IE Insp Repts 50-352/81-09 & 50-353/81-07 on 810602-05. Noncompliance Noted:On 810603,RCPB Valve 2F023A Observed W/O Plywood Cover Fitted Against Weld Prep & Tape Sealed
ML20009G137
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 07/07/1981
From: Mcbrearty R, Lester Tripp
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML20009F927 List:
References
50-352-81-09, 50-352-81-9, 50-353-81-07, 50-353-81-7, NUDOCS 8108030363
Download: ML20009G137 (4)


Text

.

.

U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT Region I 50-352/81-09 Report No.

50-353/81-07 50-352 Docket No.

50-353 CPPR-106 License No. CPPR-107 Priori ty

__ Category A

--

Licensee:

Philadelphia Electric Company 2301 Market Street Philadelphia, Pennsylvania 19101 Facility Name:

Limerick Generating Station, L' nits 1 & 2 Inspection at:

Limerick, Pennsylvania Inspection conducted: June 2-5, 1981 Inspectors:

M 3O /N/

s R. McBrearty, Reactor Inspector y

date signed date signed l

j date signed Approved by:

/

-

F8 N

(L. E. Tripp, Chief, Materials and Processes date signed Section, Engineering Inspection Branch Inspection Sumary:

Inspection on June 2-5,1981 (Combined Report Nos. 50-352/81-09; 50-353/81-07)

Areas Inspected:

Routine, unannounced inspection of safety related components l

including storage, maintenance and inspection activities. The inspection involved l

34 inspector-hours onsite by one regional based NRC inspector.

Results: One item of ncncompliance was identified.

(Failure to properly protect recirculation system 28" gate valve, para. 2)

l l

Region I Form 12

,

(Rev. April 77)

l l

8108030363 810715

'

I PDR ADOCK 05000352 G

PDR

,

<

_

.

.

.

.

-

.

DETAILS _

1.

Persons Contacted Philadelphia Electric Company (PEco)

  • J. M. Corcoran, Field Quality Assurance Branch Head
  • F. J. Coyle, QA Engineer
  • E. C. Gibson, QA Engineer Bechtel Power Corporation
  • A. Arch, Assistant Project Field Engineer
  • R. J. Bulchis, RPE
  • B. Dragon, QA Engineer
  • H. D. Foster, Project Field QC Engineer H. Gilbert, Lead Mechanical QC Engineer J. Gray, Lead Piping QC Engineer J. Havens, Piping Superintendent
  • E. R. Klossin, Project QA Engineer
  • J. L. Martin, Lead Site QA Engineer
  • K. L. Quinter, Assistant Project Field QC Engineer
  • D. C. Thompson, Assistant Project Field QC Engineer
  • A. G. Weedman, Project Field Engineer
  • denotes those present at the exit meeting.

2.

Storage and Maintenance - Safety Related Components The inspector reviewed procedures and specifications, observed the storage condition and examined records of activities associated with storage and maintenance of the following components:

Recirculation System 28-inch Gate Valves Nos. 1F023A&B, 1F031A&B,

-

2F023A&B, 2F031A Main Steam Isolation Valves Nos. 1F022A, B, C, & D

-

-

Core Spray Pumps Nos. LAP 206,1BP206,1CP206 and IDP206 The above items were considered with regard to criteria delineated in the following:

Lunkenheimer Valve Company Brochure SP2224, Pevision D

-

General Electric Company Specification No. 22A2724, Revision 3

-

-

.

.

Bechtel Job Rule JR-G-7, Revision 18

-

Bechtel Job Rule JR-R-10, Revision 15

-

Bechtel SF/ PSP G-3-1, Revision 4

-

Bechtel SF/ PSP G-5-1, Revision 3

-

PECo LGSQAP 13

-

a.

Observa,tions The inspector visually examined the storage areas in Units 1 and 2 for the components listed above.

Compliance with applicable storage requirements was ascertained for the listed components with the exception of Unit 2 recirculation system valve No. 2F023A.

'

IE combined inspection report number 352 and 353/ 81-04 covering the period of March 2-27, 1981, documents noncompliance number 352/ El-04-02 and 353/ 81-04-01 regarding recirculation system gate valves which were not properly protected.

The inspector found a condition similar to the above such that the end cover for valve 2F0 23A was not attached, the valve interior and the end weld prep was not protected as specified in the General Electric Company specification 22A2724, Revision 3. Paragraph 4.1.2.1.2 of the specification requires that, "... Internal cleanliness of equipment...

shall be maintained by closing openings where possible by plugging, capping and/or sealing....

Butt weld preps on valves...shall have plywood fitted against the prep and tape sealed." The failure to properly protect the recirculation system valve is contrary to 10 CFR

,

50, Appendix B, Criterion V (353/81-07-01).

i Prior to completion of the inspection the licensee representative reported

'

l that the condition was corrected. The inspector verified that the valve end cover was properly attached.

i l

At the exit meeting the licensee representative stated that the item t

would be i... ected more frequently to minimize the possibility for the I

condition to exist in the future.

b.

Record Review The inspector examined maintenance and installation inspection records to ascertain that the associated activities were performed at the required frequency.

i i

L-

-

.

.

The following were included in the inspector's review:

Maintenance Log and Maintenance Action Cards for recirculation

-

system 28 inch gate valves Installation Inspection Records for Unit 1 recirculation system

-

valves Installation Inspection Records for Unit 1 main steam isolation

-

valves Installation Inspection Records for Unit I core spray pumps

-

No items of noncompliance were identified.

3.

Exit Interview The inspector met with licensee representatives (denoted in paragraph 1)

at the conclusion of the inspection on June 5, 1981.

The inspector sum-marized the purpose and scope of the inspection and the findings.

-