IR 05000250/1990005

From kanterella
Jump to navigation Jump to search
Insp Repts 50-250/90-05 & 50-251/90-05 on 900226-0302.No Violations or Deviations Noted.Major Areas Inspected:Routine Unannounced Insp in Area of Inservice Insp,Including Review of Program Implementing Procedures
ML17347B613
Person / Time
Site: Turkey Point  
Issue date: 03/09/1990
From: Blake J, Newsome R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17347B612 List:
References
50-250-90-05, 50-250-90-5, 50-251-90-05, 50-251-90-5, NUDOCS 9003210249
Download: ML17347B613 (16)


Text

(p,(( R Egg ')p

~

P qO'+*<<+

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MAR I ETTA ST R E ET, N.W.

ATLANTA,GEORGIA 30323 Report Nos.:

50-250/90-05 and 50-251/90-05 Licensee:

Florida Power and Light Company 9250 West Flagler Street Miami, FL 33102 Docket Nos.:

50-250 and 50-251 License Nos.:

DPR-31 and DPR-41 Facility Name:

Turkey Point 3 and

Inspection Conducted:

February 26 - March 2, 1990 Inspector:

R.

W.

ewsome Approved. by:

J

. 'Bla e, Chic a erials and Processes Section E gineering Branch Division of Reactor Safety SUMMARY Date Signe Date Signed Scope This routine, unannounced inspection was conducted on site in the area of Inservice Inspection ( ISI)

and included a

review of the ISI program implementing procedures and the Unit 3 ISI plan for this outage; reviews of nondestructive examination (NDE) procedures; observations of in-progress NDE examinations; independent examination verifications; reviews of NDE personnel qualifications; reviews of NDE equipment calibration and material certification documentation; and, a review of completed NDE examination data.

Results In the areas inspected, violations or deviations were not identified.

This inspection indicated that ISI nondestructive examinations were being conducted adequately.

Also, documentation of examination results, personnel qualifications, and material certification records were adequate.

9OO321O249 9O(.)3(.)'P'OP P'L Ocy, 0. O(.)O25(.)

PDC:

REPORT DETAILS Persons Contacted Licensee Employees

  • J. Arias, Jr., Technical Assistant To Plant Manager E. Anderson, Senior Specialist, Inservice Inspection (ISI)
  • J. Anderson, Supervisor Quality Assurance (QA) Regulatory Compliance
  • M. Blew, ISI Coordinator G. Boyers, ISI F. Carr, NDE Supervisor/Juno Beach Staff
  • J. Cross, Plant Manager
  • V. Kaminskas, Supervisor, Technical Department
  • W. McKnight, ISI
  • L. Pearce, Operations Superintendent
  • D. Powell, Supervisor, Regulatory Compliance Group
  • C. Bedding, ISI
  • K. Remington, Supervisor, Systems Performance Other licensee employees contacted during this inspection included craftsmen, engineers, mechanics, security force members, technicians, and administrative personnel.

NRC Resident Inspectors

  • R. Butcher, Senior Resident Inspector G. Schnebli, Resident Inspector T. McElhinney, Resident Inspector
  • Attended exit interview Acronyms and initialisms used throughout this report are listed in the last paragraph.

Inservice Inspection The inspector reviewed documents and records and observed activities, as indicated below, to determine whether ISI was being conducted in accordance with applicable procedures, regulatory requirements, and licensee commitments.

The applicable code for ISI is the American Society of Mechanical Engineers Boiler and Pressure Vessel (ASME BSPV)

Code,Section XI, 1980 edition with addenda through Winter 1981.

Nondestructive examinations, including visual examinations, are being conducted by

e

EBASCO for the licensee.

Steam generator tubing eddy current (EC) data collection and primary data analysis is being accomplished by a variety of contractor NDE laboratories for the licensee.

Florida Power and Light personnel are performing the secondary EC data evaluation using an automated eddy current data evaluation system.

a.

ISI Program Review, Units 3 and 4 (73051)

The inspector reviewed the following documents relating to the ISI program to determine whether the plan had been approved by the licensee and to assure that procedures and plans had been established (written, reviewed, approved and issued)

to control and accomplish the following applicable activities:

organizational structure including qualifications, training, responsibilities, and duties of personnel responsible for ISI; audits including procedures, frequency, and qualification of personnel; general Quality Assurance requirements including examination reports, deviations from previously established program, material certifications, and identification of components to be covered; work and inspection procedures; control of processes including suitably controlled work

. conditions, special methods, and use of qualified personnel; corrective action; document control; control of examination equipment; quality records including documentation of indications and NDE findings, review of documentation, provisions to assure legibility and retrievability, and corrective action; scope of the inspection including description of areas to be examined, examination category, method of inspection, extent of examinations, and justifi-cation for any exception; definition of inspection interval and extent of examination; qualification of NDE personnel; and, controls of generation, approval, custody, storage and maintenance of NDE records.

JNS-PTN-300.90 (R1)

1990 Inservice Inspection Outage Schedule JNS-MCI.QI 2.14 (R4)

(Sections I thru 18)

ADM-MCI-5.1 (RO)

Nuclear Energy Manual For ASME Section XI Inservice Inspection Of Nuclear Power Plant Components The Preparation, Review And Approval Of Administrative Procedures ADM-CIS-17.1 (RO)

Quality Assurance Records b.

Review of NDE Procedures, Units 3 and 4 (73052)

(I)

The inspector reviewed the procedures listed below to determine whether these procedures were consistent with regulatory requirements and licensee commitments.

The procedures were also reviewed in the areas of procedure approval, requirements for

e

qualification of NDE personnel, and compilation of required records; and, if applicable, division of responsibility between the licensee and contractor personnel if contractor personnel are involved in the ISI effort.

NDE-5.11 (R3)

Ultrasonic Examination Of Dissimilar Metal Piping Welds NDE-5.13 (R3)

Ul trasoni c Examinati on Of Nozzl e Inner Radius Areas NDE-5.16 (R3)

NDE-3.3 (R2)

NDE-4.1 (R3)

NDE-4.3 (R2)

NDE-1.3 (R2)

Ultrasonic Examination Technique For The Evaluation Of Cracking In Feedwater Piping Liquid Penetrant Examination Solvent Removable Visible Dye Technique Visual Examination VT-1 Welds/Bolting/Bushing/Washers Visual Examination VT-3/VT-4 Eddy Current Examination Of Non-Ferromagnetic Tubing With Multi-Frequency Techniques MIZ-18 Turkey Point Units 3 and 4 Steam Generator ECT Data Analysis Guideline (R2)

All procedures listed above had been reviewed during previous NRC inspections.

Only current revisions were reviewed during this inspection.

(2)

The inspector reviewed the Ultrasonic procedures to ascertain whether they had been reviewed and approved in accordance with the licensee's established gA procedures.

The procedures were also reviewed for technical adequacy and conformance with ASME,Section V, Article 5 and other licensee commitments/requirements in the following, areas:

type of apparatus used; extent of coverage of weldment; calibration requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method for demonstrating penetration; limits for evaluating and recording indications; recording significant indications; and, acceptance limits.

(3)

The inspector reviewed the Liquid Penetrant procedure to ascertain whether it had been reviewed and approved in accordance with the licensee's established gA procedures.

The procedure was also reviewed for technical adequacy and conformance with ASME,Section V, Article 6, and other licensee

(4)

commitments/requirements in the following areas:

specified method; penetrant materi al ident ificat ion; penetrant materi a 1 s analyzed for sulfur; penetrant materials analyzed for total halogens; surface temperature; acceptable pre-examination surface conditioning; method used for pre-examination surface cleaning; surface drying time prior to penetrant application; method of penetrant application; penetrant dwell time; method used for excess penetrant removal; surface drying prior to developer application, if applicable; type of developer; examination technique; evaluation techniques; and, procedure requalification.

The inspector reviewed the Visual examination procedures to determine whether they contained sufficient instructions to assure that the following parameters were specified and controlled within the limits permitted by the applicable code, standard, or any other specification requirement:

method direct visual, remote visual or translucent visual; application

- hydrostatic testing, fabrication procedure, visual examination of welds, leak testing, etc.;

how visual examination is to be performed; type of surface condition available; method or implement used for surface preparation, if any; whether direct or remote viewing is used; sequence of performing examination, when applicable; data to be tabulated, if any; acceptance criteria is specified and consistent with the applicable code section or controlling specification; and, report form comple-tion.

(5)

The inspector reviewed the Eddy Current procedures for technical content relative to:

multichannel examination unit, multichannel examination indication equipment is specified, examination sensitivity, method of examination, method of calibration and calibration, sequence, and acceptance criteria.

All procedures reviewed appeared to contain the necessary elements for conducting the specific examination.

Observation of Work and Work Activities, Unit 3 (73753)

The inspector observed work activities, reviewed certification records of NDE equipment and materials, and reviewed NDE personnel qualifications for personnel that had been utilized during the required ISI examinations during this outage.

The observations and reviews conducted by the inspector are documented below.

The inspector observed calibration activities and the in-process ultrasonic (UT) examinations of 4 High Head Safety Injection, 8" diameter, circumferential pipe welds being examined by EBASCO examiners.

These observations were compared with the applicable procedures and the ASNE BSPV Code in the following areas:

availability of and compliance with approved NDE procedures; use

0'

of knowledgeable NDE personnel; use. of NDE personnel qualified to the proper level; type of apparatus used; calibration requirements; search units; beam angles; DAC curves; reference level for monitoring discontinuities; method of demonstrating penetration; extent of weld/component examination coverage; limits of evaluating and recording indications; recording significant indications; and, acceptance limits.

The inspector conducted an independent ultrasonic verification examination, using EBASCO equipment, on portions of 3 of the Safety Injection welds previously observed being examined by the EBASCO ultrasonic examiners.

These examinations were conducted in order to evaluate the technical adequacy of the ultrasonic examination procedure being used by the licensee and to assess the validity of the information being reported by the ultrasonic examiners.

The verification ultrasonic examinations conducted by the inspector indicated that the procedure being used to conduct the examinations is adequate and the verification examination results compared favorably with the information being reported by the ultrasonic examiners.

The following listed ultrasonic equipment and materials certification records were reviewed:

Ultrasonic Instruments Manufacturer/Model Serial No.

Krautkramer/USL-48 Krautkramer/USL-48 Sonic/MK I Sonic/136 213537 213222 06422B 136-207A The inspector reviewed spectrum analysis data for the ultrasonic transducers listed below:

Serial No.

B09728 G03519 H12310 C24771 F21933 Size 5 II 5 II

.25" 1.0"

]

0 II

~Fre uenc 2.25 MHz 2.25 MHz 2.25 MHz 2.25 MHz 2.25 MHz Ultrasonic Couplant Batch Number 8330 Ultrasonic Calibration Blocks UT-6, UT-21, UT-20, UT-53,

& UT-26

The inspector observed the in process liquid penetrant (PT)

examinations of 2 Low Pressure Safety Injection, 8" diameter, circumferential pipe welds.

The observations were compared with the applicable procedure and the ASME BSPV Code in the following areas:

specified method, penetrant materials identified; penetrant materials analyzed for halogens and sulfur; acceptable pre-examination surface; surface temperature; surface drying time prior to penetrant application; method of penetrant application; penetrant dwell time; method used for excess penetrant removal; surface drying prior to developing, if applicable; type of developer; examination technique; evaluation technique; and, reporting of examination results.

The NRC inspector re-evaluated one of the above observed welds following the PT examiners evaluation of the welds but prior to the developer being removed from the weld surfaces.

This re-evaluation was conducted in order to determine if the evaluations performed by the PT examiners was in accordance with the applicable procedure acceptance criteria and to determine if the examination results were being reported as required.

The re-evaluations conducted by the NRC inspector indicated that the proper evaluation was made by the PT examiners and that the examination results were being reported as required.

The inspector's review of the below listed liquid penetrant materials certification records indicated that the sulfur and halogen content of the material was within acceptable content limits.

Materials Batch Number Liquid Penetrant Cleaner/Remover Developer 89F06K, 89K039 87M025 888019 The inspector reviewed records indicating that a

10 pound lift test had been performed on magnetic particle (MT) alternating current (AC) yokes 1784 and 811.

The certification record for the lift test plate that was used to conduct the tests, No. 4, was reviewed to confirm the weight of the test plate.

A review of the magnetic particle material certification record for batch number 87D005 indicated the particles met the applicable specifications requirements.

The inspector observed one in-process visual (VT) examination.

This examination was being conducted on a

14" diameter Regenerative Heat Removal pipe, variable spring hanger, and included the hanger structural members.

This observation was made to:

determine whether the applicable drawing, instructions or travelers clearly specify the procedure to be used and that a

e

copy of the procedure is available in the area where the work is being performed; identify for record review the personnel performing the examination and ascertain whether they are qualified to perform the assigned task; determine whether the required tools and examination aids (as specified in the examination procedure)

are available at the work location; determine whether the specific areas, locations and extent of examination are clearly defined; determine whether the test attributes are as specified in the applicable test procedure; ascertain whether the defects are evaluated in accordance with the procedure requirements, correct acceptance criteria is used, and the inspection results are reported in a prescribed manner.

The NRC inspector conducted an independent examination of the item previously observed being examined by the EBASCO visual examiners.

This examination was conducted in order to evaluate the adequacy of the examination procedure being used by the licensee's contractor and to assess the validity of the, information being reported by the examiners.

This re-examination generally agreed with the results reported by the visual examiners.

Steam Generator Tubing Eddy Current Examination The inspector observed the EC activities indicated below.

The observations were compared with the applicable procedures and the Code in the following areas:

method for maximum sensitivity is applied; method of examination has been recorded; examination equipment has been calibrated in accordance with the applicable performance reference; amplitude and phase angle have been calibrated with the proper calibration reference and is recalibrated at predetermined frequency; required coverage of steam generator tubes occurs during the examination; acceptance criteria is specified or referenced and is consistent with the procedure or the ASHE Code; and, results are consistent with the acceptance criteria.

(a)

In-'process tube data acquisition, incIuding calibration confirmation and tube location verifications, was observed for 24 SG-B tubes.

(b)

In-process eddy current data evaluation, including calibration confirmation, was observed for

SG-8 tubes.

These observations included both primary and secondary data analysis.

The NRC inspector co-evaluated 14 of the SG tubes during the observations of the primary and secondary analyst's evaluations.

The sample of evaluations, some having reportable indications and some with no reported indications, was conducted in order to

'J0

confirm the validity of the reported tubing condition.

The co-evaluation analysis conducted by the inspector agreed well with the reported results.

Certification records for EC calibration standards Z-1545, Z-1546, and Z-1547 were reviewed for material type, correct fabr ication, and artificial flaw location and size.

(6)

The inspector reviewed personnel qualification documentation for

NDE examiners which included EC data collection and EC data analysis personnel.

These personnel qualifications were reviewed in the following areas:

employer's name; person certified; activity qualified to perform; current period of certification; signature of employer's designated representative; basis used for certification; and, annual visual acuity, color vision examination, and periodic recertification.

The NDE personnel appeared to be adequately qualified in all cases reviewed.

d.

Data Review and Evaluation, Unit 3 (73755)

(I)

Records of completed ISI nondestructive examinations for 31 UT, 18 PT, 10 MT, and

VT examinations were selected and reviewed to ascertain whether:

the method(s),

technique, and extent of the examination complied with the ISI plan and applicable NOE procedures; findings were properly recorded and evaluated by qualified personnel; programmatic deviations were recorded as required; personnel, instruments, calibration blocks, and NDE materials (penetrants, couplants)

were designated.

(2)

The inspector reviewed the. eddy current data analysis results and a

sample of associated completed records for over

SG-B tubes.

The reviews were compared with the applicable procedures and the ASME BSPV Code in the following areas:

the multichannel eddy current examination equipment has been identified; material permeability has been recorded; method of examination has been recorded; and, results are consistent with acceptance criteria.

All of the examination reports reviewed appeared to contain the required examination information including disposition of indications, if any.

A random sample of current examination results were compared with historical examination results.

No major discrepancies were noted during the comparison.

In the areas inspected, violations or deviations were not identifie.

Exit Interview The inspection scope and results were summarized on March 2, 1990, with those persons indicated in paragraph 1.

The inspector described the areas inspected and discussed in detail the inspection results listed below.

Although reviewed during this inspection, proprietary information is not contained in this report.

Dissenting comments were not received from the licensee.

5.

Acronyms and Initialisms AC ASME BSPV DAC EC ECT ISI MT MHz NDE.

No.

NRC PT gA R

SG UT VT Alternating Current American Society of Mechanical Engineers Boiler and Pressure Vessel Distance Amplitude Curve Eddy Current Eddy Current Test Inservice Inspection Magnetic Particle Megahertz Nondestructive Examination Number Nuclear Regulatory Commission Liquid Penetrant equality Assurance Revision Steam Generator Ultrasonic Visual