|
---|
Category:SYSTEMATIC ASSESSMENT OF LICENSEE PERFORMANCE
MONTHYEARIR 05000344/19900091990-08-15015 August 1990 Errata to SALP Rept 50-344/90-09 for Jan 1989 - Mar 1990, Consisting of Revised Page 18 to Reflect Effort by Util Engineering Groups in Design of ATWS Mitigation Sys Actuation Circuitry IR 05000344/19880511989-03-0909 March 1989 SALP Rept 50-344/88-51 for Dec 1987 - Dec 1988 IR 05000344/19870411987-11-30030 November 1987 SALP Rept 50-344/87-41 for 861101-871130 IR 05000344/19870011987-01-29029 January 1987 SALP Meeting Rept 50-344/87-01 on 870123.Results of NRC Assessment of Licensee Performance for Nov 1985 - Oct 1986 Discussed IR 05000344/19860431986-12-19019 December 1986 SALP Rept 50-344/86-43 for Nov 1985 - Oct 1986 IR 05000344/19850351985-12-17017 December 1985 SALP Rept 50-344/85-35 for Nov 1984 - Oct 1985 1990-08-15
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000344/19990061999-09-0909 September 1999 Insp Rept 50-344/99-06 on 990630-0701,21 & 0404-08.No Violations Noted.Major Areas Inspected:Organization,Mgt & Cost Controls & Decommissioning Performance & Status Review, Insp of Transportation Activities & Maint & Surveillance IR 05000344/19990051999-05-0707 May 1999 Insp Repts 50-344/99-05 & 72-0017/99-04 on 990419-22.No Violations Noted.Major Areas Inspected:Decommissioning Performance & Status Review IR 05000344/19990041999-05-0707 May 1999 Insp Repts 50-344/99-04 & 72-0017/99-02 on 0322-25 & 29- 0408.Non-cited Violations Noted.Major Areas Inspected: Licensee Readiness to Load Sf Into Independent ISFSI IR 05000344/19990031999-04-20020 April 1999 Insp Repts 50-344/99-03 & 72-0017/99-03 on 990301-04,15-18 & 22-25.No Violations Noted.Major Areas Inspected:Site Tours & Review of Licensee Preparedness for ISFSI Operations IR 05000344/19990021999-04-13013 April 1999 Insp Rept 50-344/99-02 on 990329-0401.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program, Including Access Authorization,Alarm Station & Communications & Access Control of Personnel & Packages IR 05000344/19980041999-01-21021 January 1999 Insp Repts 50-344/98-04 & 72-0017/98-01 on 981106-07 & 1202-10.Violations Noted.Major Areas Inspected: Decommissioning & Dismantlement Activities at Plant Site ML20202C2111999-01-21021 January 1999 Notice of Violation from Insp on 971207-10.Violation Noted: Licensee Did Not Perform Survey to Assure Compliance with 10CFR20.1902(d) IR 05000344/19982021998-10-30030 October 1998 Insp Rept 50-344/98-202 on 980831-0903.No Violations Noted. Major Areas Inspected:Safety Review Program Re Modular Sf Cooling Sys & Maint Program IR 05000344/19980031998-08-25025 August 1998 Insp Rept 50-344/98-03 on 980727-30.No Violations Noted. Major Areas Inspected:Sfp Safety,Ore,Decommissioning Performance & Status Review,Organization Mgt & Cost Controls & Solid Radioactive Waste & Transport IR 05000344/19980021998-07-0101 July 1998 Insp Rept 50-344/98-02 on 980601-04.No Violations Noted. Major Areas Inspected:Activities Including Spent Fuel Pool Safety,Occupational Radiation Exposure & Decommissioning Performance & Status Review IR 05000344/19980011998-05-22022 May 1998 Insp Rept 50-344/98-01 on 980504-07.No Violations Noted. Major Areas Inspected:Specific Areas of Licensee Physical Security Program IR 05000344/19982011998-04-29029 April 1998 Insp Rept 50-344/98-201 on 980223-26.No Violations Noted. Major Areas Inspected:Safety Review Program & Insp follow- Up ML20199D7511998-01-23023 January 1998 Cover Page for Insp Rept 50-344/97-05 on 971201-03, Inadvertently Omitted in Original Submittal ML20199F0361998-01-23023 January 1998 Insp Rept 50-344/97-05 on 971201-03.Violations Noted.Major Areas Inspected:Status of Dismantlement Activities,Changes to Util Emergency Exercise Plan Implementing Procedures & Decommissioning ML20199F0291998-01-15015 January 1998 Notice of Violation from Insp on 971201-03.Violation Noted: Licensee Failed to Ensure Adequate Survey of Certain Contaminated Tools IR 05000344/19970041997-11-21021 November 1997 Insp Repts 50-344/97-04 & 72-0017/97-04 on 970929-1002.No Violations Noted.Major Areas Inspected:Fuel Debris Processing,Dry Cask Storage & Control of Radioactive Matl. Insp Repts Reissued Due to Omission of Pages 4 & 5 ML20198N3461997-10-31031 October 1997 Insp Repts 50-344/97-04 & 72-0017/97-04 on 970929-1010.No Violations Noted.Major Areas Inspected:Fuel Debris Processing Preparation for Pouring Concrete for Portion of ISFSI Pad & Control & Release of Contaminated Matl ML20210S7131997-09-0909 September 1997 Notice of Violation from Insp on 970721-24.Violation Noted: from 960923-970515,licensee Failed to Conduct Surveys Adequate to Evaluate Quantity of Radioactive Matl Released from Radiological Controlled Area IR 05000344/19970031997-09-0909 September 1997 Insp Repts 50-344/97-03 & 72-0017/97-03 on 970721-24. Violations Noted.Major Areas Inspected:Control of Radioactive Material,Spent Fuel Pool Debris Project,Dry Cask Storage,Spent Fuel Pool & Health Physics Activities IR 05000344/19970021997-05-0606 May 1997 Insp Repts 50-344/97-02 & 72-0017/97-02 on 970414-17.No Violations Noted.Major Areas Inspected:Health Physics, Training Program,Spent Fuel Pool,Independent Spent Fuel Storage Installation & Fuel Building Crane Tests IR 05000344/19970011997-02-25025 February 1997 Insp Repts 50-344/97-01 & 72-0017/97-01 on 970204-06. Violations Noted.Major Areas Inspected:Review of Radiation Protection Program,Compliance W/Ts,Operations Involving Licensee Insp of Spent Fuel & Quality Assurance Program ML20135B7491997-02-25025 February 1997 Notice of Violation from Insp on 970204-06.Violation Noted: Licensee Had Not Audited Annual Radiological Environmental Report TS 6.9.1.5.1 Since 890519 IR 05000344/19960081997-02-13013 February 1997 Insp Repts 50-344/96-08 & 72-0017/96-02 on 961104-07.No Violations Noted.Major Areas Inspected:Decommissioning Activities Related to Ongoing Efforts to Decontaminate Facility & Place Spent Fuel in Storage at ISFSI IR 05000344/19960051997-02-13013 February 1997 Correction to Insp Repts 50-344/96-05 & 72-0017/96-02. Requests That Encl Pages Be Added as Last Two Pages of Listed Insp Rept ML20059A1421993-12-15015 December 1993 Notice of Violation from Insp on 930930-1112.Violation Noted:Detailed Construction Package 1 Associated W/Request for Design Change 78-103,installed in May 1980,did Not Correctly Translate Design Basis Into Applicable Procedures IR 05000344/19930151993-12-14014 December 1993 Insp Rept 50-344/93-15 on 931115-18.No Violations Noted. Major Areas Inspected:Operational Status of EP Program & of Annual EP Exercise IR 05000344/19930141993-12-0606 December 1993 Insp Rept 50-344/93-14 on 930930-1112.Violations Noted.Major Areas Inspected:Resident Insp of Operational Safety Verification,Maintenance,Surveillance & follow-up of Previously Identified Items IR 05000344/19930121993-10-22022 October 1993 Insp Rept 50-344/93-12 on 930817-0929.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Maint,Surveillance & Followup of Previously Identified Items IR 05000344/19930131993-09-24024 September 1993 Insp Rept 50-344/93-13 on 930913-17.No Violations Noted. Major Areas Inspected:Listed Portions of Licensee Physical Security Program IR 05000344/19930111993-09-0303 September 1993 Insp Rept 50-344/93-11 on 930706-0816.No Violations or Deviations Noted.Major Areas Inspected:Operational Safety Verification,Maint,Surveillance & Followup of Previously Identified Items IR 05000344/19930101993-08-12012 August 1993 Insp Rept 50-344/93-10 on 930706-08.No Violations Noted. Major Areas Inspected:Chemistry & Radiation Protection Program Organization & Staffing & Solid Radwaste Storage IR 05000344/19930081993-06-25025 June 1993 Insp Rept 50-344/93-08 on 930422-0531.No Violations Noted. Major Areas Inspected:Operational Safety Verification,Maint, Emergency Preparedness & Followup of Previously Identified Items PNO-V-93-002, on 930113,L Marbet Held Press Conference W/ Portland,Or Media & Alleged That NRC Had Inappropriately Authorized Feb 1992 Restart of Plant.Util Announced on 930104 That Operation of Plant Would Be Permanently Ceased1993-01-13013 January 1993 PNO-V-93-002:on 930113,L Marbet Held Press Conference W/ Portland,Or Media & Alleged That NRC Had Inappropriately Authorized Feb 1992 Restart of Plant.Util Announced on 930104 That Operation of Plant Would Be Permanently Ceased IR 05000344/19920321993-01-0808 January 1993 Insp Rept 50-344/92-32 on 921027-1207.Violations Noted.Major Areas Inspected:Maintenance,Surveillance,Event Followup & Followup of Previously Identified Items ML20127E9461993-01-0808 January 1993 Notice of Violation from Insp on 921027-1207.Violation Noted:Licensees Corrective Actions Not Effective in That,On 921112 & 15,access Doors to Plant Issue Warehouse Not Controlled by Authorized Personnel PNO-V-93-001, on 930104,Licensee Notified Region V That Util Board Decided That Plant Will Not Be Restarted & Currently Shutdown for Insp & Repair of SG Tubes.Licensee Notified Media1993-01-0404 January 1993 PNO-V-93-001:on 930104,Licensee Notified Region V That Util Board Decided That Plant Will Not Be Restarted & Currently Shutdown for Insp & Repair of SG Tubes.Licensee Notified Media IR 05000344/19920341992-12-31031 December 1992 Meeting Rept 50-344/92-34 on 921201.Areas Discussed:Sg Tube Leak & Licensees Subsequent Insp of SGs IR 05000344/19920331992-12-29029 December 1992 Insp Rept 50-344/92-33 on 921207-11.No Violations or Deviations Noted.Major Areas Inspected:Licensee Erosion/ Corrosion Program Activities,Including Followup of Previously Identified Items IR 05000344/19920281992-12-21021 December 1992 Insp Rept 50-344/92-28 on 921109-1215.No Violations or Deviations Noted.Major Areas Inspected:Rev 7 to Emergency Plan Implementing Procedure EP-001, Emergency Classification PNO-V-92-038, on 921209,B Roberts Plans to Notify News Media of Request of or Energy Facility Siting Council to Hold Hearing on Utility Steam Generator Safety1992-12-0808 December 1992 PNO-V-92-038:on 921209,B Roberts Plans to Notify News Media of Request of or Energy Facility Siting Council to Hold Hearing on Utility Steam Generator Safety PNO-V-92-037, on 921201,meeting Conducted at Plant to Address 921109 Steam Generator Tube Leak & Licensee Request for Emergency TS Change to Permit Restart1992-12-0101 December 1992 PNO-V-92-037:on 921201,meeting Conducted at Plant to Address 921109 Steam Generator Tube Leak & Licensee Request for Emergency TS Change to Permit Restart ML20126E9101992-11-25025 November 1992 Notice of Violation from Insp on 920915-1026.Violation Noted:Supervisor Informed of Receipt of a Nonconforming Component,Chlorine Detector & Did Not Initiate an Ncr ML20126E9131992-11-25025 November 1992 Notice of Deviation from Insp on 920915-1026.Deviation Noted:Containment Air Locks Not Tested Using Pressure Decay Method IR 05000344/19920301992-11-25025 November 1992 Insp Rept 50-344/92-30 on 920915-1026.Violations Noted. Major Areas Inspected:Operational Safety Verification, Maintenance,Surveillance & Followup of Previously Identified IR 05000344/19920311992-11-10010 November 1992 Insp Rept 50-344/92-31 on 920928-1002.No Violations Noted. Major Areas Inspected:Environ Monitoring,Cr Ventilation & Control of Radwaste Activities PNO-V-92-004, on 920225,Trojan Power Plant Entered Mode 2 After Extended Outage.Plant Currently Critical at Less than 1 Percent Power & Licensee Conducting Low Power Physics Testing.Tests Expected to Be Completed by 9202271992-02-25025 February 1992 PNO-V-92-004:on 920225,Trojan Power Plant Entered Mode 2 After Extended Outage.Plant Currently Critical at Less than 1 Percent Power & Licensee Conducting Low Power Physics Testing.Tests Expected to Be Completed by 920227 IR 05000344/19910161991-06-0404 June 1991 Insp Rept 50-344/91-16 on 910506-16.No Violations or Deviations Noted.Major Areas Inspected:Proposed Rev 6 to Emergency Procedure (EP)-001, Emergency Classification PNO-V-91-002, on 910303,Trojan Declared an Unsual Event & Initiated Plant Shutdown Due to Inability to Meet Requirements of TS 3.8.2.1,which Requires That Four 120 Volts AC Preferred Instrument Busses Be Operable1991-03-0505 March 1991 PNO-V-91-002:on 910303,Trojan Declared an Unsual Event & Initiated Plant Shutdown Due to Inability to Meet Requirements of TS 3.8.2.1,which Requires That Four 120 Volts AC Preferred Instrument Busses Be Operable ML20062F9301990-11-0808 November 1990 Notice of Violation from Insp on 900902-1006.Violation Noted:Temp of Train B Component Cooling Water Pump (ASME Code Class 3 Pump) Taken W/Instrument W/Scale More than Three Times Ref Value of Bearing Temp PNO-V-90-045, State of or Measure 4 Re Closure of Facility Defeated in 901106 Vote.Util Will Hold News Conference1990-11-0707 November 1990 PNO-V-90-045:State of or Measure 4 Re Closure of Facility Defeated in 901106 Vote.Util Will Hold News Conference 1999-09-09
[Table view] |
Inspection Report - Trojan - 1987001 |
---|
|
|
Text
..
,
.,
,
-
.
. 7 - _, ,
- '
'. i - ' , < .
'
3;'
'
-1 _
J 1
,A' ;l
~c.n_'Q;D, , .? .;,, :q,,
,
>
'
,
? _
,. (;j > ' t;- r .
-
.
-
, . y .o _%- , .
-
/ -
. ~..
,U. ' S. NUCLEAR REGULATORY COMISSION . -
y
' ' ~
'
,,; , ,
'
e
-
4 %. . , .
<
-
3 ' REGION V' V '.l . '
'
.
'*-
~
.
. a ' ;; ,
'n ' n,
-s - .
+ , ,a;i.... L Report No. 450-344/87-01 3 ' '" - N 4
'
x , ,
,
. , .
~ ~
, .e ,
, , .. s
,
'
"
- '. , ,.;e
'
-
Dock'et No. 50-344 "/^ i s I!(r ' ' ,
-
.
~
, .,
_
,.
License'No. NPF-1- I '
- ,, , 1 C,. . '
. .s
'
__
~
- .
t : ,
-
Licens'ee: _
Portland. General Electric' Company 3 -
'
,
-
' ,#121 S.;W.' Salmon' Stree i~ '
'
-Portland, Oregon 97204:
~
. .
_
, Facility Name: ,TrojanNuclearPlant
'
Inspection at: P etland' General Elec hic Company Headquarters, Portl'and, s
-
regon <
Report Prepared,by: ad &%)[ + +
[ / #f /7 ;
D. B. Pereira, Reactor Inspector - -Date Signed Approved'by:
-
" ~
b ' ?
'M. M. Mendonca, Chief
.
. Date Signed-Reactor Projects Section 1 ,
-
'
Meeting Summary:
'
^
M4eting on January 23, 1987 (Meeting Report No. 50-344/87-01)
-
. Scope: SALP management-meeting to discuss the results of the NRC assessment >
of 3the licensee's performance from November 1, 1985 through,0ctober 31, 1986, ,
'
.as part.of the NRC's Systematic. Assessment of Licensee Performance (SALP)
program. Specific areas addressed included: Engineering and Construction, Quality Assurance,' Radiological Controls,' and Trainin ~Results: A summary of the NRC licensee performance assessment:was presente ,
9 e
'
f
%
B702240176 870202 '
PDR ADOCK 05000344 G PDR -
'
.
' A (
., -
.
DETAILS Meeting Attendees
-
- Licensee Attendees
,
W. J. Lindblad, President T. D. Walt, Manager, Radiological Safet C. P. Yundt, General Manager, Technical Functions C. A. Olmstead, Trojan Plant General Manager A. N. Roller, Manager,-Nuclear Plant Engineering-G. A. Zimmerman, Manager, Nuclear Regulation Branc D. R. Keuter, Manager, Technical ~ Services -
M. C. Street, General Manager, Security ' NRC Attendees J. B. Martin, Regional Administrator
~
B. H. Faulkenberry, Deputy' Regional Administrator D. F. Kirsch, Director, Reactor Safety and Projects R. A. Scarano,' Director, Radiological Safety and-Safeguards M. M. Mendonca, Chief, Reactor Projects Section 1 J. L. Crews, -Senior Reactor Engineer S. A. Richards,-Chief, Engineering Section D. B. Pereira, Project Inspector G.' Kellund, Resident Inspector J. L. Montgomery, Branch Chief, Nuclear Materials Safety and Safeguards R. C. Barr, Senior Resider.t Inspector G.- Yuhas, Chief, Facilities Radiological Protection Section F. Wenslawski, Branch ~ Chief, Emergency Preparedness and
. Radiological Protection G. Suh, Resident Inspector Oregon Department of Energy M. W. Alsworth, Manager, Reactor Safety 2. Results of SALP The NRC SALP Board conclusions and recommendations were discusse The licensee representatives discussed their perception of the SALP report and described actions planned to address specific items in the repor The discussion centered around the licensee's ability to utilize available resources to critically assess events Jnd deficiencies in the operation of their facility and then to followup their assessment with thorough corrective actio The following functional areas of identified concerns were discussed:
_
.
. - 4
. .
, ,
p
,,,.
V
, Engineering and Construction
.(1)' Several violations were discussed and the' root cause appeared
'
<
.to'be a lack of understanding of the design basis and proper operation of the' system by the licensee's staf (2) The licensee was encouraged to continue its engineering design basis development program and implementation of the systems engineer progra (3) The integration of the engineering improvement program into-
-operations, maintenance, testing and training was discussed and recognized as a major contributor to the licensee's performance in this fun,ctional are The' licensee committed to continuing the design basis development-and systems engineer program The licensee had presently 25 system engineers and,5 supervisory engineers in the program, Quality Assurance Reorganization
'
(1) -The licensee. was encouraged to continue the increase involvement in site maintenance activities by the Quality Assurance (QA) organizatio It was noted that an additional 14 personnel were added to the QA staff making a total of 40, which all but eight are at the sit (2) Formation of the Performance Monitoring / Events Analysis group was taken as a positive step of monitoring and trending licensee activities and in identifying areas of declining performanc (3) The licensee was to be commended for the work done last year in this area, however, they should understand that they are in a critical stage of personality development and that a lot of effort and improvements were still neede The licensee stressed their continued support of the QA involvement in the site activities as well as *he serformance monitoring / events analysis group. The licensee +ch IN the QA organization was getting better.and was~more agg: aio in its audits of plant activities.' In' addition, the Qn pec.,r,nel were having a higher involvement of all activities, rather than just surveillance actiritie Radiological Controls Several licensee problems were discussed, notably the spent resin cask transfer event, inadequacies in controls for issuance of respirators'to workers, failure to maintain records of radiation and contamination surveys, and lack of attention to detai ,, __ m
.
. , , 3 ,
- ,,
- ~
. 3; ,
'
1 4 The licensee agreed that -lack of attention to detail was a major'
-
problem in this functional area as discovered in a QA audit. The
-
' licensee stressed that there were significant changes in procedures
-
and more quality control and QA involvement in radiological control activities. .The license indicated that holding people accountable would be a major step in: eliminating some of the problem ' Training
'
~
(1) -The' Board recognizes.INP0 accreditation'of training areas are 77 progressing satisfactor '
,(2) , A site specific . simulator acquisition was encourage ~
, (3) Careful. assessment of the need for resources should continue to s be a focus of PG The licensee. responded that its trairing department has approximately 25 personnel, and that its plans are to ensure full
.INP0 accreditation by the end of 1987. .The si te speci fic s mu i lato contract will be forthcoming in May; 1987iwith the simulator to be
'
operational in 198 .
,
d
i
,
N
^L
>
s i
f 1