IP 92709

From kanterella
Jump to navigation Jump to search

text

Issue Date: 05/16/19 1 92709

NRC INSPECTION MANUAL IRIB

INSPECTION PROCEDURE 92709

CONTINGENCY PLANS FOR LICENSEE STRIKES OR LOCKOUTS

PROGRAM APPLICABILITY: IMC 2201C, IMC 2515C, IMC 2600B, IMC 2681E3

92709-01 INSPECTION OBJECTIVES

To evaluate the adequacy of the licensee’s contingency plan prior to the strike/lockout to

determine if:

a. The required minimum number of qualified personnel will be available for the proper

operation, security, and safety of the facility.

b. Reactor operation and facility security will be maintained as required.

c. The plan complies with the requirements in Technical Specifications and the Code of

Federal Regulations (CFR).

92709-02 INSPECTION REQUIREMENTS

02.01 Determine the adequacy of the licensee's strike/lockout contingency plans and whether

these plans have been reviewed by the facility's safety review committees or

appropriate managers.

02.02 Determine the adequacy of the licensee’s safeguards contingency plan.

a. The availability and operability of equipment required.

b. The requirements for minimum onsite shift staffing of the facility.

c. The licensee has scheduled covered workers such that the work hours conform to the

requirements specified in 10 CFR 26.205.

02.03 Determine if the licensee’s contingency plan will meet the requirements for minimum

onsite shift staffing of the facility. Verify that the licensee has scheduled covered

workers such that the work hours conform to the requirements specified in 10 CFR 26.205.

Issue Date: 05/16/19 2 92709

02.04 Determine if the licensee’s contingency plan will meet regulatory requirements in the

following areas:

a. Plant management

b. Operations

c. Maintenance

d. Security

e. Chemistry and radiation protection

f. Surveillance and calibrations

g. Administrative controls

h. Nuclear criticality safety (fuel facility)

i. Material control and accounting (fuel facility)

02.05 Determine if licensed personnel who will be performing licensed activities are qualified,

per 10 CFR 55.53(e) and (f).

02.06 Prior to the strike/lockout, perform the following:

a. Verify that the licensee has properly trained, or will have trained prior to shift

assignment, non-licensed personnel who will be performing functions to which they are

not normally assigned.

b. Verify through observation and discussion with one of each of the following plant

personnel that they understand their function under the modified staffing plan as

follows:

1. Plant management.

2. Senior reactor operators and reactor operators (at reactor sites), plant operators

(at fuel facilities).

3. Maintenance.

4. Health Physics.

5. Security supervision.

6. Other personnel responsible for operational or safety functions.

Issue Date: 05/16/19 3 92709

c. Evaluate the effectiveness of site security.

02.07 Verify that support from local agencies is adequate to ensure the following:

a. Unimpeded access of personnel to the plant.

b. Unencumbered delivery of support goods to the site and unencumbered offsite

shipment of radioactive materials.

c. Mitigation of any possible threat to the site, including abusive or violent strikers.

d. Unimpeded access of medical care and ambulance services to treat injured or

contaminated persons.

e. Unimpeded access of the local fire department to supplement the site fire fighting unit.

02.08 Confirm that site staffing will be sufficient and qualified to implement the site emergency

plan.

02.09 Verify that the emergency communication equipment and the Emergency Notification

System, or criticality alarm system, where applicable, are available and operable.

02.10 Meet with the site employee concerns program (ECP) coordinator or ombudsman to

determine if contract negotiations have had any adverse impact on the safety conscious

work environment at the site.

92709-03 INSPECTION GUIDANCE

General Guidance. Events have shown that, once negotiations have gone beyond the end of a

contract date, bargaining unit personnel can strike (Oyster Creek 2003, Nine Mile Point 2011),

or licensee management can decide to lock out bargaining unit personnel (Fermi 1992,

Honeywell 2010 and Pilgrim 2012) with little or no warning. Even if negotiations are ongoing

and bargaining unit staff plan to work without a signed agreement, implementation of this

inspection procedure should occur four to six weeks prior to the expiration of the current

contract so that sufficient time exists to resolve any discrepancies that may be identified in the

licensee’s contingency plan. The licensee's contingency plan should be available for immediate

implementation prior to the expiration of the current contract period, and NRC assessment of

that plan should provide confidence of successful implementation, if the plan is required.

Regional staff will monitor and update contract dates for, at least, security personnel, operators,

chemistry staff, maintenance personnel, and radiation protection staff. Regional management

and the resident inspector staff, as appropriate, will determine the need to implement this

procedure.

Issue Date: 05/16/19 4 92709

The general requirements of 10 CFR associated with security, emergency situations, and

operator training and qualification apply to the strike/lockout situation. The primary guidance

available should be in the licensee's emergency and contingency plans.

Specific Guidance

03.01 The licensee's approved strike/lockout provisions are required to be incorporated into

the site emergency and safeguards contingency plans. To evaluate the licensee's strike/lockout

contingency planning, discuss with licensee management the overall impact of the

strike/lockout, including the number and job classifications of potential strikers. Discuss with

licensee management the training and qualification process for personnel who will be

performing duties they are not normally assigned. The inspector should keep abreast of any

contingency plan changes or contingency plans that are approved by the licensee prior to or

during the strike/lockout. The inspector should keep regional management informed of

contingency plans which are not updated in accordance with the current policies and

procedures and which do not meet all of the requirements outlined in 02.01 through 02.10 of this

inspection procedure.

03.02 If the strike/lockout involves security staff at a power reactor site, the inspector should

evaluate changes to the licensee's safeguards contingency plan that have not been reviewed by

the NRC. Physical security inspectors should lead the review of strike contingency plans

involving security staffing. At a power reactor site, resident inspector staff will monitor possible

changes to these plans and coordinate with the physical security inspectors regarding the need

for compensatory measures on a daily basis. Resident inspectors should also inform regional

management of any changes and/or adverse conditions, and assist security inspectors in

assessing the impact.

Non-power reactors having formula quantities of special nuclear material (SNM) are required to

implement 10 CFR Part 73 safeguards contingency strike/lockout provisions only when the SNM

(i.e. fuel) becomes non-self-protecting.

03.03 When evaluating shift staffing, the inspector should determine whether the licensee has

made appropriate provisions to maintain site coverage for licensed operators, and workers in

the areas of radiation protection, chemistry, and engineering. Nuclear power plant licensed

operator control room staffing is discussed in 10 CFR 50.54(m). The inspector should verify

that the licensee has appropriately to conducted requalification training as needed, while

ensuring that work hours remain within the fitness-for-duty requirements outlined in 10 CFR 26.

The inspector should reference IP 93002, “Managing Fatigue,” for additional guidance

associated with work hour requirements. Non-power reactor staffing requirements are

contained in the facility's technical specifications. Fuel facility staffing requirements are

contained in the approved license application.

03.04 Specific requirements are found in the facility's technical specifications and license, and

in the Code of Federal Regulations. Licensee commitments may also be found in the final

safety analysis report (FSAR).

Issue Date: 05/16/19 5 92709

03.05 The portion of the licensee's strike/lockout contingency plans addressing the prestrike/lockout stage should allow sufficient time for licensed and non-licensed personnel to

become proficient in the positions that they will fill during the strike/lockout. The inspector

should use caution, and limit the length of any discussions held with shift personnel so as not to

distract them from their duties.

a. Licensed operators and senior operators must maintain their license in an active status

as specified in 10 CFR 55.53, "Conditions of Licenses." Activities addressed in 10 CFR 50.54, (i) through (m) must be performed by operators licensed under 10 CFR 55.

b. Fuel facility personnel should be proficient in conversion processes, recovery

processes, criticality controls, material controls, accounting controls and other

operations applicable to the facility.

c. It is recommended that inspectors observe just-in-time training scenarios for newly

configured crews on a plant-referenced simulator to verify that individuals are proficient

in their new roles. Inspectors should observe a minimum of one scenario.

03.06. Prior to the strike/lockout, perform the following:

a. The inspectors should review and understand the process used by the licensee to train

non-licensed personnel who will be performing functions they are not normally

assigned.

b. For personnel in the following non-licensed areas, inspectors should gather and review

a range of one to three training records per area and verify these personnel have been

trained in accordance with licensee programs: Fire Brigade, Chemistry Technician,

Health Physics, Maintenance, Security, and Auxiliary Operator.

c. To evaluate the effectiveness of site security, the physical security inspectors should

inspect security station manning and proper implementation of any security

compensatory measures. The inspectors should discuss with plant management any

previous and potential safeguards threats and the plans to counter these threats.

03.07 The principal offsite support agencies to be contacted by the licensee should include

the following:

a. State police.

b. Local law enforcement agency (LLEA).

c. Local fire department and ambulance service (if separate).

d. Local hospitals.

e. State radiological health agency

Issue Date: 05/16/19 6 92709

f. Fuel oil suppliers (inspectors should verify that the licensee has confirmed that

drivers/suppliers will cross picket lines. If drivers/suppliers will not cross picket lines,

then inspectors should verify that other arrangements for obtaining fuel oil are available

and appropriate).

g. All other suppliers, e.g., food vendors or compressed gas/chemical deliveries.

(inspectors should verify that the licensee has confirmed that drivers/suppliers will cross

picket lines. If drivers/suppliers will not cross picket lines, then inspectors should verify

that other arrangements for getting supplies are available and appropriate.)

The LLEA should be prepared to deal with adverse conditions created by aggressive strikers.

Arrangements should have been made between the licensee and the LLEA to resolve

predictable legal or jurisdictional problems.

The inspectors’ vehicles should be well marked and identified to the LLEA and union pickets to

allow for ease of access to the plant. Inspectors should follow regional instructions regarding

use of vehicles at a strike location. Such guidance should include use of government vehicles

and unique labeling for resident inspector staff privately-owned vehicles to ensure that LLEA

and pickets recognize NRC employees. Out-of-state license plates have been used to identify

temporary replacement staff who have been subjected to harassment by picketers.

The inspector should establish a point-of-contact with site union officials to discuss overall

issues and NRC concerns, i.e., unfettered site access. NRC personnel should develop a plan

covering what actions should be taken when access to the site has been impeded or personal

safety has been threatened by picketers. This plan should be briefed to appropriate staff. If the

inspector has noted any difficulty with site access, regional management should be immediately

informed. As determined by NRC management, the inspector or NRC manager should contact

the site union official and clarify expectations regarding NRC access to the facility, including the

use of LLEA escort, if appropriate. The inspector in no way should engage in negotiations

between the union and licensee or act as a mediator.

Inspectors should verify that the licensee has a process in place to inform licensee personnel on

what actions should be taken in the event that their access to the site has been impeded or that

personal safety has been threatened.

03.08 Any changes to emergency response organization (ERO) compliment, by position

number, or response time to staff emergency response facilities, should be compared to the

licensee’s emergency plan and the licensee’s staffing analysis (required by Part 50, Appendix E,

Section IV.A.9) to verify that the licensee will continue to maintain the effectiveness of the

emergency plan as required by 10 CFR 50.54(q)(2). Resident inspectors should contact

regional EP inspectors for guidance in assessing such changes.

The inspectors should review the process used by the licensee to qualify personnel for their

ERO positions during a strike/lockout and verify that it was conducted in accordance with

licensee emergency plan requirements.

Issue Date: 05/16/19 7 92709

03.09 Emergency communication equipment may include telephones, radios,

radiotelephones, and walkie-talkies.

03.10 The employee concerns program coordinator or site ombudsman should have a system

that accounts for the number of open cases and allegations that will determine whether there is

an adverse effect on the safety conscious work environment at a site. Additionally, inspectors

should refer to IP 71152, “Problem Identification and Resolution,” for guidance on reviewing the

safety conscious work environment at a site and on determining whether supplemental

inspection activities are necessary.

92709-04 RESOURCE ESTIMATE

This inspection procedure requires approximately 70-100 hours to complete. If required, an

additional inspector should assist the resident inspector staff with review of strike/lockout

preparations or baseline inspection activities. Physical security inspectors should lead for

strikes/lockouts involving security staff and regional specialist should assist as needed in the

review of contingency plans whenever licensed staff or ERO members are involved to ensure

that sufficient personnel are available to meet license requirements. The resident inspector can

take credit for baseline inspection activities when performing this procedure. If it is anticipated

that the strike/lockout will be extended, support resources should be identified and, if possible, a

site coverage schedule developed in advance of the strike/lockout.

92709-05 REFERENCES

10 CFR 26.205

10 CFR 40.31

10 CFR 50.34

10 CFR 50.47

10 CFR 50.54

10 CFR 50, Appendix E

10 CFR 55.31

10 CFR 55.53

10 CFR 60.160

10 CFR 70.22

10 CFR 73, Appendix C

Issue Date: 05/16/19 8 92709

IP 71152, “Problem Identification and Resolution”

IP 93002, “Managing Fatigue”

RG 5.73, “Fatigue Management for Nuclear Power Plant Personnel”

NEI 06-11, “Managing Personnel Fatigue at Nuclear Power Sites”

Technical Specifications

92709-06 PROCEDURE COMPLETION

Meeting the inspection objectives defined in section 92709-01 of this inspection procedure will

constitute completion of this procedure.

END

Attachment 1: Revision History page

Issue Date: 05/16/19 Att1-1 92709

Attachment 1 - Revision History for IP 92709

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training Required

and Completion Date

Comment Resolution

and Closed Feedback

Form Accession

Number (PreDecisional, Non-Public

Information)

08/21/92 Revised to incorporate inspection

requirements from IP 92710, update the

procedure and format, and incorporate minor

editorial changes to improve procedure

applicability for use at a non-power reactor

and fuel facilities.

ML050910418

03/30/05

CN 05-009

Revised to improve the review of various

areas not specified in the procedure and to

establish communication links previously not

specified.

N/A ML12136A174

03/14/14

CN 14-007

Revised to capture lessons learned from

licensee strikes in Region I.

None FBF 92709-1442

ML14071A186

ML14071A192

FBF 92709-1729

ML13310A788

Issue Date: 05/16/19 Att1-2 92709

Commitment

Tracking

Number

Accession

Number

Issue Date

Change Notice

Description of Change Description of

Training Required

and Completion Date

Comment Resolution

and Closed Feedback

Form Accession

Number (PreDecisional, Non-Public

Information)

NA ML19086A278

05/16/19

CN 19-015

Periodic review of procedure. Responsible

branch reassigned to reflect current

responsibilities and minor grammatical edits

to clarify inspection area. No substantive

revision to this procedure was warranted at

this time.

None

FBF 92709-2204

ML19112A060