IR 05000331/2025002

From kanterella
Jump to navigation Jump to search
Restart Inspection Report 05000331/2025002
ML25345A204
Person / Time
Site: Duane Arnold 
Issue date: 12/11/2025
From: April Nguyen
NRC/RGN-III/DORS
To: Wheaton R
NextEra Energy Duane Arnold
References
IR 2025002
Download: ML25345A204 (0)


Text

SUBJECT:

DUANE ARNOLD ENERGY CENTER - RESTART INSPECTION REPORT 05000331/2025002

Dear Ray Wheaton:

On August 31, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed inspections at Duane Arnold Energy Center. The enclosed inspection report documents these inspection results, which the inspectors discussed on September 10, 2025, with Justin Both and other members of your staff.

Due to the temporary cessation of government operations, which commenced on October 01, 2025, the NRC began operating under its Office of Management and Budget-approved plan for operations during a lapse in appropriations. Consistent with that plan, the NRC operated at reduced staffing levels throughout the duration of the shutdown.

However, the NRC continued to perform critical health and safety functions and make progress on other high-priority activities associated with the ADVANCE Act and Executive Order 14300.

On November 13, 2025, following the passage of a continuing resolution, the NRC resumed normal operations. However, due to the 43-day lapse in normal operations, the Office of Nuclear Reactor Regulation granted the Regional Offices an extension on the issuance of the calendar year 2025 inspection reports that should have been issued by November 13, 2025, to December 31, 2025. The NRC resumed the routine cycle of issuing inspection reports on November 13, 2025.

No violations of more than minor significance were identified during this inspection.

December 11, 2025 On August 27, 2020, Duane Arnold ceased permanent power operations as detailed in the letter from NextEra to the NRC, Certification of Permanent Cessation of Power Operations, (Agencywide Document Access and Management System (ADAMS) Accession No. ML20240A067). On October 12, 2020, NextEra removed all fuel from the reactor, as detailed in the letter from NextEra to the NRC, Certification of Permanent Removal of Fuel from the Reactor Vessel for Duane Arnold Energy Center, (ADAMS Accession No. ML20286A317). On January 23, 2025, NextEra submitted a letter to the NRC requesting exemptions from certain portions of the requirements of Title 10 of the Code of Federal Regulations (10 CFR) 50.82(a)(2) to pursue the potential reauthorization of power operations at Duane Arnold (ADAMS Accession No. ML25023A270). The NRCs initial acceptance to review Duane Arnolds request for exemptions was documented in ADAMS at Accession No. ML25056A149 on February 27, 2025.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, April M. Nguyen, Lead Palisades Restart Team Division of Operating Reactor Safety Docket No. 05000331 License No. DPR-49 Enclosure:

As stated cc w/ encl: Distribution via LISTSERV Signed by Nguyen, April on 12/11/25

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) performed inspections of the licensees activities to verify radiation safety activities were appropriately performed, work activities were appropriately planned and executed with safety measures in place for heavy lifts, and preliminary onsite in-vessel visual inspection (IVVI) activities.

List of Violations No violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The Duane Arnold Energy Center ceased power operations and subsequently removed all fuel from the reactor, as certified in a letter to the NRC on October 12, 2020. On January 23, 2025, NextEra submitted a letter to the NRC requesting exemptions from certain portions of the requirements of 10 CFR 50.82(a)(2) to pursue the potential reauthorization of power operations.

The NRC is conducting inspections to evaluate and assess the licensees activities for potential restoration to an operational status.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the referenced inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted.

Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

REACTOR SAFETY

CORNERSTONES

71111.08G - Inservice Inspection Activities (BWR)

Nondestructive Examination and Welding Activities (IP Section 03.01)

From June 2 to June 27, 2025, the inspectors observed and verified Duane Arnolds nondestructive examination (NDE) activities of the reactor pressure vessel (RPV) conducted in accordance with the requirements of the American Society of Mechanical Engineers (ASME)

Code Section XI and BWRVIP-03, BWR Vessel and Internals Project, Reactor Pressure Vessel and Internals Examination Guidelines, Revision 21. The purpose of these inspections was to verify that the reactor coolant system boundary, reactor vessel internals, and risk-significant piping system boundaries are appropriately monitored for degradation. The NRC inspectors also verified that the examination results were thoroughly reviewed and appropriately evaluated, and that required corrective actions to address identified indications and defects will be appropriately implemented. During this inspection period, Duane Arnold completed the NDE activities and evaluation of the data. Further NRC inspections will occur as additional activities are conducted.

The inspectors verified that the following nondestructive examination activities were conducted appropriately per the ASME Code or required standard, and that any potential indications and defects were identified and evaluated at the proper thresholds:

BWRVIP Reactor Internals Exams

ASME Section XI

  • VT of surveillance sample holder bracket to RPV welds (Cat. B-N-2, Item B13.20)
  • VT of upper and lower guide rod brackets and feedwater sparger end bracket attachment welds (Cat. B-N-2, Item B13.30)
  • VT of core shroud support welds, in core dry tubes, top guide (Cat B-N-2, Item B13.40)

71111.20 - Refueling and Other Outage Activities

Heavy Lifts (IP Section 03.01)

From March 25 to March 26, 2025, inspectors reviewed the licensees control of heavy loads program to ensure that lifts were performed in accordance with regulatory requirements and applicable industry standards. Since fuel has been removed from the facility, the licensee has eliminated their previous licensing basis requirements associated with the control of heavy loads program. However, the inspectors observed that the licensee generally continued to perform critical lifts in accordance with the previously established control of heavy loads program. Specifically, the inspectors reviewed documents associated with the inspection and testing of the reactor building overhead crane, slings, and special lifting devices for critical lifts within the reactor building.

The licensee identified one deviation from the previously established procedure.

However, the control of heavy loads requirements was not applicable in the current plant configuration. Specifically, there is no longer heating within the reactor building. The reactor building crane had a previously established minimum operating temperature for single failure proof lifts. During this evolution, the lift was going to be performed at a temperature below the cranes previously established limit. The licensee recognized this gap and implemented the required action to re-perform NDE on critical areas of the crane prior to any critical lifts associated with controlling heavy loads in the future. The licensee documented this observation in Condition Report CR 2510971, RB Crane Operation at Lower Temperatures, dated March 20, 2025.

From March 31 to April 2, 2025, inspectors observed on-site activities and preparations for the licensees lift of the RPV head. The inspectors assessed the RPV head lift operations via direct observation on the refuel floor. The inspectors attended the pre-job brief prior to the evolution, observed the rigging of the RPV head, and the load lift from the reactor cavity to the refuel floor.

RADIATION SAFETY

CORNERSTONE From March 25 through July 18, 2025, the inspectors conducted on-site inspection activities to assess the radiological protection program. These inspections were conducted during several radiological activities that utilized various aspects of the licensees radiation protection program.

These activities included entry into the drywell, reactor vessel disassembly, in-vessel inspections, and removal of several control rod mechanisms.

The inspectors performed walkdowns of the facility to assess radiological controls, including posting and labeling of radioactive material storage areas, High Radiation Areas (HRAs), and contamination areas. The inspectors noted that the labels for containers holding radioactive material had not been updated to reflect reduced dose rates and contamination levels based on 5 years of decay. In addition, the inspectors identified the door that had held the radiation area sign for the reactor building had been removed, and no new sign was posted at the access.

The inspectors concluded this was a minor violation of 10 CFR 20.1902(a), which requires that licensees post each radiation area with a conspicuous sign or signs bearing the radiation symbol and the words CAUTION, RADIATION AREA. The licensee immediately placed an appropriate posting to correct the issue. In addition, the inspectors observed workers monitoring out of the Radiologically Controlled Area (RCA). Although workers generally adhered to site procedures, the inspectors observed one instance in which an individual used a monitor to release a drill, contrary to site procedures. However, this drill had not been used on any equipment in the RCA, and the inspectors determined the survey that was performed was adequate and that no violation of NRC requirements occurred. The inspectors shared this observation with the licensee as an example of establishing clear expectations for the workforce.

The inspectors also observed and reviewed various radiological surveys that were conducted to support activities. The surveys observed included dose rate measurements, contamination surveys, and airborne radioactivity surveys. In addition to the observation of radiological surveys, the inspectors reviewed calibration records and routine source checks of various radiation detection instrumentation.

The inspectors observed several evolutions that included the use of temporary ventilation systems and respiratory protection to limit the intake of airborne radioactive material. The inspectors assessed whether breathing air systems provided respirable air, that individuals were qualified to wear respirators, and that the respirators were utilized appropriately. The inspectors noted that although the sites procedure discussed establishing breathing air pressure for airline respirators, none of the pressures in the procedure were above the minimum pressure that the vendor manual stated was required for the make/model being used. The inspectors brought this concern to the attention of the licensee. After reviewing the information, the licensee assessed the capability of their breathing air system to ensure it could accommodate the higher pressure and performed an emergent change to their procedure to increase the required pressure to align with the vendor manual prior to use of these respirators. The licensee also initiated an action to review the respiratory protection procedure in full.

In addition to observing activities to limit the intake of radioactive material, the inspectors observed many aspects of the program designed to control the amount of external radiation exposure received. This included observation of real-time, remote monitoring of accumulated dose via a telemetry system, use of routine electronic dosimetry monitoring, and use of extremity dosimetry.

In addition to observing activities related to occupational radiation safety, the inspectors reviewed aspects of gaseous effluent releases. In preparation for entering the drywell, the facility reinitiated the standby gas treatment (SBGT) system, which had been removed from service since the shutdown, and revised the decommissioning offsite dose assessment manual (DODAM) to reflect this change. The inspectors reviewed the changes to the DODAM and walked down accessible portions of the SBGT system, including the filter trains, to verify the system was in-tact and functioning. In addition, the inspectors reviewed effluent sampling results and subsequent dose calculations performed for periods in which SBGT was in operation. The inspectors also reviewed a routine liquid effluent release sample and analysis.

The inspectors conducted these reviews using IP 71124.01, Radiological Hazard Assessment and Exposure Controls, 71124.03, Airborne Radioactivity, 71124.04, Occupational Dose Assessment, 71124.05, Radiation Monitoring Instrumentation, and 71124.06, Radioactive Gaseous and Liquid Effluent Treatment, as applicable.

INSPECTION RESULTS

No violations of more than minor significance were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified that no proprietary information was retained or documented in this report.

  • On September 10, 2025, the inspectors presented the inspection results to Justin Both, Director of Restart Construction, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08G

NDE Reports

180-9394693-000

Duane Arnold Energy Center Unit 1 Restart Project IVVI

Final Report Summer 2025

08/19/2025

71111.08G

NDE Reports

GARN1-RFO25-

29970

In Vessel Visual Inspection (IVVI) of Reactor Pressure

Vessel Internal Components Duane Arnold Energy Center:

Refueling Outage (RFO) 25

10/20/2016

71111.08G

Procedures

BWRVIP Administrative Document

71111.08G

Procedures

Augmented Inspection Administrative Document

71111.08G

Procedures

54-ISI-173-008

ASME Section XI Examination Coverage

71111.08G

Procedures

54-ISI-30-030

Written Practice for the Qualification and Certification of NDE

Personnel for ASME BPVC Section XI

71111.08G

Procedures

54-ISI-363-011

Remote Visual Examination of Reactor Pressure Vessel

Internals, Components, and Associated Repairs in Boiling

Water Reactors

71111.08G

Procedures

54-ISI-650-002

ASME Section XI Flaw Characterization

71111.08G

Procedures

ACP 1211.36

Reactor Pressure Vessel Inspection Procedure 71111.20

Corrective Action

Documents

2510971

RB Crane Operation at Lower Temperatures

03/20/2025

71111.20

Work Orders

41002152-01

Reactor Building Crane Periodic Inspection and Lubrication

03/26/2025

71111.20

Work Orders

41002152-02

Perform NDE on Critical Welds on Bridge

03/20/2025

71111.20

Work Orders

41002152-03

Tool E189 Five-Year QC NDE and Dimensional Examination

03/26/2025

71111.20

Work Orders

41002152-04

Tool-E190A: Five-year QC NDE and Dimensional

Examination

03/20/2025

71111.20

Work Orders

41002152-05

Tool-E195 Inspect Remote Shield Block Lifting Device

03/20/2025

71111.20

Work Orders

41002152-06

Tool E199: Perform Five-year QC NDE of Critical Welds

03/20/2025

71111.20

Work Orders

41002152-07

Tool E198: Five-Year QC NDE and Dimensional

Examination

03/20/2025

71111.20

Work Orders

41002152-08

Inspect Slings

2/24/2025

71124.01

ALARA Plans

IVVI, Blade Inspection, OD and ID, Unlatching Drives

71124.01

ALARA Plans

Under Vessel Work to Include PIPs, De-Torque, Drive Pull,

Blank Flange and All Support Activities

71124.01

Corrective Action

Documents

2517240

NRC Identified: Missing Radiation Area Posting

06/11/2025

Resulting from

Inspection

71124.01

Corrective Action

Documents

Resulting from

Inspection

2517354

Worker Used SAM/TEM to Free Release Tool

06/12/2025

71124.01

Miscellaneous

Work Checklist for CRD Removal

05/28/2025

71124.01

Procedures

ACP 1411.23

Equipment and Material Controls in Radiologically Controlled

Areas

71124.01

Procedures

RP-AA-102-1000

Alpha Monitoring

71124.01

Radiation

Surveys

DA-M-20250319-

Dry well

03/19/2025

71124.01

Radiation

Surveys

HP048

Air Sample Record for Reactor Cavity

03/26/2025

71124.01

Radiation

Surveys

PDA-M-

201005-7

Reactor Cavity

10/05/2020

71124.01

Radiation

Surveys

PDA-M-

201006-3

Reactor Cavity

10/06/2020

71124.01

Radiation

Surveys

PDA-M-

250319-2

Drywell

03/19/2025

71124.01

Radiation

Surveys

PDA-M-

250326-1

Reactor Cavity Initial Entry

03/26/2025

71124.01

Radiation

Surveys

PDA-M-

250326-2

Reactor Cavity After Drywell Head Removal

03/26/2025

71124.01

Radiation

Surveys

PDA-M-

250611-1

RB5 Routine

06/11/2025

71124.01

Radiation Work

Permits (RWPs)

25-0008

Routine Security and Firewatch Entries

71124.01

Radiation Work

Permits (RWPs)

25-0051

Routine Work and Inspections

71124.01

Radiation Work

Permits (RWPs)

25-0112

Refuel Floor Work

71124.01

Radiation Work

Permits (RWPs)

25-3016

Restart: Refuel Pool Work

71124.01

Radiation Work

Permits (RWPs)

25-4009

DFO-All Drywell Work Activities

71124.01

Radiation Work

Permits (RWPs)

25-4040

Restart: CRD Project Support

71124.03

Corrective Action

Documents

Resulting from

Inspection

2519722

NRC Inspector Found a Respiratory Protection Procedure

Error

07/17/2025

71124.03

Miscellaneous

Honeywell North Air-Fed Suits - Mururoa MTH2 Technical

Information

N/A

71124.03

Miscellaneous

NRC Approval of Request From L-HU-05-010

2/28/2005

71124.03

Miscellaneous

Approval for Use of Delta Protection Mururoa V4F1 R

Supplied Air Suites Requested in L-2009-072

08/31/2009

71124.03

Miscellaneous

CC8414X2T-US

Mururoa MTH2 US Ventilated Protective Clothing

User Guide

G

71124.03

Miscellaneous

L-2009-072

Request for Use of Delta Protection Mururoa V4F1 R

Supplied Air Suites

04/28/2009

71124.03

Miscellaneous

L-HU-05-010

Request for Approval of Use of Delta Protection Respiratory

Protection Equipment

10/20/2005

71124.03

Procedures

ACP 1411.20

Respiratory Protection

71124.03

Procedures

HPP 3106.05

Breathing Air Quality Assurance Test

71124.05

Calibration

Records

Calibration record for Canberra Sirius-5PBG

Serial Number 2502-034-SRC5PGB

03/25/2025

71124.05

Calibration

Records

Calibration record for Canberra Sirius-5PBG

Serial Number 2502-035-SRC5PGB

03/25/2025

71124.05

Calibration

Records

Calibration of the Mirion Fastscan WBC System

04/25/2025

71124.05

Calibration

Records

Dosimeter 082373 Calibration Report

09/05/2025

71124.05

Calibration

Records

Dosimeter 097860 Calibration Report

09/05/2024

71124.05

Calibration

Records

Dosimeter 840570

Calibration Report

06/04/2024

71124.05

Calibration

Records

Dosimeter 968669

Calibration Certificate

01/15/2025

71124.05

Calibration

Records

Dosimeter 969048

Calibration Certificate

01/15/2025

71124.05

Calibration

AMS-4 IES HP1115 Certificate of Calibration

03/18/2025

Records

71124.05

Corrective Action

Documents

Resulting from

Inspection

2517240

HPP 3110.87 - Calibration of the ARGOS 5AB Personnel

Monitor

06/11/2025

71124.05

Procedures

HPP 3110.87

Calibration of the ARGOS 5AB Personnel Contamination

Monitor

71124.06

Miscellaneous

Defueled Offsite Dose Assessment Manual

71124.06

Work Orders

40988324

Gaseous Effluent Sampling and Analysis

06/11/2025

71124.06

Work Orders

40989742

Effluent Tritium Sampling and Analysis

06/23/2025

71124.06

Work Orders

41008685

In-Leakage Liquid Effluent Release Through Dilution

Structure

03/12/2025