IR 05000334/2025004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000334/2025004 and 05000412/2025004
ML26028A061
Person / Time
Site: Beaver Valley
Issue date: 01/28/2026
From: Glenn Dentel
Division of Operating Reactors
To: Blair B
Vistra Operations Company
References
IR 2025004
Download: ML26028A061 (0)


Text

January 28, 2026

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - INTEGRATED INSPECTION REPORT 05000334/2025004 AND 05000412/2025004

Dear Barry Blair:

On December 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2. On January 12, 2026, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Glenn T. Dentel, Acting Chief Projects Branch 2 Division of Operating Reactor Safety

Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000334 and 05000412

License Numbers:

DPR-66 and NPF-73

Report Numbers:

05000334/2025004 and 05000412/2025004

Enterprise Identifier: I-2025-004-0041

Licensee:

Vistra Operations Company, LLC

Facility:

Beaver Valley Power Station, Units 1 and 2

Location:

Shippingport, PA

Inspection Dates:

October 1, 2025 to December 31, 2025

Inspectors:

N. Day, Senior Resident Inspector

A. Nugent, Resident Inspector

P. Cataldo, Senior Reactor Inspector

B. Dyke, Senior Operations Engineer

R. Rolph, Senior Health Physicist

C. Henckel, Operations Engineer

Approved By:

Glenn T. Dentel, Acting Chief

Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees

performance by conducting an integrated inspection at Beaver Valley Power Station, Units 1

and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the

NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer

to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On August 7, 2025, the unit started

coast down operations for the upcoming Unit 1, refueling outage 30. The unit was shut down for

refueling outage 30 on October 12, 2025. The unit was returned to rated thermal power on

November 25, 2025, and remained at or near rated thermal power for the remainder of the

inspection period.

Unit 2 operated at or near rated thermal power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in

effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with

their attached revision histories are located on the public website at http://www.nrc.gov/reading-

rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared

complete when the IP requirements most appropriate to the inspection activity were met

consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection

Program - Operations Phase. The inspectors performed activities described in IMC 2515,

Appendix DProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 2515,</br></br>Appendix D" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., Plant Status, observed risk significant activities, and completed on-site portions of

IPs. The inspectors reviewed selected procedures and records, observed activities, and

interviewed personnel to assess licensee performance and compliance with Commission rules

and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated readiness for seasonal extreme weather conditions prior to

the onset of extreme cold for the following systems:

Unit 2, service water underground valve pits on December 1, 2025

Unit 1, emergency diesel generators (EDGs) on December 2, 2025

Units 1 and 2, turbine buildings on December 2, 2025

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1)

Unit 1, 1-1 EDG starting air system, December 2, 2025

(2)

Unit 2, 'A' auxiliary feedwater following completion of Unit 2 23B auxiliary feedwater

pump test per 2OST-24.3, December 9, 2025

(3)

Unit 2, diesel fuel oil system, trains 'A' and 'B' following restoration from licensee

inspection of Unit 2 EDG 2-2 fuel oil transfer pump per Drawing RM-0436-001,

December 10, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a

walkdown and performing a review to verify program compliance, equipment functionality,

material condition, and operational readiness of the following fire areas:

(1)

Unit 2, fan room, cable spreading area, west communication room, and

instrumentation and relay area, fire areas 2-CB-5, 3-CR-1, 2-CB-4, 2-CB-1, and

2-CB-6, October 2, 2025

(2)

Units 1 and 2, intake structure, fire areas 3-IS-1, 3-IS-2, 3-IS-3, 3-IS-4, and 3-IS-6,

December 1, 2025

(3)

Unit 2, safeguards building 737' elevation, fire areas 2-SG-1S and 2-SG-1N,

December 3, 2025

71111.08P - Inservice Inspection Activities (PWR)

The inspectors verified, through remote document review following the government shutdown,

that the reactor coolant system (RCS) boundary, reactor vessel internals, risk-significant piping

system boundaries, and containment boundary are appropriately monitored for degradation and

that repairs and replacements were appropriately fabricated, examined, and accepted by

reviewing the following activities at Beaver Valley Unit 1, during refueling outage 1R30, from

November 17 through December 12, 2025.

PWR Inservice Inspection Activities Sample - Nondestructive Examination (NDE) and Welding

Activities (IP Section 03.01) (1 Sample)

The inspectors verified that the following nondestructive examination and welding activities

were performed appropriately:

(1)

American Society of Mechanical Engineers (ASME)Section XI Repair and

Replacement (R&R) activity, for replacement of Class 2 river water piping

segment WR-87, under order 200956059, including welding, phased array

ultrasonic testing (UT) of welds F01, F03, and F04, and radiographic testing

(RT) of weld F02; NDE reports for UT contained in IIA Report No. 25-01-434

and RT contained in TEAM Report No. 1100-006602-01-CR-1Jl

Class I Volumetric UTs of reactor coolant butt weld RC-71-8-S-02 (NDE

Report UT-BV-1R30-025), safety injection butt weld SI-260-1502-Q1 (NDE

Report UT-BV-1R30-021) and safety injection butt weld SI-261-1502-Q1 (NDE

Report UT-BV-1R30-022)

Remote UT of ten (10), remaining thermal shield support block bolts

(Westinghouse NDE Report WDI-PJF-353109-NDE-002)

Remote Enhanced Visual Inspection (EVT-1) of Rx Vessel Internals (thermal

shield support block bolts, 330 degree thermal shield flexure, and core barrel

upper girth weld); Westinghouse NDE Report WDI-PJF-353109-EPP-001,

Revision 1

General Visual examination of the containment liner and moisture barrier

under 1BVT-1.47.1, Containment Structural Integrity Test, Revision 18, Work Order 200924126, and Condition Report (CR)-2025-07827

  • Augmented visual examination of reactor vessel bottom-mounted

instrumentation nozzles, based on ASME Code Case N-722, Category B15.80

(NDE Report VT-BV-1R30-017) and Category B15.100 (NDE Report VT-BV-

1R30-151)

PWR Inservice Inspection Activities Sample - Vessel Upper Head Penetration Inspection

Activities (IP Section 03.02) (1 Sample)

The inspectors verified that the licensee conducted the following vessel upper head

penetration inspections and addressed any identified defects appropriately:

(1)

Visual examination based on ASME Code Case N-729-6, of penetrations 48

and 55 (Westinghouse NDE Report WDI-PJF-352692-NDE-002)

Volumetric examination of 62 reactor pressure vessel head penetrations,

based on ASME Code Case N-729-6 and applicable requirements of Title 10

of the Code of Federal Regulations 50.55a

PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities

(IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program

through a review of the following evaluations:

(1)

Boric acid evaluation and corrective actions for 1RC-241 (CR-2025-07257)

Boric acid evaluation and corrective actions for 1RC-459 (CR-2025-07266)

Boric acid evaluation and corrective actions for the 1B residual heat removal

heat exchanger (CR-2025-07908)

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1)

The inspectors reviewed and evaluated the licensed operator examination failure

rates for the Unit 1 requalification annual operating exam completed on April 3, 2025.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1)

The inspectors observed and evaluated licensed operator performance in the control

room during the Unit 1 plant shutdown for 1R30 on October 12, 2025.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1)

The inspectors observed and evaluated "just in time" operator simulator training

session for the Unit 1 shutdown preparations for 1R30 on October 9, 2025.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (4 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following

structures, systems, and components (SSCs) remain capable of performing their intended

function:

(1)

Unit 1, containment, system 47, October 7, 2025

(2)

Unit 1, river water, system 30, December 12, 2025

(3)

Unit 1, rod control and protection system, system 1, December 15, 2025

(4)

Unit 1, 4KV electrical, system 36, December 17, 2025

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to

ensure the following SSC remains capable of performing its intended function:

(1)

Unit 1, hydraulic oil for feedwater isolation system evaluated for equivalency via

Notification (NOTF) 601507590, November 13, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the

following planned and emergent work activities to ensure configuration changes and

appropriate work controls were addressed:

(1)

Unit 1, Yellow risk window for decay heat removal during 1R30, October 15, 2025

(2)

Unit 1, plant protection scheme for low heat safety injection pump B unavailability,

December 12, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the

following operability determinations and functionality assessments:

(1)

Unit 1, residual heat removal flow control valve due to flow fluctuation as described in

CR 2025-08052, October 28, 2025

(2)

Unit 1, transition to Mode 4 using Limiting Condition for Operation (LCO) 3.0.4.b with

inoperable recirculation spray train 'A', November 18, 2025

(3)

Unit 1, turbine driven auxiliary pump run differential pressure during Mode 3 following

refueling outage per CR 2025-08780 during 1OST-24.9, November 19, 2025

(4)

Units 1 and 2, operability determination for Unit 1, RCS pressure detector and Unit 2,

main steam pressure detector following Part 21 notification from Rosemount Nuclear

Instruments made on November 25, 2025, per CR 2025-09136, December 4, 2025

(5)

Unit 2, turbine driven auxiliary feedwater pump alignment per Licensing

Requirements Manual Table 3.6.1-1 for inoperable 2MSS-SOV105D per CR 2025-

008799, December 15, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)

Limited Use Change to 1OM-7.4.A to allow isolation of the RCP seal injection header

during CVCS startup in order to fill reactor cavity with charging pumps for refueling,

rather than the low head safety injection pumps, on October 18, 2025

(2)

Temporary plant power due to replacement of transformer 1-9 via design equivalent

change package 23-1030-003, October 14, 2025

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated Unit 1 refuel outage 30, from October 12 to

November 20, 2025.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system

operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (6 Samples)

(1)

Unit 1, EDG 1-2 following outage maintenance per 1OST-36.2, October 22, 2025

(2)

Unit 1, EDG 1-1 following outage maintenance per 1OM-36.AV, 1OM-36.4.AM, and

operability evaluation in CR 2025-8381, November 7, 2025

(3)

Unit 1, recirculation spray heat exchanger 'C' minimum wall weld repair and welding

NDE per Work Order 200984933, November 10, 2025

(4)

Unit 1, recirculation spray heat exchanger 'A' post tube sheet plugging pressure

testing per Work Order 200986227, November 12, 2025

(5)

Unit 1, type B test of river water outlet piping mechanical expansion joint from

recirculation spray heat exchanger 'A' following replacement of mechanical expansion

joint and heat exchanger outlet piping per Work Order 200956058, November 17,

2025

(6)

Unit 1, EDG 1-1 run following maintenance on the 1A fuel transfer pump per 1OST-

36.1, December 16, 2025

Surveillance Testing (IP Section 03.01) (1 Sample)

(1)

Unit 1, low head safety injection pump 'B' quarterly test per 1OST-11.2 on

December 11, 2025

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1)

Unit 2, low head safety injection pump test per 2OST-11.2, October 7, 2025

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)

Unit 1, containment penetration 17 which underwent local leakage rate testing per

1OST-47.116 on October 22, 2025

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1)

The inspectors evaluated how the licensee identifies the magnitude and extent of

radiation levels, identifies the concentrations and quantities of radioactive materials,

and assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1)

The inspectors evaluated how the licensee instructs workers on plant-related

radiological hazards and the radiation protection requirements intended to protect

workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and

controlling contamination and radioactive material:

(1)

Licensee surveys of potentially contaminated material leaving the Unit 2 radiologically

controlled area

(2)

Workers exiting the Unit 1 radiologically controlled area

Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following

radiological work:

(1)

Transfer Canal decontamination

(2)

Reactor Head and Internals moves

(3)

Reactor Head inspections

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (3 Samples)

The inspectors evaluated licensee controls of the following high radiation areas and very

high radiation areas:

(1)

Unit 1, Chemical and Volume Control Tank Room

(2)

Unit 2, Chemical and Volume Control Tank Room

(3)

Dry Drum Storage area

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section

03.06) (1 Sample)

(1)

The inspectors evaluated licensee records to determine radiation worker and

radiation protection technician performance as it pertains to radiation protection

requirements.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (2 Samples)

(1)

Unit 1 (October 1, 2024 through September 30, 2025)

(2)

Unit 2 (October 1, 2024 through September 30, 2025)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1)

Unit 1 (October 1, 2024 through September 30, 2025)

(2)

Unit 2 (October 1, 2024 through September 30, 2025)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1)

October 1, 2024 through September 30, 2025

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual

Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample

(IP Section 02.16) (1 Sample)

(1)

October 1, 2024 through September 30, 2025

71152A - Annual Follow-up Problem Identification and Resolution

Annual Follow-up of Selected Issues (Section 03.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program

related to the following issues:

(1)

The inspectors reviewed CR-2025-00331, CR-2025-08345, CR-2025-08462, and CR-

2025-08674 and corrective action procedures to assess the effectiveness of the

licensee in prioritizing and evaluating the quench spray QS-1 piping leak and

repairs. The inspectors focused on the extent of condition reviews performed via

NDEs for similar piping.

71152S - Semiannual Trend Problem Identification and Resolution

Semiannual Trend Review (Section 03.02) (1 Sample)

(1)

Following multiple minor transient combustible storage issues, the inspectors

reviewed the licensees corrective action program to identify potential trends in

storage of combustible materials that might be indicative of a more significant safety

issue.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this

report.

  • On January 12, 2026, the inspectors presented the integrated inspection results to

Barry Blair, Site Vice President, and other members of the licensee staff.

On December 12, 2025, the inspectors presented the Refueling Outage 1R30 Inservice

inspection results to Hope Gilliam, Manager of Regulatory Compliance, and other

members of the licensee staff.

On December 18, 2025, the inspectors presented the RP PI Verifications inspection

results to Barry Blair, Site Vice President, and other members of the licensee staff.

On December 18, 2025, the inspectors presented the Radiological Hazard Assessment

and Exposure Control inspection results to Barry Blair, Site Vice President, and other

members of the licensee staff.