IR 05000298/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000298/2024004
ML25035A012
Person / Time
Site: Cooper 
(DPR-046)
Issue date: 02/07/2025
From: Douglas Dodson
NRC/RGN-IV/DORS/PBC
To: Dia K
Nebraska Public Power District (NPPD)
References
IR 2024004
Download: ML25035A012 (1)


Text

February 07, 2025

SUBJECT:

COOPER NUCLEAR STATION - INTEGRATED INSPECTION REPORT 05000298/2024004

Dear Khalil Dia:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Cooper Nuclear Station. On January 07, 2025, the NRC inspectors discussed the results of this inspection with John Dent, Jr., Executive Vice President and Chief Nuclear Officer, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Douglas E. Dodson II, Chief Reactor Projects Branch C Division of Operating Reactor Safety Docket No. 05000298 License No. DPR-46

Enclosure:

As stated

Inspection Report

Docket Number:

05000298

License Number:

DPR-46

Report Number:

05000298/2024004

Enterprise Identifier:

I-2024-004-0010

Licensee:

Nebraska Public Power District

Facility:

Cooper Nuclear Station

Location:

Brownville, NE

Inspection Dates:

October 1, 2024, to December 31, 2024

Inspectors:

G. Birkemeier, Resident Inspector

K. Chambliss, Senior Resident Inspector

J. Drake, Senior Reactor Inspector

G. Kolcum, Senior Resident Inspector

J. O'Donnell, Senior Health Physicist

E. Simpson, Nuclear Systems Scientist

Approved By:

Douglas E. Dodson II, Chief

Reactor Projects Branch C

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Cooper Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Cooper Nuclear Station began the inspection period in a scheduled refueling outage. The station performed a reactor startup on November 2, 2024, ending the outage. The unit reached rated thermal power on November 7, 2024. On November 8, 2024, the operators lowered power to 65 percent for a control rod sequence exchange. The unit returned to rated thermal power on November 9, 2024. On November 22, 2024, the operators lowered power to 80 percent for a control rod sequence exchange. The unit returned to rated thermal power on November 23, 2024. On December 15, 2024, the operators lowered power to 98 percent due to a feedwater flow instrumentation malfunction. The unit returned to rated thermal power on December 19, 2024. The unit remained at rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)4160-volt alternating current (VAC) division 2 system on November 14, 2024

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the core spray division 1 system on December 12, 2024.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)reactor building, 931-foot 6-inch elevation, on November 5, 2024 (2)refueling outage fire door impairments on November 13, 2024 (3)division 2 emergency diesel generator room, 917-foot 6-inch and 903-foot 6-inch elevations, on November 13, 2024 (4)cable spreading room, 918-foot elevation, on November 14, 2024

71111.08G - Inservice Inspection Activities (BWR)

BWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding

Activities (IP Section 03.01)

The inspectors evaluated Cooper Nuclear Station boiling water reactor nondestructive testing during refueling outage RE 33 by reviewing the following examinations and records from October 6 - November 13, 2024:

(1)

Ultrasonic examination Feedwater, FWB-BJ-2, elbow to pipe, DW-953-135 DAZ-AFR Residual heat removal, RAD-BF-7, pipe to pipe DW-901-270 DA Reactor pressure vessel, NVE-BD-N8B, nozzle to shell weld, DW-921-285 DAZ Reactor pressure vessel, NVIR-BD-N8B, nozzle to inner radius section, DW-921-285 DAZ Reactor pressure vessel, NVIR-BD-N9, nozzle to inner radius section o

Visual examination Reactor pressure vessel, longitudinal weld, VLC-BB-3 Reactor pressure vessel, longitudinal weld, VLD-BB-1 Reactor pressure vessel, longitudinal weld, VLD-BB-2

  • There were no relevant indications accepted for continued service

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during reactor startup following the refueling outage on November 5, 2024.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator emergency preparedness scenario on November 29, 2024.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)one-time deferral of 20-year diesel fuel oil tank inspection on November 5, 2024 (2)fuel pool cooling maintenance rule function FPC-F01 in monitoring and control of fuel pool cooling maintenance activities during fall 2024 refueling outage on November 13, 2024

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)motor control center K and motor control center Q contact replacement and torquing and 250-volt direct current (VDC) division 1 complete subsystem replacement activities on November 13, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)risk assessment and management of shut down cooling during reduced inventory on October 6, 2024 (2)planned Yellow offline risk window during emergency diesel generator division 1 sequential load testing on October 18, 2024 (3)planned Yellow offline risk window for 4160 VAC bus F outage and emergency station service transformer outage on October 21, 2024 (4)planned Yellow offline risk window due to unavailability of all four residual heat removal pumps during shutdown cooling supply valve maintenance on October 21, 2024 (5)planned Yellow offline risk window due to both trains of low-pressure coolant injection being unavailable during residual heat removal cross divisional surveillance testing on November 14, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (2 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)intermediate range monitor B maintenance during outage activities on November 4, 2024 (2)source range instrument B inoperable during refuel movement activities on November 14, 2024

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1)main turbine stop valve limit switch configuration on November 13, 2024

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage RE33 activities from September 28, 2024, to November 2, 2024.

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1)off-line emergency core cooling system injection check valve operating in-service torque test following removal of temporary configuration change and complete replacement of terminal box due to suspected steam leak damage on November 14, 2024 (2)refurbishment and re-termination of residual heat removal heat exchanger division 1 service water outlet valve on November 14, 2024 (3)post work testing following maintenance on residual heat removal shut down cooling motor operated valves on November 14, 2024 (4)post work testing following complete replacement of 250 VDC division 1 batteries on November 15, 2024 (5)positioner replacement and packing adjustment for outboard main steam isolation valve A and refurbishment for all four outboard main steam isolation valves on November 15, 2024 (6)completion of modification of emergency station service transformer on November 15, 2024 (7)complete replacement of auxiliary contacts in safety-related motor control centers on November 15, 2024 (8)automatic depressurization system manual valve actuation following repair of instrument line to pressure switch low-low set function for MS-RV-71RV on December 3, 2024

Surveillance Testing (IP Section 03.01) (4 Samples)

(1)core standby cooling system initiation logic relay contact testing on October 23, 2024 (2)residual heat removal cross divisional surveillance testing on November 4, 2024 (3)emergency diesel generator division 1 load sequence test on November 14, 2024 (4)reactor protection system division 2 electrical protection assembly calibrations and functional tests on November 14, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1)local leak rate tests for various containment isolation valves located inside and outside containment on November 13,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards.

Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1)surveys of potentially contaminated material leaving the radiologically controlled area (2)workers exiting the drywell during a refueling outage

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1)desludging the torus, including diving using special work permit (SWP) 2024-508 (2)pulling and bending local power range monitors using SWP 2024-547 (3)under vessel and control rod drive mechanism exchange using SWP 2024-506 (4)valve work in the steam tunnel using SWP 2024-503 High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (5 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1)

(HRA) reactor water cleanup heat exchanger room on the 931-foot elevation of the reactor building (2)

(HRA) ladder lock in the hall on the 958-foot elevation of the reactor building (3)

(HRA) fuel pool cooling heat exchanger room gate on the 958-foot elevation of the reactor building (4)

(HRA) high integrity container storage pit (3 gates) on the 903-foot elevation of the augmented radwaste building (5)

(HRA) spent resin tank room in the radwaste building basement Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Permanent Ventilation Systems (IP Section 03.01) (2 Samples)

The inspectors evaluated the configuration of the following permanently installed ventilation systems:

(1)control room emergency filter system (2)technical support center emergency filter system

Temporary Ventilation Systems (IP Section 03.02) (2 Samples)

The inspectors evaluated the configuration of the following temporary ventilation systems:

(1)high efficiency particulate air filtration (RPS-700-1 and RPS-700-2) utilized for turbine deck sandblasting operations for work tent operations, SWP-202-564, Task 1; Work Order 5483010-0830 (2)high efficiency particulate air filtration (DUST COLL-1) utilized for turbine deck sandblasting operations for work tent operations, SWP-202-564, Task 1; Work Order 5483010-0830

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices.

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicator submittals listed below:

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15)===

(1) July 1, 2023, through June 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) July 1, 2023, through June 30, 2024

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)reactor recirculation A motor generator set voltage regulator tuning trip resulting in unplanned power change on October 24, 2024 (2)review of apparent cause analysis performed as a result of high vibrations observed during 2-year in-service test for residual heat removal service water booster pump B on December 16, 2024

71153 - Follow Up of Events and Notices of Enforcement Discretion Notice of Enforcement Discretion (IP Section 03.04)

(1) On November 15, 2024, the inspectors evaluated the licensee actions surrounding Notice of Enforcement Discretion EA-24-036, which can be accessed at http://www.nrc.gov/reading-rm/doc-collections/enforcement/notices/noedreactor.html.

The inspectors previously documented NCV 05000298/2024002-05, Failure to Translate the Design Requirements into Plant Configuration, associated with the cause of the need to request a Notice of Enforcement Discretion.

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 11, 2024, the inspectors presented the occupational radiation safety inspection results to Khalil Dia, Site Vice President, and other members of the licensee staff.
  • On October 11, 2024, the inspectors presented the inservice inspection results to Khalil Dia, Site Vice President, and other members of the licensee staff.
  • On November 13, 2024, the inspectors presented the inservice inspection re-exit meeting inspection results to Matthew Nee, Acting Director of Nuclear Assurance, and other members of the licensee staff.
  • On January 7, 2025, the inspectors presented the integrated inspection results to John Dent Jr., Executive Vice President and Chief Nuclear Officer, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

CR-CNS-

23-00556, 2023-00665, 2023-00666, 2023-00783, 2023-

01842, 2023-02262, 2023-02366

71111.04

Procedures

2.2.15

Startup Transformer

71111.04

Procedures

2.2.16

Normal Station Service Transformer

71111.04

Procedures

2.2.17

Emergency Station Service Transformer

71111.04

Procedures

2.2.18.1

4160V Auxiliary Power Distribution System

71111.04

Procedures

2.2.18.3.DIV2

4160V Div 2 Distribution Support

71111.04

Procedures

2.2.18.4

4160V Distribution Abnormal Power

2.2A.CS.DIV1

System Operating Procedure, Core Spray Component

Checklist (Div 1)

71111.04

Procedures

2.2A 4160.Div0

4160 VAC Non-Divisional Auxiliary Power Checklist

71111.04

Procedures

2.2A_4160.DIV2

4160 VAC Auxiliary Power Checklist (DIV 2)

71111.04

Work Orders

WO 5480579

CNS-FP-229

Cable spreading room, elevation 918'-0"

71111.05

Fire Plans

CNS-FP-237

Division 2 emergency diesel generator room, elevations

917-foot 6-inches and 903-foot 6-inches

71111.05

Procedures

2.2.30

Fire Protection System

71111.05

Procedures

2.2.30A

Fire Protection System Component Checklist

71111.05

Procedures

2.2.30B

Fire Protection System Instrument Valve Checklist

71111.05

Procedures

2.3_FP-1

Fire Protection Annunciator 1

71111.05

Procedures

2.3_FP-2

Fire Protection (Manual Pull Alarms) Annunciator 2

71111.05

Procedures

2.3_FP-3

Fire Protection Annunciator 3

71111.05

Procedures

2.3_FP-4

Fire Protection Annunciator 4

71111.05

Procedures

2.3_FP-5

Fire Protection Annunciator 5

71111.08G

Corrective Action

Documents

CR-CNS-

22-04197, 2022-04218, 2022-04392, 2022-04405, 2022-

04491, 2022-04492, 2022-04560, 2022-04562, 2022-04735,

22-04869, 2022-04908, 2022-04931, 2022-04954, 2022-

05016, 2022-05017, 2022-06210, 2022-06231, 2022-06757,

22-06880, 2023-00149, 2023-00572, 2023-01001, 2023-

03700, 2023-04238, 2023-04346, 2023-04724, 2023-05269,

24-00353, 2024-00537, 2024-00556, 2024-00862, 2024-

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01188, 2024-01273

71111.08G

Corrective Action

Documents

Resulting from

Inspection

CR-CNS-

24-04398, 2024-04405, 2024-04409

71111.08G

Procedures

Administrative

Procedure 0-

CNS-IS-109

Compressed Gas Cylinder Handling and Storage

71111.08G

Procedures

CNS Operations

Manual

Maintenance

Procedure 7.7.3.1

General Welding Standard for ASME and ANSI Code

Applications

71111.08G

Procedures

CNS Operations

Manual

Surveillance

Procedure

6.MISC. 504

ASME Class 1 10 Year System Leakage Test

71111.08G

Procedures

CNS Operations

Manual

Surveillance

Procedure

6.RCIC.502

ASME Section XI System Leakage Test of The Class 2

Reactor Core Isolation Cooling (RCIC) System in Steam

Tunnel

71111.08G

Procedures

Operations

Manual

Engineering -

Programs

Maintenance

Procedure

7.7.10.2

P1-B Welding Procedure Specification

71111.08G

Procedures

Operations

Manual

Engineering -

Programs

Maintenance

P1-G Welding Procedure Specification

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedure

7.7.10.4

71111.08G

Procedures

Operations

Manual

Engineering -

Programs

Maintenance

Procedure

7.7.10.6

P1-BG Welding Procedure Specification

71111.08G

Procedures

54-1S1-270-049

Wet or Dry Magnetic Particle Examination Procedure

71111.08G

Procedures

54-1S1-369-006

VT-1, VT-3

General and Detailed Visual Examinations

71111.08G

Procedures

54-1S1-650-001

ASME Section XI Flaw Characterization

71111.08G

Procedures

54-1S1-806-007

PDI Generic Procedure for the Ultrasonic Through-Wall and

Length Sizing of Planar Flaws in Reactor Pressure Vessel

Welds PDI-UT-7

71111.08G

Procedures

54-ISI-135-012

Conventional and Phased Array Ultrasonic Linearity

Measurements

71111.08G

Procedures

54-ISI-173

ASME Section XI Examination Coverage

71111.08G

Procedures

54-ISI-240-051

Visible Solvent Removable Liquid Penetrant Examination

Procedure

71111.08G

Procedures

54-ISI-805-012

PDI Generic Procedure for Ultrasonic Examination of

Reactor Pressure Vessel Welds PDI-UT-6

71111.08G

Procedures

54-ISI-829-014

PDI Generic Procedure for the Ultrasonic Examination of

Dissimilar Metal Welds PDI-UT-10

71111.08G

Procedures

54-ISI-835-020

Ultrasonic Examination of Ferritic Pipe Welds

71111.08G

Procedures

54-ISI-836-020

PDI Generic Procedure for the Ultrasonic Examination of

Austenitic Piping Welds PDI-UT-2

71111.08G

Procedures

54-ISl-363-010

Remote Visual Examination of Reactor Pressure Vessel

Internals Components, and Associated Repairs in Boiling

Water Reactors

71111.08G

Procedures

54-ISl-837-015

Ultrasonic Through-Wall Sizing in Piping Welds

71111.08G

Procedures

Administrative

Procedure 0.7.1

Control Of Combustibles

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.08G

Procedures

CNS Operations

Manual

Engineering

Procedure 3.10.1

UT (Ultrasonic Testing) Thickness Measurements and

Gridding Procedure

71111.08G

Procedures

CNS Operations

Manual

Engineering

Procedure

3.28.1.6

Visual Examination of Containment Bolting, VT-1

71111.08G

Procedures

CNS Operations

Manual

Surveillance

Procedure

6.1RHR.501

ASME Section XI Periodic Pressure Test of The Class 2

Residual Heat Removal System Loop A

71111.08G

Procedures

CNS Operations

Manual

Surveillance

Procedure

6.HPCI.502

ASME Section XI System Leakage Test of The Class 2 High

Pressure Coolant Injection (HPCI) System Pressure

Retaining Components in The Steam Tunnel

71111.08G

Work Orders

WO 242441, 5381126, 5381199, 5391483, 5391485, 5391487,

5391488, 5407844, 5465374, 5465451

71111.11Q

Procedures

5.7.1

Emergency Classification

71111.11Q

Procedures

5.7.1.1

Emergency Classification Process

71111.11Q

Procedures

5.7.7

Activation of TSC

71111.11Q

Procedures

5.7.8

Activation of OSC

71111.11Q

Procedures

5.7.9

Activation of EOF

71111.11Q

Procedures

5.8

Emergency Operation Procedures (EOPs)

71111.12

Miscellaneous

0-CNS-LI-101

Evaluation 2024-2, Attachment 1 - 50.59 Evaluation Form

71111.12

Miscellaneous

NEDC 88-233

Emergency Diesel Generator Fuel Requirements

71111.12

Procedures

2.1

CNS QC Program Description

71111.12

Procedures

2.5

CNS QC Functions

71111.12

Procedures

2.6

CNS QC Inspections

71111.12

Procedures

2.2.32

Fuel Pool Cooling and Demineralizer System

117

71111.12

Procedures

2.2.32A

Fuel Pool Cooling and Demineralizer System Component

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Checklist

2.2.32B

Fuel Pool Cooling and Demineralizer System Instrument

Valve Checklist

6.1REC.101

REC Surveillance Operation (IST) (DIV 1)

Revision 23

6.CSCS.402

Off-Line ECCS Injection Check Valve Operating IST Torque

Test and Position Indication Test

Revision 22

7.3.1.11

GE Type IAC Relay Testing and Maintenance

Revision 11

Procedures

6.MISC.401

Position Indicator Inservice Testing (IST)

Revision 22

71111.12

Work Orders

WO 5483396, 5482639, 5483471, 5475486, 5475513, 5491663,

5375177, 4921470, 5475615

71111.13

Miscellaneous

CS-1-RE33 SDC

WINDOW

Protected Equipment Clearance Order

71111.13

Miscellaneous

EE-1-ESST-RE33

Protected Equipment Clearance Order

71111.13

Miscellaneous

RHRB-1-RE33

RHR B SDC

Protected Equipment Clearance Order

71111.13

Miscellaneous

TCC-5493954

Temp Power During 4160V F Bus Outage

71111.13

Procedures

0-PROTECT-EQP

Protected Equipment Program

71111.13

Procedures

3-CNS-DC-151

PSA Maintenance and Update

71111.13

Procedures

3-CNS-DC-355

Technical Specification Surveillance Frequency Control

Program

71111.13

Procedures

3-CNS-DC-355-

Surveillance Test Interval Change (STIC) Evaluations

71111.13

Procedures

3-CNS-HU-104

Engineering Task Risk & Rigor

71111.13

Procedures

CNS-LI-100

Administrative Procedure Process Applicability

Determination

71111.15

Corrective Action

Documents

CR-CNS-

24-04177, 2024-03943, 2024-04049

71111.15

Procedures

2.0.12

Operator Challenges

71111.15

Procedures

2.0.3

Conduct of Operations

108

2.0.6

Operational Event Response and Review

71111.15

Procedures

6.2SRM.302

SRM Channel Functional Test (Reactor Not In Run With

Shorting Link Switches Closed) (DIV 2)

Revision 20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

6.IRM.301

IRM Channel Functional Test (Mode Switch Not In Run)

(DIV 1)

Revision 23

6.NMS.601

IRM and SRM Detector Travel Measurement

Revision 11

Work Orders

WO 5483320, 5475537, 5475554, 5531972

71111.18

Engineering

Changes

DC-5547470

Turbine Stop Valve Limit Switches

Revision 0

71111.18

Procedures

3-CNS-DC-112

Engineering Change Request and Project Initiation Process

71111.18

Procedures

3-CNS-DC-128

Fire Protection Program Change Review

71111.18

Procedures

3.4

Configuration Change Control

AH

71111.18

Procedures

3.4.4

Temporary Configuration Change

3.4.5

Engineering Evaluations

71111.18

Procedures

6.RPS.302

Main Turbine Stop Valve Closure and Steam Valve

Functional Test

Revision 67

71111.20

Corrective Action

Documents

CR-CNS-

24-05071, 2024-03265

71111.20

Miscellaneous

5.3AC-Outage

Restore SDC, Lesson SKL05151332

71111.20

Procedures

2.1.1

Startup Procedure

207

71111.20

Procedures

2.1.1.2

Technical Specifications Pre-Startup Checks

71111.20

Procedures

2.1.20.1

Restoration form RPV Refueling

71111.20

Procedures

2.1.20.2

Cycle Specific Fuel Transfer and Alternate Cooling

Guideline

71111.20

Procedures

2.1.20.3

RPV Refueling Preparation (Wet Lift of Dryer and Separator)

71111.20

Procedures

2.1.6

Primary Containment Access Preparation and Closeout

Activities

71111.20

Procedures

2.2.31

Fuel Handling - Refueling Platform

71111.20

Procedures

2.2.31A

Fuel Handling - Refueling Platform Component Checklist

2.4PC

Primary Containment Control

6.PC.522

Standby Nitrogen Injection and PC Purge and Vent System

Local Leak Rate Tests

Revision 22

6.REACT.603

Shutdown Margin Evaluation

Revision 14

71111.20

Procedures

6.SC.603

Technical Specification Verification of Secondary

Containment Manual Valves and Blind Flanges

Revision 11

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

6.SC.701

Technical Specification Verification of Secondary

Containment Access Doors and Hatches

Revision 6

Work Orders

WO 5475605, 5467676, 5475576, 5475663, 5531972, 5475672,

5166168, 5497232, 5467146, 5474619, 5475720, 5475475,

5483286, 5475615, 5475486, 5465406, 5475513, 5482781,

5475605, 5475515, 5475570, 5484635, 5475695, 5475582,

5482689

71111.24

Procedures

2. 7.2.42.2

RHR Heat Exchanger Maintenance

71111.24

Procedures

2.6.1RHR.102

RHR Pump Operability Test (IST) (Div 1)

71111.24

Procedures

3. 7.2.44.2

RHR-MOV-M027A and RHR-MOV-M027B Maintenance

71111.24

Procedures

3.6.1DG.302

Undervoltage Logic Function, Load Shedding, and

Sequential Loading Test (Div 1)

101

4.7.3.31.6

Safety-related 125V/250V Battery Cell Replacement

6.1DG.302

Undervoltage Logic Functional Load Shedding, and

Sequential Load Test (DIV 1)

Revision 100

71111.24

Procedures

6.1EE.301

Undervoltage Relay Testing of Model GE IAV-54E (DIV 1)

Revision 1

71111.24

Procedures

5.7.2.24

Main Steam Isolation Valve Maintenance

71111.24

Procedures

6.2.2.17

Emergency Station Service Transformer

71111.24

Procedures

6.2RHR.102

RHR Pump Operability Test (IST) (Div 2)

71111.24

Procedures

6.ADS.201

ADS Manual Valve Actuation (IST)

71111.24

Procedures

6.CSCS.301

CSCS Initiation Logic Relay Contact Testing

6.CSCS.402

Off-Line ECCS Injection Check Valve Operating IST Torque

Test and Position Indication Test

71111.24

Procedures

6.RHR.301

RHR Initiation and Containment Spray Logic System

Functional Test

Revision 29

71111.24

Procedures

7.0.8.1

System Leakage Testing

71111.24

Procedures

7.7.3.13

Motor Control Center and Local Auxiliary Shutdown Panels

Examination and Maintenance

71111.24

Work Orders

WO 5482617, 5568290, 5481065, 5482639, 5483471, 5475493,

5483151, 5483199, 5483200, 5483205, 5483206, 5483207,

5475495, 5547958, 5483482, 5482639, 5483471, 5466382,

5481065, 5475486, 5474617, 5482689, 5482692, 5484635,

5512195, 5483386, 5375177, 5482617, 5568290

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

ALARA Plans

23-02

MS-V-1008 Repairs

05/16/2023

71124.01

ALARA Plans

23-03

MS-V-70 Leak Repairs

05/16/2023

71124.01

ALARA Plans

23-06

RWCU-P-B Power Frame Replacement

11/30/2023

71124.01

ALARA Plans

24-05

Refuel

08/29/2024

71124.01

ALARA Plans

24-35

Fuel Pool Cooling Maintenance

08/01/2024

71124.01

ALARA Plans

24-36

RWCU Outage

07/18/2024

71124.01

Corrective Action

Documents

CR-CNS-

23-04784, 2023-04881, 2023-05045, 2023-05081, 2023-

234, 2023-05290, 2024-00542, 2024-00656, 2024-00906,

24-00907, 2024-00937, 2024-00947, 2024-00992, 2024-

01097, 2024-01110, 2024-01409, 2024-01427, 2024-02856,

24-03047, 2024-04339, 2024-04365, 2024-04370

71124.01

Corrective Action

Documents

LO-2024-

0077-015, 0077-016, 0077-017, 0077-018, 0134-001

71124.01

Miscellaneous

NLS2024003

CFR 31.5(c)(5) Required 30 Day Report - Unauthorized

Disassembly of Liquid Scintillation Detector

01/15/2024

71124.01

Procedures

0-CNS-LI-102

Corrective Action Process

71124.01

Procedures

9.ALARA.1

Dosimetry Administration

71124.01

Procedures

9.ALARA.4

Radiation Work Permits

71124.01

Procedures

9.ALARA.5

ALARA Planning and Controls

71124.01

Procedures

9.ALARA.6

ALARA Program

71124.01

Procedures

9.NISP-RP-03

Radiological Air Sampling

71124.01

Procedures

9.NISP-RP-04

Radiation Protection Posting and Labeling

71124.01

Procedures

9.NISP-RP-05

Access Control for Radiologically Controlled Areas

71124.01

Procedures

9.NISP-RP-07

Radioactive Material Control

71124.01

Procedures

9.NISP-RP-10

Radiological Job Coverage

71124.01

Procedures

9.RADOP.1

Radiation Protection at CNS

71124.01

Procedures

9.RADOP.123

Radiological Controls for Highly Radioactive Objects

71124.01

Procedures

9.RADOP.2

Radiation Safety Standards and Limits

71124.01

Radiation

Surveys

CNS-2309-0016

Condenser Phase Separation Tanks

09/15/2023

71124.01

Radiation

Surveys

CNS-2311-0012

RWCU Pump Room 1B

11/27/2023

71124.01

Radiation

CNS-2311-0013

RWCU Pump 1B Impeller Removal

11/28/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Surveys

71124.01

Radiation

Surveys

CNS-2405-0028

Dryer/Separator Pit to Remove Main Steam Line Boxes

05/22/2024

71124.01

Radiation

Surveys

CNS-2406-0017

Radwaste Building 877' Quarterly Survey

06/19/2024

71124.01

Radiation

Surveys

CNS-2409-0024

RWCU Pump Room 1B

09/16/2024

71124.01

Radiation

Surveys

CNS-2409-0110

Drywell - Under Vessel - Initial Survey

09/30/2024

71124.01

Radiation

Surveys

SWP 2023-115

Air Sample for RWCU-P-B Impeller Removal

11/28/2023

71124.01

Radiation

Surveys

SWP 2024-111

Air Sample for Removal/Repair of FPC-AO-A011B

01/25/2024

71124.01

Radiation Work

Permits (RWPs)23-115

RWCU Pump "B" Maintenance

71124.01

Radiation Work

Permits (RWPs)24-051

OPS and RP Activities - SWP for ALL Buildings

71124.01

Radiation Work

Permits (RWPs)24-110

Turbine Building - Locked HRA Activities

71124.01

Radiation Work

Permits (RWPs)24-115

Steam Leak Mitigation

71124.01

Radiation Work

Permits (RWPs)24-508

Torus Desludge SUPPORT

71124.01

Radiation Work

Permits (RWPs)24-510

ISI and FAC

71124.01

Radiation Work

Permits (RWPs)24-547

Refuel Floor Misc. - SWP

71124.01

Self-Assessments 2023

Radiation Protection Program Annual Report

05/28/2024

71124.01

Self-Assessments LO-2023-0211

Radiological Hazard Assessment and Exposure Controls

and In-Plant Airborne Radioactivity Control and Mitigation

and Performance Indicator Verification

07/31/2024

71124.01

Self-Assessments QAD 2024-016

NIOS Audit 24-04, Radiological Controls

09/11/2024

71124.03

Corrective Action

Documents

CR-CNS-

22-05204, 2022-06660, 2023-03848, 2024-01498, 2024-

2582, 2024-02713, 2024-02906

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.03

Procedures

15.HV.102

TSC Emergency Ventilation Charcoal and HEPA Filter Leak

Test, Fan Capacity Test, and Charcoal Sampling

71124.03

Procedures

15.HV.104

Training Center Emergency Ventilation Charcoal and HEPA

Filter Leak Test, Fan Flow and Pressurization Test, and

Charcoal Sampling

71124.03

Procedures

9.INST.37

Constant Air Monitors

71124.03

Procedures

9.RESP.1

Respiratory Protection Program

71124.03

Procedures

9.RESP.2

Self-Contained Breathing Apparatus

71124.03

Procedures

9.RESP.5

Air Quality Monitoring

71124.03

Procedures

HSI-10

Respiratory Protection

71124.03

Radiation Work

Permits (RWPs)24-506

Undervessel CRDMs Changeout

09/27/2024

71124.03

Radiation Work

Permits (RWPs)24-564

TG Deck Sandblasting

09/27/2024

71124.03

Self-Assessments QAD 2024-016

NIOS Audit 24-04, "Radiological Controls"

09/11/2024

71124.03

Work Orders

5482799-0030

Remove Shoot Out Steel

09/27/2024

71124.03

Work Orders

5483010-0830

Dust Blast LP1 Rotor

07/27/2024

71152A

Corrective Action

Documents

CR-CNS-

24-00260

71152A

Drawings

2008612

Cooper Nuclear Station Residual Heat Removal Service

Water Booster Pumps, Contract E-68-25

71152A

Procedures

0-CNS-LI-102

Corrective Action Process

71152A

Procedures

2.2.70

RHR Service Water Booster Pump System

71152A

Procedures

6.2SWBP.101

RHR Service Water Booster Pump Flow Test and Valve

Operability Test (Div 2)

71153

Procedures

2.0.3

Conduct of Operations

108

71153

Procedures

3.3SAFE

Safety Assessment

71153

Procedures

3.4

Configuration Change Control

AH

71153

Procedures

3.4.5

Engineering Evaluations

2