ROP 15 Annual Assessment Letter for Limerick Generating Station, Units 1 and 2 (Report 05000352/2014001 and 05000353/2014001)
ML15062A213
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 03/04/2015
From: Ho Nieh
Division Reactor Projects I
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
BOWER, FL
Shared Package
ML15049A476 List:
References
IR 2014001
Download: ML15062A213 (5)


Text

March 4, 2015

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR LIMERICK GENERATING STATION, UNITS 1 AND 2 (REPORT 05000352/2014001 AND 05000353/2014001)

Dear Mr. Hanson:

On February 9, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of the Limerick Generating Station (Limerick) Units 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014 through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Limerick Generating Station, Units 1 and 2 during the most recent quarter was within the Regulatory Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because of one or more greater-than-green Security Cornerstone inputs as described in the NRC Inspection Report Nos. 05000352/2014405 and 05000353/2014405, sent on October 23, 2014. Therefore, the NRC plans to conduct a supplemental inspection in accordance with Inspection Procedure 95001, Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. By a letter (ML15028A450) dated January 27, 2015, your staff notified the NRC of your readiness for the 95001 supplemental inspection and this onsite inspection has been scheduled for the week of March 16, 2015.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. In addition to ROP baseline inspections, the NRC will perform Inspection Procedure (IP) 60855.1, Operation of an Independent Spent Fuel Storage Installation (ISFSI) at Operating Plants. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence. In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5262 with any questions you have regarding this letter.

Sincerely,

/RA/

Ho K. Nieh

Director

Division of Reactor Projects

Docket Nos.: 50-352, 50-353 License Nos.: NPF-39, NPF-85

Enclosure: Limerick Generating Station Inspection/Activity Plan

cc: Distribution via ListServ

ML15062A213

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DRP RI/DRP RI/DRP

NAME SBarber/ GSB FBower/ FLB HNieh/ HKN

DATE 02/19/15 02/19 /15 02/25/15

Page 1 of 2 01/26/2015 09:40:28 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Limerick Inspection / Activity Plan 01/01/2015 - 06/30/2016 10/6EXAM

- INITIAL OL EXAM

1 FY15-LIMERICK INITIAL OPERATOR LICENSING EXAM U01892 01/12/2015 01/21/2015 71124

- RADIATION PROTECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/16/2015 03/20/2015 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/16/2015 03/20/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/16/2015 03/20/2015 1, 2 IP Occupational Dose Assessment 71124.04 03/16/2015 03/20/2015 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/16/2015 03/20/2015 71124

- RADIATION PROTECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/13/2015 04/17/2015 1, 2 IP Occupational ALARA Planning and Controls 71124.02 04/13/2015 04/17/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 04/13/2015 04/17/2015 1, 2 IP Occupational Dose Assessment 71124.04 04/13/2015 04/17/2015 1, 2 IP Radiation Monitoring Instrumentation 71124.05 04/13/2015 04/17/2015 7111108G

- U2 INSERVICE INSPECTION

2 IP Inservice Inspection Activities - BWR 7111108G 04/20/2015 04/24/2015 CDBI

- COMPONENT DESIGN BASIS INSPECTION

1, 2 IP Component Design Bases Inspection 7111121 06/08/2015 06/12/2015 1, 2 IP Component Design Bases Inspection 7111121 06/22/2015 06/26/2015 1, 2 IP Component Design Bases Inspection 7111121 07/06/2015 07/10/2015 71124

- REMP

1, 2 IP Radiological Environmental Monitoring Program 71124.07 07/13/2015 07/17/2015 ISFSI

- ISFSI LOADING INSPECTION

1, 2 IP Operation Of An ISFSI 60855 07/13/2015 07/17/2015 1, 2 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 07/13/2015 07/17/2015 12/7EXAM

- INITIAL OL EXAM

1 FY16 - LIMERICK INITIAL OPERATOR LICENSING EXAM U01912 12/07/2015 12/11/2015

FY16 - LIMERICK INITIAL OPERATOR LICENSING EXAM U01912 01/18/2016 01/22/2016 71124

- RADIATION PROTECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/14/2015 09/18/2015 1, 2 IP Occupational ALARA Planning and Controls 71124.02 09/14/2015 09/18/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 09/14/2015 09/18/2015 1, 2 IP Occupational Dose Assessment 71124.04 09/14/2015 09/18/2015 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Page 2 of 2 01/26/2015 09:40:28 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Limerick Inspection / Activity Plan 01/01/2015 - 06/30/2016 71124

- RADIATION PROTECTION

1, 2 IP Radiation Monitoring Instrumentation 71124.05 09/14/2015 09/18/2015 1, 2 IP Performance Indicator Verification 71151 09/14/2015 09/18/2015 7111111B

- REQUAL INSP W/ P/F RESULTS

1, 2 IP Licensed Operator Requalification Program 7111111B 11/16/2015 11/20/2015 EP

- EP EXERCISE

1, 2 IP Exercise Evaluation 7111401 11/16/2015 11/20/2015 1, 2 IP Exercise Evaluation - Scenario Review 7111408 11/16/2015 11/20/2015 71124.08

- RADWASTE

1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 01/11/2016 01/15/2016 71124

- RADIATION PROTECTION

1 IP Radiological Hazard Assessment and Exposure Controls 71124.01 02/22/2016 02/26/2016

IP Occupational ALARA Planning and Controls 71124.02 02/22/2016 02/26/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 02/22/2016 02/26/2016 1, 2 IP Occupational Dose Assessment 71124.04 02/22/2016 02/26/2016 1, 2 IP Radiation Monitoring Instrumentation 71124.05 02/22/2016 02/26/2016 ISI

- U1 INSERVICE INSPECTION

1 IP Inservice Inspection Activities - BWR 7111108G 03/28/2016 04/01/2016 71124

- RADIATION PROTECTION

1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/28/2016 04/01/2016 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/28/2016 04/01/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 03/28/2016 04/01/2016 1, 2 IP Occupational Dose Assessment 71124.04 03/28/2016 04/01/2016 1, 2 IP Radiation Monitoring Instrumentation 71124.05 03/28/2016 04/01/2016 TRI FI

- TRIENNIAL FIRE PROTECTION

1, 2 IP Fire Protection [Triennial]

7111105T 06/06/2016 06/10/2016 1, 2 IP Fire Protection [Triennial]

7111105T 06/20/2016 06/24/2016 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.