( 'A.'l'K(F08.X REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9806190197 DOC.DATE: 98/06/15 NOTARIZED: NO FACIL:50-275 Diablo Canyon Nuclear Power Plant, Unit 1, Pacific Ga
~
~
~
~
~
50-323 Diablo Canyon Nuclear Power Plant, Unit 2, Pacific Ga AUTH.NAME AUTHOR AFFILIATION MERSCHOFF,E.W.
Region
(Post 820201)
RECIP.NAME RECIPIENT AFFILIATION RUEGER,G.M.
Pacific Gas
&, Electric Co.
DOCKET 05000275 05000323 SUBJECT:
Forwards SALP repts 50-275/98-99
& 50-323/98-99 for period of 960818-980509.Overall performance in plant support area remained superior.
DISTRIBUTION CODE:
IE40D COPIES RECEIVED:LTR (
ENCL (
SIZE:
+
(0 TITLE: Systematic Assessment of Licensee'erformance (SALP) Report NOTES:
E RECIPIENT ID CODE/NAME PD4-2 LA BLOOM,S COPIES RECIPIENT LTTR ENCL ID CODE/NAME
1 PD4-2 PD
~ 1 COPIES LTTR ENCL
1 INTERNAL: ACRS DEDRO NRR/DRCH/HHFB NRR/DRPM/PECB NUDOCS-ABSTRACT OGC/HDS3
1
1
1
1
1
1 COMMISSION R
NRR/DRCEf7HO B
NRR/DRPM/PERB OE DIR RGN4 FILE
5
1
1
1
1
1
EXTERNAL: L ST LOBBY WARD NOAC
1
1 LITCO BRYCE,J H NRC PDR
1
1 D
NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE. TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)
ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED:
LTTR
ENCL
UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
611 RYAN PLA2A DRIVE, SUITE 400
SUBJECT:
SYSTEMATICASSESSMENT OF LICENSEE PERFORMANCE (SALP)
REPORT 50-275/98-99; 50-323/98-99
Dear Mr. Rueger:
Enclosed for your review is the SALP report for the Diablo Canyon Power Plant for the period of August 18, 1996, through May'9, 1998. A meeting to discuss this report with you and your staff is scheduled for 10:00 a.m. on July 8, 1998, at the PG8E Community Center in San Luis Obispo, California. During this meeting, you are encouraged and expected to candidly comment on our report. Although this meeting is a forum between Pacific Gas and Electric Company and the NRC, it willbe open to observation by members of the public and other interested parties.
In accordance with NRC policy, I have reviewed the recommendations of the SALP Board and concur with the ratings and the views. The functional areas of Maintenance and Plant Support were rated as Category 1, indicating superior performance.
The Operations and Engineering functional areas were rated as Category 2, indicating good safety performance.
Performance in the Plant Support area was again determined to be superior.
Improvements were observed in the component areas of radiological controls, emergency preparedness, security, fire protection, and housekeeping.
Performance in the Maintenance area achieved the superior level with improvements in the management of maintenance backlogs and the reduction of plant events due to balance of plant problems.
The SALP Board observed that maintenance management was properly focused on the challenges of implementing planned organizational changes and assuring effective work control.
Performance in the Operations area remained good with improvement noted.
Operations management demonstrated effective oversight and conservative decision making. The SALP Board recognized that, since the previous assessment, management had clarified and communicated expectations, and was working to develop full staff acceptance and 980bi90i97 980bi5 PDR ADOCK 05000275
Pacific Gas and Electric Company-2-implementation of those expectations.
The Board observed that continued attention is needed to consistently achieve management's expectations for procedure adherence and proper clearance program implementation.
Performance in the Engineering area was good with improvement noted in several areas.
The large engineering backlog noted in the previous assessment period was effectively reviewed, prioritized, and issues worked so that only a small number of quality-related items remained.
Engineering management developed and was implementing innovative initiatives to retain design basis knowledge, assure effective knowledge transfer, and centralize various data bases.
The ongoing organizational transition warrants continued management attention. The Board noted that while engineering procedures and programs remained good, some process modification was needed to assure earlier and more effective consideration of the regulatory aspects of design changes and design basis fidelityverifications.
Overall, the SALP Board observed strong Nuclear Quality Services audits and improvement in self-assessments by all program functions.
Continued performance improvements willbe dependent on management's use of these audits and assessments.
In accordance with Section 2.790 of the NRC's "Rules of Practice" Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the SALP report willbe placed in the NRC's Public Document Room.
Ifyou have any questions about the SALP report, we would be pleased to discuss them with you. Although no written response is required, you may submit written comments within 30 days of the SALP meeting.
Sincerely, Ellis W. Merscho Regional Admin trator Docket Nos.: 50-275 50-323
'License Nos.: DPR-80 DPR-82 Enclosure:
As stated
Pacific Gas and Electric Company-3-cc w/enclosure Dr. Richard Ferguson Energy Chair Sierra Club California 1100 lith Street, Suite 311 Sacramento, California 95814 Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164 Pismo Beach, California 93448 Chairman San Luis Obispo County Board of Supervisors Room 370 County Government Center San Luis Obispo, California 93408 Mr. Truman BurnshMr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Rm. 4102 San Francisco, California 94102 Robert R. Wellington, Esq.
Legal Counsel Diablo Canyon Independent Safety Committee 857 Cass Street, Suite D Monterey, California 93940 Mr. Steve Hsu Radiologic Health Branch State Department of Health Services P.O. Box 942732 Sacramento, California 94234 Christopher J. Warner, Esq.
Pacific Gas and Electric Company P.O. Box 7442 San Francisco, California 94120 Robert P. Powers, Vice President and Plant Manager Diablo Canyon Power Plant P.O. Box 56 Avila Beach, California 93424
Pacific Gas and Electric Company Managing Editor Telegram-Tribune 1321 Johnson Avenue P.O. Box 112 San Luis Obispo, California 93406
Pacific Gas and Electric Company-5-m 15 $98 E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to Frank Talbot (FXT)
E-Mail report to Richard Correia (RPC)
bcc to DCD (IE40)
bcc distrib. by RIV:
The Chairman (MS: 16-G-15)
Commissioner Dicus Commissioner Diaz Commissioner McGaffigan Regional Administrator Deputy Regional Administrator DRP Director Project Engineer Branch Chief (DRP/TSS)
L. J. Callan, EDO (MS: 17-G-21)
B. Boger, (A)ADP, NRR Associate Dir. for Insp., and Tech. Assmt, NRR SALP Program Manager, NRR/ILPB (2 copies)
W. Bateman, NRR Project Director S. Bloom, NRR Project Manager MIS System RIV File B. Murray, DRS/PSB C. Hackney, RSLO Records Center, INPO B. Henderson, PAO C. Gordon DRP File SRls at all RIVsites DOCUMENT NAME: R:i DcttDC899SF.KEP To receive cop of document, Indicate in box: "C" = Copy without enctosures
"E" = Cop with enctosures
"N"= No co y RIV:C:DRP/E HJWong*
6/5/98'D:DRS DDChamberlain*
6/5/98 (T)
NRR:PD IV-2 WHBateman 6/5/98 (T)
D:WCFO KEPerkins*
6/5/98 EWM r 6/
/9
- previously concurred OFFICIAL RECORD COPY
Pacific Gas and Electric Company-5;.
JUN l 5 l998 E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
E-Mail report to Frank Talbot (FXT)
E-Mail report to Richard Correia (RPC)
bcc to DCD (IE40)
bcc dlstrib. by RIV:
The Chairman (MS: 16-G-15)
Commissioner Dicus Commissioner Diaz Commissioner MCGaffigan Regional Administrator Deputy Regional Administrator DRP Director, Project Engineer Branch Chief (DRP/TSS)
L. J. Callan, EDO (MS: 17-G-21)
B. Boger, (A)ADP, NRR Associate Dir. for Insp., and Tech. Assmt, NRR SALP Program Manager, NRR/ILPB (2 copies)
W. Bateman, NRR Project Director S. Bloom, NRR Project Manager MIS System RIV File B. Murray, DRS/PSB C. Hackney, RSLO Records Center, INPO B. Henderson, PAO C. Gordon DRP File SRls at all RIVsites DOCUMENT NAME: R:I DciDC899SF.KEP To receive cop of document, Indicate In box: "C" = Copy without enciosures
"E" = Copy with enciosures "N"= No co y RIV:C:DRP/E HJWong*
DD:DRS DDChamberlain*
NRR:PD IV-2 D:WCFO WHBateman*
KEPerkins*
EWM r 6/5/98 6/5/98 6/5/98 (T)
6/5/98 (T)