IR 05000298/1986017
| ML20199E494 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 06/12/1986 |
| From: | Bennett W, Jaudon J, Greg Pick NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML20199E485 | List: |
| References | |
| 50-298-86-17, NUDOCS 8606230314 | |
| Download: ML20199E494 (4) | |
Text
.
..
.
APPENDIX U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
NRC Inspection Report: 50-298/86-17 License: DPR-46 Docket: 50-298 Licensee: Nebraska Public Power District P. O. Box 499 Columbus, Nebraska 68601 Facility Name: Cooper Nuclear Station (CNS)
Inspection At: CNS Site, Brownville, Nebraska Inspection Conducted: April 28 through May 2, 1986 Inspectors:
11/
M d /A 86
.
'
.[R.LBer61ett, Project Engineer, Project Date 3ection A, Reactor Projects Branch l
WIM4A
- LM j)w [' 1%b G. h. Pf:k,/ Reactor Engineer, Operations ate Sectidn, bactor Safety Branch
.
,
71.2 /
M 6/
8d Approved:
J. P./Jaudph, Chief,' Project Section A Dat'e
L Redctor(Projects Branch Inspection Sununary Inspection Conducted April 28 through May 2, 1986 (Report 50-298/86-17)
Areas Inspected:
Routine, unannounced inspection of surveillance test procedures and records.
Resuits:. Within the one area inspected, no violations or deviations were identified.
g6230314860617 ADOCK 05000298 G
_
.
..
..
DETAILS
.1.
Persons Contacted
- R. D. Black, Operations Supervisor
)
- R. Brungardt, Operations Manager
- G. Horn, Division Manager
- H. A. Jantzen, Instrument & Control (I&C) Supervisor
- J. Peaslee, Surveillance Coordinator
- J. Sayer, Technical Manager
- V. L. Wolstenholm, Quality Assurance Manager The NRC inspectors also contacted other site personnel including operations, I&C, administrative, and clerical personnel.
- Denotes those attending the exit interview conducted on May 2, 1986.
2.
Surveillance Procedures and Records The purpose of this inspection was to ascertain whether the surveillance of safety-related systems and components is being conducted in accordance with approved procedures as required by the Technical Specifications and inservice testing (IST) programs for pumps and valves.
The NRC inspectors reviewed the following surveillance procedures for content, workability, and compliance with Technical Specifications (TS).
J Number Rev.
Subject Issue Date 6.2.2.5.8
RHR Loops A and B Injection Valve Time Delay 10/17/85 Calibration and Functional / Functional Test 6.2.2.5.16
RHR Loop A & B Shutdown Cooling PCIS Isolation 10/22/81 Functional Test 6.3.4.1
CS Test Mode Surveillance Operation 01/30/86 6.2.2.5.12 10 RHR Loops A & B Pump and Valve Control Logic 11/13/84 Functional Test 6.3.8.2
Standby Liquid Control System Pump Operational 08/18/85 Test 6.3.12.1
Diesel Generator Operability Test 03/06/86 6.3.15.2
Station Battery Service Test 08/29/85
.
.
- ..
.
.
f-
- Number Rev.
Subject Issue Date 6.3.15.2A
Station Battery Performance Test 08/29/85 6.3.1.1
Primary Containment Local Leakage Tests 03/13/86 6.2.2.4.1
CS Loops A and B Flow Instruments Calibration 01/30/86 and Functional Test 6.2.2.3.1
HPCI Steam Line High Flow Calibration and 01/30/86 Functional / Functional Test 6.2.1.4.1
PCIS Main Steam Line High Temp Functional Test 07/05/85 6.2.4.1
Daily Surveillance (Technical Specifications) 02/06/86
,
Several questions were identified by the NRC inspectors; however, they were promptly and satisfactorily answered by the licensee.
Review by the NRC inspectors determined that the surveillance program at Cooper Nuclear Station is being controlled in a thorough and professional manner. The NRC inspectors concluded, however, that this is occurring because of the competence of personnel administering the program, not because of a thorough documented procedure for coritrolling the program.
No written procedures, for instance, exist for feedback to the surveillance coordinator for required scheduling changes for the IST program. This feedback is happening via memoranda. The surveillance scheduling is performed manually, but it is planned to shift to computerized scheduling in the future.
~ The NRC inspectors reviewed all completed copies since January 1,1986, for Procedures 6.3.4.1, 6.3.12.1, 6.2.2.5.12, 6.2.2.3.1, 6.2.1.4.1, and 6.2.2.5.8.
The inspectors noted that checkmarks were utilized to indicate performance of procedure steps. The person performing the steps then signs at the bottom of the page verifying that the checkmarks were made by him.
In several instances, specifically Procedure 6.2.1.4.1 performed on January 16, 1986, and Procedure 6.2.2.3.1 performed on April 22, 1986, the
NRC inspectors noted that more than one signature appeared on a page signifying that they had checkmarked that page. The NRC inspectors and licensee representative were unable to determine who had performed what step in those procedures.
The licensee stated that their new procedure format will require initials for each step performed instead of checkmarks. The use of checkmarks to denote performance of procedure steps is corsidered an open item (298/8517-01) pending future review of surveillance procedures utilizing the new procedure format.
The NRC inspectors also noted that out-of-specification data were taken on Procedure 6.3.12.1, performed on April 15, 1986, and that some data were not taken on 6.3.12.1, performed on April 23, 1986.
In both of these instances, the licensee found the errors, however, they were not found during shift supervisor review but were detected during engineering review.
This failure to identify out-of-specification data during shift supervisor
..
-
.
.
. -..
.
. --
.
_.
..
- ..
..
.
'
.
,
r-review is considered an open item (298/8617-02) pending future review of completed surveillance procedures to determine if licensee corrective action in this area has been effective.
The NRC inspectors observed the performance of two surveillance tests.
The tests observed were performed in accordance with the procedure. _ Proper reviews were done by all appropriate personnel, and proper control and monitoring of the plant was exhibited by all operators.
The NRC inspectors reviewed the qualifications _of I&C technicians. All I&C technicians complete extensive classroom training and on-the-job training and must pass a test prior to being qualified to perform I&C surveillance procedures. The I&C technicians must perform or observa all
surveillance procedures prior to completing qualification. Upon qualification, they may perform all I&C surveillance procedures.
No violations or deviations were identified in this inspection.
3.
Exit Interview An exit interview was held on May 2, 1986, with the personnel denoted in paragraph 1 of this report. The NRC senior resident inspector also attended this meeting. At this meeting, the scope of the inspection and the findings were summarized.
,
e f
I i
- - -
,
.. _ _.
_,,,
..,