Category:INSPECTION REPORT
MONTHYEARIR 05000297/20242022024-09-16016 September 2024 North Carolina State University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000297/2024202 and Notice of Violation IR 05000297/20242012024-04-0101 April 2024 North Carolina State University - U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000297/2024201 IR 05000297/20232012023-10-0404 October 2023 North Carolina State University - U.S. Nuclear Regulatory Commission Security Inspection Report No. 05000297/2023201 (Public) ML22181B1842022-08-0101 August 2022 North Carolina State University - NRC Safety Inspection Report 2022202 IR 05000297/20222012022-06-0303 June 2022 North Carolina State University U.S. Nuclear Regulatory Commission Safety Inspection Report No. 05000297/2022201 IR 05000297/20202022020-12-0808 December 2020 North Carolina Station University - USNRC Inspection Report 05000297/2020202 IR 05000297/20202012020-07-31031 July 2020 North Carolina State University; U.S. Nuclear Regulatory Commission Routine Inspection Report No. 05000297/2020201 IR 05000297/20182012018-08-31031 August 2018 North Carolina State University - U.S. Nuclear Regulatory Commission Routine Inspection Report No. 50-297/2018-201 IR 05000297/20172022017-08-0808 August 2017 Cover Letter - North Carolina State University - U.S. Nuclear Regulatory Commission Security-Related Inspection Report No. 50-297/2017-202 IR 05000297/20162012016-05-25025 May 2016 North Carolina State University - NRC Routine Inspection Report 05000297/2016201, April 25 -27, 2016 IR 05000297/20152012015-05-29029 May 2015 IR 05000297/2015-201 - 04/27/15-04/30/15, North Carolina State University - U.S. Nuclear Regulatory Commission Routine Inspection Report IR 05000297/20152022015-05-29029 May 2015 IR 05000297/2015-202 - 04/27/15-04/30/15, North Carolina State University - U.S. Nuclear Regulatory Commission Security-Related Inspection Report No. 50-297/2015-202 IR 05000297/20142012014-02-19019 February 2014 IR 05000297-14-201, on January 21-23, 2014, at North Carolina State University - NRC Routine Inspection Report No. 50-297/14-201 IR 05000297/20132012013-02-0707 February 2013 IR 05000297-13-201 on January 7-10, 2013 at the North Carolina State University - NRC Announced IR 05000297/20122022012-02-28028 February 2012 IR 05000297-12-202 on February 13-16, 2012 at North Carolina State University, Transmittal Letter for NRC Security -Related Inspection Report No. 50-297/2012-202 IR 05000297/20122012012-02-28028 February 2012 IR 05000297-12-201 on February 13 to 17, 2012 at the North Carolina State University - NRC Routine Inspection Report No. 50-297/2012-201 IR 05000297/20102022011-07-28028 July 2011 IR 05000297-10-202 on December 20-22, 2010 at North Carolina State University, NRC Special Inspection Report No. 50-297/2010-202 and Notice of Violations ML1106203562011-03-10010 March 2011 IR 2011-201, on 02/07/11 - 202/10/11, North Carolina State University, Announced Routine Inspection IR 05000297/20102012010-03-0101 March 2010 IR 05000297-10-201; North Carolina State University; 02/1-4/2010; Pulstar Nuclear Reactor Facility; NRC Announced Routine Inspection Report IR 05000297/20092022009-02-12012 February 2009 IR 05000297-09-202, on 01/12/2009 - 01/14/2009, for Nc State of University IR 05000297/20092012009-02-12012 February 2009 IR 05000297-09-201, on 01/12 - 15/2009, North Carolina State University Pulstar Nuclear Reactor Facility NRC Inspection Report IR 05000297/20082012008-02-0707 February 2008 IR 05000297-08-201, on January 28 to February 1, 2008, North Carolina State University, Pulstar Reactor IR 05000297/20062032007-01-0404 January 2007 Inspection Report No. 05000297-06-203 IR 05000297/20062022006-12-22022 December 2006 NRC Inspection Report No. 50-297/2006-202 on 12/04 - 12/08/2006 for North Carolina State University Pulstar Research Reactor Facility IR 05000297/20062012006-08-17017 August 2006 IR 05000297-06-201, on 05/22/2006 - 05/26/2006, North Carolina State University IR 05000297/20042012005-02-16016 February 2005 IR 05000297-04-201, on 10/25/04 - 10/29/04 for North Carolina State University Pulstar Research Reactor Facility IR 05000297/20012022002-01-0909 January 2002 IR 05000297/2001-202, North Carolina State Univ Pulstar Research Reactor, Inspection on 12/10-12/13/2001 Re Organization & Staffing, Review & Audit Functions, Procedures, Radiation Protection Program, Effluent & Environmental Monitoring. No IR 05000297/19992011999-03-0202 March 1999 Insp Rept 50-297/99-201 on 990209-12.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Included Onsite Review of Various Aspects of Licensee Programs Concerning Conduct of Operations & Emergency Preparedness IR 05000297/19982011998-05-0404 May 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-297/98-201.NRC Will Examine Implementation of Corrective Action During Future Insp ML20217C0721998-03-18018 March 1998 Insp Rept 50-297/98-201 on 980120-23.Violations Noted.Major Areas inspected:on-site Review of Selected Aspects of Licensee Class II Nonpower Research Reactor Operation Including;Safeguards,Security Program & Matl Control IR 05000297/19972011997-09-0909 September 1997 Insp Rept 50-297/97-201 on 970609-12.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee IR 05000297/19930021993-10-15015 October 1993 Partially Withheld Insp Rept 50-297/93-02 on 930928-29 (Ref 10CFR2.790).No Violations Noted.Major Areas Inspected: Procedures,Fixed Site Physical Protection of Special Nuclear Matl of Low Strategic Significance & Matl Control IR 05000297/19930011993-02-0909 February 1993 Insp Rept 50-297/93-01 on 930125-29.Violation & Deviation Noted.Major Areas Inspected:Staff Organization,Operating Logs & Records,Procedures,Design Changes,Committee Activities,Emergency Preparedness & Maint Activities IR 05000297/19900021990-11-14014 November 1990 Insp Rept 50-297/90-02 on 901029-1101.No Violations or Deviations Noted.Major Areas Inspected:Review & Oversight of Reactor Activities IR 05000297/19890041989-11-0808 November 1989 Insp Rept 50-297/89-04 on 891003-04.Noncited Violation Noted.Major Areas Inspected:Onsite Review of Followup of Previous Enforcement Issues & Allegation Followup IR 05000297/19890031989-09-28028 September 1989 Partially Withheld Insp Rept 50-297/89-03 on 890907 (Ref 10CFR2.790).No Violations or Deviations Noted.Major Areas Inspected:Nuclear Matl Accounting Records & Repts & Physical Inventory IR 05000297/19890021989-09-15015 September 1989 Partially Withheld Insp Rept 50-297/89-02 on 890817 (Ref 10CFR2.790).No Noncompliance Noted.Major Areas Inspected: Plans & Procedures,Repts of Safeguards Events & Fixed Site Physical Protection of SNM of Low Strategic Significance IR 05000297/19890011989-09-12012 September 1989 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-297/89-01 ML20245G2371989-08-0101 August 1989 Insp Rept 50-297/89-01 on 890628-30.Violation Noted Major Areas Inspected:Staff Organization,Training,Radiation Control & Surveillance Activities,Environ Monitoring & Transportation Activities IR 05000297/19880041988-10-31031 October 1988 Insp Rept 50-297/88-04 on 880926-29.Violations Noted.Major Areas Inspected:Onsite Review of Licensee Radiation Protection Program,Including Staff Organization,Training, Radiation Control & Surveillance Activities IR 05000297/19880031988-06-0909 June 1988 Insp Rept 50-297/88-03 on 880523-26.Violation Noted.Major Areas Inspected:Recent Activities to Reduce & Monitor Pool Leakage & Completed Biennial Insp of Licensee IR 05000297/19880011988-04-0404 April 1988 Insp Rept 50-297/88-01 on 880301-04.No Violations or Deviations Noted.Major Areas Inspected:Leaks in RCS Piping Outside Reactor Bldg & in Isolable Portion of Reactor Primary Sys within Bldg IR 05000297/19870031987-11-17017 November 1987 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-297/87-03 ML20235W0881987-10-0707 October 1987 Insp Rept 50-297/87-03 on 870929-30.Violations Noted. Major Areas Inspected:Internal & External Exposure Control & Assessment,Control of Radioactive Matl & Contamination, Surveys,Monitoring & Transportation of Radioactive Matl IR 05000297/19870011987-03-27027 March 1987 Insp Rept 50-297/87-01 on 870316-18.Violations Noted:Failure to Post Required Documents,Failure to Comply W/Dot Requirements for Transportation of Radioactive Matls & Failure to Verify Authorization of Intended Recipient IR 05000297/19860021986-06-0404 June 1986 Partially Withheld Insp Rept 50-297/86-02 on 860521-22 (Ref 10CFR2.790 & 73.21).No Noncompliance Noted.Major Areas Inspected:Plans & Procedures,Safeguards Events Repts & Low Strategic Significance SNM Fixed Physical Protection IR 05000297/19860011986-05-14014 May 1986 Insp Rept 50-297/86-01 on 860414-18.No Violation or Deviation Noted.Major Areas Inspected:Biennial Research Reactor Insp,Including Logs & Records,Review & Audit, Requalification Training & Procedures IR 05000111/19820021982-04-21021 April 1982 IE Insp Repts 50-111/82-02 & 50-297/82-01 on 820315-19. Noncompliance Noted:Control Room Left Unattended & Reactor Safeguards Advisory Group Not Convened Semiannually IR 05000111/19820011982-02-19019 February 1982 IE Insp Rept 50-111/82-01 on 820202-03.No Noncompliance Noted.Major Areas Inspected:Radiation Protection Associated W/Dismantling Reactor IR 05000297/19810011981-08-14014 August 1981 Forwards IE Insp Rept 50-297/81-01 on 810803-04.No Noncompliance Noted.Insp Rept Withheld (Ref 10CFR2.790) 2024-09-16
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000297/19992011999-03-0202 March 1999 Insp Rept 50-297/99-201 on 990209-12.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Included Onsite Review of Various Aspects of Licensee Programs Concerning Conduct of Operations & Emergency Preparedness ML20217C0721998-03-18018 March 1998 Insp Rept 50-297/98-201 on 980120-23.Violations Noted.Major Areas inspected:on-site Review of Selected Aspects of Licensee Class II Nonpower Research Reactor Operation Including;Safeguards,Security Program & Matl Control IR 05000297/19972011997-09-0909 September 1997 Insp Rept 50-297/97-201 on 970609-12.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee IR 05000297/19930021993-10-15015 October 1993 Partially Withheld Insp Rept 50-297/93-02 on 930928-29 (Ref 10CFR2.790).No Violations Noted.Major Areas Inspected: Procedures,Fixed Site Physical Protection of Special Nuclear Matl of Low Strategic Significance & Matl Control IR 05000297/19930011993-02-0909 February 1993 Insp Rept 50-297/93-01 on 930125-29.Violation & Deviation Noted.Major Areas Inspected:Staff Organization,Operating Logs & Records,Procedures,Design Changes,Committee Activities,Emergency Preparedness & Maint Activities IR 05000297/19900021990-11-14014 November 1990 Insp Rept 50-297/90-02 on 901029-1101.No Violations or Deviations Noted.Major Areas Inspected:Review & Oversight of Reactor Activities IR 05000297/19890041989-11-0808 November 1989 Insp Rept 50-297/89-04 on 891003-04.Noncited Violation Noted.Major Areas Inspected:Onsite Review of Followup of Previous Enforcement Issues & Allegation Followup IR 05000297/19890031989-09-28028 September 1989 Partially Withheld Insp Rept 50-297/89-03 on 890907 (Ref 10CFR2.790).No Violations or Deviations Noted.Major Areas Inspected:Nuclear Matl Accounting Records & Repts & Physical Inventory IR 05000297/19890021989-09-15015 September 1989 Partially Withheld Insp Rept 50-297/89-02 on 890817 (Ref 10CFR2.790).No Noncompliance Noted.Major Areas Inspected: Plans & Procedures,Repts of Safeguards Events & Fixed Site Physical Protection of SNM of Low Strategic Significance ML20245G2371989-08-0101 August 1989 Insp Rept 50-297/89-01 on 890628-30.Violation Noted Major Areas Inspected:Staff Organization,Training,Radiation Control & Surveillance Activities,Environ Monitoring & Transportation Activities IR 05000297/19880041988-10-31031 October 1988 Insp Rept 50-297/88-04 on 880926-29.Violations Noted.Major Areas Inspected:Onsite Review of Licensee Radiation Protection Program,Including Staff Organization,Training, Radiation Control & Surveillance Activities IR 05000297/19880031988-06-0909 June 1988 Insp Rept 50-297/88-03 on 880523-26.Violation Noted.Major Areas Inspected:Recent Activities to Reduce & Monitor Pool Leakage & Completed Biennial Insp of Licensee IR 05000297/19880011988-04-0404 April 1988 Insp Rept 50-297/88-01 on 880301-04.No Violations or Deviations Noted.Major Areas Inspected:Leaks in RCS Piping Outside Reactor Bldg & in Isolable Portion of Reactor Primary Sys within Bldg ML20235W0881987-10-0707 October 1987 Insp Rept 50-297/87-03 on 870929-30.Violations Noted. Major Areas Inspected:Internal & External Exposure Control & Assessment,Control of Radioactive Matl & Contamination, Surveys,Monitoring & Transportation of Radioactive Matl IR 05000297/19870011987-03-27027 March 1987 Insp Rept 50-297/87-01 on 870316-18.Violations Noted:Failure to Post Required Documents,Failure to Comply W/Dot Requirements for Transportation of Radioactive Matls & Failure to Verify Authorization of Intended Recipient IR 05000297/19860021986-06-0404 June 1986 Partially Withheld Insp Rept 50-297/86-02 on 860521-22 (Ref 10CFR2.790 & 73.21).No Noncompliance Noted.Major Areas Inspected:Plans & Procedures,Safeguards Events Repts & Low Strategic Significance SNM Fixed Physical Protection IR 05000297/19860011986-05-14014 May 1986 Insp Rept 50-297/86-01 on 860414-18.No Violation or Deviation Noted.Major Areas Inspected:Biennial Research Reactor Insp,Including Logs & Records,Review & Audit, Requalification Training & Procedures IR 05000111/19820021982-04-21021 April 1982 IE Insp Repts 50-111/82-02 & 50-297/82-01 on 820315-19. Noncompliance Noted:Control Room Left Unattended & Reactor Safeguards Advisory Group Not Convened Semiannually IR 05000111/19820011982-02-19019 February 1982 IE Insp Rept 50-111/82-01 on 820202-03.No Noncompliance Noted.Major Areas Inspected:Radiation Protection Associated W/Dismantling Reactor IR 05000297/19800011980-06-25025 June 1980 IE Insp Rept 50-297/80-01 on 800605.No Noncompliance Noted. Major Areas Inspected:Licensee Security Plan,Security Organization,Access Control,Surveillance & Protection Against Sabotage.Details Withheld (Ref 10CFR.2790) IR 05000111/19790031979-12-21021 December 1979 IE Insp Rept 50-111/79-03 on 791105-06 & 11.No Noncompliance Noted.Major Areas Inspected:Preparation & Shipment of Spent Fuel Assemblies IR 05000111/19790021979-04-0202 April 1979 IE Insp Repts 50-111/79-02 & 50-297/79-02 on 790313-16. Noncompliance Noted:Failure to Develop Procedures Required to Establish 10CFR21 Program & Failure to Document & Approve Temporary Procedure Change IR 05000111/19790011979-03-0808 March 1979 IE Insp Repts 50-111/79-01,50-297/79-01 & 70-0041/79-01 on 790220-21.Noncompliance Noted:Failure to Measure & Rept Accountability Values Re Production & Consumption of Snm. Details Withheld (Ref 10CFR2.790) IR 05000160/19780041978-10-20020 October 1978 IE Inspec Repts 50-160/78-04, 50-276/78-02, 50-297/78-04 & 70-0386/78-04 on 780926-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspec Incl:Nuc Matl Control & Accounting Procedures Review IR 05000297/19780031978-10-0202 October 1978 Inspec Rept 50-297/78-03 on 780817 During Which No Items of Noncompliance Were Noted.Major Area Inspected:Physical Security Plan 1999-03-02
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000297/19992011999-03-0202 March 1999 Insp Rept 50-297/99-201 on 990209-12.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Included Onsite Review of Various Aspects of Licensee Programs Concerning Conduct of Operations & Emergency Preparedness ML20217C0721998-03-18018 March 1998 Insp Rept 50-297/98-201 on 980120-23.Violations Noted.Major Areas inspected:on-site Review of Selected Aspects of Licensee Class II Nonpower Research Reactor Operation Including;Safeguards,Security Program & Matl Control ML20217C0501998-03-18018 March 1998 Notice of Violation from Insp on 980120-23.Violation Noted: Licensee Developed Various Health Physics Instructions That Were Reviewed & Approved by Reactor Health Physicist,But Not by Radiation Protection Committee IR 05000297/19972011997-09-0909 September 1997 Insp Rept 50-297/97-201 on 970609-12.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp & Verification of CA Previously Committed to by Licensee IR 05000297/19930021993-10-15015 October 1993 Partially Withheld Insp Rept 50-297/93-02 on 930928-29 (Ref 10CFR2.790).No Violations Noted.Major Areas Inspected: Procedures,Fixed Site Physical Protection of Special Nuclear Matl of Low Strategic Significance & Matl Control PNO-II-93-022, on 930505,false Media Rept of Damage to Research Reactor Was Heard by Resident Inspector.On 930503, Substantial Fire in Electronics Research Lab Building Across Street Did Not Impact Building Containing Research Reactor1993-05-0505 May 1993 PNO-II-93-022:on 930505,false Media Rept of Damage to Research Reactor Was Heard by Resident Inspector.On 930503, Substantial Fire in Electronics Research Lab Building Across Street Did Not Impact Building Containing Research Reactor ML20034E9821993-02-11011 February 1993 Notice of Violation from Insp on 930125-29.Violation Noted: Minutes of Meetings Held by Reactor Safeguards Advisory Group Indicate That Meetings Were Held at Intervals Exceeding Required 8 Months ML20034E9841993-02-11011 February 1993 Notice of Deviation Fron Insp on 930125-29.Deviation Noted: Revised Emergency Plan Was Not Submitted to Radiation Protection Council Until 921001 IR 05000297/19930011993-02-0909 February 1993 Insp Rept 50-297/93-01 on 930125-29.Violation & Deviation Noted.Major Areas Inspected:Staff Organization,Operating Logs & Records,Procedures,Design Changes,Committee Activities,Emergency Preparedness & Maint Activities ML20217C6691991-07-0808 July 1991 Exam Rept 50-297/OL-91-01 on 910603-04.Exam Results:Both Applicants Passed Exam IR 05000297/19900021990-11-14014 November 1990 Insp Rept 50-297/90-02 on 901029-1101.No Violations or Deviations Noted.Major Areas Inspected:Review & Oversight of Reactor Activities ML20011F3721990-01-29029 January 1990 Exam Rept 50-297/OL-89-01 on 891127-28.Exam Results:All Reactor Operators Passed Written Exams & Operating Tests IR 05000297/19890041989-11-0808 November 1989 Insp Rept 50-297/89-04 on 891003-04.Noncited Violation Noted.Major Areas Inspected:Onsite Review of Followup of Previous Enforcement Issues & Allegation Followup IR 05000297/19890031989-09-28028 September 1989 Partially Withheld Insp Rept 50-297/89-03 on 890907 (Ref 10CFR2.790).No Violations or Deviations Noted.Major Areas Inspected:Nuclear Matl Accounting Records & Repts & Physical Inventory IR 05000297/19890021989-09-15015 September 1989 Partially Withheld Insp Rept 50-297/89-02 on 890817 (Ref 10CFR2.790).No Noncompliance Noted.Major Areas Inspected: Plans & Procedures,Repts of Safeguards Events & Fixed Site Physical Protection of SNM of Low Strategic Significance ML20245G2321989-08-0202 August 1989 Notice of Violation from Insp on 890628-30.Violations Noted: Failure to Provide Adequate Training to Radiation Safety Ofc Personnel Performing Contamination Surveys & Failure to Follow Environ Procedures for Collecting Air Filters ML20245G2371989-08-0101 August 1989 Insp Rept 50-297/89-01 on 890628-30.Violation Noted Major Areas Inspected:Staff Organization,Training,Radiation Control & Surveillance Activities,Environ Monitoring & Transportation Activities ML20205R0001988-11-0202 November 1988 Notice of Violation from Insp on 880926-29.Violation Noted: Failure to Have & Maintain Approved Procedures Utilized by Radiation Protection Ofc to Conduct Liquid Effluent & Environ Sample Radiological Analyses IR 05000297/19880041988-10-31031 October 1988 Insp Rept 50-297/88-04 on 880926-29.Violations Noted.Major Areas Inspected:Onsite Review of Licensee Radiation Protection Program,Including Staff Organization,Training, Radiation Control & Surveillance Activities ML20195J3641988-06-13013 June 1988 Notice of Violation from Insp on 880523-26.Violation Noted: Reactor Safeguards Advisory Group Did Not Meet During 870408-880225 IR 05000297/19880031988-06-0909 June 1988 Insp Rept 50-297/88-03 on 880523-26.Violation Noted.Major Areas Inspected:Recent Activities to Reduce & Monitor Pool Leakage & Completed Biennial Insp of Licensee ML20154D2561988-05-0505 May 1988 Exam Rept 50-297/OL-88-02 on 880426.Exam Results:Reactor Operator Passed IR 05000297/19880011988-04-0404 April 1988 Insp Rept 50-297/88-01 on 880301-04.No Violations or Deviations Noted.Major Areas Inspected:Leaks in RCS Piping Outside Reactor Bldg & in Isolable Portion of Reactor Primary Sys within Bldg PNO-II-88-015B, on 880229,licensee Informed NRC That 1 Mwt Pool Reactor Had Been Shutdown Due to Primary Coolant Leak Outside Containment.Two Leaks Identified.Util Plans to Isolate Leak & Test Further to Assure That Leak Is in Liner1988-03-24024 March 1988 PNO-II-88-015B:on 880229,licensee Informed NRC That 1 Mwt Pool Reactor Had Been Shutdown Due to Primary Coolant Leak Outside Containment.Two Leaks Identified.Util Plans to Isolate Leak & Test Further to Assure That Leak Is in Liner PNO-II-88-015A, analysis of Reactor Water Sample Indicates That Concentrations of Radionuclides Less than NRC Limit for Release to Unrestricted Area.Cold Leg Has Been Drained & Leg Currently Being Drained1988-03-0303 March 1988 PNO-II-88-015A:analysis of Reactor Water Sample Indicates That Concentrations of Radionuclides Less than NRC Limit for Release to Unrestricted Area.Cold Leg Has Been Drained & Leg Currently Being Drained PNO-II-88-015, on 880229,licensee Informed NRC That Unit,A 1 Mwt Pool Reactor Had Been Shut Down Due to Primary Coolant Leak Outside Containment.Region II Has Dispatched Both Health Physics & Operations Inspector to Review Event1988-03-0101 March 1988 PNO-II-88-015:on 880229,licensee Informed NRC That Unit,A 1 Mwt Pool Reactor Had Been Shut Down Due to Primary Coolant Leak Outside Containment.Region II Has Dispatched Both Health Physics & Operations Inspector to Review Event ML20150B2371988-02-23023 February 1988 Exam Rept 50-297/OL-88-01 on 880202-03.Exam Results:One of Two Reactor Operators Passed Written Exam & Operating Exam & Senior Reactor Operator Passed Both Exams PNO-V-88-013A, on 880114,reactor Bldg Overpressurization Occurred.Investigation Revealed That High/Low Pressure Trip Circuit for Train B Fan Trip Circuit Inoperable.Licensee Continuing Investigation to Determine Root Cause1988-02-19019 February 1988 PNO-V-88-013A:on 880114,reactor Bldg Overpressurization Occurred.Investigation Revealed That High/Low Pressure Trip Circuit for Train B Fan Trip Circuit Inoperable.Licensee Continuing Investigation to Determine Root Cause ML20235W0801987-10-0909 October 1987 Notice of Violation from Insp on 870929-30.Violation Noted: Operating Procedures for Radiation Control Not Written &/Or Followed for Listed Incidents ML20235W0881987-10-0707 October 1987 Insp Rept 50-297/87-03 on 870929-30.Violations Noted. Major Areas Inspected:Internal & External Exposure Control & Assessment,Control of Radioactive Matl & Contamination, Surveys,Monitoring & Transportation of Radioactive Matl ML20206D3851987-04-0202 April 1987 Notice of Violation from Insp on 870316-18 IR 05000297/19870011987-03-27027 March 1987 Insp Rept 50-297/87-01 on 870316-18.Violations Noted:Failure to Post Required Documents,Failure to Comply W/Dot Requirements for Transportation of Radioactive Matls & Failure to Verify Authorization of Intended Recipient IR 05000297/19860021986-06-0404 June 1986 Partially Withheld Insp Rept 50-297/86-02 on 860521-22 (Ref 10CFR2.790 & 73.21).No Noncompliance Noted.Major Areas Inspected:Plans & Procedures,Safeguards Events Repts & Low Strategic Significance SNM Fixed Physical Protection ML20211A4381986-05-19019 May 1986 Exam Rept 50-297/OL-86-01 on 860423-24.Exam Results:All Five Candidates Passed Oral & Written Exams IR 05000297/19860011986-05-14014 May 1986 Insp Rept 50-297/86-01 on 860414-18.No Violation or Deviation Noted.Major Areas Inspected:Biennial Research Reactor Insp,Including Logs & Records,Review & Audit, Requalification Training & Procedures IR 05000111/19820021982-04-21021 April 1982 IE Insp Repts 50-111/82-02 & 50-297/82-01 on 820315-19. Noncompliance Noted:Control Room Left Unattended & Reactor Safeguards Advisory Group Not Convened Semiannually ML20054H0981982-04-21021 April 1982 Notice of Violation from Insp on 820315-19 IR 05000111/19820011982-02-19019 February 1982 IE Insp Rept 50-111/82-01 on 820202-03.No Noncompliance Noted.Major Areas Inspected:Radiation Protection Associated W/Dismantling Reactor IR 05000297/19800011980-06-25025 June 1980 IE Insp Rept 50-297/80-01 on 800605.No Noncompliance Noted. Major Areas Inspected:Licensee Security Plan,Security Organization,Access Control,Surveillance & Protection Against Sabotage.Details Withheld (Ref 10CFR.2790) IR 05000111/19790031979-12-21021 December 1979 IE Insp Rept 50-111/79-03 on 791105-06 & 11.No Noncompliance Noted.Major Areas Inspected:Preparation & Shipment of Spent Fuel Assemblies ML19274F0041979-04-0202 April 1979 Notice of Violation from Insp on 790313-16 IR 05000111/19790021979-04-0202 April 1979 IE Insp Repts 50-111/79-02 & 50-297/79-02 on 790313-16. Noncompliance Noted:Failure to Develop Procedures Required to Establish 10CFR21 Program & Failure to Document & Approve Temporary Procedure Change IR 05000111/19790011979-03-0808 March 1979 IE Insp Repts 50-111/79-01,50-297/79-01 & 70-0041/79-01 on 790220-21.Noncompliance Noted:Failure to Measure & Rept Accountability Values Re Production & Consumption of Snm. Details Withheld (Ref 10CFR2.790) IR 05000160/19780041978-10-20020 October 1978 IE Inspec Repts 50-160/78-04, 50-276/78-02, 50-297/78-04 & 70-0386/78-04 on 780926-27 During Which No Items of Noncompliance Were Noted.Major Areas Inspec Incl:Nuc Matl Control & Accounting Procedures Review IR 05000297/19780031978-10-0202 October 1978 Inspec Rept 50-297/78-03 on 780817 During Which No Items of Noncompliance Were Noted.Major Area Inspected:Physical Security Plan 1999-03-02
[Table view] |
Text
a
0 UNITED STATES
># H0,#'o NUCLEAR REGULATORY COMMISSION
f*
REGION ll e
j 101 MARIETTA STREET, N.W.
AT LANTA, GEORGI A 30323
'+9.....,o-Report No.:
50-297/86-01 Licensee: North Carolina State University Raleigh, NC 27607 Docket No.:
50-297 License No.:
R-120 Facility Name: PULSTAR Reactor Inspection Conducted: April 14-18, 1986 Inspector:
d
$!/
h na nu P. T. Burnett
/
/
Date' Signed
Approved by:
C//V/ d F. Jape, Section Chief g/
Date Signed Engineering Branch Division of Reactor Safety
'
S'JMMARY Scope:
This routine, unannounced inspection was on site in the area of biennial research reactor inspection.
Results: No violations or deviations were identified.
J pgg6oE8H8t80$7
I
-
_
-
.
__
.-
.
.
.
REPORT DETAILS 1.
Persons Contacted Licensee Employees
- P. J. Turinsky, Head - Department of Nuclear Engineering
- B. W. Wehring, Director - Nuclear Reactor Program
- G. D. Miller, Associate Director - Nuclear Reactor Program
- T. C. Bray, Reactor Operations Manager D. W. Morgan, Radiation Protection Officer S. J. Bilyj, Chief of Reactor Maintenance S. M. Grady, Chief Reactor Operator Other licensee employees contacted included Nuclear Engineering Department faculty, reactor operators, health physics technicians, and office personnel.
- Attended exit interview 2.
Exit Interview The inspection scope and findings were summarized on April 18, 1986, with those persons indicated in paragraph 1 above.
The inspector described the areas inspected and discussed in detail the inspection findings.
No dissenting comments were received from the licensee.
The licensee did not identify as proprietary any of the materials provided to or reviewed by the inspector during this inspection. The following inspector followup item was identified by the inspector and committed to by the licensee:
Inspector followup item 297/86-01-01: Establish a program for trending unidentified primary system water loss by October 18, 1986 - paragraph 5.e.
3.
Licensee Action on Previous Enforcement Matters This subject was not addressed in the inspection.
4.
Unresolved Items No unresolved item was identified during this inspection.
5.
Biennial Inspection Items (40750)
a.
Logs and Records Operations logs for the periods June 13 to August 24, 1984 and January 20 to March 29, 1986 were reviewed.
Over the many startups performed, the agreement between estimated critical position (ECP) and actual critical position (ACP) satisified the acceptance criterion of
+/- 200 percent millirho (pcm) in each case.
Maximum power as
,
.
,
indicated by the N-16 monitor was always within the license limit of 1000 KW.
Pool water purity was consistently high as evidenced by resistivity values ranging from 5 to 6 megohms.
Run sheets, the records of irradiations and reactor usage, were reviewed for the periods given above.
All reactor usage was routine with no new experiments requiring special review or consideration.
The startup and shutdown checklists for the above periods were reviewed and found to be complete and in order. The unscheduled scram and snutdown log was reviewed for the period December 2, 1983 to April 15, 1986.
During that period, there were 52 unscheduled shutdowns and scrams. The overwhelming majority were from operator ranging errors on the linear nuclear instrument channel, which generates a scram at full scale on every scale.
Others came from loss of commercial power and instrument drift.
Recognizing that all scrams come frome single rather than coincident scrams, as on power reactors, the scram rate does not appear excessive.
The maintenance log was reviewed for the 1985 calendar year.
None of the maintenace appeared to be of safety significance. However, the log and history reports were not filled out as completely as necessary to describe fully the the corrective action taken or when the maintenance was completed.
At the exit interview, the licensee agreed to review the practice in that area.
b.
Review and Audit The Reactor Safety Advisory Committee (RSAG), a subcommittee of the Radiation Protection Council (RPC), met semi-annually between December 1983 and December 1985 to appraise the activities of the nuclear operations program.
The most recent appraisal made use of the new Reactor Operations Checklist.
The minutes and checklists completed by the individual committee members reflected far more than pro forma interest and review, which appears to resolve a concern identified in inspection 83-02.
Another concern raised in inspection 83-02 was the use of advance changes to procedures based upon the approval of the nuclear operations administrator prior to review by the RPC.
That practice has been abandoned.
c.
Requalification Traie,ing An active requalification training program was confirmed by review of posted lecture schedules, the on-the-job log of operator and checklist performance, and discussions with licensed personne.
.
.
d.
Procedures The Pulstar Operations Manual (POM) was reviewed along with the procedures for startup and shutdown of the reactor.
Special emphasis was placed upon review of procedures for calculating the estimated critical position (ECP) and shutdown margin (SDM).
It was confirmed that these procedures used up-to-date information for the calculations.
The basic data come from the Pulstar Data Summary, Volume II for which revision 19, issued on September 4,1985, included the results of rod worth measurements on August 5,1985.
The summary also provides the values of the reactivity worths of the experimental facilities.
T e.
Surveillance Tests The following completed surveillance tests were reviewed:
(1)
PS-4-01-2, PS-4-02-2, PS-4-03-2, and PS-4-04-2 were performed on July 12, 1984 to satisfy the requirement of Technical Specifica-tion 4.2.C to visually inspect the control rods biennialy.
(2)
PS-4-07-1(Revision 1), Fuel Inspection, was performed on July 12, 1984, to satisfy the biennial fuel inspection requirement of Technical Specification 4.1.a.
(3)
PS-3-01-4:S1 (Revision 1), Calormetric Power Calibration, was last performed on December 3,1985, to satisfy the requirements of Technical Specification 4.3.C.
Prior to performing this test PS-1-10 (Revision 1), Calibration of Temperature Measuring Channels, and PS-2-03:S1, Calibration of Flow Measuring Channel, were completed.
A review of the records sir:e May 1983 confirmed that these tests were performed, in each case, three to 15 days in advance of the power calibration.
For the flow calibration a calibrated orifice is used.
The RTDs were calibrated in water baths against a standard thermometer.
It was confirmed that the standard current source used to calibrate the nuclear channels was routinely calibrated by a standards laboratory, which issued a certificate of calibration.
A primary water log is maintained and water additions are recorded and plotted.
However, that activity does not lead to any conclusion on primary system integrity, which prudence dictates should be monitored, although not required by the Technical Specifications.
At the exit interview, the licensee committed to establish a program to monitor and trend unidentified water loss by comparing inventory changes with known losses such as pump seal leakage and water sampling and calculable losses such as evaporation to arrive at a periodic loss rate.
That program is to be in place within six months. This commitment will be tracked as Inspector Followup Item 297/86-01-01, Establish a program for trending unidentified primary system water loss by October 18, 1986.
__
..
.
.
f In general, the surveillance procedures lacked detail in method and acceptance criteria and, hence, appeared to require a high degree of skill to perform.
After this issue was raised, the licensee demonstrated that these procedural weaknesses had been recognized, and corrective action was in progress.
Drafts of several expanded procedures had been completed or were in active preparation.
f.
Experiments Currently authorized experiments are identified and described in the Projects Book.
Nineteen different projects are or have been approved by the RPC.
The Radiation Protection Officer issues letters identifying authorized project users by name and project number.
g.
Radiation Protection The inspection confirmed that the fifteen fixed reactor building area monitors are calibrated annually.
The calibrations were last performed in the _ period March to April 1985.
They were scheduled to begin the week of April 21, 1986, which is within the allowed 15-month period.
A monthly radiation survey of the reactor building, dated March 21, 1986, was posted on the doorway from the control room to the reactor bay.
Contamination surveys of the reactor bay are performed three to four times per week.
Six station dosimetry badges were read monthly by an independent contractor.
The contractors evaluation of deliberately exposed badges was within 10% of prediction in all cases in 1985.
'
A review of the personal dosimetry records for ten persons, six operators, two users, and two health physicists, indicated that for 1985, the maximum monthly exposure was about 40 mrem, and the maximum annual dose was less than 200 mrem, h.
Emergency Plan, Training, and Drills The Pulstar Emergency Plan (Revision 1), which was issued on January 1,
1985 and approved by the NRC on May 1,1985, was reviewed for familiarization.
'
Memoranda in the files confirmed that the emergency evacuation horns were activated five times (approximately hourly) on both September 16 and 17,1985 and again on January 22 and 23,1986, to acquaint all
current users of the facilities with the sound of the horn.
An unannounced emergency drill was conducted on August 27, 1985.
A review of the critiques of the drill showed it to be successful.
It, like most of those that preceded it, simulated a spill of radioactive material.
Considering the nature of the facility, a spill is the most likely emergency, but is far from the limiting event.
It was suggested
_. _
.
.
to the licensee that some drill in the near future should simulate the design basis accident. The licensee stated that such a drill was being planned.
From June 11, 1985 to November 27, 1985, there were ten emergency training sessions conducted for 60 people from seven responding organizations.
These included the state police, a local hospital, the fire department, the university public safety office and Wake County Emergency Management Office as well as the campus radiation protection office and the nuclear reactor program.
No violations or deviations were identified.
6.
Plant Tour A tour of the facility revealed all areas to be clean, uncluttered, and free of extraneous material.
Access to all areas was well controlled.
The conduct of several operators was observed on several occasions, and all were attentive to their duties.
7.
Witnessing of an Experiment An experimental demonstration of reactivity coefficients for a class of utility operators was witnessed.
The reactor was made critical at 100 KW with forced convection cooling (500 gpm).
A pair of thermocouples to measure inlet and outlet temperature was installed through one pair of coolant holes in a fuel assembly.
The primary pump was tripped, and the operator maintained power at 100 KW by withdrawing control rods in gang.
Inlet and outlet temperature were monitored as flow reversed from downward forced convection to upward natural convection.
After natural convection flow had stabilized, forced downward convection was re-established without further operator intervention.
Power rapidly increased and stablized below the license limit.
This latter action was a well-controlled simulation of the cold water accident.
All aspects of the demonstration appeared to be well-planned and well-controlled.
.
e