IR 05000250/2019003
| ML19298B835 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 10/25/2019 |
| From: | Randy Musser NRC/RGN-II/DRP/RPB3 |
| To: | Moul D Florida Power & Light Co |
| Randy Musser REG-II/RPB3 | |
| References | |
| IR 2019003 | |
| Download: ML19298B835 (12) | |
Text
October 25, 2019
SUBJECT:
TURKEY POINT UNITS 3 & 4 - INTEGRATED INSPECTION REPORT 05000250/2019003 AND 05000251/2019003
Dear Mr. Moul:
On September 30, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Turkey Point Units 3 & 4. On October 10, 2019, the NRC inspectors discussed the results of this inspection with Mr. Brian Stamp, Site Director, and other members of your staff.
The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Randall A. Musser, Chief Reactor Projects Branch 3 Division of Reactor Projects
Docket Nos. 05000250 and 05000251 License Nos. DPR-31 and DPR-41
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000250 and 05000251
License Numbers:
Report Numbers:
05000250/2019003 and 05000251/2019003
Enterprise Identifier: I-2019-003-0020
Licensee:
Florida Power & Light Company (FPL)
Facility:
Turkey Point Units 3 & 4
Location:
Homestead, FL 33035
Inspection Dates:
July 01, 2019 to September 30, 2019
Inspectors:
R. Carrion, Senior Reactor Inspector
J. Orr, Senior Resident Inspector
J. Reyes, Resident Inspector
R. Taylor, Senior Project Engineer
Approved By:
Randall A. Musser, Chief
Reactor Projects Branch 3
Division of Reactor Projects
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Turkey Point Units 3 & 4 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Unit 3 began the inspection period at rated thermal power. On September 26, 2019, the unit was down powered to 30 percent to reduce radiation levels in containment for workers performing maintenance on the containment inboard exhaust purge valve POV-3-2603. The unit was returned to rated thermal power on September 29, 2019, and remained at or near rated thermal power for the remainder of the inspection period.
Unit 4 operated at or near rated thermal power for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Impending Severe Weather Sample (IP Section 03.03) (1 Sample)
- (1) The inspectors evaluated readiness for impending adverse weather conditions for Hurricane Dorian from August 28 through September 3, 2019.
71111.04Q - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (6 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) A and B auxiliary feedwater (AFW) pumps while the C AFW pump was out of service (OOS) on July 2, 2019
- (2) Unit 3 and Unit 4 class 1E 125-Volt DC battery systems while the 4A battery was OOS and the spare class 1E battery was supplying the 4A DC bus on July 15, 16, and 19, 2019
- (3) Unit 3 and Unit 4 AFW train 1 and train 2 while the B AFW pump was OOS for emergent maintenance on July 30, 2019 (4)4A emergency diesel generator (EDG) while the 4B EDG was inoperable for a 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> endurance run on August 8, 2019 (5)3B and the spare class 1E station batteries and associated chargers, while the 3A battery was OOS for maintenance on September 9, 2019 (6)3B EDG while the 3A EDG was OOS to install new radiators, engine power packs, and overhaul on September 19, 20, 23 and 24, 2019
71111.05Q - Fire Protection
Quarterly Inspection (IP Section 03.01) (6 Samples)
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Fire zones (FZs) 81, 82, 86 and 87 for the Unit 3 and Unit 4 start-up, auxiliary, and main transformers on July 01, 2019
- (2) FZs 45, 47, 54 and 55 for the Unit 3 and Unit 4 charging pump rooms and component cooling water pump rooms on July 01, 2019
- (3) FZ 122 for the electric and diesel driven fire pumps, jockey pumps, and raw water tank areas on August 12, 2019
- (4) FZs 30, 31, 38 and 40 for the Unit 3 and Unit 4 containment spray pump and pipe and valve rooms on August 15, 2019
- (5) FZs 4, 5, 6, 7, 8, and 9 for the 2 and 4 elevation common areas of the auxiliary building on August 21, 2019
- (6) FZs 25, 25A, 98, 101, and 104 for the Units 3 and Unit 4 cable spread room, electrical equipment room, Unit 4 B DC equipment room, Unit 3 A DC equipment room, and class 1E spare battery room on August 22, 2019
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
- (1) Unit 3 and Unit 4 4kV switchgear rooms on July 8, August 6, 22, 23, and 26, 2019
===71111.07T - Heat Sink Performance
Triennial Review (IP Section 02.02)===
The inspectors evaluated heat exchanger/sink performance on the following:
(1)3B and 4A Component Cooling Water (CCW) Heat Exchangers, Cooled by Intake Cooling Water Section 02.02b (2)3A and 4B Residual Heat Removal (RHR) Heat Exchangers, Closed Loop, Section 02.02c
- (3) Cooling Canals, Heat Sink, Section 02.02d, specifically Sections 02.02d#6 and 02.02d#7 were completed.
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (2 Samples)
- (1) The inspectors observed and evaluated licensed operator performance in the Main Control Room during an unannounced fire drill on September 17, 2019.
- (2) The inspectors observed and evaluated licensed operator performance in the Main Control Room during reactivity operations on Unit 3 while diluting the reactor coolant system boron concentration to maintain rated power, and during Unit 4 AFW train 2 surveillance testing on September 30, 2019.
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated a requalification training simulator scenario administered to an operating crew on August 20, 2019
71111.12 - Maintenance Effectiveness
Routine Maintenance Effectiveness Inspection (IP Section 02.01) (1 Sample)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
- (1) Action Request (AR) 2322902, B AFW pump tripped early at 6,403 rpm (event date was July 31, 2019), on August 26 and 28, and September 25 and 26, 2019.
Quality Control (IP Section 02.02) (1 Sample)
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance activities:
- (1) Work Order (WO) 40224302, 3A EDG radiator core replacement, quality control sample on August 12, 15, 16, 19, and 20, and September 16, 2019.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) Unit 3 and Unit 4 online risk with BS-4-1403, basket strainer to intake cooling water (ICW) supply for the 4C CCW heat exchanger, and E232 condensing unit for the electric equipment room air handling unit V76 OOSs on July 1, 2019
- (2) Unit 3 and Unit 4 online risk with the 3A1 battery charger and the 3A CCW heat exchanger OOSs on July 16 and 19, 2019
- (3) Unit 3 and Unit 4 online risk with Unit 3 and Unit 4 AFW train 1 and A AFW pump OOSs and the Unit 4 control rods aligned for manual operation on August 12, 2019
- (4) Unit 3 and Unit 4 online risk with the Unit 3 and Unit 4 AFW train 1, Unit 3 ICW A header, and the 3B charging pump OOSs on September 11 and 12, 2019
- (5) Unit 3 and Unit 4 online risk with the 3A EDG, 3A charging pump, and the 4D 4kV switchgear room air conditioner 4S230 OOSs on September 16, 17, 19, and 20, 2019
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 02.02) (6 Samples)
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) AR 2321378, unsupported conduit in 3A battery room on August 7, 2019
- (2) AR 2320534, reactor coolant system response after inadvertent 3C charging pump trip on July 11, 2019
- (3) AR 2320780, 4B residual heat removal pump seal leak-off unsatisfactory during surveillance testing on July 12, 2019
- (4) AR 2323337, 4C ICW pump abnormal vibration on August 5, 8, and 12, 2019
- (5) AR 2325249, corroded through conduits resulting in a potential internal flood concern for the 4A and 4B 4kV switchgear rooms on August 22, 23, and September 12, 2019
- (6) AR 2328937, 3A EDG noise during post maintenance testing; AR 02328803, 3A EDG radiator fan shaft deflection; AR 2329174, 3A EDG high vibration data on generator outboard axial; and AR 2329403, 3A EDG engine analysis results for noise on cylinder #19 on September 24, 26, 27, and 30, 2019
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)
The inspectors evaluated the following temporary or permanent modifications:
- (1) Engineering Change (EC) 293163 dewetron recorder and current transformers at 4A 480V load center for ground monitoring on August 21 and 22, 2019
- (2) EC 293789, fabrication of a new washer and gasket for use on taper pin in Unit 3 containment purge exhaust inboard valve, POV-3-2603 on September 27 and 30, 2019
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (8 Samples)
The inspectors evaluated the following post maintenance tests:
(1)0-SME-003.15, Station Battery 60 Month Maintenance after 4A battery bank replacement, WO 40598604 (2)3-OSP-075.2, Auxiliary Feedwater Train 2 Operability Verification and 0-OSP-075.11, Auxiliary Feedwater Inservice Test after B AFW pump governor replacement, WO
===40555048 (3)3-OSP-023.1, Diesel Generator Operability Test after 3A EDG radiator core replacement, WO 40224302 (4)4-OSP-047.1A, Charging Pump 4A Group A Pump Test after crankcase oil change, interlock control pressure switch replacement, oil pump drive chain and suction stabilizer maintenance, WOs 40569110, 40609831, 40632633, and 40680407 (5)0-SME-003.15, Station Battery 60 Month Maintenance after 3A battery bank replacement, WO 40569388 (6)0-OSP-075.11, Auxiliary Feedwater Inservice Test after repair of the A AFW pump inboard journal bearing seal plates, WO 40682368 (7)3-OSP-023.1, Diesel Generator Operability Test after 3A EDG power pack replacement and overhaul, WO 40537362 (8)3-OSP-051.5, Local Leak Rate Tests, after 3-POV-2603, Unit 3 containment purge exhaust inboard valve modification that installed a machined washer and seal on the tapered locked pin, WO 40387403
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
(1)3-OSP-202.2, RHR Pump and Piping Venting; 3-OSP-068.2, Containment Spray Gas Accumulation Management Program; and 0-OSP-202.3, Safety Injection Pump and Piping Venting, on July 25, 2019 (2)4-OSP-023.2, 4B Diesel Generator 24 Hour Full Load Test, on August 6, 2019
Inservice Testing (IP Section 03.01)===
(1)3-OSP-062.2B, Safety Injection Pump 3B Group Pump Test, on July 5, 2019
71114.06 - Drill Evaluation
Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)
The inspectors evaluated:
- (1) Emergency preparedness drill in the simulator control room, technical support center and the emergency operating facility, on August 8,
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification
The inspectors verified licensee performance indicators submittals listed below:
MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===
- (1) Unit 3 July 2018 through June 2019
- (2) Unit 4 July 2018 through June 2019
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (IP Section 02.03) (3 Samples)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) AR 232037232037 B AFW pump overspeed cam device not returned to required normal position causing overspeed trip during test. This issue was selected for follow-up to verify FPL's corrective actions were appropriate to address clarifications to procedural ambiguities that contributed to the overspeed trip and additional unavailability of the B AFW pump.
- (2) AR 1823645 & 2306639, foreign material concerns in CCW systems due to degradation of valve rubber seats. This issue was selected for follow-up to ensure FPL intended to perform extent of condition inspections for a population of CCW rubber seated valves that if degraded could introduce foreign material in the Unit 3 and Unit 4 CCW systems.
- (3) AR 2170587, tornado missile protection walkdowns. This issue was selected to verify that FPL resolved any identified tornado missile protection vulnerabilities that were not in conformance with Turkey Point's current license basis.
71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)
The inspectors evaluated the following licensee event reports (LERs):
- (1) LER 05000250/2019-001-00, Unit 3 Manual Reactor Trip Following Grid Disturbance (ADAMS accession: ML19179A290): The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER therefore no performance deficiency was identified. The inspectors also concluded that no violation of NRC requirements occurred. The circumstances surrounding this LER are documented in Inspection Report 05000250/2019002 and 05000251/2019002 Section 71153 (ADAMS Accession No. ML19219B126).
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 10, 2019, the inspectors presented the integrated inspection results to Mr.
Brian Stamp, Site Director, and other members of the licensee staff.
- On July 18, 2019, the inspectors presented the heat sink inspection results to Mr. Brian Stamp, Site Director, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.07T Drawings
5610-C-1168
Cooling Canals System Layout, Sheet 1
Revision 10
5610-C-1168
Cooling Canals System Layout, Sheet 2
Revision 5
5613-M-3019
Intake Cooling Water System, Sheet 1
Revision 41
5613-M-3019
Intake Cooling Water System, Sheet 2
Revision 30
5613-M-3030
Component Cooling Water System, Sheet 1
Revision 27
5613-M-3030
Component Cooling Water System, Sheet 2
Revision 20
5614-M-3019
Intake Cooling Water System, Sheet 1
Revision 39
5614-M-3019
Intake Cooling Water System, Sheet 2
Revision 28
5614-M-3030
Component Cooling Water System, Sheet 1
Revision 32
5614-M-3030
Component Cooling Water System, Sheet 2
Revision 25
Miscellaneous
Component Cooling Water System Health Reports for Unit 4
from 1st Quarter 2018 through 2nd Quarter 2019
Component Cooling Water Units 3 and 4 Heat Exchanger
Operability Curves from October 2017 through July 2019
(Selected weekly curves were reviewed.)
Intake Cooling Water System Health Reports for Unit 3 from
1st Quarter 2018 through 2nd Quarter 2019
Intake Cooling Water System Health Reports for Unit 4 from
1st Quarter 2018 through 2nd Quarter 2019
Unit 3 Component Cooling Water System Flow Balance for
2017
Unit 3 Component Cooling Water System Flow Balance for
2018
Unit 3 ICW Crawl-Thru Inspection of B Header, C Pump as
related to Work Order 40526237 01
dated
10/14/2018
Unit 4 Component Cooling Water System Flow Balance for
2017
dated
10/25/17
Unit 4 Component Cooling Water System Flow Balance for
2019
Component Cooling Water System Health Reports for Unit 3
from 1st Quarter 2018 through 2nd Quarter 2019
5610-019-DB-001
Design Basis Document: Determination of Affects on
Revision 11
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Accident Analyses
5610-019-DB-002
Component Design Requirements: Intake Cooling Water
System
Revision 11
5610-030-DB-001
Design Basis Document: Component Cooling Water System
Revision 8
5610-030-DB-002
Component Design Requirements: Component Cooling
Water System
Revised
01/27/2016
5610-050-DB-001
Design Basis Documents: Determination of Affects on
Accident Analyses
Revision 11
5610-050-DB-002
Component Design Requirements Document: Residual Heat
Removal System
Revision 11
Florida Power &
Light Company
Environmental
Engineering
Report No. 72-8
Engineering Design of the Turkey Point Cooling Reservoir
dated June
1972
SPEC-M-081
CCW Heat Exchangers Tube Integrity Inspection Turkey
Point Units 3 and 4 and St. Lucie Units 1 and 2
Revision 1
SPEC-M-086
Intake Cooling Water System Piping Inspection
Revision 0
Procedures
0-ADM-651
Nuclear Chemistry Parameters Manual
Revision 11
0-PMM-030.01
CCW Heat Exchanger Cleaning and Inspection
Revision 6
0-PMM-030.04
CCW Heat Exchanger Cleaning and Tube Plugging
Revision 1
3-OSP-019.4
Component Cooling Water Heat Exchanger Performance
Monitoring
Revision 8
3-OSP-030.4
Component Cooling Water Heat Exchanger Performance
Test
Revision 16
4-OSP-019.4
Component Cooling Water Heat Exchanger Performance
Monitoring
Revision 9
4-OSP-030.4
Component Cooling Water Heat Exchanger Performance
Test
Revision 8
CY-TP-104-0031
Component Cooling Water Sampling
Revision 0B