Insp Repts 50-250/85-29,50-251/85-29,50-335/85-22 & 50-389/85-22 on 850819-21.No Violations Noted.Major Areas Inspected:Emergency Preparedness,Emergency Response Facilities & NRC Response Team Coordination
ML17342A239
Person / Time
Site: Saint Lucie, Turkey Point, 05000000
Issue date: 09/26/1985
From: Cunningham A, Stansberry W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17342A238 List:
References
50-250-85-29, 50-251-85-29, 50-335-85-22, 50-389-85-22, NUDOCS 8510220396
Download: ML17342A239 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTASTREET, N.W.

ATLANTA,GEORGIA 30323 OCT 04 1985 Report Nos.:

50-250/85-29, 50-251/85-29, 50-335/85-22 and 50-389/85-22 Licensee:

Florida Power and Light Company 9250 West Flagler Street Miami, FL 33101 ll Docket Nos ~:

50-250, 50-251, 50-335 and 50-389 License Nos.:

DPR-31, DPR-41, DPR-67 and NPF-16 Facility Name:

Turkey Point and St.

Lucie r

Inspection Conducted:

u ust 1 -21, 1985 Inspector:'..

Stan berr Da gned Approved by:

A. L. Cunningha A ting Section Chief Emergency Prepa edness e

Division of Radiation Safety and Safeguards D te S gned SUMMARY

'cope:

This special announced inspection entailed 18 inspector-hours on site and at the General Office in the areas of Emergency Preparedness, Emergency Response Facilities, NRC Response Team Coordination, and NRC Hurricane Response Equipment, Coordination and Procedures.

Results:

Of the four areas inspected, no violations or deviations were identified.

85l0220396 8M004 PDR ADOCK 05000~50

PDR

)

~

~

iL

REPORT DETAILS 1.

Persons Contacted Licensee Employees A. Meade, Security Office (TWC)

M. Hardage, TCD Supervisor, Midway Center

  • J. Maisler, Acting Emergency Planning Supevisor

~D. Mothena, Emergency Planning Coordinator G. Casto, Emergency Planning Coordinator Attended exit interview 2.

Exit Interview The inspection scope and findings were summarized on August 21, 1985, with those persons indicated in paragraph 1 above.

The licensee did not identify as proprietary any of the materials provided to or reviewed by the inspector during this inspection.

l 3.

Licensee Action on Previous Enforcement Matters This subject was not addressed in the inspection.

4.

Independent Inspection Effort (92706)

The inspector held discussions with licensee representatives regarding emergency preparedness, emergency response facilities, Region II Incident Response Teams, NRC-Licensee interface during emergencies and NRC Hurricane equipment, procedures and coordination.

Experience and lessions learned from the Full Field Exercise of the Federal Radiological Emergency Response Plan at Plant St. Lucie, in March 1984 were discussed.

A draft copy of the logistical needs of the Region II Incident Response Teams was presented and discussed.

The inspector discussed NRC response team organization, NRC concept of operation, roles and responsibility of the site team, and interface areas between the NRC and licensee response team.

The NRC Hurricane response team and High Frequency Radio equipment installed at their facilities were reviewed and discussed.,

The licensee was informed that the antenna and tuners have been mounted and should not be dismounted.

Region II'future plans to improve the hurricane communication system was also discussed.