IR 05000334/2025401
| ML25350A376 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 12/16/2025 |
| From: | Brice Bickett Decommissioning, ISFSI, and Reactor Health Physics Branch |
| To: | Blair B Vistra Operations Company |
| References | |
| IR 2025401 | |
| Download: ML25350A376 (0) | |
Text
December 16, 2025
SUBJECT:
BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - SECURITY BASELINE INSPECTION REPORT 05000334/2025401 AND 05000412/2025401
Dear Barry Blair:
On December 11, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2, and discussed the results of this inspection with Bob Kristophel, General Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Brice A. Bickett, Chief Security, Emergency Preparedness and Incident Response Branch Division of Radiological Safety & Security
Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000334 and 05000412
License Numbers:
Report Numbers:
05000334/2025401 and 05000412/2025401
Enterprise Identifier: I-2025-401-0014
Licensee:
Vistra Operations Company, LLC
Facility:
Beaver Valley Power Station, Units 1 and 2
Location:
Shippingport, PA
Inspection Dates:
December 08, 2025 to December 11, 2025
Inspectors:
C. Davis, Physical Security Inspector
Approved By:
Brice A. Bickett, Chief
Security, Emergency Preparedness and Incident Response Branch
Division of Radiological Safety & Security
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Beaver Valley Power Station, Units and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
SAFEGUARDS
71130.01 - Access Authorization
The inspectors evaluated the access authorization program. The following elements were evaluated:
Access Authorization (1 Sample)
- (1) 20 Requirements (02.01 a - c, 02.02 a - j, 02.03 a - c, 02.04 a, 02.05 a, b, 02.07 a)
71130.08 - Fitness For Duty Program
The inspectors evaluated the fitness for duty program by completing the following inspection elements:
Fitness For Duty Program (1 Sample)
(1)23 Requirements (02.01 a, 02.02 a, 02.03 a, b, 02.04 a - c, 02.05 a - d, f - l, 02.06 a, b, d, 02.10, 02.12 a)
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified that no proprietary information was retained or documented in this report.
- On December 11, 2025, the inspectors presented the security baseline inspection results to Bob Kristophel, General Plant Manager, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
23-03998
23-04705
23-04706
23-08659
23-07871
23-08691
23-08691
24-01756
24-01908
25-00405
25-01331
25-03465
25-03891
25-04083
25-04088
Procedures
FLT-SY-9000
Access Authorization Program
Revision 0
Self-Assessments EVAL-2025-0002
25 AA-PADS FFD Audit Report
Corrective Action
Documents
23-00882
23-01641
23-03998
24-03637
24-04177
Procedures
Generic Fitness-for-Duty and Behavior Observation Lesson
Plan
Revision 4
Generic Plant Access Training Lesson Plan
November
21
FLT-AS-PL0013
Fitness for Duty Policy
FLT-SY-9100
Fitness for Duty Program
Revision 0