Annual Operating Report - 2003
ML040631005
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 02/24/2004
From: Caves J
Progress Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
HNP-04-014
Download: ML040631005 (4)


Text

aJ Progress Energy FEB 2 4 2004 SERIAL: HNP-04-014 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50400/LICENSE NO. NPF-63 ANNUAL OPERATING REPORT - 2003 Ladies and Gentlemen:

In accordance with Harris Nuclear Plant Technical Specification 6.9.1.2, Progress Energy Carolinas, Inc. provides the Annual Operating Report for 2003. This report includes information regarding; (1) individuals receiving exposures greater than 100 mrem/yr and their associated man-rem exposure according to work and job functions, (2) primary coolant specific activity limits, and (3) challenges to the pressurizer power-operated relief valves and safety valves for 2003.

If you have questions regarding this submittal, please contact me at (919) 362-3137.

Sincerely, J. R. Caves Supervisor - Licensing/Regulatory Programs Harris Nuclear Plant MGW Enclosure c: Mr. R. A. Musser (NRC Senior Resident Inspector, HNP)

Mr. C. P. Patel (NRR Project Manager, HNP)

Mr. L. A. Reyes (NRC Regional Administrator, Region II)

Ms. S. A. Burrows (NRC REIRS Project Manager)

Progress Energy Carolinas, Inc.

Harris Nuclear Plant P.O. Box 165 New Hill. NC 27562

Enclosure to SERIAIL HNP-04-014

.Page 1  :

Report ID: TIBH932 PASSPORT Page: 1 10 CFR PART 20 TOTAL EXPOSURE SYSTEM Date: 02/05/04 WORK AND JOB FUNCTION REPORT / MANAGEMENT REPORT Time: 10:02 Facility: HNP Report for Calendar Year: 200 I This report was produced with pocket dosimeter data.

This report produced for : NRC Task: ** Resource Type:**** Resource Code: ***** and Department Code: ****

Number of Persons Receiving Over 100 miilirem is 256 . Total man-rem: 53.673

--- Number of Individuals ------- -------- Year to Date Dose -------

Station Utility Contractors Station Utility Contractors Employees Employees and Others Employees Employees and Others OPERATIONS & SURVEILLANCE Maintenance Personnel 1.00 1.00 1.00 .075 .006 .002 Operating Personnel' 9.00 .00 .00 .515 .000 .000 Health Physics Personnel 17.00 .00 7.00 .685 .000 .093 Supervisory Personnel .00 1.00 .00 .000 .001 .000 Engineering Personnel 2.00 .00 .00 .087 .000 .000 ROUTINE MAINTENANCE Maintenance Personnel 30.00 .00 30.00 1.426 .000 1.771 Operating Personnel 2.00 .00 .00 .003 .000 .000 Health Physics Personnel 17.00 .00 14.00 .518 .000 .322 Supervisory Personnel .00 .00 .00 .000 .000 .000 Engineering Personnel 4.00 2.00 .00 .062 .053 .000 INSERVICE INSPECTION Maintenance Personnel 4.00 .00 1.00. .015 .000 .002 Operating Personnel 1.00 00 .00 .002 .000 A000 Health Physics Personnel 1.00 .00 2.00 .001 .000 .004 Supervisory Personnel .00 .00 .00 .000 .000 .000 Engineering Personnel 4.00 .00 .00 .133 .000 .000 SPECIAL MAINTENANCE Maintenance Personnel 8.00 .00 2.00 1.138 .000 .182 Operating Personnel .00 .00 .00 .000 .000 .000 Health Physics Personnel 8.00 .00 3.00 .438 .000 .190 Supervisory Personnel .00 .00 .00 .000 .COO .000 Engineering Personnel 2.00 .00 .00 .025 .000 .000 WASTE PROCESSING Maintenance Personnel 1.00 .00 .06 .002 .000 .000 Operating Personnel 4.00 .00 .00 .009 .000 .000 Health Physics Personnel 7.00 .00 1.00 .127 .000 .002 Supervisory Personnel .00 .00 .00 .000 .000 .000 Engineering Personnel 1.00 .00 .00 .006 .000 .000 REFUELING Maintenance Personnel 40.00 19.00 97.00 6.369 4.190 20.706 Operating Personnel 12.00 2.00 .00 1.480 .343 .000 Health Physics Personnel 20.00 4.00 28.00 2.604 .571 4.305 Supervisory Personnel .00 1.00 .00 .000 .187 .000 Engineering Personnel 7.00 3.00 20.00 .939 .611 3.473 TOTAL Maintenance Personnel 84.00 20.00 131.00 9.025 4.196 22.663 Operating Personnel 28.00 2.00 .00 2.009 .343 .000 Health Physics Personnel 70.00 4.00 55.00 4.373 .571 4.916 Supervisory Personnel .00 2.00 .00 .000 .188 .000 Engineering Personnel 20.00 5.00 20.00 1.252 .664 3.473

      • Grand TotalI *** 202.00 33.00 206.00 16.659 5.962 3 1.052

Enclosure to SERIAL: HNP-04-014 Page 2 2003 ANNUAL OPERATING REPORT - PRIMARY COOLANT IODINE SPIKES During 2003, activity levels in the primary coolant did not exceed 1.0 PCi/gram dose equivalent 1-131 or 100/E-bar pCi/gram gross radioactivity as set forth in Technical Specification 3.4.8.

Enclosure to SERIAL: HNP-04-014 Page 3 2003 ANNUAL OPERATING REPORT - PRESSURIZER RELIEF AND SAFEMY VALVE CHALLENGES During 2003, there were no challenges to the pressurizer power-operated relief valves (PORVs) or safety valves.