, Sht. 3

Fire Protection Fire-Water Permanent & Temporary Fire

Pump House

M-41-1, Sht. 1

Nuclear Boiler

M-41-1, Sht. 2

Nuclear Boiler

M-49-1, Sht. 1

RCIC

M-50-1, Sht. 1

RCIC Pump Turbine

Engineering

Changes

80106533

Replace Pyrotechnics Panels, Reactor Building Smoke

Detectors

80112397

New Fire Door at U2 Reactor Building South Wall, Elevation

2

80112930

Fire Detection System Upgrade, DCP Part 1

80112931

Fire Detection System Upgrade, DCP Part 2

80117295

Delete CREG Deluge Flow Trip

80120545

TSC (RB6, 132) Smoke Detector Changes and Retired CAS

Floor Detector Removal

80122468

MPT FP On-Line Initiation Interlock

Engineering

Evaluations

0003-00A3-013-

001

Hope Creek Manual Action Feasibility Assessment by

Hughes Associates, Inc.

70143136-0410

Scenerio 35, Time Validation to Secure HPCI by Opening

Breaker 10, HPCI Relay Vertical Board

2/11/13

80107159-0025

Time Validation to Secure HPCI by Opening Breaker 10,

HPCI Relay Vertical Board

3/17/18

Fire Plans

FP-HC-3413

HPCI Pump & Turbine Room, RHR Pump & Heat Exchanger

Rooms

FP-HC-3423

MCC Area, RHR Heat Exchanger Room, Safeguard

Instrument Rooms & RACS Pumps & Heat Exchanger Area

FP-HC-3424

MCC Area

FP-HC-3433

A SACS Heat Exchanger & Pump Room

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FP-HC-3523

Diesel/Control & Radwaste Building

FP-HC-3533

Electric Access Area

FP-HC-3542

Control Equipment Mezzanine Area

FP-HC-3543

Electric Access Area and HVAC Wing

FP-HC-3562

HVAC Equipment, Inverter & Battery Rooms

Miscellaneous

10855-M660-51

Installation and Operating Instructions for Engine Driven Fire

Pump Control Panel

5/2/80

313234-01

Patterson Pump Company Motor Driven Fire Pump - Pump

Performance Curve

313235-01

Patterson Pump Company Diesel Engine Driven Fire Pump -

Pump Performance Curve

55700508

Unannounced Fire Drill

6/25/18

55752660

Unannounced Fire Drill Assessed by Independent Third

Party

9/19/18

55826571

Offsite Assistance Training and Fire Drill

11/14/18

80121712

Fire Drill Lessons Learned Program, 1st Quarter 2018

80121712

Fire Drill Lessons Learned Program, 2nd & 3rd Quarter 2018

BC001

Place A RHR loop in Suppression Pool Cooling IAW

of HC.OP-IO.ZZ-0008

BD008

Place RCIC in Service from the RSP and Commence

Injection to the Reactor Vessel IAW HC.OP-AB.HVAC-0002

Bisco Test Report

748-134

Bisco Product Equivalency Fire Test Utilizing Bisco SF-20

and Bisco SE-Foam

5/14/84

EA002

PERFORM Steps 1.1 and 1.2 of HC.OP-IO.ZZ-0008,

4, Shutdown from Outside Control Room A RHR

Loop Suppression Pool Cooling

HC Standing

Order 2019-17

Procedure HC.OP-AB.HVAC-0002 Control Room

Environment Condition C clarification and emphasis to

secure HPCI

3/15/19

HCGS UFSAR

Table 9A-14, Fire Hazard Analysis Tabulation Summary

HCGS UFSAR

Appendix 9A, Appendix R Comparison to NRC Generic Letter 81-12

HCGS UFSAR

Section 9.5, HCGS Safe Shutdown Analysis and Fire

Hazards Analysis

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NOH04IO008C-

Operator Lesson Plan for Shutdown from Outside Control

Room, HC.OP-IO.ZZ-0008

11/6/13

NOH04IOP008C

Operator Lesson Plan PowerPoint Slide deck for Shutdown

from Outside Control Room, HC.OP-IO.ZZ-0008

2/8/18

NOSA-HPC-18-

Fire Brigade Drills

9/28/18

NRC Information Notice 2009-29

Potential Failure of Fire Water Supply Pumps to

Automatically Start Due to a Fire

11/24/09

NUREG-1852

Demonstrating the Feasibility and Reliability of Operator

Manual Actions in Response to Fire

10/2007

PM018-0366

EDG B Electrical Control Schematic

11/29/95

SB005

Open the RPS circuit breakers in accordance with Step 5.1.2

of HC.OP-IO.ZZ-0008.NOH04ABPROCUC-08, Lesson Plan

for Upgraded Abnormal Operating Procedures

11/4/15

TCP 2018-008

RB1 room 4315

TCP 2018-053

AB3 room 3202

TCP 2019-019

AB1 room 5501

TCP 2019-031

RB7 room 4220

TCP 2019-034

RB1 room 4211

Procedures

CC-AA-211

Fire Protection Program

CC-AA-320-011

Transient Loads

CY-AB-140-410

Hope Creek Station Diesel Fuel Oil Testing Program

FP-AA-002

Fire Protection Impairment Program

FP-AA-005

Fire Protection Surveillance and Periodic Test Program

FP-AA-010

Pre-Fire Plans

FP-AA-011

Control of Transient Combustible Material

FP-AA-012

Fire Protection Organization, Duties and Staffing

FP-AA-014

Fire Protection Training Program

FP-AA-024

Fire Drill Performance

FP-AA-105

Compensatory Measure Firewatch Program

FP-HC-004

Actions for Inoperable Fire Protection - Hope Creek Station

HC-OP-102-106

Hope Creek Master List of Time Critical and Time Sensitive

Operator Activities

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HC.FP-PM.KC-

0038

Annual and Monthly Fire Extinguisher Inspection

HC.FP-ST.KC-

0009

Diesel Driven Fire Pump Operability Test

HC.FP-ST.QB-

0039(F)

Standby Self Contained 8 Hour Battery Powered Emergency

Light Unit Test and Inspection

HC.FP-ST.QK-

29(F)

Class 1 Fire Detection Functional Test

HC.FP-ST.ZZ-

0031(F)

Class 1 Fire Damper Functional Test

HC.IC-CC.FC-

0013

RCIC Turbine Pump Control

HC.MD-CM.PG-

0002

Low Voltage Breaker Overhaul and Repair

HC.MD-PM.PB-

0001

4.16kV Breaker Cleaning and Maintenance

HC.OP-AB.FIRE-

001(Q)

Fire - Spurious Operations

HC.OP-

AB.HVAC-

0002(Q)

Control Room Environment

HC.OP-AB.ZZ-

0001

Transient Plant Conditions

HC.OP-AB.ZZ-

0135(Q)

Station Blackout // Loss of Offsite Power // Diesel Generator

Malfunction

HC.OP-AM.TSC-

23

Alternate Containment Flooding Via Fire Water

HC.OP-AM.TSC-

24

Remote Operation of SRVs With RPV Injection

HC.OP-EO.ZZ-

0318

Containment Venting

HC.OP-IO.ZZ-

0008(Q)

Shutdown from Outside Control Room

HC.OP-ST.SV-

Remote Shutdown Monitoring Instrumentation Channel

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

0001

Check

HC.OP-ST.SV-

0002

Remote Shutdown Control Operability

HC.OP-ST.SV-

0003

Remote Shutdown Control Operability

HC.OP-ST.SV-

0004

Remote Shutdown Control Operability

HC.OP-ST.SV-

0012

Remote Shutdown Control Operability

HR-AA-07-106

Respirator/Heat Stress Surveillance Exam

HR-AA-07-107

Fire Department Surveillance Exam

SH.FP-TI.FP-

0001(Z)

FP Freeze Prevention and Winter Readiness

Work Orders

299934

Non-Class 1 Fire Suppression Water System Flush

3/11/18

30308297-10

B.5.b Hope Creek Equipment Inventory

2/25/18

30318289

Class 1 Fire Detector Functional Test

7/28/18

30324901

Firefighting and Rescue Equipment Inventory

10/08/18

30327322

Firefighting and Rescue Equipment Inventory

1/07/19

30330339

Fire Engine Operability Test and Firefighting Equipment

Inventory

1/27/19

30330998

Fire Department and EMS Equipment Inspection and

Inventory

2/10/19

50087206

Flood and Fire Barrier Penetration Seal Inspection

10/02/06

50135226

Fire Main Flow Test

5/11/14

50167497

Fire Main Flow Test

01/11/18

50179725

Fire Pump Capacity Test

9/21/16

50184932

Pre-Action Sprinkler System Functional Test and Inspection

6/9/17

50186965

Class I Fire Suppression Water System Flush

8/2/17

50187289

Deluge System 1D28 Functional Test

7/6/16

50189177

Fire Pump Capacity Test

2/3/17

50195504

Pre-Action Sprinkler System Functional Test and Inspection

6/5/18

50196834

Deluge System 1D28 Functional Test

8/2/18

50197517

Class I Fire Suppression Water System Flush

10/9/18

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

50199093

Class 1 Fire Detector Functional Test

3/31/18

201002

Class 1 Fire Detector Functional Test

7/31/18

202975

Class 1 Fire Detector Functional Test

10/8/18

203065

Class 1 Fire Detector Functional Test

9/30/18

HC.FP-ST.QB-

0070(F)

Standby Self Contained 8 Hour Battery Powered Emergency

Light Unit Test and Inspection

1/18/19

HC.OP-ST.SV-

0001

Remote Shutdown Monitoring Instrumentation Channel

Check

2/10/18

HC.OP-ST.SV-

0001

Remote Shutdown Monitoring Instrumentation Channel

Check

2/10/18

HC.OP-ST.SV-

0002

Remote Shutdown Control Operability

4/12/15

HC.OP-ST.SV-

0003

Remote Shutdown Control Operability

5/6/18

HC.OP-ST.SV-

0004

Remote Shutdown Control Operability

10/31/16

HC.OP-ST.SV-

0005

Remote Shutdown Control Operability

4/13/18

HC.OP-ST.SV-

0012

Remote Shutdown Control Operability

11/8/16