IR 05000315/2024004

From kanterella
Jump to navigation Jump to search
Reissue - Donald C. Cook Nuclear Plant - Integrated Inspection Report 05000315/2024004 and 05000316/2024004
ML25056A100
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 02/25/2025
From: Nestor Feliz-Adorno
NRC/RGN-III/DORS/ERPB
To: Ferneau K
Indiana Michigan Power Co
References
IR 2024004
Download: ML25056A100 (1)


Text

SUBJECT:

REISSUE - DONALD C. COOK NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000315/2024004 AND 05000316/2024004

Dear Kelly Ferneau:

This reissuance corrected information contained in the description and corrective action sections for non-cited violation (NCV) 05000315,05000316/2024004-01 which was previously sent to you dated January 27, 2025 (ADAMS Accession No. ML25023A140).

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Donald C. Cook Nuclear Plant. On January 15, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as an NCV consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Donald C. Cook Nuclear Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Donald C. Cook Nuclear Plant.

February 25, 2025 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Néstor J. Féliz Adorno, Chief Engineering and Reactor Projects Branch Division of Operating Reactor Safety Docket Nos. 05000315 and 05000316 License Nos. DPR-58 and DPR-74

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000315 and 05000316

License Numbers:

DPR-58 and DPR-74

Report Numbers:

05000315/2024004 and 05000316/2024004

Enterprise Identifier:

I-2024-004-0056

Licensee:

Indiana Michigan Power Company

Facility:

Donald C. Cook Nuclear Plant

Location:

Bridgman, MI

Inspection Dates:

October 01, 2024, to December 31, 2024

Inspectors:

A. Guieb, Project Engineer

T. Hartman, Senior Project Engineer

Z. Helgert, Resident Inspector

E. Kokkinis, Project Engineer

J. Kutlesa, Senior Emergency Preparedness Inspector

J. Mancuso, Senior Resident Inspector

L. Rodriguez, Senior Reactor Analyst

Approved By:

Néstor J. Féliz Adorno, Chief

Engineering and Reactor Projects Branch

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Donald C. Cook Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Identify and Correct Condition Adverse to Quality Causes Damage to Rod Control Cluster Assembly Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000315,05000316/2024004-01 Open/Closed

[H.12] - Avoid Complacency 71152A A self-revealed finding of very low safety significance (i.e., Green) and an associated non-cited violation (NCV) of 10 CFR 50, Appendix B, Criterion XVI, Corrective Actions, were identified for the licensees failure to assure that conditions adverse to quality are promptly identified. Specifically, the licensee failed to identify an interference to the fuel upender during refueling activities. This interference contacted several safety-related rod control cluster assemblies (RCCAs) on top of the fuel assemblies (F/As) ultimately damaging the RCCA on F/A LS69.

Additional Tracking Items

Type Issue Number Title Report Section Status URI 05000316,05000315/20 23011-01 Safety-Related Motor Control Center Bus Bar Commercial Grade Dedication 71111.21N.03 Closed LER 05000316/2024-002-00 LER 2024-002-00 for Donald C. Cook Nuclear Plant, Unit 2, Manual Reactor Trip Following Rapid Downpower for Steam Leak 71153 Closed LER 05000316/2024-002-01 LER 2024-002-01 for Donald C. Cook Nuclear Plant, Unit 2, Manual Reactor Trip Following Rapid Downpower for Steam Leak 71153 Closed

PLANT STATUS

Unit 1 began the inspection period at rated thermal power. On November 21, 2024, Unit 1 experienced a power transient from a full open turbine control valve caused by a faulty controller. In response, the unit was manually lowered to 95 percent of rated thermal power. After fixing the controller, the unit returned to full rated thermal power on November 22, 2024, and remained at or near full rated thermal power for the remainder of the inspection period.

Unit 2 began the inspection period at rated thermal power. On December 14, 2024, Unit 2 reduced power to approximately 90 percent of rated thermal power for main turbine valve testing. The unit returned to full rated thermal power later the same day and remained at or near full rated thermal power for the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures on November 19, 2024

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 1 west essential service water (ESW) following planned surveillance on November 25, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 29 A/B: Unit 1 east/west ESW pump rooms, 591' elevation on October 4, 2024
(2) Fire pump house on October 24, 2024
(3) Fire Zone 12/22: quadrant 2 piping tunnel, Unit 1/2, 587'-0" on October 31, 2024
(4) Fire Zone 1/1A/B/E/F: auxiliary building basement and containment spray pump rooms, Unit 1/2, 573' on November 8, 2024

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on October 30, 2024

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 2-HE-15W, Unit 2 west component cooling water heat exchanger on December 18, 2024

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (2 Samples)

(1) The inspectors observed and evaluated RQ-S-4905 as-found simulator practice evaluation on October 22, 2024.
(2) The inspectors observed and evaluated an as-found simulator evaluation scenario on October 29, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples 1 Partial)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)

(Partial)

Unit 1 and 2 250 Volt Safety-Related Batteries

(2) Unit 2 Train B post-accident hydrogen monitoring system (PACHMS) and its 10 CFR 50.65 (a)(1) monitoring plan
(3) Auxiliary building Spent Fuel Pool ventilation system and its 10 CFR 50.65 (a)(1)monitoring plan

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) AB loop feed enclosure parts

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Risk management during 2 AB emergency diesel generator (EDG) work on October 16, 2024
(2) Risk management during 1W ESW relay testing on November 20, 2024
(3) Risk management during Unit 2 Train A reserve auxiliary transformer unplanned outage on December 12, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples 1 Partial)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) AR 2024-6650; Ice Bed Temperature Following Glycol Restoration on October 15, 2024
(2) AR 2024-8471; 1-HV-CLV-2A Lower Containment Fan Breaker failure on November 21, 2024
(3) AR 2024-5485; Neutra Clean on Batteries on December 9, 2024
(4) AR 2024-8838; Crack Identified on Cell 57 on December 11, 2024 (5)

(Partial)

AR 2024-9165; Unit 2 West ESW Outlet Check Valve Sticking on December 16, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (4 Samples)

(1)2-MRV-213 steam generator 1 power operated relief valve (PORV) PMT on October 7, 2024

(2) Unit 2 AB EDG following preventative maintenance on October 17, 2024
(3) Unit 1 CD EDG surveillance run following maintenance on October 29, 2024
(4) Unit 2 south safety injection pump run following preventative maintenance on December 19, 2024

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Unit 2 CD EDG monthly surveillance on October 3, 2024
(2) U2 turbine driven auxiliary feedwater pump planned quarterly surveillance run, on October 30, 2024

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) North Spent Fuel Pool surveillance, on November 7, 2024

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • PMP-2080-EPP-101, Emergency Classification, Revision 30
  • PMP-2080-EPP-101, Emergency Classification, Revision 31 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) RQ-E-4906; as-found simulator practice evaluation on December 10,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (October 1, 2023, through September 30, 2024)
(2) Unit 2 (October 1, 2023, through September 30, 2024)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Damage to the rod control cluster assembly on August 12, 2024
(2) Containment fire alarm response procedures and preparation changes on December 31, 2024

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in battery cell cracks that might be indicative of a more significant safety issue on November 15, 2024
(2) The inspectors reviewed the licensees corrective action program to identify potential trends in transients related to feedwater control that might be indicative of a more significant safety issue on November 25, 2024

===71153 - Follow-up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01) (1 Sample 1 Partial)

(1)

(Partial)

The inspectors evaluated the unexpected opening of a turbine control valve and licensees performance on November 21, 2024

(2) The inspectors evaluated an Unusual Event declaration due to an invalid fire alarm within containment and licensees response on November 3, 2024 Event Report (IP Section 03.02)===

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000316/2024-002-00, Unit 2 Manual Reactor Trip Following Rapid Downpower for Steam Leak, (ADAMS Accession No. ML24197A088) and LER 05000316/2024-002-01, Unit 2 Manual Reactor Trip Following Rapid Downpower for Steam Leak, (ADAMS Accession No. ML24256A172). The inspectors determined that the cause of the condition described in these LERs was not reasonably within the licensees ability to foresee and correct, and therefore was not reasonably preventable. No performance deficiency nor violation of NRC requirements was identified. These LERs are Closed.

INSPECTION RESULTS

Unresolved Item (Closed)

Safety-Related Motor Control Center Bus Bar Commercial Grade Dedication URI 05000316,05000315/2023011-01 71111.21N.03

Description:

On August 31, 2023, the NRC issued inspection report 2023011-01 (ADAMS Accession Number ML23233A187) which opened unresolved item (URI) 05000316,05000315/2023011-01, Safety-Related Motor Control Center Bus Bar Commercial Grade Dedication. The URI was related to Design Specification ES-BUS-BAR-0001-QCN, Purchase and Design Specification for Vertical Bus Bar, Revision 0, and commercial grade item Dedication Evaluation 34780, Bus, Bar, Vertical, Set of 3, Tin Plated Copper, Three Phase, Without Hardware, Revision 0. These documents supported the dedication of Cutler-Hammer 9800 Series motor control center (MCC) vertical bus bars. To disposition the URI, the inspectors reviewed the licensees white paper titled, DC Cook Response to Proposed Non-Cited Violation. The inspectors also reviewed documents related to the bus bars such as procurement documents and procedures, design documents, preventive maintenance procedure, safety classification determination procedures, vendor manual, and installation work orders. The inspectors also interviewed licensee staff.

The inspectors identified a minor violation for the licensees failure to assure the purchased tin plated copper bus bars conformed to procurement documents, which was contrary to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion VII, Control of Purchased Material, Equipment, and Services, and a performance deficiency (PD). Specifically, since the licensee failed to identify the tin plating as a critical characteristic to be verified for the dedication of the bus bars in evaluation 34780, they failed to ensure the tin plating conformed to the procurement documents. The tin plating of the bus bars had a safety function to maintain circuit integrity because electrical current had to pass through the plating to get to the copper base of the bus bars, therefore it had the same safety function as the copper in the bus bars. The inspectors determined the performance deficiency was of minor safety significance because they answered no to the questions of Inspection Manual Chapter (IMC) 0612 Appendix B, Issue Screening Directions, Block 4, Is the performance deficiency More-than-Minor? Specifically, since the licensee procured the bus bars from a reliable company that only had the capability to apply four different metallic coatings, all of which could perform the safety function, and the licensee performed a receipt inspection of the bus bars which could reliably detect a non-conductive coating on the bus bars, the inspectors determined the PD was of minor safety significance.

The licensee entered this issue into their corrective action program (CAP) as AR 2023-4974 and AR 2024-9269.

This failure to comply with 10 CFR 50, Appendix B, Criterion VII, constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

Failure to Identify and Correct Condition Adverse to Quality Causes Damage to Rod Control Cluster Assembly Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000315,05000316/2024004-01 Open/Closed

[H.12] - Avoid Complacency 71152A A self-revealed finding of very low safety significance (i.e., Green) and an associated non-cited violation (NCV) of 10 CFR 50, Appendix B, Criterion XVI, Corrective Actions, were identified for the licensees failure to assure that conditions adverse to quality are promptly identified. Specifically, the licensee failed to identify an interference to the fuel upender during refueling activities. This interference contacted several safety-related rod control cluster assemblies (RCCAs) on top of the fuel assemblies (F/As) ultimately damaging the RCCA on F/A LS69.

Description:

On April 18, 2024, during core reload activities, an overload alarm occurred while transporting F/A LS69 with the fuel upender. The licensee placed the upender in the down position and visually inspected it (without using a camera), finding no apparent interferences.

Because the alarm coincided with a faster portion of the upending process, which causes additional drag, the licensee concluded that this condition triggered the alarm. F/A LS69 was then upended without further alarms.

The fuel handling tool in containment, however, was unable to latch onto F/A LS69. After initial troubleshooting, the licensee decided to replace the RCCA on LS69 and transferred the assembly through the canal into the Spent Fuel Pool (SFP). Once there, the SFP tool also could not latch onto the F/A, prompting additional troubleshooting. Inspection via a camera revealed that the RCCA on LS69 was damaged, preventing engagement by either fuel handling tool.

Further licensee troubleshooting identified a pipe plug, which was installed in a port for local leak rate testing, was protruding into the upenders path. The licensee adjusted the fuel transfer carts tolerance setpoint, raising its top and moving the RCCAs away from the pipe plug protrusion. The licensee also inspected other RCCA-equipped F/As already in the core, finding no additional issues. Following the replacement of LS69s RCCA, fuel moves resumed and were completed without further issues.

During their investigation, the licensee noted that three prior overload alarms had occurred during the fuel upending process, all involving F/As with RCCAs. In each case, the licensee performed only a visual inspection without a camera and, therefore, did not detect the protruding pipe plug. They concluded, as with F/A LS69, that the alarms were caused by the speed-up zone of the fuel upender and, thus, did not identify the plugs interference until the damage to LS69s RCCA prompted further scrutiny.

Corrective Actions: Immediate corrective actions were replacement of the damaged RCCA and adjustment of the fuel transfer carts tolerance setpoint. Long term corrective actions include plans for replacing the protruding pipe plug and the implementation of lessons learned to prevent similar troubleshooting failures in the future.

Corrective Action References: AR 2024-3442 Fuel Assembly Unable to be Grappled Due to RCCA Interference

Performance Assessment:

Performance Deficiency: The licensees failure to identify and correct a protruding pipe plug that was contacting RCCAs, a condition adverse to quality, was contrary to 10 CFR 50, Appendix B, Criterion XVI, and was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more-than-minor because if left uncorrected, it would have the potential to lead to a more significant safety concern. Specifically, while this incident only damaged the RCCA on F/A LS69, if left uncorrected, it would have the potential to result in damage to F/As or the introduction of foreign material, thereby increasing the likelihood of fuel damage.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power.

The finding screened as Green, or very low safety significance, because the inspectors answered no to the Exhibit 3, Barrier Integrity Screening Questions, Section A questions.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, the refueling team did not challenge earlier troubleshooting decisions, even as recurring alarms suggested potential errors, thereby overlooking the possibility of mistakes in the previous work.

Enforcement:

Violation: 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in part, that measures be established to ensure that conditions adverse to quality, such as deficiencies and nonconformances, are promptly identified and corrected.

Contrary to the above, between April 17, 2024, and April 18, 2024, the licensee failed to identify and correct a condition adverse to quality associated with an obstruction along the path of the fuel upender. Specifically, the licensee failed to identify and correct an obstruction contacting multiple safety-related RCCAs during core reload, despite multiple alarms and repeated troubleshooting attempts. This failure ultimately caused damage to the RCCA on F/A LS69, a safety-related component.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors confirmed that proprietary information was controlled to protect from public disclosure.

  • On January 15, 2025, the inspectors presented the integrated inspection results to K. Ferneau, Executive VP and Chief Nuclear Officer, and other members of the licensee staff.
  • On December 17, 2024, the inspectors presented the emergency action level change and emergency plan change inspection results to D. Burgoyne, Emergency Preparedness Manager and other members of the licensee staff.
  • On December 18, 2024, the inspectors presented the commercial grade dedication unresolved item 2023011-01 follow-up inspection results to K. Ferneau, Executive VP and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-IHP-5040-

EMP-004

Plant Winterization and De-Winterization

07/08/2024

2-OHP-4022-

001-009

Seiche

2/05/2023

2-OHP-4022-

001-010

Severe Weather

10/29/2024

71111.01

Procedures

PMP-5055-001-

001

Winterization/Summerization

10/15/2024

71111.04

Procedures

1-OHP-4030-119-

2W

West Essential Service Water System Test

D.C. Cook

Nuclear Plant

Fire Safety

Analysis

Fire Area: AA11 Unit 1 Quadrant 2 Piping Tunnel

(El. 591 ft)

D.C. Cook

Nuclear Plant

Fire Safety

Analysis

Fire Area: AA27 Unit 2 Quadrant 2 Piping Tunnel

(El. 591 ft)

Fire Pre-Plans

Volume I

Fire Zone 85: Turbine Building Unit 2 (S.E. Portion)

Elev. 591'-0"

Fire Pre-Plans

Volume I

Turbine Building Unit 2 (S.W. Portion) Elev. 591'-0"

Fire Pre-Plans

Volume I

Fire Zone 22: Quadrant 2 Piping Tunnel Unit 2 Elev. 591'

Fire Pre-Plans

Volume I

Fire Zone 12: Quadrant 2 Piping Tunnel Unit 1 Elev. 591'

Fire Plans

Fire Pre-Plans

Volume II

Support Buildings and Yard Areas

71111.05

Miscellaneous

Drill No: 424-016-

C

Unit 2 TAC Pump Motor

000

71111.07A

Procedures

2-EHP-8913-

001-002

Heat Exchanger Inspection

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-OHP-5030-019-

2W

West Essential Service Water System Flush and Flow

Data Collection

RQ-S-4905-U12-

T1

Period 4905 U12 Training Session 1 - Practice Eval

71111.11Q

Miscellaneous

TRP-2070-TAP-

300-OPS

Operations Training Examination and Simulator Exercise

Guide Development

06/04/2024

23-5586

Failure of Both 12-HV-BD-AFX-1/2

08/02/2023

24-0624

2-QC-596-1 Failed its 15% As Found Quarterly Check

01/23/2024

24-1102

PACHMS-02 Exceeded Condition Monitoring Criteria

2/07/2024

24-5176

AFX Volumetric Calculation Flow Rate Not in Band

06/22/2024

24-7884

2-HV-AFX Flow Rate Out of Band

10/20/2024

24-8196

EACE 2024-5586-16 CAs Failed Effectiveness Review

10/31/2024

Corrective Action

Documents

24-8609

Risk Tracking for Failure of Both HV-BD-AFX-1/2

11/20/2024

Drawings

OP-12-5148

Auxiliary Building Ventilation

Maintenance Rule Scoping Document - Auxiliary Building

Spent Fuel Pool Ventilation System

Engineering

Evaluations

Auxiliary Building Spent Fuel Pool Ventilation

System - (a)(1) Action Plan

03/27/2024

Loop Feed Enclosure Materials and Quality Levels

10/09/2024

IEEE Recommended Practice for Maintenance, Testing,

and Replacement of Vented Lead-Acid Batteries for

Stationary Applications

2/09/2010

2-THP-6020-

PAS-619

PACHMS Calibration

Miscellaneous

PMP-2350-INS-

001

Inspection Contact and Information Request

10/09/2024

NDE Reports

VTD-COMS-0001

COMSIP Instruction Manual for Units 1 & 2 Post-Accident

Containment Hydrogen

03/18/2004

1-OHL-5030-

SOM-005

Unit 1 Auxiliary Tour

2-IHP-4030-

28-001

Spent Fuel Pool Exhaust Ventilation System Surveillance

71111.12

Procedures

2-MHP-4050-

FHP-006

Control of Loads Over the Spent Fuel Pool and Fuel/Insert

Handling in the Spent Fuel Pool

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2-OHP-4021-

28-011

Auxiliary Building Ventilation

2-OHP-4030-

28-028

Fuel Handling Area Exhaust Ventilation System Test

Corrective Action

Documents

AR 2024-9093

TR201CD Thermistor String Post Unsupported

and Leaning

2/12/2024

E-1300

345/34.5kV One Line Diagram

OP-1-12002

Main Auxiliary One-Line Diagram Bus C & D

Engineered Safety System (Train A)

Drawings

OP-2-12001

Main Auxiliary One-Line Diagram Bus A & B

Engineered Safety System (Train B)

71111.13

Procedures

PMP-2291-OLR-

001

On-Line Risk Management

2013-8916

Ann122 drop 81 Ice Cond Temp High Pt Reading 24.6

06/18/2013

23-9354

Cracks on Walls of Battery 1-BATT-AB Cells 55 and 113

2/13/2023

24-3070

Crack Identified in 1-BATT-AB Cell 22

04/09/2024

24-5037

Possible Check Valve Hung Up On ESW

06/14/2024

24-6650

Ice Bed Temperature Following Glycol Restoration

06/30/2024

24-8171

AR Was Not Appropriately Upgraded from NCAP

to A CAQ

10/30/2024

24-8471

1-HV-CLV-2A Fan Breaker Failure

11/13/2024

24-8838

Jar Wall Crack Identified on 1-BATT-AB Cell 57

2/03/2024

Corrective Action

Documents

24-9165

Additional Analysis Needed for Already Identified

Condition

2/16/2024

DC-15156

Westinghouse Ice Condenser Temperature Monitoring

System

09/24/2021

OP-1-12002-83

Main Auxiliary One-Line Diagram Bus C & D

Engineered Safety System (Train A)

01/25/2023

Drawings

OP-1-12032-21

MCC Aux One-Line 600v Bus 11C, 11D Engineered

Safety System (Train A)

1-EZC-C-4B

Question Response

11/21/2024

71111.15

Miscellaneous

Instrument

Configuration

Document 1-

Ice Condenser Temperature Recorder 1-SG-7

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

REC-007

Procedures

1-OHP-4030-132-

217A

DG1CD Load Sequencing and ESF Testing

2/06/2024

Corrective Action

Documents

AR 2023-3275-1

Revise Procedure 12-HIP-5030-EMP-013 to Replace

Aluminum Bus

06/28/2023

AR 2023-4974

NRC Inspection - Design Control Violation

07/06/2023

Corrective Action

Documents

Resulting from

Inspection

AR 2024-9269

Minor Violation from URI on NRC CGD Inspection

2/18/2024

Engineering

Changes

EC-0000056979

Replacement Vertical Bus, MCC 2-ABD-B

Engineering

Evaluations

34780

Commercial Grade Dedication Evaluation for Vertical

Bus Bar

09/10/2020

White Paper - DC Cook Response to Proposed

Non-Cited Violation

07/18/2023

1-2-EDS-606

Approved Terminals Fastening Method

197350

Receipt Inspection Report for Vertical Bus Bar

09/24/2020

CE-NEYS-0010

Penetrox A and Penetrox A-13

DCCPS-604-

QCS

Cable Terminations and Splices

ES-BUS-BAR-

0001-QCN

Purchase and Design Specification for Vertical Bus Bar

and 1

Miscellaneous

VTD-CHAM-0056

Cutler-Hammer Instruction Manual for Unitrol Motor

Control Center

2-EHP-5043-

CGD-001

Commercial Grade Dedication

2-EHP-5043-

SCD-001

Safety Classification Determinations

2-IHP-5030-

EMP-013

Electrical Enclosure 10 Year Preventive Maintenance and

MCCB/TOLR Testing

2-MMP-3120-

NETS-001

Receipt Inspection of Safety Related/Safety Interfaced

Material and Equipment

71111.21N.03

Procedures

GUIDE-T-0015

Guideline for Implementing the Safety Classification

Determination Process

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

55538754-05

Replace Degraded 2-AB-D Bus Bars

05/05/2021

55553408-01

Perform Detailed Inspection and Cleaning of

MCC 1-TBG-BW

04/21/2022

Work Orders

55553408-05

1-TBG-BW; Replace MCC Bus Bars

04/21/2022

Corrective Action

Documents

22-6192

Terry Turbine Trip latch engagement

08/01/2022

Drawings

OP-2-5106A-60

Flow Diagram Aux Feedwater Unit No 2

Miscellaneous

IST Program 5th

Interval, Rev 5

Donald C. Cook IST Program Plan - 5th Interval

1-OHP-4021-032-

001CD

DG1CD Operation

2-OHP-4030-

018-130N

North Spent Fuel Pit Pump Surveillance Test

2-OHP-4030-208-

051S

South Safety Injection Pump System Test

2-OHP-4030-232-

-27CD

CD Diesel Generator Operability Test (Train A)

10/03/2024

2-OHP-4030-232-

27CD

DG2CD Slow Speed Start

10/05/2024

2-OHP-4030-256-

017T

Turbine Driven Auxiliary Feedwater System Test

Procedures

PMI-5071

Inservice Testing

C10045579001

2-MRV-213: 2-IHP-6030-IMP-427

10/07/2024

C10045579005

2-MRV-213

10/07/2024

C10063594001

2-MRV-213-F, Replace Filter Element

10/07/2024

C10074649001

OPS: 256-017T, TURBINE DRIVEN AUX FW TEST,

GROUP B

10/31/2024

C10074894001

OPS: 12-OHP-4030-018-130N N Spent Fuel Pit Pump

Qtrly Surv

11/7/2024

C10076893

South Safety Injection Pump Group B Test

2/19/2024

C10076969001

MTI, 1-V2H-R8N6S1, Check for Loose Connections,

Replace V/I Converter Card if necessary

10/09/2024

71111.24

Work Orders

C10077355005

MTI, 1-DGCD-AVAR-REM, Check Potentiometer Knob

and Indicating Plate

10/29/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

C10077355012

OPS: DG1CD, Inoperable Perform 1-OHP-4030-114-021

  1. 20

10/29/2024

CEP - 48

DC Cook Nuclear Plant Emergency Plan

CEP - 49

DC Cook Nuclear Plant Emergency Plan

PMP-2080-EPP-

101

Emergency Classification

71114.04

Procedures

PMP-2080-EPP-

101

Emergency Classification

71114.06

Miscellaneous

RQ-E-4906-U2-A

Simulator Evaluation Exercise Guide Period 4906

As Found Simulator Evaluation Unit 2 Primary

Corrective Action

Documents

24-7969

May 2024 Failure of 2AB EDG not Counted

as MSPI Failure

10/22/2024

PMP-7110-PIP-

001

Reactor Oversight Program Performance Indicators and

Monthly Operating Report Data Sheets and MSPI

Derivation Sheets (Emergency AC Power System;

October 2023 through September 2024)

PMP-7110-PIP-

001

Reactor Oversight Program Performance Indicators and

Monthly Operating Report Data Sheets and MSPI

Derivation Sheets (Reactor Coolant System Leakage;

October 2023 through September 2024)

71151

Miscellaneous

PRA-MSPI-Basis

MSPI Basis Document

10/03/2023

24-8233

Containment Fire Circuit

11/03/2024

24-8234

Lack of Circuit Cards Slowed Response to Alarming

Condition

11/04/2024

71152A

Corrective Action

Documents

24-8267

2-OHP-4024-201 Drop 92 and PMP-2270-SDR-001

Require Change

11/05/2024

20-7975

1-BATT-AB Jar Lid Cracking

10/01/2020

23-9311

1-BATT-AB Cracks Developing on Additional Batteries

2/12/2023

23-9354

Cracks on Walls of Battery 1-BATT-AB Cells 55 and 113

2/13/2023

24-3070

Crack Identified in 1-BATT-AB Cell 22

04/09/2024

24-3222

Unit 2 AB Batter Has at Least 10 Cells with Cracks on Lid

04/12/2024

24-5220

U-1 BOP Cell 109 Crack

06/25/2024

71152S

Corrective Action

Documents

24-5485

Battery Acid Cleaner for Station Batteries

07/09/2024

71153

Calculations

ENPM 99-070

2-QRV-251 Actuator Sizing/Capability Evaluation

05/28/1999

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

11/21/2024

Hourly LEFM RX Power Over 100% During Transient

11/21/2024

2013-11790

Chesterton 5800 Packing Kits with No End Rings

08/12/2013

24-8233

Containment Fire Circuit

11/03/2024

24-8234

Lack Of Circuit Cards Slowed Response to

Alarming Condition

11/04/2024

24-8252

E-plan implementation MSP Not Contacted Within

Minutes

11/03/2024

24-8641

SPC Failure While Swapping on CV2 in Unit 1

11/21/2024

Corrective Action

Documents

24-8641

SPC Failure While Swapping on CV2 in Unit 1

11/21/2024

Corrective Action

Documents

Resulting from

Inspection

24-8267

2-OHP-4024-201 Drop 92 and PMP-2270-SDR-001

Require Change

11/05/2024

Drawings

OP-2-98974-2

Fire Protection Containment Detection Sheet #1

Elementary Diagram

Unit 1 Control Room Narrative Log

11/21/2024

Miscellaneous

Apparent Cause

Evaluation

U2 Identified RCS Leakage from 2-QRV-251

10/09/2024

1-OHP-4021-011-

001

At-Power Operation Including Load Swings

1-OHP-4021-050-

001

Turbine Generator Normal Startup and Operation

2-OHP-4024-201

Annunciator #201 Response: Plant fire System

OHI-4000

Conduct of Operations

143

Procedures

PMP-2270-SDR-

001

Fire Protection Suppression, Detection Systems, and

Rated Assemblies

29