Inservice Testing (IST) Program Plan, Revision 18
ML021490048
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/17/2002
From: Becker J
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
DCL-02-061
Download: ML021490048 (134)


Text

Pacific Gas and Electric Company James R. Becker Station Director May 17, 2002 Diablo Canyon Power Plant Mail Code 104/5/504 PO Box 56 Avila Beach, CA 93424 805.545.3462 Fax 820.545.4234 PG&E Letter No. DCL-02-061 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Units 1 and 2 Inservice Testing (1ST) Proaram Plan, Revision 18

Dear Commissioners and Staff:

Enclosed for your information is the Diablo Canyon Power Plant Units 1 and 2 IST Program Plan, Revision 18. Submittal of the IST Program Plan is recommended in accordance with the guidance provided in NUREG-1482, "Guidelines for Inservice Testing at Nuclear Power Plants," Question Group 61.

Revision 18 of the IST Program Plan incorporates editorial corrections and updates to the program plan. Revision bars in the enclosure identify changes to the IST Program Plan.

Sincerely, James R. ecker ddm1469 Enclosure cc:

Ellis W. Merschoff David L. Proulx Diablo Distribution cclenc:

Girija S. Shukla State of California A member of the STARS (Strategic Teaming and Resource Sharing) Atilance Callaway -

Comanche Peak o Diablo Canyon -

Palo Verde - South Texas Project

  • Wolf Creek

AU4fi

Enclosure PG&E Letter DCL-02-061 REVISION 18, MARCH 2002 INSERVICE TESTING PROGRAM SECOND TEN-YEAR INTERVAL DIABLO CANYON POWER PLANT

REVISION 18 MARCH 01, 2002 INSERVICE TESTING PROGRAM SECOND TEN-YEAR INTERVAL DIABLO CANYON POWER PLANT UNITS 1 AND 2 USNRC DOCKET NOS. 50-275/50-323 FACILITY OPERATING LICENSE NOS. DPR-80/82 COMMERCIAL OPERATION DATES: MAY 7, 1985/MARCH 13, 1986 Prepared by:

Reviewed by:

Approved:

Approved by:

Joflfn Hjalmarso nST Coordinator 02/07/2002 Edward ChaloupkV, Power Production Engineer

&2/07/2002 PSRC Date c*e/Oc "Jim Becker'\\tation Director 10006618.IST 40MIS 1

REVISION 18 MARCH 01, 2002 INSERVICE TESTING PROGRAM-PLAN SECOND TEN-YEAR INTERVAL INTRODUCTION This volume describes the Inservice Testing (IST) Program Plan for Diablo Canyon Power Plant's safety-related components (pumps and valves) which are classified ASME Code Class 1, Class 2, and Class 3.

This IST Program Plan complies with the requirements of 10 CFR Part 50.55a(a), Part 50.55a(b) (2), and Part 50.55a(f), effective December 31, 1992, as follows:

10CFR50.55a(f) 10CFR50.55a(f) (4) 10CFR50.55a(b) (2) 10CFR50.55a(f) (4) (ii) -

10CFR50.55a(f) (4) (iv) -

10CFR50.55a(f) (5) (i) -

For a pressurized water-cooled nuclear facilities (PWR) whose construction permit was issued prior to January 1, 1971 (Unit l's was issued April 23, 1968 and Unit 2's was issued December 9, 1970), pumps and valves must meet the requirements of paragraphs (f) (4) and (5).

Throughout the service life of a PWR, ASME Code Class 1, 2, or 3 pumps and valves must meet the IST requirements set forth in Section XI of the ASME B&PV Code and Addenda that are incorporated by reference in paragraph (b) of this section, to the extent practical within the limitations of design, geometry and materials of construction of such components.

...references to Section XI of the ASME B&PV Code refer to Section XI, Division 1, and include addenda through the 1988 Addenda and editions through the 1989 Edition.

Inservice tests conducted during successive 120-month intervals must comply with the requirements of the latest edition and addenda of the Code incorporated by reference in paragraph (b) of this section 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed in paragraph (b).

IST of pumps and valves may meet the requirements set forth in subsequent editions and addenda that are incorporated by reference in paragraph (b),

subject to the limitations and modifications listed in paragraph (b), and subject to Commission approval. Portions of editions or addenda may be used provided that all related requirement of the respective additions or addenda are met.

The IST program for a PWR must be revised, as necessary, to meet the requirements of paragraph (f) (4).

(1) 10006618.1ST 40MIS 2

REVISION 18 MARCH 01, 2002 The 1989 Edition of the ASME Boiler and Pressure Vessel Code,Section XI, is no longer involved in testing of pumps and valves. This responsibility has been assumed by the ASME/ANSI Operations and Maintenance of Nuclear Power Plants Standard (OM).Section XI, Subsections IWP (pumps) and IWV (valves), no longer contains requirements for pump and valve testing. Instead these subsections state that testing shall be performed in accordance with the requirements stated in ASME/ANSI OM (Part 6)

(or (Part 10)). Table IWA-1600-1 of Subsection IWA of Section XI gives the specific revision dates for ASME/ANSI OM Parts 6 and 10 as 1987 including 1987A addenda. The 1987A addenda was later corrected to the OMa-1988 addenda. This is also stated in 10CFR50.55a(b) (2) (viii).

The initial testing interval for Unit 1 began May 7, 1985, and for Unit 2 began March 13, 1986, when the respective Units were placed into commercial operation.

The second ten-year interval began January 1, 1996 for Unit 1 and June 1, 1996 for Unit 2.

ASME Section XI, subsection IWA-2400, allows each IST interval to be decreased or extended by as much as one year (see also NRC NUREG-1482, section 3.3.1). This allowance has been applied as follows:

(a)

Unit l's first ten-year IST interval has been increased by approximately 8 months.

(b)

Unit 2's first ten-year IST interval has been increased by approximately 2.5 months.

(2) 10006618.1ST 40MIS 3

REVISION 18 MARCH 01, 2002 Where conformance with certain Code requirements is impractical, requests for relief, in accordance with 10CFR50.55a(a) (3) and 10CFR50.55a(f) (5), are included in each section with supporting information and proposed alternatives. Preservice tests, where required, have been completed. All preservice test data is available for review at the plant site.

ASME SECTION XI CODE BOUNDARY DRAWINGS The ASME Code Classification Boundary Drawings, PG&E Number 102028 (Unit 1) and 104628 (Unit 2), are located in Section 2.0 of the Inservice Inspection (ISI) Program Plan. Regulatory Guide 1.261 was used as the governing document in setting up the Inservice Inspection and Testing Program (ISIT) boundary. The drawings show the Code Class 1, 2, and 3 systems and components subject to inservice inspection and testing requirements. Systems and components are identified by Code Class and are color coded as applicable to indicate exemptions from various code requirements 2. These drawings are extracted from the piping schematics (P&ID's) for the plant that are contained in Section 3.2 of the FSAR. All ASME Code Class 1, 2, and 3 components subject to inservice testing are shown on the drawings. To emphasize the Section XI Code Boundaries, P&ID pages containing lines other than ASME Code Piping have been omitted and non-ASME lines have been ghosted on the pages included.

An explanation of the color coding system is provided at the end of the drawings.

Regulatory Guide 1.26, "Quality Classifications and Standards for Water-Steam-, and Radioactive-Waste-Containing Components of Nuclear Power Plants.

As allowed by Paragraphs IWB-1220, IWC-1220, IWC-1230, and Table IWD-2500-1 of Section XI.

(3) 10006618.IST 40MIS 4

REVISION 18 MARCH 01, 2002 INSERVICE TESTING OF PUMPS AND VALVES The pump and valve testing program demonstrates the operational readiness of Code Class 1, 2, and 3 pumps and valves which are required to perform a specific function in shutting down the reactor to the cold shutdown condition or in mitigating the consequences of an accident. This program is presented in the attached Tables.

Table 1.0 (Pump IST Program) includes the pump name and number, the Code Class, applicable surveillance test procedure and test parameters, i.e., speed, differential pressure, discharge pressure, flow rate, pump bearings vibration, applicable relief request numbers, and remarks.

Table 1. 1 contains all of the pump requests for relief from Code requirements.

Table 2.0 (Valve IST Program) includes the system name and number, valve number, description, P&ID coordinates, Code class, Code category, size, valve type (ball, butterfly, check, diaphragm, gate, globe, plug, or relief valve), actuator type (air operated, electric motor, electrohydraulic, manual, or solenoid-operated), normal valve position, test requirements, the test frequency, applicable stroke time and direction, relief request number (or cold shutdown or refueling outage justification numbers),

procedure number, and remarks.

Table 2.1 contains all valve cold shutdown justifications per OMa-1988, Part 10, section 6.2(d).

Table 2.2 contains all valve refueling outage justifications per OMa-1988, Part 10, section 6.2(d).

Table 2.3 contains all of the valve requests for relief from Code requirements.

(4) 10006618.1ST 40MIS 5

REVISION 18 MARCH 01, 2002 HOT STANDBY AS THE SAFE SHUTDOWN CONDITION NUREG-1482 Section 2.2 requires that the IST PP state the Safe Shutdown condition of the plant. Safe shutdown at Diablo Canyon Power Plant is defined as HOT STANDBY. DCPP SSER 7, page 3-3 and SSER 22, pages 93-95 indicate that DCPP is considered to be a Class 2 plant wherein a single suction line from RCS Hot Leg is considered acceptable since the plant has a safety related Auxiliary Feedwater system enabling decay heat removal for extended periods at Hot Standby. Technical Specification Bases B 3.3.4 states that "safe shutdown condition is defined as MODE 3. With the unit in MODE 3, Auxiliary Feedwater (AFW) System and the Steam Generator (SG) safety valves can be used to remove core decay heat and meet all safety requirements." Hence, DCPP is considered to be a Hot Standby plant.

(5) 10006618.1ST 40MIS 6

INSERVICE TESTING PROGRAM PLAN - PUMPS TABLE 1.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 1 OF 2 The attached sheets identify the pumps that are subject to the testing requirements of OMa-1988, Part 6, and the requests for relief from code requirements.

LEGEND:

CODE CLASS ASME Code Class taken from DWG 102028 Revision 21 (104628 Rev. 19 for Unit 2), "ASME CODE BOUNDARIES FOR INSERVICE INSPECTION AND TESTING PROGRAM."

TEST FREQUENCY NOTATION Notation M

Q A

NA TEST PARAMETER NOTATION Notation N

Dp Q

V P

Frequency At least once per 31 days At least once per 92 days At least once per 366 days Not applicable Parameter Pump Speed (if variable speed)

Pump Differential Pressure Flow Rate Pump Vibration Pump Discharge Pressure 10006618.1ST 40MIS 7

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS TABLE 1.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 2 OF 2 P&ID CODE TEST PARAMETERS AND FREQUENCY RELIEF REMARKS PUMP NAME AND NUMBER COORD CLASS PROCEDURE N

Dp P

Q V

REQUEST Safety Injection Pump 1 Safety Injection Pump 2 Centrifugal Charging Pump 1 Centrifugal Charging Pump 2 Residual Heat Removal Pump 1 Residual Heat Removal Pump 2 Containment Spray Pump 1 Containment Spray Pump 2 Auxiliary Feed Pump 2 (Mtr)

Auxiliary Feed Pump 3 (Mtr)

Auxiliary Feed Pump 1 (Turb)

Auxiliary Saltwater Pump 1 Auxiliary Saltwater Pump 2 Component Cooling Water Pump 1 Component Cooling Water Pump 2 Component Cooling Water Pump 3 Boric Acid Transfer Pump 1 Boric Acid Transfer Pump 2 MU Water Transfer Pump 01 MU Water Transfer Pump 02 57-E 57-D 43D-C 43D-D 36-D 36-A 36-D 36-A 43-D 43-D 43-C 311B-A 31B-C 50-D 52-D 54-D 52B-A 52B-B 73-D 76-D P-SIP P-SIP P-CCP P-CCP P-RHR P-RHR P-CSP P-CSP P-AFW P-AFW P-AFW P-ASW P-ASW P-CCW P-CCW P-CCW P-BAT P-BAT P-MUW P-MUW NA NA NA NA NA NA NA NA NA NA Q

NA NA NA NA NA NA NA NA NA Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q

  • Dp > 1455 psid
  • Dp > 1455 psid
  • Dp > 2400 psid
  • Dp > 2400 psid
  • Dp > 165 psid
  • Dp > 165 psid
  • Dp > 205 psid
  • Dp > 205 psid Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q Q

Q RR2 RR5 RR5 RR4 RR4 RR4

  • Per Tech Spec Bases 10006618.1ST 40MIS 8

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS TABLE 1.1 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 1 OF 8 COMPONENT All Pumps in IST Program Turbine-driven Auxiliary Feedwater Pumps Centrifugal Charging Pumps Component Cooling Water Pumps Auxiliary Saltwater Pumps RELIEF REQUEST APPROVAL STATUS Denied, NRC Letter dated 06/24/97 Approved, NRC Letter dated 03/19/98 Deleted, Design Change eliminated need Approved, NRC Letter dated 02/25/98 Approved, NRC Letter dated 12/30/98 10006618.1ST 40MIS 9

RELIEF REQUEST P-RR1 P-RR2 P-RR3 P-RR4 P-RR5 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 2 OF 8 NO. P-RR2 Pumps:

Turbine-driven Auxiliary Feedwater Pump 1-1 Turbine-driven Auxiliary Feedwater Pump 2-1 Code Class:

3 Test Reqt:

Part 6, Section 6. 1, "Acceptance Criteria" states "If deviations fall within the alert range of Table 3, the frequency of the testing...shall be doubled.... "

According to Table 3a, for centrifugal pumps with speeds

> 600 rpm, any measured vibration levels greater than 0.325 in/sec fall within the Alert Range. Relief is requested from the 0.325 in/sec alert range value.

Functions:

The auxiliary feedwater (AFW) system provides a backup source of feedwater to the secondary side of the steam generators (SGs) when the main feedwater system is unavailable. This maintains the heat removal capability of the SGs. The system also functions as a source of feedwater during plant startups and shutdowns. The turbine-driven AFW pumps (AFWPs) are used as back up to the motor-driven AFWPs.

The turbine-driven AFWPs are tested on recirculation flow in accordance with ASME/ANSI OMa-1988 and Technical Specification SR 3.7.5.2.

Basis:

PG&E requests relief based on 10CFR50.55a(a) (3) (i). The alternative testing provides an acceptable level of quality and safety.

Baseline testing and subsequent quarterly testing of the turbine-driven AFWPs is performed while on recirculation because the only other available flow path is into the steam generators which could result in thermal cycling of FW/AFW nozzles. The baseline vibration levels for the outboard pump bearings were measured at 0.312 in/sec for pump 1-1 and 0.316 in/sec for pump 2-1 in February 1992. The baseline vibration levels were investigated and the pumps were found to be operating acceptably. Subsequent testing on a monthly basis has shown that there is no increasing trend in vibration levels. Some data scatter occurs which occasionally results in vibration readings in the alert range of 0.325 in/sec to 0.700 in/sec. The upper limit of the observed vibration data scatter is approximately 0.400 in/sec.

An alert level of 0.450 in/sec will prevent normal vibration from putting the pump on alert, yet it will still provide sufficient warning if the pump trends toward the action limit.

10006618.1ST 40MIS 10 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 3 OF 8 NO. P-RR2 (cont.)

Per the ASME Code, any vibration level greater than 0.325 in/sec is within the alert range and requires doubling the pump's testing frequency. Since these pumps were baselined, subsequent tests have yielded vibration levels averaging 0.248 in/sec for Unit 1 and 0.317 in/sec for Unit 2. To further investigate this vibration issue, vibration readings were taken on Pump 2-1 at full flow condition. The vibration levels dropped from > 0.300 in/sec on recirculation to 0.099 in/sec at full flow.

Vibration spectral analysis indicates that the predominant frequency is five times pump speed which correlates with the pump vane pass frequency because the pump impellers have five vanes each. When the pumps are operated at low flow, during surveillance testing, the relative flow to the impeller is not aligned with the impeller vane. This causes vibration at vane passing frequency (5X). The operating design flow of these pumps is 870 gpm. Due to thermal fatigue and plant transient concerns, the surveillance test is run with the pump on recirculation flow of approximately 50 gpm.

These recirculation vibration levels do not warrant doubling the testing frequency. In addition, industry experience has shown that extended or frequent operation at minimum flow can cause pumps to degrade.

In the case of the turbine-driven AFWPs, vibration at an alert level of 0.325 in/sec when tested on recirculation is not indicative of a potential pump problem.

Operation of the pumps at vibration levels of up to 0.45 in/sec for short periods of time during quarterly pump testing will not cause the pump to degrade. When the pumps are operated for normal and emergency operations, the flows will be higher and the vibration significantly reduced.

Alternative:

PG&E will set the vibration alert level to 0.450 in/sec for the turbine-driven AFWP bearings for pump testing on recirculation flow. The current action level of 0.700 in/sec will remain unchanged. The vibration levels will continue to be evaluated to the 0.325 in/sec alert level during full flow testing.

Full flow vibration testing will be performed on a COLD SHUTDOWN frequency not to exceed once per 92 days. The test will be performed in Mode 1, 2 or 3 when adequate steam flow is available. During the test, only the bearings which have had vibration levels greater than 0.325 in/sec during the quarterly tests will be monitored, in order to decrease the length of time that cold water is injected into the steam generators.

10006618.1ST 40MIS 11 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 4 OF 8 NO. P-RR4 System: Component Cooling Water PumpoW Component Cooling Water Pump 1-1 Component Cooling Water Pump 1-2 Component Cooling Water Pump 1-3 Component Cooling Water Pump 2-1 Component Cooling Water Pump 2-2 Component Cooling Water Pump 2-3 Code Class:

3 3

3 3

3 3

P&ID Coordinate 102028 E-250 102028 E-252 102028 E-254 104628 E-250 104628 E-252 104628 E-254 Functions:

The component cooling water (CCW) system removes heat from safety-related and nonsafety-related system components during normal operation and plant shutdown and transfers it to the ultimate heat sink via the auxiliary saltwater (AWS) system. The CCW pumps (CCWPs) are horizontally mounted centrifugal pumps.

The CCW system provides for safe shutdown and cooldown of the reactor by removing heat from safety-related and nonsafety-related system components after normal reactor shutdown, and from vital system components after an accident leading to an emergency shutdown.

Test Requirement Operation and Maintenance (OM) Part 6, para 5.2.(b), during pump test resistance of the system, shall be varied until flow equals the reference value.

Basis For Relief A variable flow measurement for the CCWP test is required because it is impractical to establish a fixed reference value(s). Relief is requested per 10CFR50.55a(f) (5) (iii). Diablo Canyon Power Plant (DCPP) had previously received relief for these pumps in the first 10 year plan.

10006618.1ST 40MIS 12 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 5 OF 8 NO. P-RR4 (cont.)

The CCW system has varying heat loads, and therefore varying flow requirements. A full flow test line with a single throttle valve for the purpose of testing was not incorporated in the initial design of the system. For some plant conditions, a reference flow condition cannot be established without adversely affecting the system flow balance and Technical Specification (TS) operability requirements. Thus, these pumps must be tested in a manner that the CCW system remains properly flow balanced during and after the testing and each supplied load remains fully operable per TS to maintain the required level of plant safety during power operation. During refueling outages, CCW flow demand varies greatly due to reactor coolant system cooldown, clearing of components for maintenance, and spent fuel pool heat exchanger cooling water demand. Past experience at DCPP has shown that CCW flow during refueling outages is usually greater than flow during power operations and it is not practical to reduce flow in order to perform the CCWP IST. At a minimum, perturbation of multiple systems is required to establish a flow point due to the multiple flow paths of the CCW system. This abnormal configuration would have to be maintained for the length of time required to take vibration data and pump hydraulic data. In addition, the requirement for the Operators to manipulate valves required to adjust CCW flow to the reference point is adverse to ALARA.

Alternative Test Perform inservice tests on CCWPs using guidance from NUREG-1482, paragraph 5.2. A reference pump curve (flow rate vs. pump head) has been developed for each of the six CCWPs.

The following elements will be performed in developing the pump curves for testing the CCWPs.

Existing data may be used in developing the curves provided it meets the criteria below.

1. Pump reference curves will be developed when the pumps are known to be operating satisfactorily.
2.

Instrumentation used to develop pump curves is at least as accurate (accuracy and range) as required by OM Part 6, Table 1.

3.

Pump curves will be constructed using a minimum of five points.

4.

Points used to construct the curves are beyond the flat portion (low flow rates) of the pump curve in a range which includes the design bases flow rate.

5.

Acceptance criteria for flow rate and differential pressure will be established by taking the more conservative of curves based on the limits of OM Part 6, Table 3b, or the operability criteria in TS or Safety Analysis Report.

6. Vibration levels will be measured over the range of pump conditions, and appropriate vibration acceptance criteria based on OM Part 6, Table 3a, will be assigned for regions of the pump curve.
7. A new reference curve will be prepared, or the previous curve will be validated, if the pump curve is affected by replacement, repair, or routine service.

10006618.IST 40MIS 13 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS TABLE 1.1 REV 18 (2002)

PAGE 6 OF 8 NO. P-RR4 (cont.)

References DCPP Final Safety Analysis Report Update Docket Numbers 50-275 and 50-323; Section 9.2.2 Component Cooling Water System.

DCPP Units 1 and 2 Technical Specification Bases for SR 3.6.6.3.

NUREG-1482 "Guidelines for Inservice testing at Nuclear Power Plants."

DCPP Supplemental Safety Evaluation Number 31, "Appendix A, Safety Evaluation Pump and Valve Inservice Testing Program," paragraph 2.3.3, "Relief Request (3)."

10006618.1ST 40MIS 14 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 7 OF 8 NO. P-RR5 System: Auxiliary Saltwater Pumps Code Class:

P&ID Coordinate Auxiliary Saltwater Pump 1-1 3

102028 B-351 Auxiliary Saltwater Pump 1-2 3

102028 C-354 Auxiliary Saltwater Pump 2-1 3

104628 E-350 Auxiliary Saltwater Pump 2-2 3

104628 C-350 Functions:

The auxiliary saltwater (ASW) system supplies cooling water from the ultimate heat sink, the Pacific Ocean, to the component cooling water (CCW) heat exchangers. The CCW system, in turn, removes heat from nuclear primary plant equipment and components during normal plant operation, plant cooldowns, refueling and accident conditions, including a loss of coolant accident.

Each DCPP unit is provided with two redundant ASW trains. Each of these trains consist of a full capacity ASW pump (ASWP) and associated piping to supply the tube side of one of the CCW heat exchangers with cooling water. Each pump may also be cross-connected so as to supply the opposite train heat exchanger.

Test Requirement OM Part 6, para 5.2.(b), during pump test, resistance of the system shall be varied until flow equals the reference value.

Basis For Relief Adjustment to a specific reference value for the ASWP test is not practical because the pump flow rate varies based on tide level (suction pressure) and heat exchanger differential pressure (system resistance),

which cannot be readily controlled. The CCW heat exchanger outlet throttle valves are the only valves which can be adjusted to set ASWP flow at the desired test flow. These valves are sealed in a throttled position which ensures the train can perform its required safety function under worst case conditions. A CCW heat exchanger is considered inoperable after its outlet valve is adjusted until a flow verification test is performed. The flow verification test requires that the system alignment with the most system resistance i.e., ASW pump #1 to CCW heat exchanger #2 (or ASW pump #2 to CCW heat exchanger #1) be used. This realignment, test and subsequent data analysis takes several hours, during which time the CCW heat exchanger is inoperable. Diablo Canyon Technical Specifications require that the second vital CCW heat exchanger be placed in service whenever ultimate heat sink temperature is greater than 64'F.

In order to meet the Technical Specification LCO, ASW pump tests performed when ultimate heat sink temperatures are above 64°F must be performed with two CCW heat exchangers in service and result in test flows of up to 14,000 gpm. When the test is run with only one CCW heat exchanger in service (normal test alignment), reference pump flow is between 11,500 and 12,500 gpm. Relief is requested per 10CFR50.55a(f) (5) (iii).

I0006618.IST 40MIS 15 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 1.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 8 OF 8 NO. P-RR5 (cont.)

Alternative Test Perform inservice tests on ASWPs using guidance from NUREG-1482, paragraph 5.2. A reference pump curve (flow rate vs. pump head) will be developed for each of the four ASWPs.

The following elements will be performed in developing the pump curves for testing the ASWPs:

1. Pump reference curves will be developed when the pumps are known to be operating satisfactorily.
2. Instrumentation used to develop pump curves is at least as accurate (accuracy and range) as required by OM Part 6, Table 1.
3. These pump curves will be constructed using a minimum of five points.
4. Points used to construct the curves are beyond the flat portion (low flow rates) of the pump curve in a range which includes the design bases flow rate.
5.

Acceptance criteria for flow rate and differential pressure will be established by taking the more conservative of curves based on the limits of OM Part 6, Table 3b, or the operability criteria in TS or Safety Analysis Report.

6. Vibration levels will be measured over the range of pump conditions, and appropriate vibration acceptance criteria based on OM Part 6, Table 3a, will be assigned for regions of the pump curve.
7. A new reference curve will be prepared, or the previous curve will be validated, if the pump curve is affected by replacement, repair, or routine service.

References DCPP Final Safety Analysis Report Update Docket Numbers 50-275 and 50-323; Section 9.2.2 Component Cooling Water System.

DCPP Units 1 and 2 Technical Specification 3.7.8.

NUREG-1482 "Guidelines for Inservice testing at Nuclear Power Plants."

10006618.IST 40MIS 16 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 1 OF 52 The attached sheets identify the system valves that are subject to the testing requirements of OMa-1988, Parts 1 and 10, and the requests for relief from code requirements.

LEGEND:

VALVE CLASS (VLV CLS)

ASME code class taken from DWG 102028 Revision 53 (104628 Rev. 47 for Unit 2) "ASME CODE BOUNDARIES FOR INSERVICE INSPECTION AND TESTING PROGRAM."

NOTE: TS indicates a non ASME code class valve that is required to be tested by Technical Specification.

IWV indicates a non ASME code class valve that is required to be tested in accordance with ASME Section XI, Subsection IWV.

VALVE CATEGORY (VLV CAT)

OM Part 10, paragraph 1.4 VALVE CATEGORIES VALVE SIZE (VLV SIZ)

ASME SIZE IN INCHES VALVE TYPE (VLV TYP) NOTATION NOTATION TYPE BA Ball Valve BV Butterfly Valve CK Check Valve DI Diaphragm Valve GA Gate Valve GL Globe Valve PL Plug Valve RV Relief Valve 10006618.1ST 40MIS 17 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 2 OF 52 LEGEND: (Continued)

ACTUATOR TYPE (ACT TYP) NOTATION NOTATION TYPE A

Air Operated E

Electric Motor H

Electrohydraulic M

Manual N

None S

Solenoid Operated NORMAL POSITION (NRM POS) NOTATION NOTATION POSITION 0

Open C

Closed LO Locked, Sealed, or De-energized (Breaker Open) Open LC Locked, Sealed, or De-energized (Breaker Open) Closed V

Variable 10006618.tST 40MIS 18 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 3 OF 52 LEGEND: (Continued)

TEST REQUIREMENT (TEST REQ) NOTATION NOTATION REQUIREMENT EC Exercise of Check Valve - Full Stroke EF Exercise of Valve - Full Stroke EP Exercise of Check Valve or Valve - Partial Stroke EM Manual Exercise of Check Valve/Disassembly Inspection EN Nonintrusive Exercise of Check Valve LT Valve Leak Test PI Position Indication Test RT Test Per OM Part 1 for Safety and Relief Valve NOTE: Valve Fail Safe testing is required by OM Part 10, paragraph 4.2.1.6. Valves with Fail Safe actuators are tested by the full stroke tests of the valves. A specific Test Requirement was not created for Fail Safe tests.

TEST FREQUENCY (TEST FRQ) NOTATION NOTATION FREQUENCY Q

At least once per 92 days.

CS At least each cold shutdown but not more frequently than once per 92 days.

(This notation identifies valves that cannot be exercised during plant operation. A statement of the technical justification for not full stroke exercising these valves during plant operation is included in Table 2.1).

R At least once per each refueling interval.

(This notation identifies valves that cannot be exercised during plant operation nor full stroke exercised during cold shutdown.

A statement of the technical justification for not full stroke exercising these valves during plant operation and whether they will be part stroked or not tested at all during cold shutdown is included in Table 2.2).

2Y At least once per 24 months.

T Per ASME/ANSI OM Part 1.

RR Tested on a rotational basis during refueling outages.

J Per 10CFR50 Appendix J, Option B.

S At least once per 184 days 10006618.IST 40MIS 19 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 4 OF 52 LEGEND: (Continued)

STROKE TIME (STR TIM)

For power operated valves, the maximum allowed stroke time is given in seconds followed by a "c" for closing, or an "o" for opening, or an "o/c" for both opening and closing. For manual valves and check valves, this column denotes that the valve has a safety function in the "c" closed position, in the "o" open position, or in both the "o/c" open and closed position.

RELIEF REQUEST (REL REQ)

Numbers in this column refer to either a cold shutdown justification (CS), a refueling outage justification (RO), or a relief request (RR). These justifications and relief requests are found in TABLES 2.1, 2.2, and 2.3 respectively.

PROCEDURE NUMBER (PROC NO.)

Identifies procedure used to meet test requirement.

REMARKS The numbers in the remarks column refer to the list of remarks on the last page of TABLE 2.0.

DRAWING REFERENCE NUMBERS UNIT 1: 1020--series UNIT 2: 1080--series UNIT 2 SPECIFIC INFORMATION INDICATED BY PARENTHESES 10006618.IST 40MIS 20 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 5 OF 52 FEEDWATER SYSTEM P& ID NO. 1020 03 VALVE VALVE P& ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FW-348 AUX FP-1 SUCT CK FROM CST FW-349 AUX FP-1 SUCT CK FROM RWS FW-350 AUX FP-2 SUCT CK FROM CST FW-352 AUX FP-3 SUCT CK FROM CST FW-353 FW-354 FW-355 FW-356 FW-361 AUX FP-2&3 SUCT CK FROM RWS AUX FP-1 RECIRC CK AUX FP-2 RECIRC CK AUX FP-3 RECIRC CK AUX FP-1 DISCH CK FW-362 AUX FP-2 DISCH CK FW-363 AUX FP-3 DISCH CK FW-367 SG-2 FW CK FW-368 SG-1 FW CK FW-369 AUX FP-1 TO SG-1 CK 42-C 3

C 8

CK N

C EP EC 41-C 3

C 8

CK N

C EM 42-D 3

C 6

CK N

C EP EC 42-D 3

C 6

CK N

C EP EC 41-D 3

C 8

CK N

C EM 43-C 3

C 1.5 CK N

C EC 43-D 3

C 1.5 CK N

C EC 44-D 3

C 1.5 CK N

C EC 44-C 3

C 6

CK N

C EP EC 44-D 3

C 4

CK N

C EP EC 44-D 3

C 4

CK N

C EP EC 47-A 2

A,C 16 CK N

OEC LT 47-A 2

A,C 16 CK N

OEC LT 47-C 2

C 3

CK N

C EP EC Q

CS RR Q

CS Q

CS RR Q

Q Q

Q CS Q

CS Q

CS CS 2Y CS 2Y Q

CS 0

0 0

0 0

0 0

0 0

0 0

0 0

0 0

0 0

c c

c c

O/c O/c P-AFW CS2 P-AFW RR1 V-18 P-AFW CS2 A-AFW P-AFW CS2 P-AFW RR1 V-18 P-AFW P-AFW P-AFW P-AFW CS3 P-AFW P-AFW CS3 P-AFW P-AFW CS3 P-AFW CS1 V-3P3 V-3P3 CS1 V-3P3 V-3P3 P-AFW CS3 P-AFW

  1. 1-BACKFLOW
  1. 1-BACKFLOW
  1. 1-BACKFLOW
  1. 2-BACKFLOW
  1. 2-BACKFLOW
  1. 2-BACKFLOW
  1. 3-ADMIN
  1. 3-ADMIN 40MIS 21 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY I0006618.IST

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 6 OF 52 FEEDWATER SYSTEM P& ID NO. 1020 03 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS AUX FP-2 TO SG-1 CK AUX FP-1 TO SG-2 CK AUX FP-2 TO SG-2 CK AUX FP-1 TO SG-3 CK AUX FP-3 TO SG-3 CK AUX FP-1 TO SG-4 CK AUX FP-3 TO SG-4 CK SG-1 AUX FW 1ST CK SG-2 AUX FW 1ST CK SG-3 AUX FW IST CK FW-380 SG-4 AUX FW 1ST CK 47-D 47-C 47-D 47-B 47-C 47-B 47-C 49-B 48-B 48-B 48-B 2

2 2

2 2

2 2

2 2

2 C

C C

C C

C C

C C

C 3

3 3

3 3

3 3

3 3

3 CK CK CK CK CK CK CK CK CK CK N

N N

N N

N N

N N

N C

C C

C C

C C

C C

C EP EC EP EC EP EC EP EC EP EC EP EC EP EC EP EC EP EC EP EC Q

CS Q

CS Q

CS Q

CS Q

CS Q

CS Q

CS Q

CS Q

CS Q

CS O/c O/c O/c O/c O/c O/c O/c O/c O/c O/c O/c O/c O/c O/c a

a 0

a CS3 CS3 CS3 CS3 CS3 CS3 CS3 CS3 CS3 CS3 P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW P-AFW 2

C 3

CK N

C EP Q

a P-AFW EC CS a

CS3 P-AFW 10006618.IST 40MIS 22 FW-370 FW-371 FW-372 FW-373 FW-374 FW-375 FW-376 FW-377 FW-378 FW-379

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 7 OF 52 FEEDWATER SYSTEM P& ID NO. 1020 03 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FW-531 SG-3 FW CK FW-532 SG-4 FW CK FCV-436 FCV-437 FCV-438 RWS SUP AUX FP-1 RWS SUP AUX FP-2 & 3 SG-1 FW ISO FCV-439 SG-2 FW ISO FCV-440 SG-3 FW ISO FCV-441 SG-4 FW ISO LCV-106 AUX FP-1 TO SG-I REG LCV-107 AUX FP-1 TO SG-2 REG LCV-108 AUX FP-1 TO SG-3 REG LCV-109 AUX FP-1 TO SG-4 REG LCV-110 AUX FP-2 TO SG-1 REG LCV-111 AUX FP-2 TO SG-2 REG 47-A 2

A,C 16 CK N

0 EC LT 47-A 2

A,C 16 CK N

0 EC LT 41-C 3

B 8

BV M

C EF 41-D 3

B 8

BV M

C EF 48-A 2

B 16 GA E

0 Pi EF 47-A 2

B 16 GA E

0 PI EF 47-A 2

B 16 GA E

0 PI EF 48-A 2

B 16 GA E

0 Pi EF 47-C 2

B 3

GL E

0 Pi EF 47-C 2

B 3

GL E

0 Pi EF 47-B 2

B 3

GL E

0 PI EF 47-B 2

B 3

GL E

0 PI EF 47-D 2

B 2

GL H

0 PI EF 47-D 2

B 2

GL H

0 Pi EF CS 2Y CS 2Y Q*

Q*

2Y CS 2Y CS 2Y CS 2Y CS 2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

c c

c c

O/c O/c NA 60c NA 60c NA 60c NA 60c NA 20o/c NA 20o/c NA 20o/c NA 20o/c NA 40o/c NA 40o/c CS1 V-3P3 V-3P3 CS1 V-3P3 V-3P3 V-3P4 V-3P4 V-2U1C CS1 V-3P2 V-2U2C CSI V-3P2 V-2U3C CS1 V-3P2 V-2U4C CS1 V-3P2 V-2U1D V-3P5 V-2U2D V-3P5 V-2U3D V-3P5 V-2U4D V-3P5 V-2U1D V-3P6A V-2U2D V-3P6A

  1. 3-ADMIN
  1. 3-ADMIN
  • Per Tech Spec
  • Per Tech Spec 10006618.IST 40MIS 23 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

VALVE VALVE NUMBER LCV-113 LCV-115 FCV-510 FCV-520 FCV-530 FCV-540 FCV-1510 FCV-1520 FCV-1530 FCV-1540 RV-536 RV-537 FEEDWATER SYSTEM VALVE DESCRIPTION AUX FP-3 TO SG-4 REG AUX FP-3 TO SG-3 REG SG-1 FW REG SG-2 FW REG SG-3 FW REG SG-4 FW REG SG-1 FW REG BYPASS SG-2 FW REG BYPASS SG-3 FW REG BYPASS SG-4 FW REG BYPASS AUX FP-1 SUCT RELIEF AUX FP-2&3 SUCT RELIEF DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 8 OF 52 P& ID NO. 1020003 P&ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 47-C 47-C 33A-E (38-C) 33A-D (38-D) 33A-A (38-E) 33A-C (38-D) 33A-E (37-B) 33A-C (38-D) 33A-A (38-E) 33A-B (38-E) 42-C (42-D) 41 -D 2

2 TS TS TS TS TS TS TS TS 3

3 B

B B

B B

B B

B B

B C

C 2

2 12 12 12 12 6

6 6

6 lxl.5 lxl.5 GL GL GL GL GL GL GL GL GL GL RV RV H

H A

A A

A A

A A

A N

N 0

0 0

0 0

0 C

C C

C C

C Pi EF PI EF EF PI EF Pi EF PI EF PI EF Pi EF PI EF PI EF PI RT RT 2Y Q

2Y Q

CS*

2Y CS*

2Y CS*

2Y CS*

2Y CS*

2Y CS*

2Y CS*

2Y CS*

2Y T

T NA 40o/c NA 40o/c 7c NA 7c NA 7c NA 7c NA 7c NA 7c NA 7c NA 7c NA NA NA V-2U4D V-3P6B V-2U3D V-3P6B V-3P1 V-2U 1C V-3P1 V-2U2C V-3P1 V-2U3C V-3P1 V-2U4C V-3P1 V-2U1C V-3P1 V-2U2C V-3P1 V-2U3C V-3P1 V-2U4C M-77 M-77

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec 100#

100#

10006618.IST 40MIS 24

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 9 OF 52 TURBINE STEAM SYSTEM P& ID NO. 1020 04 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS MS-1015 MS-1068 MS-2015 MS-2066 MS-3015 MS-3062 MS-4015 MS-4062 MS-5166 SG-1 10% STM DUMP ISO VALVE SG-1 MS LINE CK SG-2 10% STM DUMP ISO VALVE SG-2 MS LINE CK SG-3 10% STM DUMP ISO VALVE SG-3 MS LINE CK SG-4 10% STM DUMP ISO VALVE SG-4 MS LINE CK SG-2 STM TO AUX FP-1 CK MS-5167 SG-3 STM TO AUX FP-1 CK FCV-22 SG-4 MSIV BYPASS FCV-23 SG-3 MSIV BYPASS FCV-24 SG-2 MSIV BYPASS FCV-25 SG-1 MSIV BYPASS 63-B 2

B 8

GA M

0 EF Q

31-A IWV C

28 CK N

0 EM R

63-D 2

B 8

GA M

0 EF Q

31-B IWV C

28 CK N

0 EM R

53-C 2

B 8

GA M

0 EF Q

31-D IWV C

28 CK N

0 EM R

53-D 2

B 8

GA M

0 EF Q

31-E IWV C

28 CK N

0 EM R

30-B 2

C 4

CK N

C EP Q

EC CS EM RR 31-C 2

C 4

CK N

C EP Q

EC CS EM RR 31-E 2

B 3

GL A

C Pi 2Y EF Q

31-C 2

B 3

GL A

C PI 2Y EF Q

31-B 2

B 3

GL A

C Pi 2Y EF Q

31-A 2

B 3

GL A

C PI 2Y EF Q

NA c

NA C

NA c

NA C

0 0

C 0

0 C

NA 5c NA 5c NA 5c NA 5c V-3R1 RO1 V-18 V-3R1 RO1 V-18 V-3R1 RO1 V-18 V-3R1 RO1 V-18 P-AFW CS4 P-AFW RR1l V-18 P-AFW CS4 P-AFW RR11 V-18 V-2U4A V-3R4 V-2U3A V-3R4 V-2U2A V-3R4 V-2U1A V-3R4 10006618.1ST 40MIS 25 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 10 OF 52 TURBINE STEAM SYSTEM P& ID NO. 1020 04 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS SG-2 STM TO AUX FP-1 SG-3 STM TO AUX FP-1 SG-1 MSIV SG-2 MSIV SG-3 MSIV SG-4 MSIV AUX FP-I STM SUP SG-1 BD ISOL OC SG-2 BD ISOL OC 30-B 31-C 31-A 31-B 31-D 31-E 31-B 72-C 72-C 2

2 2

2 2

2 2

2 2

B B

B B

B B

B B

B 4

4 28 28 28 28 4

3 3

GA GA CK CK CK CK GA GA GA E

E A

A A

A E

A A

0 0

0 0

0 0

C 0

0 PI EF PI EF Pi EF PI EF Pi EF PI EF PI EF Pi EF PI EF 2Y Q

2Y Q

2Y CS 2Y CS 2Y CS 2Y CS 2Y Q

2Y Q

2Y Q

NA 30o/c NA 30o/c NA 5c NA 5c NA 5c NA 5c NA 30o NA 1Oc NA 1Oc CS5 CS5 CS5 CS5 V-2U2E V-3R6 V-2U3E V-3R6 V-2U1A V-3R2 V-2U2A V-3R2 V-2U3A V-3R2 V-2U4A V-3R2 V-2U5B V-3R5 V-2J4 V-3S2 V-2J4 V-3S2 10006618.1ST 40MIS 26 FCV-37 FCV-38 FCV-41 FCV-42 FCV-43 FCV-44 FCV-95 FCV-151 FCV-154

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 11 OF 52 TURBINE STEAM SYSTEM P& ID NO. 1020 04 VALVE VALVE P&ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS SG-3 BD ISOL OC SG-4 BD ISOL OC SG-4 SAMPLE ISOL OC SG-3 SAMPLE ISOL OC SG-2 SAMPLE ISOL OC SG-1 SAMPLE ISOL OC SG-1 BD ISOL IC SG-2 BD ISOL IC SG-3 BD ISOL IC SG-4 BD ISOL IC PCV-19 SG-1 10% ATM DUMP 72-D 72-E 72-E 72-D 72-C 72-C 71-C 71-C 71-D 71-E 30-A 2

2 2

2 2

2 2

2 2

2 B

B B

B B

B B

B B

B 3

3

.75

.75

.75

.75 3

3 3

3 GA GA GL GL GL GL GL GL GL GL A

A A

A A

A A

A A

A 0

0 0

0 0

0 0

0 0

0 PI EF PI EF Pi EF PI EF PI EF Pi EF PI EF PI EF Pi EF PI EF 2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

2Y Q

NA 1Oc NA 1Oc NA 1Oc NA 1Oc NA 1Oc NA 1Oc NA 5c NA 5c NA 5c NA 5c 2

B 8

GL A

C PI 2Y NA EF Q

20o/40c 10006618.1ST 40MIS 27 FCV-157 FCV-160 FCV-244 FCV-246 FCV-248 FCV-250 FCV-760 FCV-761 FCV-762 FCV-763 V-2J4 V-3S2 V-2J4 V-3S2 V-2J4 V-3S2 V-2J4 V-3S2 V-2J4 V-3S2 V-2J4 V-3S2 V-2N1 V-3R3 V-2N 1 V-3R3 V-2N1 V-3R3 V-2N1 V-3R3 V-2U1B V-3R1

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 12 OF 52 TURBINE STEAM SYSTEM P& ID NO. 1020 04 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FR TIM REQ NO.

REMARKS Q

PCV-20 SG-2 10% ATM DUMP PCV-21 SG-3 10% ATM DUMP PCV-22 SG-4 10% ATM DUMP RV-3 RV-4 RV-5 RV-6 RV-7 RV-8 SG-1 SAFETY SG-1 SAFETY SG-1 SAFETY SG-1 SAFETY SG-2 SAFETY SG-2 SAFETY RV-9 SG-2 SAFETY RV-10 SG-2 SAFETY 30-C 31-D 31-E 30-A 31-A 31-A 31-A 30-B 31-B 31-B 31-B 2

B 8

GL A

C Pi EF 2

B 8

GL A

C PI EF 2

B 8

GL A

C Pi EF 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 2

C 6

RV N

C RT 10006618.1ST 40MIS 28 2Y Q

2Y Q

2Y Q

T T

T T

T T

T NA 20o/40c NA 20o/40c NA 20o/40c NA NA NA NA NA NA NA V-2U2B V-3R1 V-2U3B V-3R1 V-2U4B V-3R1 M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 1065#

1078#

1090#

1103#

1065#

1078#

1090#

1103#

T NA PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 13 OF 52 TURBINE STEAM SYSTEM P& ID NO. 1020 04 VALVE VALVE P&ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RV-11 RV-12 RV-13 RV-14 RV-58 RV-59 RV-60 RV-61 RV-222 RV-223 RV-224 RV-225 SG-3 SAFETY SG-3 SAFETY SG-3 SAFETY SG-3 SAFETY SG-4 SAFETY SG-4 SAFETY SG-4 SAFETY SG-4 SAFETY SG-1 SAFETY SG-2 SAFETY SG-3 SAFETY SG-4 SAFETY 31-D 31-D 32-D 31-D 31-E 31-E 32-E 31-E 31-A 31-B 31-D 31-E 2

2 2

2 2

2 2

2 2

2 2

2 C

C C

C C

C C

C C

C C

C 6

6 6

6 6

6 6

6 6

6 6

6 RV RV RV RV RV RV RV RV RV RV RV RV N

N N

N N

N N

N N

N N

N C

C C

C C

C C

C C

C C

C RT RT RT RT RT RT RT RT RT RT RT RT T

T T

T T

T T

T T

T T

T NA NA NA NA NA NA NA NA NA NA NA NA M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 M-77 1065#

1078#

1090#

1103#

1065#

1078#

1090#

1103#

1115#

1115#

1115#

1115#

10006618.1ST 40MIS 29 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 14 OF 52 AUXILIARY STEAM SYSTEM P& ID NO. 1020 06 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO. REMARKS AXS-208 AXS STM SUP TO CONT ISO IC 43-E AXS-26 AUX STM SUP TO CONT ISO OC 43-D 2

A 2

CK N

C LT J

C 2

A 2

GA M

LC LT J

c 10006618.IST 40MIS 30 V-670 V-670 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 15 OF 52 REACTOR COOLANT SYSTEM P& ID NO. 1020 07 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FR TIM REQ NO.

REMARKS Q

RCS-508 RCS-512 PCV-455C RV & STM LK OFF HDR TO PRT MISC EQUIP DR TANK ISOL OC PZR PORV PCV-456 PZR PORV PCV-474 PZR PORV 8000A PZR PORV ISOL 8000B PZR PORV ISOL 8000C PZR PORV ISOL 8010A PZR SAFETY 8010B PZR SAFETY 8010C PZR SAFETY 8028 RV DISC HDR TO PRT ISOL IC 8029 PRI WTR TO PRT ISOL OC 44-E 3

C 4

CK N

C EM 48-A 2

A 3/4 GL M

LC LT 40-C 1

B 2

GL A

C PI EF 40-B 1

B 2

GL A

C Pi EF 40-C 1

B 2

GL A

C PI EF 41-C 1

B 3

GA E

0 Pi EF 41-C 1

B 3

GA E

0 PI EF 40-B 1

B 3

GA E

0 PI EF 43-D 1

A,C 6

RV N

C RT 43-D 1

A,C 6

RV N

C RT 42-D 1

A,C 6

RV N

C RT 47-C 2

A,C 4

CK N

C LT EM 48-D 2

A 3

BA A

0 PI LT EF R

i 2Y CS 2Y CS 2Y CS 2Y Q

2Y Q

2Y Q

T T

T J

R 2Y i

Q 0

c NA 2.9o NA 2.9o NA 2.90 NA 20c NA 20c NA 20c NA NA NA c

O/c NA c

1oc R014 V-18 V-671 V-2T1 CS6 V-3J2 V-2T1 CS6 V-3J2 V-2T1 CS6 V-3J2 V-2T1 V-3J1A V-2T1 V-3JlB V-2T1 V-3J1C M-77 M-77 M-77 V-671 RO14 V-18 V-2J7 V-652A V-3S7 RV function 2485#

2485#

2485#

RV function 10006618.IST 40MIS 31 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 16 OF 52 REACTOR COOLANT SYSTEM P& ID NO. 1020 07 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 8034A PRT TO GA ISOL IC 8034B PRT TO GA ISOL OC 8045 8046 8047 N2 TO PRT ISOL OC PRI WTR TO PRT ISOL IC N2 TO PRT ISOL IC 8078A REACTOR VESSEL HEAD VENT 8078B REACTOR VESSEL HEAD VENT 8078C REACTOR VESSEL HEAD VENT 8078D REACTOR VESSEL HEAD VENT 48-E 48-E 48-E 48-D 48-E 75-B 75-B 75-B 75-B 2

A 3/8 GL A

0 Pi LT EF 2

A 3/8 GL A

C Pi LT EF 2

A 3/4 DI A

0 PI LT EF 2

A,C 3

CK N

C LT EC 2

A,C 3/4 CK N

C LT EC 2

B 1

GL S

LC PI EF 2

B 1

GL S

LC Pi EF 2

B 1

GL S

LC PI EF 2

B 1

GL S

LC Pi EF 2Y J

Q 2Y J

Q 2Y J

Q R

R R

R 2Y CS 2Y CS 2Y CS 2Y CS NA C

lOc NA c

1Oc NA c

10c C

C c

C NA 10Oo NA 10Oo NA 10Oo NA 10o V-204 V-676B V-3S8 V-2J7 V-676B V-3S8 V-2J7 V-652B V-3S8 V-652A RR2 V-652A V-652B RR2 V-652B V-2T2 CS7 V-2T2 V-2T2 CS7 V-2T2 V-2T2 CS7 V-2T2 V-2T2 CS7 V-2T2 10006618.1ST 40MIS 32 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

CHEMICAL AND VOLUME CONTROL SYSTEM DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 17 OF 52 P& ID NO. 1020 08 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION c

BA SUP TO BLENDER VCT OUT ISOL VCT OUT ISOL RCP SEAL WTR RETRN ISOL OC EMERG BORATE CENT CHG PP RECIRC CENT CHG PP RECIRC CHG LINE ISOL OC CHG LINE ISOL RCP SEAL WTR RETRN ISOL IC COORD CLS CAT SIZ TYP TYP POS REQ 40B-B 2

B 2

GL A

C Pi EF 43B-D IWV B

4 GA E

0 Pi EF 43B-D IWV B

4 GA E

0 Pi EF 39-E 2

A 4

GA E

0 PI LT EF 41B-A 2

B 2

GL E

C PI EF 41B-A IWV B

2 GL E

0 Pi EF 41B-A 2

B 2

GL E

0 PI EF 47B-C 2

B 3

GA E

0 Pi EF 47B-C 2

B 3

GA E

0 PI EF 38-D 2

A,C 3/4 CK N

0 LT EC EC FRQ TIM REQ NO, REMARKS 2Y Q

2Y CS 2Y CS 2Y J

CS 2Y Q

2Y CS 2Y CS 2Y CS 2Y CS R

R R

NA 10o NA 1Oc NA 1Oc NA c

1Oc NA 1Go NA 1Oc NA loc NA 14c NA 14c c

c 0

V-2K V-3E1 V-211 CS8 V-3K12 V-211 CS8 V-3K12 V-211 V-645 CS9 V-3K2 V-2K V-3E5 V-211 CS10 V-3K9 V-211 CS10 V-3K9 V-211 CS11 V-3K13 V-211 CS1l V-3K13 V-645 RR2 V-645 RO15 V-645

  1. 5 - Hosgri RV function 10006618.1ST 40MIS 33 FCV-110A LCV-1 12B LCV-1 12C 8100 8104 8105 8106 8107 8108 8109

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 18 OF 52 CHEMICAL AND VOLUME CONTROL SYSTEM P& ID NO. 1020 08 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 8112 RCP SEAL WTR RETRN ISOL IC 8145 PZR AUX SPRAY 8146 NORMAL CHG 8147 ALTERNATE CHG 8148 PZR AUX SPRAY BYP 8149A LTDN ORF RO-27 ISOL IC 38-E 2

A 4

GA E

0 PI 2Y LT J

EF CS 43-D 1

B 2

GL A

C Pi 2Y EF CS 43-D 2

B 2

GL A

0 PI 2Y EF CS 42-D 2

B 2

GL A

C PI 2Y EF 43-D 1

B 2

GL A

C PI EF 43-C 2

A 2

GL A

C PI LT EF CS 2Y CS 2Y J

CS NA c

1Oc NA 1o NA 20o NA 20o NA 1o NA c

1oc V-211 V-645 CS9 V-3K2 V-2S CS12 V-3K8 V-2S CS32 V-3K5 V-2S CS32 V-3K5 V-2S CS12 V-3K8 V-2Y V-635 CS30 V-3K7A 10006618.IST 40MIS 34 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 19 OF 52 CHEMICAL AND VOLUME CONTROL SYSTEM P& ID NO. 1020 08 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 8149B LTDN ORF RO-27 ISOL IC 8149C LTDN ORF RO-27 ISOL IC 8152 LTDN LINE ISOL OC 8367A RCP-1 SEAL INJ 2ND CK IC 8367B RCP-2 SEAL INJ 2ND CK IC 8367C RCP-3 SEAL INJ 2ND CK IC 8367D RCP-4 SEAL INJ 2ND CK IC 8368A RCP-1 SEAL INJ 1ST CK IC 8368B RCP-2 SEAL INJ 1ST CK IC 8368C RCP-3 SEAL INJ 1ST CK IC 8368D RCP-4 SEAL INJ 1ST CK IC 43-C 2

A 2

GL A

0 Pi 2Y LT J

EF CS 43-C 2

A 2

GL A

C PI LT EF 44-C 2

A 2

GL A

0 Pi LT EF 31-C 1

C 2

CK N

0 EC 33-C 1

C 2

CK N

0 EC 35-C 1

C 2

CK N

0 EC 37-C 1

C 2

CK N

0 EC 30-B 2

A,C 2

CK N

0 LT EC EC 33-B 2

A,C 2

CK N

0 LT EC EC 35-B 2

A,C 2

CK N

0 LT EC EC 37-B 2

A,C 2

CK N

0 LT EC EC 2Y J

CS 2Y J

CS Q

Q Q

Q R

R Q

R R

Q R

R Q

R R

Q NA c

1Oc NA c

1Oc NA C

10c 0

0 0

c c

0 c

c 0

c c

0 c

c 0

V-2Y V-635 CS30 V-3K7A V-2Y V-635 CS30 V-3K7A V-2J8 V-635 CS13 V-3K7B M-54 M-54 M-54 M-54 V-641 RR2 V-641 M-54 V-641 RR2 V-641 M-54 V-641 RR2 V-641 M-54 V-641 RR2 V-641 M-54 10006618.1ST 40MIS 35 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 20 OF 52 CHEMICAL AND VOLUME CONTROL SYSTEM P& ID NO. 1020 08 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RCP-1 SEAL INJ 3RD CK IC RCP-2 SEAL INJ 3RD CK IC RCP-3 SEAL INJ 3RD CK IC RCP-4 SEAL INJ 3RD CK IC PZR AUX SPRAY CK CHG TO LOOP 3 COLD LEG CK CHG TO LOOP 4 COLD LEG CK CHG LINE CK CHG TO LOOP 3 COLD LEG CK CHG TO LOOP 4 COLD LEG CK VCT OUTLET CK EMER BORATE REV FLO CK RECIP CHG PP-3 DISCH CK CENT CHG PP-I DISCH CK CENT CHG PP-2 DISCH CK 30-B 1

C 2

CK N

0 EC 33-B 1

C 2

CK N

0 EC 35-B 1

C 2

CK N

0 EC 37-B 1

C 2

CK N

0 EC 42-E 1

C 2

CK N

C EC 41-E 1

C 3

CK N

0 EC 41-E 1

C 3

CK N

0 EC 43-B 2

C 3

CK N

0 EC 41-E 1

C 3

CK N

0 EC 41-E 1

C 3

CK N

0 EC 143-C 2

C 4

CK N

0 EC 41B-B 2

C 2

CK N

C EC 45B-C 2

C 2

CK N

0 EC EC 45B-B 2

C 4

CK N

C EP EC EC 45B-A 2

C 4

CK N

C EP EC EC Q

Q Q

Q cs cs cs cs cs cs R

Q Q

R Q

R R

Q R

R M-54 M-54 M-54 M-54 CS12 V-3K8 CS32 V-3K5 CS32 V-3K5 CS32 V-3K5 CS32 V-3K5 CS32 V-3K5 ROll M-86G V-3E5 P-PDP R02 V-25 P-CCP R02 V-15 R02 V-25 P-CCP R02 V-15 R02 V-25 10006618.UST 40MIS 36 8372A 8372B 8372C 8372D 8377 8378A 8378B 8378C 8379A 8379B 8440 8445 8475 8478A 8478B

  1. 7-OPEN PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 21 OF 52 CHEMICAL AND VOLUME CONTROL SYSTEM P& ID NO. 1020 08 VALVE VALVE P& ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS CENT CHG PP-1 RECIRC CK CENT CHG PP-1 RECIRC CK CHG FLO TO CL 3 BYPAS CK BA TRANSFER PP-2 (PP-1)

DISCH CK BA TRANSFER PP-I (PP-2)

DISCH CK PDP RV TO VCT1 LETDOWN RV TO PRT RCP SEAL WTR RETURN HDR RV SEAL WTR HX1 INLT RV TO VCT CHG PPS SUC HDR REL TO PZR 44B-B 45B-A 42-E 52B-B (57B-B) 52B-A (57B-A) 44B-D 44-C 37-E 41B-D 40D-B (43B-B) 2 2 1

2 C

C C

C 2

2 3/4 2

CK CK CK CK N

N N

N C

C C

0 EC EC EC EC Q

Q R

Q 0

0 0

0 2

C 2

CK N

0 EC Q

o 2

2 2

NA 2

C C

C C

C 3/4xl 2

2 2

3/4 RV RV RV RV RV N

N N

N N

C RT T

C RT T

C RT T

C RT T

C RT T

0 0

0 0

0 P-CCP P-CCP RO17 V-15 P-BAT P-BAT M-77 M-77 M-77 M-77 M-77 RV function 2720#

600#

150#

150#

220#

10006618.1ST 40MIS 37 8479A 8479B 8483 8487A 8487B RV-8116 RV-8117 RV-8121 RV-8123 RV-8125 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 22 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FI-927 ISOL OC CHG INJ TO RCS CHG INJ TO RCS SI PP-1 DISCH ISOL OC SI PP-2 DISCH ISOL OC CHG INJ TO RCS CHG INJ TO RCS CHG PP SUCT FROM RHR SI PP SUCT FROM RHR RWST TO CHG PP SUCT 42-E 43-D 43-C 54-E 54-D 45-C 45-B 48-B 58-C 48-C 2

A 3/4 GL M

LC LT 2

B 4

GA E

C PI EF 2

B 4

GA E

C Pi EF 2

A 4

GA E

LC PI LT EF 2

A 4

GA E

LC Pi LT EF 2

B 4

GA E

C Pi EF 2

B 4

GA E

C Pi EF 2

B 8

GA E

C PI EF 2

B 8

GA E

C PI EF 2

B 8

GA E

C PI EF J

2Y Q

2Y Q

2Y R*

CS 2Y R*

CS 2Y Q

2Y Q

2Y R

2Y R

2Y CS c

NA 1Go NA 1Go NA c

20o NA C

20o NA 1Go NA 1Go NA 20o NA 20o NA 1lo V-651B V-2J6 V-3E9 V-2J6 V-3E9 V-2J6 V-7E CS14 V-3L1 V-2J6 V-7E CS14 V-3L1 V-2C V-3E11 V-2C V-3E1l V-2V1 R03 V-3L16 V-2V1 R03 V-3L16 V-2Z CS26 V-3Kll

  • Per Tech Spec
  • Per Tech Spec 10006618.1ST 40MIS 38 SI-161 8801A 8801B 8802A 8802B 8803A 8803B 8804A 8804B 8805A PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 23 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RWST TO CHARG PP SUCT SI PP1 SUC TO CCP SUC XTIE SI PP1 SUC TO CCP SUC XTIE ACCUM-1 DISCH ISOL ACCUM-2 DISCH ISOL ACCUM-3 DISCH ISOL ACCUM-4 DISCH ISOL RHR TO CLD LEGS-1&2 ISOL OC RHR TO CLD LEGS-3&4 ISOL OC RHR TO COLD LEG-1 CK RHR TO COLD LEG-2 CK 48-C 48-B 48-B 31-D 33-D 35-D 37-D 54-C 54-B 52-C 52-B B

B B

B B

B B

B B

A,C A,C 8

4 4

10 10 10 10 8

8 6

6 GA GA GA GA GA GA GA GA GA CK CK E

E E

E E

E E

E E

N N

C C

C LO LO LO LO LO LO C

C PI EF Pi EF PI EF PI EF PI EF Pi EF PI EF PI EF Pi EF LT EN LT EN 2Y CS 2Y Q

2Y Q

2Y CS 2Y CS 2Y CS 2Y CS 2Y CS 2Y CS R*

R R*

R NA 110 NA 20o NA 20o NA 30o NA 30o NA 30o NA 30o NA 20c NA 20c C

0 C

0 V-2Z CS26 V-3Kll V-2H V-3L3 V-2H V-3L3 V-2P1 CS33 V-3L4 V-2P1 CS33 V-3MA V-2P1 CS33 V-3L4 V-2P1 CS33 V-3L4 V-2J3 CS15 V-3L5 V-2J3 CS15 V-3L5 V-5A2 RO13 V-18B V-5A2 RO13 V-18B 8805B 8807A 8807B 8808A 8808B 8808C 8808D 8809A 8809B 8818A 8818B 10006618.IST 40MIS 39

  • Per Tech Spec
  • Per Tech Spec

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 24 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RHR TO COLD LEG-3 CK RHR TO COLD LEG-4 CK SI TO COLD LEG-1 CK SI TO COLD LEG-2 CK SI TO COLD LEG-3 CK SI TO COLD LEG-4 CK CHG INJ 2ND OFF CK SI PP-I DISCH ISOL SI PP-2 DISCH ISOL SI COLD INJECT ISOL OC 52-B 52-A 52-C 52-B 50-B 50-A 41-D 55-E 55-D 1

1 1

1 1

1 1

2 2

A,C A,C A,C A,C A,C A,C C

B B

6 6

2 2

2 2

3 4

4 CK CK CK CK CK CK CK GA GA N

N N

N N

N N

E E

C C

C C

C C

C 0

0 LT EN LT EN LT EC LT EC LT EC LT EC EP EC Pi EF PI EF R*

R R*

R R*

R R*

R R*

R R*

R CS R

2Y Q

2Y Q

C 0

C 0

c 0

c 0

C 0

c 0

0 0

NA 20c NA 20c RO13 RO13 R04 R04 R04 R04 R09 R09 54-C 2

B 4

GA E

LO PI 2Y NA V-5A2 V-18B V-5A2 V-18B V-5Al V-15 V-5Al V-15 V-5Al V-15 V-5Al V-15 V-4A V-15 V-2J6 V-3L2A V-2J6 V-3L2B V-2J6

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec EF CS 20c CS16 V-3L6 10006618.IST 40MIS 40 8818C 8818D 8819A 8819B 8819C 8819D 8820 8821A 8821B 8835

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 25 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS SI TEST LINE ISOL IC SI ACCUM 1 NIT FILL & VENT SI ACCUM 2 NIT FILL & VENT SI ACCUM 3 NIT FILL & VENT SI ACCUM 4 NIT FILL & VENT SI ACCUM 1 DRAIN SI ACCUM 2 DRAIN SI ACCUM 3 DRAIN SI ACCUM 4 DRAIN N2 SUP TO ACCUM ISOL OC SI PP-1 TO TST LINE ISO OC CHG INJ LOOP-M CK CHG INJ LOOP-2 CK CHG INJ LOOP-3 CK CHG INJ LOOP-4 CK 38-C 171-E 173-E 175-E 177-E 170-D 172-D 174-D 177-D 39-E 54-E 40-E 40-B 40-C 40-D 2

A 3/4 GL A

C Pi 2Y LT J

EF Q

2 B

1 GL A

C Pi 2Y 2

B 1

GL A

C PI 2Y 2

B 1

GL A

C PI 2Y 2

B 1

GL A

C Pi 2Y 2

B 1

GL A

C PI 2Y 2

B 1

GL A

C Pi 2Y 2

B 1

GL A

C Pi 2Y 2

B 1

GL A

C Pi 2Y 2

A 1

GL A

0 Pi 2Y LT J

EF Q

2 A

3/4 GL A

C Pi 2Y LT J

EF Q

1 C

1.5 CK N

C EC R

1 C

1.5 CK N

C EC R

1 C

1.5 CK N

C EC R

I C

1.5 CK N

C EC R

10006618.1ST 40MIS 41 8871 8875A 8875B 8875C 8875D 8876A 8876B 8876C 8876D 8880 8883 8900A 8900B 8900C 8900D NA c

1Oc NA NA NA NA NA NA NA NA NA c

1Oc NA c

1Cc 0

0 0

0 V-201 V-651B V-3S5 V-2P2 V-2P2 V-2P2 V-2P2 V-2P2 V-2P2 V-2P2 V-2P2 V-2J7 V-651A V-3S5 V-2J7 V-651B V-3S5 V-15 V-15 V-15 V-15 R09 R09 R09 R09 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

SAFETY INJECTION SYSTE VALVE NUMBER 8905A 8905B 8905C 8905D 8916 8919A 8919B 8922A 8922B 8923A 8923B 8924 VALVE DESCRIPTION SI TO HOT LEG-1 CK SI TO HOT LEG-2 CK SI TO HOT LEG-3 CK SI TO HOT LEG-4 CK N2 SUP TO ACCUM CK IC SI PP-1 TO RWST CK SI PP-2 TO RWST CK SI PP-1 DISCH CK SI PP-2 DISCH CK SI PP-1 SUCT SI PP-2 SUCT RWST TO CHG PP CK DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 26 OF 52 1-ýIM P& ID NO. 1020 09 P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 52-E 52-E 52-D 52-D 38-E 57-E 57-D 56-E 56-D 58-E 58-D 48-C 1

1 1

1 2

2 2

2 2

2 2

2 A,C A,C A,C A,C A,C C

C C

C B

B C

2 2

2 2

1 3/4 3/4 4

4 6

6 8

CK CK CK CK CK CK CK CK CK GA GA CK N

N N

N N

N N

N N

E E

N C

C C

C C

C c

C C

0 0

C EC LT EC LT EC LT EC LT LT EC EC EC EC EC EC EC PI EF Pi EF EP EC EC R

R*

R R*

R R*

R R*

R R

Q Q

R Q

R Q

2Y Q

2Y Q

CS R

R 0

c 0

c 0

c 0

c c

c 0

0 0

c 0

c NA 30c NA 30c 0

0 c

R04 V-15 V-5C R04 V-15 V-5C R04 V-15 V-5C R04 V-15 V-5C V-65IA RR2 V-651A P-SIP P-SIP RO5 V-15 P-SIP RO5 V-15 P-SIP V-2H V-3L1OA V-2H V-3L1OB V-3K10 R020 V-15 R020 M-86G

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec 10006618.IST 40MIS 42

rA.,Irl I.,

.. JJL3 Mtr-Lr-k-l k-AflI Ul lrAIN fI LJICILSli'S AINI SllIN

'S VT LK EAS.Itr.N I LIINI 310

& X 4

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 27 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS LOOP-1 COLD INJ CK LOOP-2 COLD INJ CK LOOP-3 COLD INJ CK LOOP-4 COLD INJ CK SI TO HOT LEG-I CK SI TO HOT LEG-2 CK SI TO HOT LEG-3 CK SI TO HOT LEG-4 CK ACCUM-1 DISCH CK ACCUM-2 DISCH CK ACCUM-3 DISCH CK ACCUM-4 DISCH CK 30-B 30-D 30-A 30-A 50-E 50-E 50-D 50-D 31-C 31-B 31-A 31-A 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 1

A,C 10 10 10 10 6

6 6

6 10 10 10 10 CK CK CK CK CK CK CK CK CK CK CK CK N

N N

N N

N N

N N

N N

N C

C C

C C

C C

C C

C C

C LT EN LT EN LT EN LT EN EC LT EC LT EC LT EC LT LT EN LT EN LT EN LT EN R*

RR R*

RR R*

RR R*

RR R

R*

R R*

R R*

R R*

R*

RR R*

RR R*

RR R*

RR RR4 RR4 RR4 RR4 R06 R06 R06 R06 RR5 RR5 RR5 RR5 V-5A2 V-18A V-5A2 V-18A V-5A2 V-18A V-5A2 V-18A V-15 V-5C V-15 V-5C V-15 V-5C V-15 V-5C V-5A1 V-18A V-5Al V-18A V-5Al V-18A V-5Al V-18A

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec 10006618.1ST 40MIS 43 8948A 8948B 8948C 8948D 8949A 8949B 8949C 8949D 8956A 8956B 8956C 8956D PAC'TFTC" (GrA S k r

.1 F('TRICT C nMPliANYV DI'IARIT.C* tCA NV(*)N DPC*WTIPDPDA NTT-TNJTTq 1 Rr)"

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 28 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 8961 SI TEST LINE ISOL OC 8974A SI RECIRC TO RWST 8974B SI RECIRC TO RWST 8976 RWST TO SI PP ISOL 8977 RWST TO SI PP CK 8980 RWST TO RHR PPS ISOL OC 8981 RWST TO RHR PP CK 8982A CONT RCRC SMP TO RHRP1 ISO 8982B CONT RCRC SMP TO RHRP2 ISO RV-8851 SI TO CL RELIEF TO PRT RV-8853A SI PP1 DISCH TO PRT RV RV-8853B SI PP2 DISCH TO PRT RV RV-8855A ACCUM 1 PRES RV RV-8855B ACCUM 2 PRES RV RV-8855C ACCUM 3 PRES RV 39-C 2

A 3/4 GL A

C PI 2Y NA 57-D IWV.

LT J

EF Q

B 2

GL E

LO PI 2Y EF CS 57-D 2

B 2

GL E

LO PI 2Y EF CS 59-D 2

B 8

GA E

LO PI 2Y EF CS 59-D 2

C 8

CK N

C EP Q

EC R

EC R

59-B 2

B 12 GA E

LO PI 2Y EF CS 59-B 2

C 12 CK N

C EC R

EC CS 52-A 2

B 14 GA E

LC PI 2Y EF R

53-A 2

B 14 GA E

LC PI 2Y EF R

55-D 2

C 3/4 RV N

C RT T

55-E 2

C 3/4xl RV N

C RT T

54-D 31-E 34-E 36-E C

10c NA 1Oc NA 1Oc NA 20c 0

0 c

NA 25c 0

c NA 25o NA 25o 0

0 2

C 3/4xl1RV N

C RT T

o 2

2 2

C C

C 1 1 1

RV RV RV N

N N

C C

C RT T

RT T

RT T

0 0

0 V-2J7 V-651B V-3S5 V-2V2 CS17 V-3L15 V-2V2 CS17 V-3L15 V-2J6 CS18 V-3L13 P-SIP R019 V-15 R019 M-86A1 V-2J3 CS19 V-3L14 R07 V-4C CS34 V-4D V-206 R08 V-3L17 V-206 R08 V-3L17 M-77 M-77 M-77 1750#

M-77 M-77 M-77 10006618.1ST 40MIS 44 1750#

1750#

700#

700#

700#

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 29 OF 52 SAFETY INJECTION SYSTEM P& ID NO. 1020 09 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RV-8855D RV-8856A RV-8856B RV-8858 ACCUM 4 PRES RV RHR PP1 DISCH TO PRT RV RHR PP2 DISCH TO PRT RV RWST TO SI PP SUCT RV 38-E 54-B 54-B 58-D 2

2 2

2 C

C C

C 1

2X3 2X3 3/4 RV RV RV RV N

N N

N C

C C

C RT RT RT RT T

T T

T 0

0 0

0 M-77 M-77 M-77 M-77 700#

600#

600#

220#

10006618.1ST 40MIS 45 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 30 OF 52 RESIDUAL HEAT REMOVAL SYSTEM P& ID NO. 1020 10 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RHR PP-I RECIRC 34-E RHR PP-2 RECIRC 34-B RHR HX-2 OUTLET 31-B RHR HX-1 OUTLET 31-D RHR PP-I SUCT OC 37-D RHR PP-2 SUCT OC 37-B RCS LOOP-4 TO RHR IC 38-D RCS LOOP-4 TO RHR RHR TO HOT LEGS-l, 2 IC 2

B 2

GL E

C PI EF 2

B 2

GL E

C PI EF 2

B 8

BA A

0 EF Pi 2

B 8

BA A

0 EF PI 2

B 14 GA E

0 PI EF 2

B 14 GA E

0 PI EF 1

A 14 GA E

LC PI LT EF 1

A 14 GA E

LC PI LT EF 2

A 12 GA E

LC PI EF LT 2Y Q

2Y Q

Q 2Y Q

2Y 2Y Q

2Y Q

2Y R*

CS 2Y R*

CS 2Y CS R*

NA lOo/c NA lOo/c 30o NA 30o NA NA 120c NA 120c NA c

160o/c NA c

160o/c NA 85o C

V-2D V-3M1A V-2D V-3M1B V-3M2B V-2J3 V-3M2A V-2J3 V-2D2 V-3M4A V-2D2 V-3M4B V-2D3 V-7C CS31 V-3M5 V-2D3 V-7C CS31 V-3M5 V-2M3 CS20 V-3M6 V-7D

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec 10006618.1ST 40MIS 46 FCV-641A FCV-641B HCV-637 HCV-638 8700A 8700B 8701 8702 8703 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 31 OF 52 RESIDUAL HEAT REMOVAL SYSTEM P& ID NO. 1020 10 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS 8716A RHR TRAIN XTIE OC 8716B RHR TRAIN XTIE OC 8730A RHR PP-1 DISCH CK 8730B RHR PP-2 DISCH CK 8740A RHR TO HOT LEG-1 CK 8740B RHR TO HOT LEG-2 CK 8742A RHR HT EX-1 DISCH CK 8742B RHR HT EX-2 DISCH CK RV-8707 RHR PPS SUCT FROM HIA RV RV-8708 RHR TO HLI&2 TO PRT RV 30-D 30-C 35-D 35-C 39-B 39-A 32-D 32-B 38-D 38-B 2

B 8

GA E

0 PI 2Y EF CS 2

B 8

GA E

0 PI 2Y EF CS 2

C 8

CK N

C EP Q

EC CS 2

C 8

CK N

C EP Q

EC CS 1

A/C 8

CK N

C EN R

EM RR LT R*

1 A/C 8

CK N

C EN EM LT 2

C 8

CK N

C EC EC 2

C 8

CK N

C EC EC 2

C 3x4 RV N

C RT 2

C 3/4xl RV N

C RT R

RR R*

CS Q

CS Q

T T

NA 20o/c NA 20o/c 0

0 0

0 0

0 c

0 0

c 0

c 0

C 0

0 V-2J3 CS27 V-3M7 V-2J3 CS27 V-3M7 P-RHR CS21 V-4A P-RHR CS21 V-4A R012 V-18C RR7 V-18 UNIT 1 UNIT 2 V-5C

  • Per Tech Spec R012 V-18C UNIT 1 RR7 V-18 UNIT 2 V-5C
  • Per Tech Spec CS28 V-4A P-RHR CS28 V-4A P-RHR M-77 450#

M-77 600#

10006618.1ST 40MIS 47 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 32 OF 52 NUCLEAR STEAM SUPPLY SAMPLING SYSTEM P& ID NO. 1020 11 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS PZR STM SAMPLE ISOL IC PZR STM SAMPLE ISOL OC 21-A 22-A 9355A PZR LIQUID SAMPLE ISOL IC 21-B 9355B PZR LIQUID SAMPLE ISOL OC 22-B HOT LEG SAMPLE ISOL IC 21-B 2

A 3/8 GL A

0 PI 2Y LT J

EF Q

2 A

3/8 GL A

0 PI 2Y LT J

EF Q

2 A

3/8 GL A

0 Pi 2Y LT J

EF Q

2 A

3/8 GL A

0 Pi 2Y LT J

EF Q

2 A

3/8 GL A

0 PI 2Y LT J

EF Q

10006618.IST 40MIS 48 9354A 9354B 9356A NA c

1Oc NA C

10c NA c

1Oc NA C

10c NA C

1Oc V-203 V-676A V-3S1 V-2J 1 V-676A V-3S1 V-203 V-659A V-3S1 V-2J 1 V-659A V-3S1 V-203 V-659B V-3S1 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 33 OF 52 NUCLEAR STEAM SUPPLY SAMPLING SYSTEM P& ID NO. 1020 11 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS HOT LEG SAMPLE ISOL OC 22-B 2

A 3/8 GL A

0 PI LT EF ACCUM SAMPLE ISOL IC 21-C 2

A 3/8 GL A

0 PI LT EF ACCUM SAMPLE ISOL OC 22-C 2

A 3/8 GL A

0 PI LT EF 2Y J

Q 2Y J

Q 2Y J

Q NA C

1Oc NA C

1Oc NA C

10c V-2J 1 V-659B V-3S1 V-203 V-659C V-3SI V-2J 1 V-659C V-3S1 10006618.1ST 40MIS 49 9356B 9357A 9357B DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 34 OF 52 CONTAINMENT SPRAY SYSTEM P& ID NO. 1020 12 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS CS-31 CS PP-1 TO MEDT ISOL OC CS-32 CS PP-2 TO MEDT ISOL OC 8992 CS ADD TK STOP 8994A NaOH CS EDUCTOR ISOL 8994B NaOH CS EDUCTOR ISOL 8998A CS ADD TK OUT CK 8998B CS ADD TK OUT CK 9001A CS PP-1 ISOL 9001B CS PP-2 ISOL 33-D 33-A 37-B 36-B 37-B 35-C 35-B 34-D 34-A 2

A

.75 GL M

LC LT J

2 A

.75 GL M

LC LT J

2 B

3 GA E

LO PI 2Y 2

B 3

GA E

C PI 2Y EF CS 2

B 3

GA E

C PI 2Y EF CS 2

A,C 3

CK N

C EC CS LT 2Y 2

A,C 3

CK N

C EC CS LT 2Y 2

A 8

GA E

C PI 2Y LT J

EF Q

2 A

8 GA E

C PI 2Y LT J

EF Q

C C

NA NA 10o NA 0

c 0

C NA c

1Go NA c

10o V-631 V-630 V-2G V-2G CS22 V-312 V-2G CS22 V-312 CS23 V-311 V-21 CS23 V-311 V-21 V-2B V-631 V-313A V-2B V-630 V-313B 10006618.1ST 40MIS 50 PASSIVE PASSIVE PASSIVE DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 35 OF 52 CONTAINMENT SPRAY SYSTEM P& ID NO. 1020 12 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS CS PP-1 DISCH CK CS PP-2 DISCH CK RHR HX-1 TO CS-A HDR RHR HX-2 TO CS-B HDR CS HDR-A ISOL CK IC CS HDR-B ISOL CK IC CS ADD CS ADD CS ADD CS HDR CS HDR TK1 VAC BREAK TK2 VAC BREAK TK1 TO AUX BLDG SMP A OC RV B OC RV 33-D 33-A 33-D 33-B 31-D 31-A 37-C 37-C 38-C 32-D 32-B 2

2 2

C C

B 8

8 8

CK CK GA N

N E

C C

C EM EM PI EF 2

B 8

GA E

C Pi EF 2

A,C 8

CK N

C LT EM 2

A,C 8

CK N

C LT EM 2

C 1.5 RV N

C RT 2

C 1.5 RV N

C RT 2

C 3/4xl RV N

C RT 2

C 3/4 RV N

C RT 2

C 3/4 RV N

C RT RR o/c RR o/c 2Y NA R

15o 2Y NA R

15o R

c RR o/c R

c RR o/c T

0 T

0 T

0 T

0 T

0 RR1O V-18 RR10 V-18 V-2B2 R03 V-314 V-2B2 R03 V-314 V-631 RR8 V-18 V-630 RR8 V-18 M-77 M-77 M-77 M-77 M-77 10006618.1ST 40MIS 51 9002A 9002B 9003A 9003B 9011A 9011B RV-930 RV-931 RV-8987 RV-9007A RV-9007B

-1.5# vac

-1.5# vac 10#

260#

260#

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 36 OF 52 COMPONENT COOLING WATER SYSTEM P& ID NO. 1020 14 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS CCW-4 SUCT X-TIE VLV BETWEEN HDRS B&C CCW-5 SUCT X-TIE VLV BETWEEN HDRS A&C CCW-16 CCW PP 2 DISCH TO HEADER B CCW-17 CCW PP 3 DISCH TO HEADER B CCW-18 CCW PP 1 DISCH TO HEADER A CCW-19 CCW PP 2 DISCH TO HEADER A CCW-23 CCW HEADER A TO C ISOLATION VALVE CCW-24 CCW HEADER B TO C ISOLATION VALVE (50-C)

(52-C)

(53-D)

(55-D)

(51-E)

(53-E)

(58-E)

(58-D) 3 B

20 BV M

LO EF EP 3

B 20 BV M

LO EF EP 3

B 20 BV M

LO EF R

Q R

Q Q

N/A N/A N/A N/A N/A 3

B 20 BV M

LO EF Q

N/A 3

B 20 BV M

LO EF Q

N/A 3

B 20 BV M

LO EF Q

N/A 3

B 24 BV M

LO EF Q

N/A 3

B 24 BV M

LO EF Q

N/A R016 V-3H15 V-3H14 RO16 V-3H15 V-3H14 P-CCW P-CCW P-CCW P-CCW P-CCW P-CCW 10006618.1ST 40MIS 52 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 37 OF 52 COMPONENT COOLING WATER SYSTEM P& ID NO. 1020 14 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS CCW-581 CCW FCV-749 BYPASS CK IC CCW-585 CCW TO RCP & RX VSL SUPPORT CK IC CCW-601 CCW-602 CCW-603 CCW-607 CCW-608 CCW-609 CCW-670 CCW PP-I HDR-A CK CCW PP-2 HDR-A CK CCW PP-3 HDR-A CK CCW PP-1 HDR-B CK CCW PP-2 HDR-B CK CCW PP-3 HDR-B CK CCW FCV-750 BYPASS CK IC CCW-695 CCW TO EXCS LTDN HX CK OC FCV-355 CCW HDR-C ISOL FCV-356 CCW TO RCP & RX VSL SUPPORT ISOL OC 71-B 72-E 52-E 53-E 55-E 52-D 53-D 55-D 73-B 98-D 59-D 72-E FCV-357 RCP THM BAR CCW RTN ISO OC 73-B 2

A,C 3/4 CK N

C LT EC EC 2

A,C 10 CK N

0 LT EC 3

C 20 CK N

0 EC 3

C 20 CK N

0 EC 3

C 20 CK N

0 EC 3

C 20 CK N

0 EC 3

C 20 CK N

0 EC 3

C 20 CK N

0 EC 2

A,C 3/4 CK N

C LT EC EC 2

A,C 4

CK N

0 LT EC 3

B 20 BV E

0 Pi EF 2

A 10 BV E

0 Pi LT EF 2

A 6

GL E

0 Pi LT EF R

R R

R R

Q Q

Q Q

Q Q

R R

R R

R 2Y CS 2Y J

CS 2Y i

CS c

0 C

c c

o/c O/c O/c O/c O/c O/c c

0 c

c c

NA 20c NA c

25c NA C

30c V-620 R015 V-620 RO15 V-620 V-619 RR2 V-619 P-CCW P-CCW P-CCW P-CCW P-CCW P-CCW V-621 RO15 V-621 RO15 V-621 V-623 RR2 V-623 V-2F CS24 V-3H3 V-2J2 V-619 CS24 V-3H4 V-2J2 V-621 CS24 V-3H5 RV function RV function 10006618.1ST 40MIS DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 38 OF 52 COMPONENT COOLING WATER SYSTEM P& ID NO. 1020 14 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-361 CCW FRM XCS LTDN HX ISO OC FCV-363 RCP'S CLR CCW RTN ISOL OC FCV-364 RHR HX-2 CCW RETURN FCV-365 RHR HX-1 CCW RETURN FCV-430 CCW HX-1 OUT ISOL FCV-431 CCW HX-2 OUT ISOL FCV-749 RCP'S CLR CCW RTN ISOL IC FCV-750 RCP THM BAR CCW RTN ISO IC LCV-69 LCV-70 RCV-16 MU WTR TO CCW HDR-A MU WTR TO CCW HDR-B CCW SURGE TK VENT 98-B 2

A 4

BV A

C PI 2Y NA LT J

c EF Q

lOc 72-B 2

A 6

BV E

0 Pi 2Y NA LT J

c EF CS 25c 60-C 3

B 12 BV A

C Pi 2Y NA EF Q

i0o 104-C 3

B 12 BV A

C PI 2Y NA EF Q

l0o 58-E 3

B 30 BV E

0 PI 2Y NA EF Q

30o 58-D 3

B 30 BV E

0 PI 2Y NA 72-B 73-B 55-B 55-B 56-C EF Q

2 A

6 BV E

0 PI 2Y LT J

EF CS 2

A 6

GL E

0 PI 2Y LT J

EF CS 3

B 3

GL A

C EF Q

3 B

3 GL A

C EF Q

3 B

3 BA A

0 Pi 2Y EF Q

30o NA c

20c NA c

30c 20o 20o NA 1Oc V-2J2 V-623 V-3S6 V-2J2 V-620 CS24 V-3H6 V-2H V-3H7 V-2H V-3H7 V-2F V-3H8 V-2F V-3H8 V-202 V-620 CS24 V-3H10 V-202 V-621 CS24 V-3H9 V-3HI11 V-3HI11 V-2F V-3H12 10006618.IST 40MIS 54 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 39 OF 52 COMPONENT COOLING WATER SYSTEM P& ID NO. 1020 14 VALVE VALVE P&ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS RCP3 THRML BARRIER CCW RTN 72-D RCP4 THRML BARRIER CCW RTN 73-D RCP2 THRML BARRIER CCW RTN 70-D RCP1 THRML BARRIER CCW RTN 74-D CCW SURGE TANK RV 57-C FCV-365 BYPASS RV 103-C CCW RTN FROM RHR HX2 RV 61-C RCP'S LO CLG RTN TO CCW RV 72-C CCW RTN XCES LTDN HX RV 98-C 3

3 3

3 3

3 3

3 2

C C

C C

3/4xl RV 3/4xl RV 3/4xl RV 3/4xl RV N

N N

N C

C C

C RT RT RT RT T

T T

T C

3x4 RV N

C RT T

0 C

C C

C 3/4x1 3/4x 1 3

3 RV RV RV RV N

N N

N C

C C

C RT RT RT RT T

T T

T 0

0 0

0 10006618.1ST 40MIS 55 RV-41 RV-42 RV-43 RV-44 RV-45 RV-46 RV-47 RV-51 RV-52 o

M-77 2335#

o M-77 2335#

o M-77 2335#

o M-77 2335#

M-77 30#

M-77 70#

M-77 70#

M-77 150#

M-77 150#

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 40 OF 52 MAKEUP WATER SYSTEM P& ID NO. 1020 16 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS MU-963 AFW PP RECIRC TO CST CK MU-965 CST TO MU H20 XFR PPS CK MU-968 MU-970 MU-971 MU H20 XFR PP-01 DISCH CK MU H20 XFR PP-02 DISCH CK MU H20 TO MISC SOURCES CK MU-1555 CST H20 MIXING PP DISCH CK MU-966 MU WATER PP RECIRC CK MU-969 MU WATER PP RECIRC CK 71-C 3

C 2

CK N

C EC Q

(78-C) 70-E (78-E) 74-D 75-D 71-E (78-E) 3 C

4 CK N

C EC Q

o 3

3 3

C C

C 4

4 4

CK CK CK N

N N

C C

C EC EC EC Q

Q Q

71-C 3

C 3

CK N

0 EC Q

(78-D) 73-D 3

75-D 3

C C

4 4

CK N

CK N

0 0

EC Q

EC Q

10006618.IST 40MIS 56 0

P-AFW V-3U2 V-3U2 V-3U2 V-3U2 V-3U1 P-MUW P-MUW 0

0 0

C 0

0 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

SALTWATER SYSTEM VALVE DESCRIPTION ASW PP-1 DISCH VAC RELIEF ASW PP-1 DISCH VAC RELIEF ASW PP-I DISCH CK ASW PP-2 DISCH CK ASW PP-2 DISCH VAC RELIEF ASW PP-2 DISCH VAC RELIEF ASW PP-2 CROSS TIE ASW PP-1 CROSS TIE ASW UNIT CROSS TIE CCW HX-1 SW INLET DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 41 OF 52 P& ID NO. 1020 17 FCV-603 CCW HX-2 SW INLET

& ID VLV VLV VLV VLV ACT NRM TST OORD CLS CAT SIZ TYP TYP POS REQ 32B-D 3

C 3

CK N

C EC 38A-E) 32B-D 3

C 3

CK N

C EC 38A-E) 34-C 3

C 24 CK N

0 EC 34-C 3

C 24 CK N

0 EC 31B-D 3

C 3

CK N

C EC 37A-E) 31B-D 3

C 3

CK N

C EC 37A-E) 35-C 3

B 24 BV E,M 0

PI EF 35-C 3

B 24 BV E,M 0

PI EF 34-C 3

B 24 BV E

C Pi EF 36-C 3

B 24 BV A

0 PI (35-C)

EF (EF 35-B 3

B 24 BV A

0 Pi EF (EF TST STR REL PROC FRQ TIM REQ NO.

REMARKS VALVE NUMBER SW-34 SW-170 SW-200 SW-201 SW-301 SW-303 FCV-495 FCV-496 FCV-601 FCV-602 P

cc I

(3 (3

3 (3'

3 (3'

RO10 RO10 RO10 RO10 V-18M V-18M P-ASW P-ASW V-18M V-18M V-2A1 V-3F1 V-2A1 V-3F2 V-2A2 V-3F3 V-2F V-3F4 V-3F4 V-2F V-3F5 V-3F5 RV function RV function RV function RV function 10006618.1ST 40MIS 57 R

R Q

Q R

R 2Y Q

2Y Q

2Y Q

2Y Q

Q 2Y Q

Q Manual Manual Closed Closed O/c O/c O/c O/c o/c O/c NA 30 o/c NA o/c NA 30 o/c NA 60o 120o NA 60o 90o P&

ID NO.

1020 17 UNIT 1 UNIT 2)

UNIT 1 UNIT 2)

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 42 OF 52 FIRE PROTECTION SYSTEM P& ID NO. 1020 18 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FP-180 (FP-867)

FCV-633 CONT FIREWATER ISOL IC CONT FIREWATER ISOL OC FP-306 FIREWATER SUPPLY TO AUX FEED PPS FP-307 FIREWATER SUPPLY TO AUX FEED PPS 73-B (73-D) 2 A,C 4

CK N

C LT J

72-B 2

A 3

GL A

0 Pi (72-E)

LT EF 37-C 3

B 8

BV M

C EF 2Y J

Q Q*

C NA NA 1Oc NA 37-C 3

B 8

BV M

C EF Q*

NA V-679 V-2J7 V-679 V-3S4 V-3P4

  • Per Tech Spec V-3P4
  • Per Tech Spec 10006618.1ST 40MIS 58 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 43 OF 52 LIQUID RADWASTE SYSTEM P& ID NO. 1020 19 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS LWS-60 N2 TO RCDT ISOL IC FCV-253 RCDT PP DISCH ISOL IC FCV-254 RCDT PP DISCH ISOL OC FCV-255 RCDT VENT ISOL IC FCV-256 RCDT VENT ISOL OC FCV-257 RCDT GAS ANAL ISOL OC 38-C 2

A,C 3/4 CK N

C LT R

EC R

38-A 2

A 2.5 BA A

0 PI 2Y LT J

EF Q

39-A 2

A 2.5 BA A

0 PI 2Y LT J

EF 38-B 2

A 3/4 BA A

0 Pi LT EF 39-B 2

A 3/4 BA A

0 PI LT EF 39-B 2

A 1/2 BA A

C PI LT EF Q

2Y J

Q 2Y i

Q 2Y J

Q C

c NA c

1Oc NA c

1Oc NA c

1Oc NA c

1Oc NA c

1Oc V-652D RR2 V-652D V-205 V-650 V-3S3 V-2J5 V-650 V-3S3 V-205 V-651C V-3S3 V-2J5 V-651C V-3S3 V-2J5 V-651D V-3S3 10006618.1ST 40MIS 59 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 44 OF 52 LIQUID RADWASTE SYSTEM P& ID NO. 1020 19 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-258 RCDT GAS ANAL ISOL IC 38-B FCV-260 N2 TO RCDT ISOL OC 38-C FCV-500 CONT SUMP DISCH ISOL IC 38-D FCV-501 CONT SUMP DISCH ISOL OC 39-D FCV-696 RX CAV SUMP SMPL SUP ISO IC 38-B FCV-697 RX CAV SUMP SMPL SUP ISO OC 39-B 2

A 1/2 BA A

0 PI 2Y NA LT J

EF Q

2 A

3/4 BA A

0 PI 2Y LT J

EF Q

2 A

2 BA A

0 PI 2Y LT J

EF Q

2 A

2 BA A

0 PI 2Y LT J

EF Q

2 A

3/8 GL S

C Pi 2Y LT R

EF CS 2

A 3/8 GL S

C Pi 2Y LT R

EF CS c

1Oc NA c

1Oc NA c

1Oc NA c

1Oc NA c

1o NA c

0oo V-205 V-651D V-3S3 V-2J5 V-652D V-3S3 V-205 V-649 V-3S3 V-2J5 V-649 V-3S3 V-682A V-682A CS25 V-3T5 V-682A V-682A CS25 V-3T5 I0006618.IST 40MIS 60 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 45 OF 52 LIQUID RADWASTE SYSTEM P& ID NO. 1020 19 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS REFUEL WTR PURIF ISOL OC REFUEL WTR PURIF ISOL OC REFUEL WTR PURIF ISOL IC REFUEL WTR PURIF ISOL IC 39-C 2

A 4

DI 38-D 2

A 4

DI 38-C 2

A 4

DI 38-D 2

A 4

DI M

LC LT M

LC LT M

LC LT M

LC LT J

c J

c J

C J

c V-646 PASSIVE V-646 PASSIVE V-646 PASSIVE V-646 PASSIVE 10006618.1ST 40MIS 61 8767 8787 8795 8796 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

VENTILATION AND AIR CONDITIONING SYSTEM VALVE VALVE P & ID NUMBER DESCRIPTION COORD VAC-1 CHP SUP FAN-I ISOL OC 45-A (45A-D)

VAC-2 CHP SUP FAN-2 ISOL OC 34-A (45A-E)

VAC-21 CONT AIR SMPL RTN ISOL IC 44-B (111-C)

VAC-116 CONT AIR SMPL POST LOCA 44-C RTN ISOL IC (11 l-D)

VAC-200 CHP SUP ISOL IC CK 35-A (48A-D)

VAC-201 CHP SUP ISOL IC CK 35-A (48A-C)

VAC-252 CONT H2 SAMPLE RTN CK IC 44-D (131-B)

VAC-253 CONT H2 SAMPLE RTN CK IC FCV-235 CONT H2 SAMPLE SUP ISOL IC Vi C

44-E (131-D) 44-C (131-A)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 46 OF 52 P& ID NO. 1020 23 TST STR REL PROC FRQ TIM REQ NO.

REMARKS R

c V-683 LV VLV VLV VLV ACT NRM TST

'LS CAT SIZ TYP TYP POS REQ 2

A 4

GA M

LC LT 2

A 4

GA M

LC LT 2

A,C 2

CK N

0 LT EC 2

A,C 3/8 CK N

C LT EC 2

A,C 4

CK N

C LT 2

A,C 4

CK N

C LT 2

A,C 3/8 CK N

C LT EC EP 2

A,C 3/8 CK N

C LT EC EP 2

A 3/8 GL S

LC PI LT EF V-683 V-668 RR2 V-668 V-682B RR2 V-682B V-683 V-683 V-678

RR2, V-678 R18 CS25 V-3T3 V-678
RR2, V-678 R18 CS25 V-3T3 V-678 V-678 CS25 V-3T3 10006618.MST 40MIS 62 R

R R

R R

R R

R R

CS R

R CS 2Y R

CS c

c C

c c

c c

c 0

0 c

0 0

NA c

10o

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 47 OF 52 VENTILATION AND AIR CONDITIONING SYSTEM P& ID NO. 1020 23 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-236 CONT H2 SAMPLE SUP ISOL OC FCV-237 CONT H2 SAMPLE RTN ISOL OC FCV-238 CONT H2 SAMPLE SUP ISOL IC FCV-239 CONT H2 SAMPLE SUP ISOL OC FCV-240 CONT H2 SAMPLE RTN ISOL OC FCV-654 INCOR CHILL WTR SUP ISOL OC FCV-655 INCOR CHILL WTR SUP ISOL IC FCV-656 INCOR CHILL WTR SUP ISOL OC 46-C (133-A) 46-D (133-B) 46-D (131-C) 46-D (133-C) 46-E (30-B) 34-D (30-B) 35-D (30-B) 34-D (30-B) 2 A

3/8 GL S

LC 2

A 3/8 GL S

LC 2

A 3/8 GL S

LC 2

A 3/8 GL S

LC 2

A 3/8 GL S

LC 2

A 2

BA A

C 2

A 2

BA A

C 2

A 2

BA A

C PI 2Y NA V-678 LT R

c V-678 EF CS 10o CS25 V-3T3 Pi 2Y NA V-678 LT R

c V-678 EF CS 10o CS25 V-3T3 PI 2Y NA V-678 LT R

c V-678 EF CS 10o CS25 V-3T3 PI 2Y NA V-678 LT R

c V-678 EF CS 10o CS25 V-3T3 PI 2Y NA V-678 LT R

c V-678 EF CS 10o CS25 V-3T3 PI 2Y NA V-2J7 LT J

c V-682D EF Q

1Oc V-3S4 Pi 2Y NA V-204 LT J

c V-682D EF Q

lOc V-3S4 PI 2Y NA V-2J7 LT J

c V-682D EF Q

lOc V-3S4 10006618.1ST 40MIS 63 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 48 OF 52 VENTILATION AND AIR CONDITIONING SYSTEM P& ID NO. 1020 23 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-657 INCOR CHILL WTR SUP ISOL IC FCV-658 CHP EXH SYS #2 DISCH ISO IC FCV-659 CHP EXH SYS #1 DISCH ISO IC FCV-660 CONT PURGE SUP ISOL IC FCV-661 CONT PURGE SUP ISOL OC FCV-662 CONT EXCESS PRES/VAC RLF ISOL IC 35-D 2

A 2

BA A

C Pi 2Y (30-B)

LT J

EF Q

35-B 2

A 4

GA E

LC PI 2Y (48A-C)

LT J

EF CS 35-B 2

A 4

GA E

LC PI 2Y (34-C)

LT J

EF CS 35-C 2

A 48 BV A

C PI 2Y (34-C)

LT S

EF CS 34-C 2

A 48 BV A

C PI 2Y LT S

EF CS 35-C 2

A 12 BV A

C PI 2Y (34-C)

LT S

EF Q

NA C

1Oc NA c

15o NA c

15o NA C

2c NA c

2c NA c

5c V-204 V-682D V-3S4 V-2X V-681 CS25 V-3T3 V-2X V-657 CS25 V-3T3 V-2Q V-661 CS29 V-3T7 V-2E1 V-661 CS29 V-3T7 V-2Q V-663 V-3T6

  • Per Tech Spec
  • Per Tech Spec
  • Per Tech Spec 10006618AST 40MIS 64 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 49 OF 52 VENTILATION AND AIR CONDITIONING SYSTEM P& ID NO. 1020 23 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-663 CONT XCESS PRES RLF ISO OC FCV-664 CONT VAC RLF OC FCV-668 CHP EXH SYS #2 DISCH ISO OC FCV-669 CHP EXH SYS #1 DISCH ISO OC FCV-678 CONT AIR SAMPLE SUP ISOL IC 31-C (34-C) 32-C (34-C) 34-B (47A-C) 34-B (47A-B) 44-A (11 -B) 2 A

12 BV A

C PI 2Y LT S

EF Q

2 A

12 BV A

C Pi 2Y LT S

EF Q

2 A

4 GA E

LC PI 2Y LT J

EF CS 2

A 4

GA E

LC PI 2Y LT J

EF CS 2

A 1

BA A

0 Pi 2Y LT J

EF Q

NA c

5c NA c

5c NA c

15o NA c

15o NA c

10c V-2E3 V-663 V-3T6 V-2E3 V-663 V-3T6 V-2X V-681 CS25 V-3T3 V-2X V-657 CS25 V-3T3 V-203 V-668 V-3T1

  • Per Tech Spec
  • Per Tech Spec 10006618.1ST 40MIS 65 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 50 OF 52 VENTILATION AND AIR CONDITIONING SYSTEM P& ID NO. 1020 23 VALVE VALVE P & ID VLV VLV VLV VLV ACT NRM TST TST STR REL PROC NUMBER DESCRIPTION COORD CLS CAT SIZ TYP TYP POS REQ FRQ TIM REQ NO.

REMARKS FCV-679 AIR SAMPLE SUP ISOL OC FCV-681 AIR SAMPLE RETURN ISOL OC FCV-698 AIR SAMPLE POST LOCA SUP ISOL OC FCV-699 AIR SAMPLE POST LOCA SUP ISOL OC FCV-700 AIR SAMPLE POST LOCA SUP ISOL OC RCV-11 PURGE EXHAUST ISOL IC RCV-12 PURGE EXHAUST ISOL OC 46-A 2

A 1

BA A

0 PI 2Y (113-B)

LT J

EF Q

46-B 2

A 1

BA A

0 Pi 2Y (113-C)

LT J

EF Q

44-B 2

A 3/8 GL S

C PI 2Y (111 -C)

LT R

EF Q

46-B 2

A 3/8 GL S

C PI 2Y (113-C)

LT R

EF Q

35-C 2

A 3/8 GL S

C PI 2Y (34-C)

LT R

EF Q

34-C 2

A 48 BV A

C Pi 2Y LT S

EF CS 34-C 2

A 48 BV A

C PI 2Y LT S

EF CS NA c

1Oc NA c

1Oc NA c

lOo/c NA c

lOo/c NA c

lOo/c NA c

2c NA C

2c V-2J1 V-668 V-3T1 V-2J1 V-668 V-3T1 V-682B V-682B V-3T4 V-682B V-682B V-3T4 V-682B V-682B V-3T4 V-2Q V-662 CS29 V-3T7 V-2E2 V-662 CS29 V-3T7

  • Per Tech Spec
  • Per Tech Spec 10006618.1ST 40MIS 66 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY INSERVICE TESTING PROGRAM PLAN - VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

COMPRESSED AIR SYSTEMS VALVE VALVE P&ID NUMBER DESCRIPTION COORD AIR-S-114 CONT SERV AIR SUP ISOL IC 41-D (48-D)

AIR-S-200 CONT SERV AIR SUP ISOL OC 42-D (47-D)

AIR-I-585 CONT NORM INST AIR SUP 42-C ISOL BYPASS OC (47-C)

AIR-I-587 CONT NRM INST AIR SUP CK IC 42-D (47-D)

FCV-584 CNT NRM INST AIR SUP ISO OC 42-C (47-C)

DIABLO CANYON POWER PLANT - UNITS 1 & 2 TABLE 2.0 REV 18 (2002)

PAGE 51 OF 52 VLV CLS 2

2 2

2 2

P& ID NO. 1020 25 VLV VLV VLV ACT CAT SIZ TYP TYP A,C 3

CK N

A 3

BA M

A 1.5 DI M

A,C 2

CK N

A 2

BA A

NRM POS C

TST REQ LT LC LT LC 0

0 TST FRQ J

STR TIM C

J c

LT J

LT R

EC R

PI 2Y LT J

EF Q

c C

c NA C

10c REL PROC REQ NO.

REMARKS V-656 V-656 PASSIVE V-654 PASSIVE V-654 RR2 V-654 V-2J7 V-654 V-3S4 10006618.1ST 40MIS 67

INSERVICE TESTING PROGRAM PLAN - VALVES TABLE 2.0 REV 18 (2002)

ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

PAGE 52 OF 52 REMARKS

  1. 1 The backflow safety function of check valves FW-348, 350, 352, is not tested, instead credit is taken for closing the manual isolation valves, FW-121, 159, and 180, prior to realigning to the raw water storage reservoir per Operating Procedure, OP D-l :V.
  1. 2 The AFW pumps' discharge check valves FW-361, 362, and 363, share the safety function of preventing backflow with the second-off checks, FW-369 through 376. Due to the difficulty of testing these valves only the second-off checks will be quarterly tested in the closed direction.
  1. 3 The leak tests for valves FW-367, 368, 531, and 532, are not required by Code as these valves do not have a safety related function to prevent back leakage. The leak test and the categorization as "A,C" is based on a corrective action in NCR DC1-91-TN-N002.
  1. 4 Deleted.

d

  1. 5 FCV-1 10A does not have an active safety function. The safety related boration flow path is through 8104 and the redundant flow path is from the RWST. However, in the Appendix R and Hosgri evaluations credit was taken for this valve to open or fail open so this valve is being administratively included in the IST program as a conservative measure since it may be considered a licensing commitment.
  1. 6 Deleted.
  1. 7 The open safety function of check valve CVCS-8440 is verified during normal operations.

10006618.IST 40MIS 68 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 1 OF 34 NO. V-CS1 Valves:

FW-367 Steam Generator #2 Main Feedwater Check FW-368 Steam Generator #1 Main Feedwater Check FW-531 Steam Generator #3 Main Feedwater Check FW-532 Steam Generator #4 Main Feedwater Check Category:

A/C Code Class: 2 Valves:

FCV-438 Steam Generator #1 Feedwater Isolation Valve FCV-439 Steam Generator #2 Feedwater Isolation Valve FCV-440 Steam Generator #3 Feedwater Isolation Valve FCV-441 Steam Generator #4 Feedwater Isolation Valve Category:

B Code Class: 2 Function:

The check valves have an active function to close to prevent backflow so that AFW pump discharge flow will be directed to the steam generators as required when the AFW system is actuated.

The isolation valves have an active safety function to close to terminate continued feedwater flow to the steam generators or to a faulted feedwater line inside containment as assumed in the plant accident analysis.

Basis:

These Main Feedwater Check Valves and Feedwater Isolation Valves cannot be exercised during power operation because closing these valves would require securing feed flow to a steam generator which would result in a reactor trip. Three loop operation has not been analyzed for at Diablo Canyon Power Plant and is not allowed.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c) and 4.3.2.2(c).

10006618.IST 40MIS 69

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 2 OF 34 NO. V-CS2 Valves:

FW-348 Aux Feedwater Pump #1 Suction Check Valve from the CST FW-350 Aux Feedwater Pump #2 Suction Check Valve from the CST FW-352 Aux Feedwater Pump #3 Suction Check Valve from the CST Category:

C Code Class: 3 Function:

These valves have an active safety function in the open direction to permit the flow of water from the CST to the AFW pumps' suction. They also have a safety function to close to maintain AFW pump suction when this suction is aligned to the raw water reservoir.

Basis:

These AFW supply check valves cannot be full stroke exercised during power operation because the only available flow path is into the steam generators which could result in thermal shock to the associated piping and fittings. These valves will be full stroked open during a shutdown to, or a startup from, a cold shutdown condition.

The backflow safety function of these check valves is not tested, instead credit is taken for closing the manual isolation valves, FW-121, 159, and 180, when realigning to the raw water storage reservoir per Operating Procedure, OP D-1 :V.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.3.2.2(c).

10006618.1ST 40MIS 70 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 3 OF 34 NO. V-CS3 Valves:

FW-361 Aux Feedwater Pump #1 Discharge Check Valve FW-362 Aux Feedwater Pump #2 Discharge Check Valve FW-363 Aux Feedwater Pump #3 Discharge Check Valve Category:

C Code Class: 3 Valves:

FW-369 Aux Feedwater Pump #1 to Steam Generator #1 Check Valve FW-370 Aux Feedwater Pump #2 to Steam Generator #1 Check Valve FW-371 Aux Feedwater Pump #1 to Steam Generator #2 Check Valve FW-372 Aux Feedwater Pump #2 to Steam Generator #2 Check Valve FW-373 Aux Feedwater Pump #1 to Steam Generator #3 Check Valve FW-374 Aux Feedwater Pump #3 to Steam Generator #3 Check Valve FW-375 Aux Feedwater Pump #1 to Steam Generator #4 Check Valve FW-376 Aux Feedwater Pump #3 to Steam Generator #4 Check Valve FW-377 Steam Generator #1 Aux Feedwater 1st off Check Valve FW-378 Steam Generator #2 Aux Feedwater 1st off Check Valve FW-379 Steam Generator #3 Aux Feedwater 1st off Check Valve FW-380 Steam Generator #4 Aux Feedwater 1st off Check Valve Category:

C Code Class: 2 Function:

These valves have an active safety function in the open direction to permit the flow of water from the AFW pump discharge lines to the steam generators. Second off check valves FW-369, FW-370, FW-371, FW-372, FW-373, FW-374, FW-375, and FW-376 also have a safety function to close to prevent the backflow of feedwater through an idle AFW pump.

Basis:

These Auxiliary Feedwater Supply Check Valves cannot be full stroke exercised during power operation because the only available flow path is into the steam generators which could result in thermal shock to the associated piping and fittings. These valves will be full stroke exercised during a shutdown to, or a startup from, a cold shutdown condition.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.3.2.2(c).

10006618.1ST 40MIS 71 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 4 OF 34 NO. V-CS4 Valves:

MS-5166 Steam Generator #2 to Aux Feedwater Pump #1 Check Valve MS-5167 Steam Generator #3 to Aux Feedwater Pump #1 Check Valve Category:

C Code Class: 2 Function:

These valves have an active safety function to open to allow steam flow to the AFW pump turbine. They also have a safety function to prevent the backflow of steam from an unfaulted steam generator escaping out of the break in a faulted steam generator.

Basis:

These check valves cannot be full stroke exercised during power operation because this would require operating the turbine-driven AFW pump at rated speed and the only available flow path for AFW is into the steam generators which could result in thermal shock to the associated piping and fittings. These valves will be part stroked on a quarterly frequency with the pump operating on its recirculation flow path. Full stroke exercising will be performed during a shutdown to, or a startup from, a cold shutdown condition.

Closure testing is covered in Valve Relief Request # 11.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.3.2.2(b).

10006618.1ST 40MIS 72 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 5 OF 34 NO. V-CS5 Valves:

FCV-41 Steam Generator #1 Main Steam Isolation Valve FCV-42 Steam Generator #2 Main Steam Isolation Valve FCV-43 Steam Generator #3 Main Steam Isolation Valve FCV-44 Steam Generator #4 Main Steam Isolation Valve Category:

B Code Class: 2 Function:

These valves have an active safety function to automatically close on high steam flow, coincident with either low-low T(avg) or low steam pressure, or on a high-high containment pressure signal.

Basis:

These valves cannot be full stroke exercised during power operation because this would require securing steam from a steam generator which would result in a reactor trip, and most likely a safety injection.

Also, three loop operation has not been analyzed for Diablo Canyon Power Plant and is not allowed.

Part stroke testing capability does exist for these valves but is not considered practical, since extremely limited (60 max., 2' nominal) valve motion is allowed due to the valve design which only provides verification that the valve is not frozen in the open position. Additionally, as a result of the valve design, performing partial stroke testing exposes the plant to an inadvertent Reactor Trip and/or Safety Injection should the valve stroke more than 6' (resulting in a flow assisted closure of the valve).

These valves will be full stroke exercised on a cold shutdown frequency.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

40MIS 73 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY 1000661 8.ST

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

COLD SHUTDOWN FREQUENCY JUSTIFICATION TABLE 2.1 REV 18 (2002)

PAGE 6 OF 34 NO. V-CS6 PCV-455C PCV-456 PCV-474 Pressurizer Power Operated Relief Valve Pressurizer Power Operated Relief Valve Pressurizer Power Operated Relief Valve Category:

B Code Class: 1 Function:

The PORVs have an active safety function to open for steam generator tube rupture accident mitigation and also for RCS low temperature overpressure protection.

Basis:

The PORVs should not be exercised during power operation by NRC direction. The NRC's current position is that these valves will be full stroke exercised during the approach to cold shutdown.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.IST 40MIS 74 Valves:

DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 7 OF 34 NO. V-CS7 Valves:

8078A Reactor Vessel Head Vent Valve 8078B Reactor Vessel Head Vent Valve 8078C Reactor Vessel Head Vent Valve 8078D Reactor Vessel Head Vent Valve Category:

B Code Class: 2 Function:

These valves have an active function to open to vent noncondensible gases from the RCS which might inhibit core cooling during natural circulation. They were installed to provide reactor vessel high point vent capability for beyond-design-bases events per the guidance of NUREG 0737 and are not relied upon to mitigate any design basis accidents as defined and analyzed in the FSAR Chapter 15 Accident Analyses.

Basis:

These Reactor Vessel Head Vent Valves should not be exercised during power operation by NRC direction. The NRC's current position is that these valves will be full stroke exercised during cold shutdown.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 75 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 8 OF 34 NO. V-CS8 Valves:

Category:

LCV-1 12B Volume Control Tank Outlet Isolation Valve LCV-1 12C Volume Control Tank Outlet Isolation Valve B

Code Class: N/A Function:

These valves have an active safety function to close to isolate the volume control tank from the suction of the charging pumps upon the receipt of a safety injection signal.

Basis:

These isolation valves should not be exercised during power operation because failure of either valve in the closed position would result in a loss of reactor system level control or injecting 2000 ppm boric acid solution from the RWST into the reactor coolant system, resulting in a possible plant shutdown. See also NRC SER dated 1/31/94 addressing LA 86 and 87.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 76 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 9 OF 34 NO. V-CS9 Valves:

8100 Reactor Coolant Pump Seal Water Return Isolation Valve, Outside Containment 8112 Reactor Coolant Pump Seal Water Return Isolation Valve, Inside Containment Category:

A Code Class: 2 Function:

These valves have an active safety function to close to isolate the seal water return line containment penetration upon receipt of a Phase A containment isolation signal.

Basis:

These isolation valves cannot be exercised during power operation because this would challenge the relief valve in the RCP seal water return line. If this relief valve failed in the open position, this would result in unnecessary reactor coolant system leakage. These valves need not be exercised in MODE 5 if the Reactor Coolant Pumps are operating and would need to be stopped and restarted solely to test cold shutdown frequency tested valves. Deferral of testing these valves is allowed per NUREG-1482 paragraph 3.1.1.4.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 77 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

COLD SHUTDOWN FREQUENCY JUSTIFICATION TABLE 2.1 REV 18 (2002)

PAGE 10 OF 34 NO. V-CS1O 8105 8106 Centrifugal Charging Pumps' Recirculation Isolation Valve Centrifugal Charging Pumps' Recirculation Isolation Valve Category:

B Code Class: 2 (8100), IN/A (61U*J)

Function:

These valves have an active safety function to close to isolate the high pressure safety injection flow path from the CVCS during safety injection system operation following a LOCA.

Basis:

These valves should not be exercised during power operation because failure of either valve in the closed position could result in pump damage if a secondary system accident occurred.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 78 Valves:

DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 11 OF 34 NO. V-CS11 Valves:

8107 Charging Line Isolation Valve 8108 Charging Line Isolation Valve Category:

B Code Class: 2 Function:

These redundant, motor-operated gate valves have an active safety function to close to isolate the normal charging flow path from the high pressure safety injection flow path upon receipt of a safety injection signal.

Basis:

These valves should not be exercised during power operation because failure of either valve in the closed position could result in loss of reactor coolant system level control, which could result in a plant shutdown. Also, failure of either of these valves in a closed position would place the plant in an LCO action statement due to a loss of the boration flow path from the boric acid tanks. See also NRC SER dated 1/31/94 addressing LA 86 and 87.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 79 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 12 OF 34 NO. V-CS12 Valves:

8145 Pressurizer Auxiliary Spray Valve 8148 Pressurizer Auxiliary Spray Bypass Valve Category:

B Code Class: 1 Valves:

8377 Pressurizer Auxiliary Spray Check Valve Category:

C Code Class: 1 Function:

Air operated globe valves 8145 and 8148, along with check valve 8377, have an active safety function to open during plant cooldown to cooldown the pressurizer when normal pressurizer spray is inoperable.

This is not an accident mitigation function but a safe shutdown function following a Hosgri earthquake.

Basis:

These valves should not be exercised during power operation because failure of either valve in the open position could result in a loss of reactor coolant system pressure control which could result in a plant shutdown.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c) and 4.3.2.2(c).

10006618.IST 40MIS 80 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 13 OF 34 Valves:

8152 Category:

A Function:

NO. V-CS13 Letdown Line Isolation Valve, Outside Containment Code Class: 2 This air operated globe valve has an active safety function to close to isolate letdown on a high room temperature in the letdown heat exchanger room. This valve also has the safety function of providing containment isolation.

Basis:

This valve should not be exercised during power operation because failure of the valve in the closed position could result in a loss of reactor coolant system level control which could result in a plant shutdown. See also NRC SER dated 1/31/94 addressing LA 86 and 87.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40M[S 81 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 14 OF 34 Valves:

8802A 8802B Category:

A Function:

NO. V-CS14 Safety Injection Pump #1 Discharge Isolation Valve, Outside Containment Safety Injection Pump #2 Discharge Isolation Valve, Outside Containment Code Class: 2 These motor operated gate valves have an active safety function to open to provide a flow path for the safety injection pumps in the Hot Leg recirculation mode.

Basis:

These valves cannot be exercised during power operation because they are required to be closed with power to the valve operators removed by Technical Specification SR 3.5.2.1. If these valves were opened during power operation and an accident were to occur, safety injection flow would go to the hot legs instead of the cold legs. The safety analysis has analyzed for flow going to the cold legs and not the hot legs.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 82 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 15 OF 34 Valves:

8809A 8809B Category:

B Function:

NO. V-CS15 RHR to Cold Legs 1&2 Isolation Valve RHR to Cold Legs 3&4 Isolation Valve Code Class: 2 These motor operated gate valves have an active safety function to close during hot leg recirculation.

These valves are exempt from type C leak testing per Appendix J, section III.C.3. They also have a passive safety function to remain open to provide a flow path from the RHR system to the SIS/RCS cold leg injection lines. These valves are normally open with the power to the actuators removed during power operations.

Basis:

These valves cannot be exercised during power operation because they are required to be open with power to the valve operators removed by Technical Specification SR 3.5.2. 1.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 83 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 16 OF 34 NO. V-CS16 Valves:

8835 Safety Injection to Cold Legs Isolation Valve Category:

B Code Class: 2 Function:

This motor operated gate valve has an active safety function to close when placing the ECCS in the hot leg recirculation mode of safety injection. This valve is exempt from type C leak testing per Appendix J, section III. C.3.

Basis:

This valve cannot be exercised during power operation because it is required to be open with power to the valve operator removed by Technical Specification SR 3.5.2. 1. Also, failure of this valve in the closed position would result in the safety injection system being not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 84 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 17 OF 34 NO. V-CS17 Valves:

8974A Safety Injection Pumps Recirculation to the Refueling Water Storage Tank Isolation Valve 8974B Safety Injection Pumps Recirculation to the Refueling Water Storage Tank Isolation Valve Category:

B Code Class: 2 (8974B), N/A (8974A)

Function:

These motor operated globe valves have an active safety function to close via an interlock prior to either 8804A or 8804B opening.

Basis:

These valves cannot be exercised during power operation because they are required to be open with power to the valve operators removed by Technical Specification SR 3.5.2. 1. Also, the failure of one of these valves in the closed position could result in damage to the safety injection pumps, if an SI signal were to start the pumps during this condition or test, thereby rendering the safety injection system not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 85 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 18 OF 34 NO. V-CS18 Valves:

Category:

8976 B

RWST to Safety Injection Pumps Suction Isolation Valve Code Class: 2 Function:

This motor operated gate valve has an active safety function to close to prevent backflow to the refueling water storage tank during the post-LOCA recirculation mode of safety injection.

Basis:

This valve cannot be exercised during power operation because it is required to be open with power to the valve operator removed by Technical Specification SR 3.5.2. 1. Also, failure of this valve in the closed position would result in the entire safety injection system being not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 86 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 19 OF 34 Valves:

8980 Category:

B Function:

NO. V-CS19 RWST to RHR Pumps Suction Isolation Valve Code Class: 2 This motor operated gate valve has an active safety function to close to prevent backflow into the refueling water storage tank if the downstream check valve leaks.

Basis:

This valve cannot be exercised during power operation because it is required to be open with power to the valve operator removed by Technical Specification SR 3.5.2.1. Also, failure of this valve in the closed position would result in the RHR portion of the safety injection system being not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 87 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 20 OF 34 Valves:

8703 Category:

A Function:

NO. V-CS20 RHR to Hot Legs Isolation Valve Code Class: 2 This motor operated gate valve has an active safety function to open to provide a flow path for hot leg recirculation after a postulated accident. This valve is an RCS high pressure to low pressure interface boundary and is therefore leak rate tested every refueling outage per Tech Spec SR 3.4.14.1.

Basis:

This valve cannot be exercised during power operation because it is required to be closed with power to the valve operator removed by Technical Specification SR 3.5.2.1. Also, failure of this valve in the open position would result in diversion of flow from the analyzed flow paths.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 88 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

COLD SHUTDOWN FREQUENCY JUSTIFICATION Valves:

8730A 8730B TABLE 2.1 REV 18 (2002)

PAGE 21 OF 34 NO. V-CS21 RHR Pump #1 Discharge Check Valve RHR Pump #2 Discharge Check Valve Category:

C Code Class: 2 Function:

These check valves have an active safety function to open to allow flow from the discharge of the RHR pumps.

Basis:

These valves cannot be full stroke exercised during power operation because the RHR pumps do not develop sufficient head to overcome reactor coolant system pressure. They will be part stroked quarterly and full stroked on a cold shutdown frequency.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.3.2.2(b).

10006618.1ST 40MIS 89 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 22 OF 34 Valves:

8994A 8994B Category:

B Function:

NO. V-CS22 NaOH to Containment Spray Eductor Isolation Valve NaOH to Containment Spray Eductor Isolation Valve Code Class: 2 These motor operated gate valves have an active safety function to open to provide a flow path during the ECCS injection phase of containment spray and then during the ECCS recirculation phase up until the time that the RWST low-low level is reached.

Basis:

These valves cannot be exercised during power operation because they could introduce NaOH into the RWST and subsequently into the reactor coolant system causing Na24 activation problems and possible chemical damage to components in the reactor coolant system. To prevent getting NaOH into the RWST, valve 8992 would have to be closed and the line flushed, which would result in the entire Spray Additive System being not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 90 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 23 OF 34 Valves:

8998A 8998B Category:

A,C Function:

NO. V-CS23 Spray Additive Tank Outlet Check Valve Spray Additive Tank Outlet Check Valve Code Class: 2 These check valves have an active safety function to open to allow the passage of sodium hydroxide solution for eduction into the containment spray flow. They also have a safety function to prevent backleakage, and thereby prevent diluting the educted NaOH solution, in the event that one of the containment spray pumps fails.

Basis:

These valves cannot be exercised during power operation because the system alignment for testing these check valves would result in the entire Spray Additive System being not OPERABLE.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c) and 4.3.2.2(c).

I0006618.1ST 40MIS 91 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS I & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 24 OF 34 Valves:

FCV-355 Category:

B Valves:

FCV-356 FCV-357 FCV-363 FCV-749 FCV-750 Category:

A Function:

NO. V-CS24 Component Cooling Water Header C Isolation Valve Code Class: 3 CCW to RCP and Reactor Vessel Support Isolation Valve RCP Thermal Barrier CCW Return Isolation Valve RCP Cooler CCW Return Isolation Valve RCP Cooler CCW Return Isolation Valve RCP Thermal Barrier CCW Return Isolation Valve Code Class: 2 FCV-355 has an active safety function to close to isolate the non-vital CCW header C after an accident to assure adequate flow to the two vital CCW loops.

FCV-356, 357, 363, 749, and 750 each have an active safety function to close to provide containment isolation.

Basis:

These valves cannot be exercised during power operation because this could result in damage to the reactor coolant pumps and a possible plant trip. These valves need not be exercised in MODE 5 if the Reactor Coolant Pumps are operating and would need to be stopped and restarted solely to test cold shutdown frequency tested valves. Deferral of testing these valves is allowed per NUREG-1482 paragraph 3.1.1.4.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 92 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 25 OF 34 NO. V-CS25 Valves:

FCV-235 Containment H2 Sample Supply Isolation Valve FCV-236 Containment H2 Sample Supply Isolation Valve FCV-237 Containment H2 Sample Return Isolation Valve FCV-238 Containment H2 Sample Supply Isolation Valve FCV-239 Containment H2 Sample Supply Isolation Valve FCV-240 Containment H2 Sample Supply Isolation Valve FCV-658 Containment H2 Purge Exhaust System #2 Suction Iso Valve FCV-659 Containment H2 Purge Exhaust System #1 Suction Iso Valve FCV-668 Containment H2 Purge Exhaust System #2 Suction Iso Valve FCV-669 Containment H2 Purge Exhaust System #1 Suction Iso Valve FCV-696 Reactor Cavity Sump Sample Supply Isolation Valve FCV-697 Reactor Cavity Sump Sample Supply Isolation Valve Category:

A Code Class: 2 VAC-252 Containment H2 Sample Return Check Valve VAC-253 Containment H2 Sample Return Check Valve Category:

A,C Code Class: 2 Function:

These valves have a passive safety function to remain closed to provide containment isolation.

Basis:

These Containment Sample Isolation Valves cannot be exercised during power operation because Technical Specification SR 3.6.3.3 and SR 3.6.3.4 requires these valves to be closed when containment integrity is required, except under strict administrative control. These valves do not receive a containment isolation signal.

VAC-252 and VAC-253 cannot be full stroke exercised during COLD SHUTDOWN because there is not a calibrated flow indicator installed in the Containment Hydrogen Monitoring System. These valves will be part stroke exercised during COLD SHUTDOWNS and full stroked exercised during REFUELING Outages.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c), 4.3.2.2(c) and 4.3.2.2(d).

10006618.1ST 40MIS 93 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 26 OF 34 Valves:

8805A 8805B Category:

B Function:

NO. V-CS26 Charging Pump Suction Valve Charging Pump Suction Valve Code Class: 2 These motor operated gate valves have an active safety function to open to provide a flow path from the refueling water storage tank to the suction of the charging pumps.

Basis:

These valves should not be exercised at power because opening these valves injects highly oxygenated, 2000 ppm borated water from the RWST into the reactor coolant system. Injecting this water results in a negative reactivity addition to the reactor coolant system which could shut the plant down. See also NRC SER dated 1/31/94 addressing LA 86 and 87.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.IST 40MIS 94 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 27 OF 34 NO. V-CS27 Valves:

8716A 8716B RHR Train Crosstie Valves RHR Train Crosstie Valves Category:

B Function:

Code Class: 2 These motor operated gate valves have an active safety function to close to go to the cold leg mode of post-LOCA safety injection. They also have an active safety function to reopen to go to the hot leg mode of post-LOCA safety injection (no stroke time requirement). These valves are exempt from type C leak testing per Appendix J, section III.C.3.

Basis:

These valves cannot be exercised during power operation because failure of the valve in the closed position would result in a loss of RHR injection flow to two of the four RCS loops from a single RHR pump.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 95 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 28 OF 34 NO. V-CS28 Valves:

8742A RHR Heat Exchanger #1 Discharge Check Valves 8742B RHR Heat Exchanger #2 Discharge Check Valves Category:

C Code Class: 2 Function:

These check valves have an active safety function to open to pass RHR flow from the RHR heat exchanger to the RCS. They also have a safety function to close (back flow) to prevent pump to pump interaction.

Basis:

These valves cannot be exercised during power operation because the RHR pumps do not develop sufficient head to overcome reactor coolant system pressure. These valves will be tested for backflow quarterly and for opening on a cold shutdown frequency.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.3.2.2(c).

10006618.1ST 40MIS 96 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 29 OF 34 NO. V-CS29 Valves:

FCV-660 FCV-661 RCV-11 RCV-12 Category:

A Containment Purge Supply Isolation Valve (IC)

Containment Purge Supply Isolation Valve (OC)

Containment Purge Exhaust Isolation Valve (IC)

Containment Purge Exhaust Isolation Valve (OC)

Code Class: 2 Function:

These valves have an active safety function to provide containment isolation.

Basis:

These valves are required to be leakrate tested every time they are exercised per Technical Specification (Tech Spec) SR 3.6.3.7. These valves are administratively maintained in their isolation (closed) position during power operations. This ensures they will perform their required safety function and eliminates concerns regarding failure of a post-exercising leak test.

These valves will be full stroke exercised on a cold shutdown frequency.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4-2.1.2(c).

10006618.1ST 40MIS 97 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 30 OF 34 NO. V-CS30 Valves:

8149A Letdown Orifice Control/Isolation Valve 8149B Letdown Orifice Control/Isolation Valve 8149C Letdown Orifice Control/Isolation Valve Category:

A Code Class: 2 Function:

These air operated globe valves have an active safety function to close to provide containment isolation and to isolate a high energy letdown line break outside containment upstream of the letdown heat exchanger.

Basis:

These valves will not be exercised during power operation due to the following causes: thermal transients on the regenerative letdown heat exchanger; hydraulic transients on the letdown line; pressure control transients resulting in the lifting of relief valve RV-8117; and charging nozzle temperature transients when charging is isolated during letdown testing. Reference NRC SER dated 1/31/94 addressing LA 86 and 87.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 98 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 31 OF 34 Valves:

8701 8702 Category:

A Function:

NO. V-CS31 RCS Loop 4 to RHR Isolation Valve RCS Loop 4 to RHR Isolation Valve Code Class: 1 The motor operated double disc gate valves isolate the low pressure Residual Heat Removal System from the High Pressure Reactor Coolant System.

Basis:

These Reactor Coolant System to RHR System Isolation Valves cannot be exercised during power operation because they are required to be closed with power to the valve operators removed by Technical Specification SR 3.5.2.1. Also, failure of this valve to the open position would result in diversion of flow from the analyzed flow paths.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c).

10006618.1ST 40MIS 99 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

COLD SHUTDOWN FREQUENCY JUSTIFICATION TABLE 2.1 REV 18 (2002)

PAGE 32 OF 34 NO. V-CS32 Valves:

Category:

Valves:

8146 8147 B

8378A 8378B 8379A 8379B Normal Charging Alternate Charging Code Class: 1 Charging to Loop 3 Cold Leg Check Charging to Loop 4 Cold Leg Check Charging to Loop 3 Cold Leg Check Charging to Loop 4 Cold Leg Check Category:

C Code Class: 1 Valves:

8378B Charging Line Check Category:

C Code Class: 2 Function:

These valves have active functions to open to supply normal and alternate charging to Loop 4 or 3 RCS Cold Legs.

Basis:

These valves should not be exercised during power operation because this would cause a thermal transient to be induced on the charging to RCS Cold Leg nozzle. This is per Westinghouse Infogram (WIG)90-025.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c) and 4.3.2.2(c).

10006618.1ST 40M[S 100 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 33 OF 34 NO. V-CS33 Valves:

8808A SI Accumulator 1 Discharge Isolation 8808B SI Accumulator 2 Discharge Isolation 8808C SI Accumulator 3 Discharge Isolation 8808D SI Accumulator 4 Discharge Isolation Category:

B Code Class: 2 Function:

These valves are open with power removed from the valve operator during power operations. They are not required to operate during an accident requiring ECCS injection. Valves can be closed to prevent accumulator injection during normal cooldown/depressurization of RCS.

Basis:

These valves cannot be exercised during power operation because Technical Specification SR 3.5. 1.1 and SR 3.5.1.5 require that accumulator discharge isolation valves remain open with power removed.

Justification:

Cold shutdown frequency testing is per Part 10, paragraph 4.2.1.2(c) and 4.3.2.2(c).

10006618.UST 40MIS 101 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.1 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

COLD SHUTDOWN FREQUENCY JUSTIFICATION PAGE 34 OF 34 NO. V-CS34 Valves:

8981 Refueling Water Storage Tank to Residual Heat Removal Pump Check Valve Category:

C Code Class: 2 Function:

This check valve has an active safety function to open to supply borated water from the RWST to the suction of the RHR pumps. This valve also has a safety function in the closed position (backflow) to limit potential post-LOCA recirculation leakage to the RWST.

Basis:

The valve cannot be full stroke exercised during power operation because the RHR pumps do not develop enough head to overcome RCS pressure.

The valve cannot be exercised during cold shutdown because both RHR pumps must be aligned to remove decay heat from the RCS; therefore no flow path exists for full stroke exercising the valve. The valve is not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

Valve 8981 will be full stroke exercised each refueling outage.

The valve can also be verified closed during cold shutdown by pressure testing the valve during plant cooldown. See refueling outage justification No. V-R07.

Justification:

The valve shall be exercised to the closed position during cold shutdown per Part 10, paragraph 4.3.2.2(c).

10006618.1ST 40MIS 102 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 1 OF 20 NO. V-RO1 Valves:

MS-1068, Steam Generator #1 Main Steam Line Check Valve MS-2066, Steam Generator #2 Main Steam Line Check Valve MS-3062, Steam Generator #3 Main Steam Line Check Valve MS-4062, Steam Generator #4 Main Steam Line Check Valve Category:

C Code Class: N/A Function:

These check valves have an active safety function to close in the event of a steam line break upstream of the main steam isolation valves. This accident mitigation function is to prevent the blowing down of more than one steam generator.

Basis:

These valves cannot be exercised closed because provisions are not provided in the plant design to verify that these valves close on reverse flow. Therefore, each refueling outage, these valves will be internally inspected using a fiberoptics scope to verify closure.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

Internal inspection using a fiberoptics scope is per Part 10, paragraph 4.3.2.4 (a), C(...other positive means."). This is also supported by NRC Generic Letter 89-04, Attachment 1, position 3.

10006618.1ST 40MIS 103 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 2 OF 20 NO. V-R02 Valves:

8475 Positive Displacement Charging Pump Discharge Check Valve 8478A Centrifugal Charging Pump #1 Discharge Check Valve 8478B Centrifugal Charging Pump #2 Discharge Check Valve Category:

C Code Class: 2 Function:

These valves have an active safety function to open to allow passage of their respective charging pump's discharge flow. They also have a safety function of preventing backflow from another charging pump while their respective pump is idle.

Basis:

8478A and 8478B cannot be full stroked open during power operation because of insufficient available flow. These valves will be part stroke exercised during power operation.

8478A and 8478B cannot be full stroked open during cold shutdown because this could result in a possible low temperature overpressurization of the RCS. These valves will be full stroke exercised on the way to or during refueling outages.

Open stroke testing for 8475 will be performed quarterly.

All of these valves cannot be tested for backflow during power operation as the only acceptable method of testing would be to perform hydros and measure for backleakage. This testing would require clearing pumps, entering ACTION statements, and numerous valve and pump manipulations which affect the pressurizer level control and letdown temperature. This can cause cavitation in the letdown line.

All of these valves cannot be tested for backflow during cold shutdown as the only acceptable method of testing would be to perform hydros and measure for backleakage. This testing would require clearing pumps, entering ACTION statements, and numerous valve and pump manipulations, along with setting up the hydro testing equipment. NUREG-1482, section 4.1.4, states that "the NRC has determined that the need to set up test equipment is adequate justification to defer backflow testing of a check valve until a refueling outage".

All three valves will be tested for backflow each refueling outage.

Justification:

Part stroke testing at power is per Part 10, paragraph 4.3.2.2(b).

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 104 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 3 OF 20 NO. V-R03 Valves:

8804A, Charging Pump Suction from RHR System Isolation Valve
8804B, Safety Injection Pump Suction from RHR System Isolation Valve
9003A, RHR Hx-1 to containment spray header A Isolation Valve
9003B, RHR Hx-2 to containment spray header A Isolation Valve Category:

B Code Class: 2 Function:

These motor-operated gate valves have an active safety function to open. This will line up the safety injection system and the containment spray system for the cold leg recirculation phase of post-LOCA safety injection.

Basis:

These valves cannot be exercised during power operation because they are interlocked with valves 8982A&B (Containment Sump Isolation Valves) that are required to be closed with power to the valve operators removed by Technical Specification SR 3.5.2.1. Valves 8982A or B cannot be opened during power operation because this would result in one train of the RHR system being not OPERABLE.

During cold shutdown, valves 8804A & B and 9003A & B cannot be exercised open because they are interlocked with valve 8701 and 8702 (RCS Loop-4 TO RHR ISOLATION VALVES) in the closed position. 8701 and 8702 are required to be open and closing one of these valves would result in both RHR trains being incapable of removing decay heat from the core.

Valves 8804A&B and 9003A&B will be full stroke exercised during refueling outages.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.2.1.2(e).

10006618.1ST 40MIS 105 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 4 OF 20 NO. V-R04 Valves:

8819A, Safety Injection to Cold Leg #1 Check Valve
8819B, Safety Injection to Cold Leg #2 Check Valve
8819C, Safety Injection to Cold Leg #3 Check Valve
8819D, Safety Injection to Cold Leg #4 Check Valve
8905A, Safety Injection to Hot Leg #1 Check Valve
8905B, Safety Injection to Hot Leg #2 Check Valve
8905C, Safety Injection to Hot Leg #3 Check Valve
8905D, Safety Injection to Hot Leg #4 Check Valve Category:

A,C Code Class: I Function:

These check valves have an active safety function to open to supply flow from the safety injection pumps to the reactor coolant system (RCS).

Basis:

These valves cannot be exercised during power operation because the safety injection pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised during cold shutdown because a maximum of zero safety injection pumps are allowed to be capable of injecting into the RCS by Technical Specification SR 3.4.12.1 to protect against a low temperature overpressurization of the RCS. Also during cold shutdown there may not be sufficient volume in the RCS to accommodate the amount of water needed to full stroke exercise these valves.

These valves will be full stroke exercised during refueling outages.

Justification:

Refueling outage frequency testing is per Part 10, paragraphs 4.2.1.2(e) and 4.3.2.2(e).

10006618.1ST 40MIS 106 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 5 OF 20 NO. V-RO5 Valves:

8922A, Safety Injection Pump #1 Discharge Check Valve
8922B, Safety Injection Pump #2 Discharge Check Valve Category:

C Code Class: 2 Function:

These check valves have an active safety function to open to supply flow from the safety injection pumps to the reactor coolant system (RCS). They also have a closure safety function (backflow) to prevent pump to pump interaction.

Basis:

These valves cannot be exercised open during power operation because the safety injection pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised open during cold shutdown because Technical Specification SR 3.4.12.1 requires that a maximum of zero safety injection pumps are capable of injecting into the RCS to protect against a low temperature overpressurization of the RCS. Also during cold shutdown there may not be sufficient volume in the RCS to accommodate the amount of water needed to full stroke exercise these valves.

These valves will be full stroked exercised open during refueling outages.

These valves will be tested for backflow quarterly.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 107 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 6 OF 20 NO. V-R06 Valves:

8949A, Safety Injection to Hot Leg #1 Check Valve
8949B, Safety Injection to Hot Leg #2 Check Valve
8949C, Safety Injection to Hot Leg #3 Check Valve
8949D, Safety Injection to Hot Leg #4 Check Valve Category:

A,C Code Class: 1 Function:

These check valves have an active safety function to open to supply safety injection flow to the reactor coolant system (RCS) hot legs.

Basis:

Valves 8949A&B cannot be exercised during power operation because neither the residual heat removal nor the safety injection pumps develop sufficient head to overcome RCS pressure. Valves 8949C&D cannot be exercised during power operation because the safety injection pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised during cold shutdown because a maximum of zero safety injection pumps are capable of injecting into the RCS by Technical Specification SR 3.4.12.1 to protect against a low temperature over-pressurization of the RCS. Valves 8949A&B cannot be exercised during cold shutdown using the RHR pump because this would result in short cycling the core and not removing decay heat properly.

These valves will be full stroke exercised during refueling outages.

Justification:

Refueling outage frequency testing is per Part 10, paragraphs 4.2.1.2(e) and 4.3.2.2(e).

10006618.1ST 40MIS 108 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 7 OF 20 NO. V-R07 Valves:

8981 Refueling Water Storage Tank to Residual Heat Removal Pump Check Valve Category:

C Code Class: 2 Function:

This check valve has an active safety function to open to supply borated water from the RWST to the suction of the RHR pumps. This valve also has a safety function in the closed position (backflow) to limit potential post-LOCA recirculation leakage to the RWST.

Basis:

The valve cannot be full stroked exercised during power operation because the RHR pumps do not develop enough head to overcome RCS pressure.

The valve cannot be exercised during cold shutdown because both RHR pumps must be aligned to remove decay heat from the RCS; therefore no flow path exists for full stroke exercising the valve. The valve is not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

Valve 8981 will be full stroke exercised each refueling outage.

The valve can be verified closed during cold shutdown by pressure testing the valve during plant cooldown. See cold shutdown justification No. V-CS34.

Justification:

The valve shall be full stroke exercised during refueling outages per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 109 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 8 OF 20 NO. V-R08 Valves:

8982A, Containment Recirc Sump to RHR Pump #1 Isolation Valve (Outside Containment)
8982B, Containment Recirc Sump to RHR Pump #2 Isolation Valve (Outside Containment)

Category:

B Code Class: 2 Function:

These motor-operated gate valves have an active safety function to open which allows the RHR pumps to take suction from the containment recirculation sumps during the cold leg recirculation phase of an accident.

Basis:

These valves cannot be exercised during power operation because they are required to be closed with power to the valve operators removed by Technical Specification SR 3.5.2.1. If these valves were opened during power operation, this would result in one train of the RHR system being not OPERABLE.

These valves cannot be exercised during cold shutdown because opening one of these valves could introduce air into the suction piping of the RHR pumps, causing the RHR pumps to be not OPERABLE for an extended period of time.

These valves will be full stroke exercised on a refueling outage frequency.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.2.1.2(e).

10006618.1ST 40MIS 110 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 9 OF 20 NO. V-R09 Valves:

8820, Charging Injection 2nd-off Check Valve
8900A, Charging Injection Loop-1 Cold Leg Check Valve
8900B, Charging Injection Loop-2 Cold Leg Check Valve
8900C, Charging Injection Loop-3 Cold Leg Check Valve
8900D, Charging Injection Loop-4 Cold Leg Check Valve Category:

C Code Class: 1 Function:

These check valves have an active safety function to open to supply safety injection flow to the reactor coolant system (RCS) cold legs from the high-head safety injection pumps (centrifugal charging pumps).

Basis:

These valves cannot be full stroke exercised during plant operation because the high RCS pressure will prevent the maximum required injection flow rate. Part stroke exercising these valves during plant operation is not practicable because any flow through the valves would result in unnecessary thermal transients on the RCS cold leg nozzles.

These valves cannot be full stroke exercised during cold shutdown because of insufficient RCS expansion volume to accommodate the high flow rates required to full stroke these valves. These high flow rates could challenge the RCS low temperature overpressure (LTOP) mitigation system. To prevent challenging the LTOP system, venting of the pressurizer by removal of a safety valve would be required.

Additionally, full stroke exercising these valves cannot be performed with a bubble in the pressurizer, because the net charging rate must be minimal to prevent thermal cycling of the pressurizer.

Valves 8900A-D cannot be part stroke exercised during cold shutdown for the same reasons that they cannot be full stroked. In addition, the charging injection flow path is not designed for throttled operation which would be required to part stroke all four parallel check valves.

These valves are not equipped with mechanical exercisers, position indicators, or differential pressure instrumentation.

These valves will be full stroke exercised on a refueling outage frequency. In addition, valve 8820 will be part stroked during cold shutdowns via a small test line.

Justification:

Part-stroking during cold shutdown is per Part 10, paragraph 4.3.2.2(d).

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

I0006618.IST 40MIS 111 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 10 OF 20 NO. V-RO10 Valves:

SW-34, ASW Pump #1 Discharge Line Vacuum Relief Check SW-170, ASW Pump #1 Discharge Line Vacuum Relief Check SW-301, ASW Pump #2 Discharge Line Vacuum Relief Check SW-303, ASW Pump #2 Discharge Line Vacuum Relief Check Category:

C Code Class: 3 Function:

These check valves have a safety related function in the open direction to serve as vacuum relief valves for the Auxiliary Saltwater System (ASW) pumps' discharge lines. Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after a LOCA, the two ASW trains are isolated from each other. If an ASW pump is stopped and later restarted in this situation, then these check valves must open to permit the passage of air into the discharge line while the pump is shut down in order to prevent water hammer and resultant damage in the line and in the CCW heat exchanger, when the pump is restarted.

The check valves have the safety related functions in the closed direction (backflow) of preventing ASW flow out the vent, and maintaining the pressure boundary integrity of the ASW system.

Basis:

These valves are disassembled and inspected on a refueling outage frequency in accordance with Part 10, paragraph 4.3.2.4(c). This will prove both the open and close functions. They will also be opened and manually stroked every 6 months for preventive maintenance reasons.

Justification:

Part 10, paragraph 4.3.2.4(c). (Refueling outage justification not required.)

40MIS 112 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2 I0006618.IST

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 11 OF 20 NO. V-ROll Valves:

8440 Volume Control Tank Outlet Check Valve Category:

C Code Class: 2 Function:

This check valve has an active safety function to close to prevent backflow from the charging pump suction header to relief valve 8123 during the post-LOCA containment sump recirculation mode of safety injection. It also has a safety function to open to provide a flow path for the charging pump mini-flow recirculation to return to the suction header of the charging pumps.

Basis:

This check valve is open during operation to provide the normal source of supply to the suction of the charging pumps. Exercising this valve during power operation would require alignment to the alternate supply which would result in injecting highly oxygenated, 2000 ppm borated water into the reactor coolant system. Injecting this water results in a negative reactivity addition to the reactor coolant system which could shut the plant down.

This valve cannot be tested for backflow during power operation as the only acceptable method of testing would be to perform hydros and measure for backleakage. This testing would require clearing pumps, entering ACTION Statements, and numerous valve and pump manipulations which affect the pressurizer level control and letdown temperature. This can cause cavitation in the letdown line.

This valve cannot be tested for backflow during cold shutdown as the only acceptable method of testing would be to perform hydros and measure for backleakage. This testing would require clearing pumps, entering ACTION Statements, and numerous valve and pump manipulations along with setting up the hydro testing equipment. NUREG-1482, Section 4.1.4, states that "the NRC has determined that the need to set up test equipment is adequate justification to defer backflow testing of a check valve until a refueling outage."

The ability to open is proven during normal operations per section 4.2.1.5. Closure will be tested on a refueling outage frequency.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 113 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 12 OF 20 NO. V-RO12 Valves:

RHR-1-8740A, RHR to Hot Leg #1 Check Valve RHR-1-8740B, RHR to Hot Leg #2 Check Valve Category:

A,C Code Class: 1 Function:

These valves have an active safety function to open to supply RHR flow to RCS Hot Legs 1 and 2.

Basis:

These valves cannot be exercised during power operation because the RHR Pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised during cold shutdown because due to lack of instrumentation necessary to individually verify full stroke capability of each valve.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

The Unit One valves will be non-intrusively tested (NIT) on a refueling outage frequency.

The Unit Two valves will be disassembled and inspected (see relief request V-RR7).

If any degradation is detected that interferes with a valve's operability then the valve will be disassembled, internally inspected, and manually full stroke exercised during the same outage.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 114 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 13 OF 20 NO. V-RO13 Valves:

8818A, RHR to Cold Leg #1 Check Valve
8818B, RHR to Cold Leg #2 Check Valve
8818C, RHR to Cold Leg #3 Check Valve
8818D, RHR to Cold Leg #4 Check Valve Category:

A,C Code Class: 1 Function:

These valves have an active safety function to open to supply RHR flow to RCS Cold Legs 1, 2, 3 and 4.

Basis:

These valves cannot be exercised during power operation because the RHR Pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised during cold shutdown because due to lack of instrumentation necessary to individually verify full stroke capability of each valve.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be non-intrusively tested (NIT) on a refueling outage frequency.

If any degradation is detected that interferes with a valve's operability then the valve will be disassembled, internally inspected, and manually full stroke exercised during the same outage.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 115 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REFUELING OUTAGE FREQUENCY JUSTIFICATION RCS-508, RCS-8028, TABLE 2.2 REV 18 (2002)

PAGE 14 OF 20 NO. V-RO14 Relief Valve and Stem Leak Off Header to PRT Check Valve Relief Valve Discharge Header to PRT Isolation Inside Containment Category:

RCS-8028 A,C Code tCass: 2 Category:

RCS-508 C

Code Class: 3 Function:

These valves have an active safety function to open to provide flow path for relief valves' discharge to PRT. RCS-8028 also has an active safety function to close to provide containment isolation.

Basis:

These valves cannot be full or part stroke exercised during power operation because the relief valve header is required to be in service during power operation. Test method employed to close stroke test RCS-8028 is local leak rate test which isolates the relief valve header from the relief valves.

These valves cannot be part or full stroke exercised during cold shutdown because the relief valve header is required to be in service.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be disassembled and manually exercised on a refueling outage frequency.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 116 Valves:

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 15 OF 20 NO. V-RO15 CCW-581, CCW-670, CVCS-8109, FCV-749 Bypass Check Valve FCV-750 Bypass Check Valve 8112 Bypass Check Valve Code Class: 2 The Bypass Check Valves have a safety function to open to relieve pressure buildup in Containment Penetrations 20, 21 and 45 when the containment penetration is isolated. They also serve as containment isolation valves, so they have a safety function in the closed direction (this function is already included on V-RR2 for valve 8109).

Basis:

These Bypass Check Valves cannot be exercised during power operation because the test would require clearing the reactor coolant pumps which are required for power operations. The tests also require that test equipment be set up inside the containment building.

These valves cannot be tested during cold shutdown because the test requires setting up test equipment inside containment, clearing reactor coolant pumps, and numerous valve manipulations.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e), and verifying closure by leak testing is preapproved per NUREG-1482, Section 4.1.4.

10006618.1ST 40MIS 117 Valves:

Category:

A,C Function:

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 16 OF 20 NO. V-RO16 Valves:

CCW-4, Suction Cross-tie Valve between CCW Headers B&C CCW-5, Suction Cross-tie Valve between CCW Headers A&C Category:

B Code Class: 3 Function:

These valves perform an active safety function in that they are manually closed to provide CCW train separation in Emergency Operating Procedures.

Basis:

These normally sealed open manual valves cannot be exercised during power operation because closing them would isolate the suction side of two CCW Pumps from one of the vital CCW Headers.

UFSAR Table 9.2-7 lists the failure of a CCW Pump to start as one of the malfunctions analyzed by the SAR. The closure of manual valve CCW-4 in conjunction with a failure of CCW Pump 1 to start would cause CCW Header B to be inoperable. The closure of CCW-5 in conjunction with the failure of CCW pump 3 to start would result in an inoperable CCW Header A.

Closure of these CCW Suction Header Cross-tie valves could also result in perturbations in CCW flow because return header flows are not equal and some flow through the suction cross-ties is needed during normal operations. These perturbations could adversely impact the ability of the CCW System to remove heat from various loads and are sufficient reason to not perform valve testing during transient plant conditions (i.e., forced outages).

Since these manual valves have very few failure mechanisms as opposed to power operated valves which have more failure mechanisms the risk of performing this test is not offset by the benefits of testing the valve and possibly identifying failure or degraded condition. The valves will be part stroke tested Quarterly and full stroke tested on a refueling outage frequency. The code committee is considering a five year frequency test for manual valves, so this is an indication of how much benefit there is to testing manual valves.

These manual valves cannot be stroked during Cold Shutdown because CCW is required to cool Residual Heat Removal System Heat Exchangers during cold shutdown, especially during the first few days of cold shutdown. The test would require splitting CCW Headers by manipulating several sealed open manual valves and aligning CCW into an abnormal system alignment.

Full stroke of these manual valves will be tested on a refueling outage frequency.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.2.1.2(e).

10006618.IST 40MIS 118 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 17 OF 20 NO. V-RO17 Valves:

8483, Charging Flow to Cold Legs Bypass Check Valve Category:

C Code Class: 1 Function:

This valve has a safety function to open to relieve pressure build up if normal and alternate charging valves 8146 and 8147 are both closed and Regenerative Heat Exchanger added heat to the charging line with resulting thermal expansion and pressure increase. The valve need only to partially open and allow flow to perform its safety function.

Basis:

This check valve cannot be exercised during power operation because opening this valve would require closing normal and alternate charging valves 8146 and 8147 which would isolate normal charging. This would result in thermal transient to be induced in the charging to RCS Cold Leg nozzles. This is per Westinghouse Infogram (WIG 90-025).

This valve cannot be tested for flow during Cold Shutdown as the only acceptable method of testing is to isolate normal and alternate charging thus isolating charging flow. The resultant differential pressure seen by 8146 or 8147 would be extremely high because all of the charging pump pressure would have to be reduced at the normal or alternate charging valve which is not set up to accomplish this. The valve can be tested during refueling outages when charging pump full flow tests using charging injection flow path are performed. During the charging pump full flow tests, the pressures differential across the normal or alternate charging valves is much lower.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(e).

10006618.1ST 40MIS 119 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 18 OF 20 NO. V-RO18 Valves:

VAC-252, Containment Hydrogen Sample Return Isolation Check Valve (IC)

VAC-253, Containment Hydrogen Sample Return Isolation Check Valve (IC)

Category:

A, C Code Class: 2 Function:

These valves have a safety function supporting the containment hydrogen monitoring capability by opening to complete the sample flow path from the containment, through the hydrogen monitor, and back to the containment. They also have a safety function in the closed direction of preventing back leakage to maintain design basis containment integrity.

Basis:

These check valves cannot be exercised during power operation because Technical Specification SR 3.6.3.3 and SR 3.6.3.4 require the Containment H2 Sample Supply and Return Isolation Valves to be closed when containment integrity is required. These valves do not receive a containment isolation signal. No other practical way of flow testing the check valves is available without opening of the Containment H2 Sample Supply and Return Isolation Valves.

Theses check valves can be partial stroke tested during Cold Shutdown by operation of the containment hydrogen monitors. Flow is provided by the H2 monitor sample pumps, which are aligned to the check valves. However, since the only available flow meter in this path is an uncalibrated rotameter full design flow through the check valves cannot be verified.

Therefore, each refueling outage, these valves will be full stroked exercised by flowing air through them and measuring the air flow using a calibrated flow instrument. Since this test involves setting up of temporary test equipment inside the containment it is impractical to perform this during Cold Shutdown.

The basis for the refueling outage frequency for the closed stroke test is explained in Request for Relief No. V-RR2.

Justification:

Refueling outage frequency testing is per Part 10, paragraph 4.3.2.2(d).

10006618.1ST 40MIS 120 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 19 OF 20 NO. V-RO19 Valves:

8977 RWST to Safety Injection Pump Check Valve Category:

C Code Class: 2 Function:

This check valve has an active safety function to open to supply borated water from the RWST to the suction of the Safety Injection Pumps. This valve also has a safety function in the closed position (backflow) to limit potential post-LOCA recirculation leakage to the RWST.

Basis:

The valve cannot be full stroked exercised during power operation because the Safety Injection Pumps do not develop enough head to overcome RCS pressure.

The valve cannot be exercised during cold shutdown because a maximum of zero Safety Injection Pumps are allowed to be capable of injecting into the RCS per Technical Specification SR 3.4.12.1 to protect against a low temperature over pressurization of the RCS.

Close exercising of valve 8977 is not practicable during power operation or cold shutdown because the test method used would require either the use of a hydro pump to pressurize the suction side of the safety injection pumps or opening of SI-8804B to pressurize the suction of the safety injection pumps using an RHR pump, neither of which can be performed when the plant is in cold shutdown. The valve is not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

Valve 8977 can be part stroke tested open quarterly and full stroke tested each refueling outage.

Justification:

The valve shall be part stroke exercised quarterly and full stroke exercised during refueling outages per Part 10, paragraph 4.3.2.2(b/d).

10006618.1ST 40M[S 121 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.2 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REFUELING OUTAGE FREQUENCY JUSTIFICATION PAGE 20 OF 20 NO. V-R020 Valves:

8924 RWST to Charging Pump Check Valve Category:

C Code Class: 2 Function:

This check valve has an active safety function to open to supply borated water from the RWST to the suction of the Charging Pumps. This valve also has a safety function in the closed position (backflow) to limit potential post-LOCA recirculation leakage to the RWST.

Basis:

The valve cannot be full stroked exercised during power operation because this would require injecting borated water from the RWST into the RCS, which could result in a plant shutdown.

The valve cannot be exercised during cold shutdown because of the high flow rates could challenge the RCS low temperature overpressure protection system.

Close exercising of valve 8924 is not practicable during power operation or cold shutdown because the test method used would require either the use of a hydro pump to pressurize the suction side of the charging pumps or opening of SI-8804A to pressurize the suction of the charging pumps using an RHR pump, neither of which can be performed when the plant is in cold shutdown. The valve is not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

Valve 8924 can be part stroke tested open during cold shutdown and full stroke tested each refueling outage.

Justification:

The valve shall be part stroke exercised during cold shutdowns and full stroke exercised during refueling outages per Part 10, paragraph 4.3.2.2(d) and 4.3.2.2(e).

10006618.1ST 40MIS 122 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS I & 2

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS TABLE 2.3 REV 18 (2002)

PAGE 1 OF 10 RELIEF REQUEST RELIEF REQUEST APPROVAL STATUS Preapproved per GL 89-04, Attach 1, position 2 Preapproved per NUREG-1482, section 4.1.4 Preapproved per GL 89-04, Attach 1, position 2 Preapproved per NUREG-1482, section 4.1.2 Preapproved per NUREG-1482, section 4.1.2 Preapproved per GL 89-04, Attach 1, position 2 Preapproved per GL 89-04, Attach 1, position 2 Preapproved per GL 89-04, Attach 1, position 2 10006618.1ST 40MIS 123 COMPONENT Auxiliary Feedwater Pump suction check valves:

FW-349, FW-353 Category A/C check valves:

AIR-I-587, CCW-585, CCW-695, LWS-60, VAC-21, VAC-116, VAC-252, VAC-253, 8046, 8047, 8109, 8368A, 8368B, 8368C, 8368D, 8916 Deleted, see Refueling Justification # V-R020 Safety injection cold leg check valves:

8948A, 8948B, 8948C, 8948D Accumulator discharge check valves:

8956A, 8956B, 8956C, 8956D Deleted, see Refueling Justification # V-RO19 Deleted, See Refueling Justification #V-R012 Containment spray ring header check valves:

9011A, 9011B Deleted, See Refueling Justification #V-RO13 Containment spray pump discharge check valves:

9002A, 9002B 2

3 4

5 6

7 8

9 10 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS RELIEF REQUEST COMPONENT TABLE 2.3 REV 18 (2002)

PAGE 2 OF 10 RELIEF REQUEST APPROVAL STATUS AFW Pump steam supply check valves:

MS-5166, MS-5167 Preapproved per GL 89-04, Attach 1, position 2 10006618.IST 40MIS 124 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 I1I

PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS FW-349, FW-353, TABLE 2.3 REV 18 (2002)

PAGE 3 OF 10 NO. V-RR1 Aux Feedwater Pump #1 Suction Check from the Raw Water Storage Reservoir Aux Feedwater Pump #2 & #3 Suction Check from the Raw Water Storage Reservoir Category:

C Code Class: 3 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves have an active safety function to open to supply an additional source of water to the steam generators via the auxiliary feedwater pumps.

Basis:

These valves cannot be exercised with flow because the water from the Raw Water Storage Reservoir would contaminate the steam generators creating chemistry problems which could effect the integrity of the steam generator tubes.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be disassembled, internally inspected, and manually full stroke exercised on a rotational basis, one valve each refueling outage. If any degradation is detected that interferes with the valve's operability, then the opposite train valve will also be disassembled, internally inspected, and manual full stroke exercised during the same outage.

Justification:

Disassembly and inspection each refueling outage is per Part 10, paragraph 4.3.2.4(c).

Disassembly and inspection sampling program is preapproved per NRC Generic Letter 89-04,, position 2.

10006618.1ST 40MIS 125 Valves:

DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 4 OF 10 NO. V-RR2 Valves:

AIR-I-587 Containment Normal Instrument Air Supply Isolation Check (OC)

CCW-585 CCW to RCP & Reactor Vessel Support Isolation Check (IC)

CCW-695 CCW to Excess Letdown Heat Exchanger Isolation Check (OC)

LWS-60 Nitrogen to RCDT Isolation Check (IC)

VAC-21 Containment Air Sample Return Isolation Check (IC)

VAC-116 Containment Air Sample Post-LOCA Return Isolation (IC)

VAC-252 Containment Hydrogen Sample Return Isolation Check (IC)

VAC-253 Containment Hydrogen Sample Return Isolation Check (IC) 8046 Primary Water to PRT Isolation Check (IC) 8047 Nitrogen to PRT Isolation Check (IC) 8109 RCP Seal Water Return Isolation Check (IC) 8368A RCP-1 Seal Injection Isolation Check (IC) 8368B RCP-2 Seal Injection Isolation Check (IC) 8368C RCP-3 Seal Injection Isolation Check (IC) 8368D RCP-4 Seal Injection Isolation Check (IC) 8916 Nitrogen Supply to Accumulator Isolation Check (IC)

Category:

A,C Code Class: 2 Test Reqt:

Part 10, section 4.3.2.1, "Exercising Test Frequency".

Function:

These check valves have the safety function to prevent reverse flow from containment to the system outside of containment.

Basis:

These check valves can only be verified closed by leakrate testing. They will be leakrate tested each refueling outage.

Justification:

Extension of test interval to refueling outage for check valves verified closed by leak testing is preapproved per NUREG-1482, section 4.1.4.

10006618.IST 40MIS 126 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 5 OF 14 PACIFIC GAS & ELECTRIC COMPANY DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 5 OF 10 NO. V-RR4 Valves:

8948A Safety Injection to Cold Leg #1 Check Valve 8948B Safety Injection to Cold Leg #2 Check Valve 8948C Safety Injection to Cold Leg #3 Check Valve 8948D Safety Injection to Cold Leg #4 Check Valve Category:

A,C Code Class: 1 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves have an active safety function to open to supply safety injection flow to the RCS cold legs.

Basis:

These valves cannot be exercised during power operation because the accumulators, RHR pumps, and SI pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be tested during cold shutdown due to lack of instrumentation necessary to individually verify full stroke capability of each valve.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be non-intrusively tested (NIT), on a sampling program, per NUREG-1482. This program will NIT one valve each refueling outage, on a rotating schedule, while partial flow testing the other three valves.

If any degradation is detected that interferes with a valve's operability then the valve will be disassembled, internally inspected, and manually full stroke exercised during the same outage. In addition, the other three valves in this group will be NIT during the same outage.

Justification:

Preapproved per NUREG-1482, section 4.1.2.

10006618.IST 40MIS 127 DIABLO CANYON POWER PLANT - UNITS I & 2 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 6 OF 10 NO. V-RR5 Valves:

8956A Accumulator #1 Discharge Check Valve 8956B Accumulator #2 Discharge Check Valve 8956C Accumulator #3 Discharge Check Valve 8956D Accumulator #4 Discharge Check Valve Category:

A,C Code Class: 1 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves have an active safety function to open to supply flow from the accumulators to the RCS during an accident condition. They also have a passive safety function to prevent backflow from the RCS into the accumulators during normal operations.

Basis:

These valves cannot be exercised during power operation because the accumulators cannot overcome RCS pressure.

These valves cannot be exercised during cold shutdowns because this could result in a possible low temperature overpressurization of the RCS.

Full flow testing of these valves during refueling outages is not feasible because of the resulting water surge into the reactor vessel and potential for high airborne radiation problems.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be non-intrusively tested (NIT), on a sampling program, per NUREG-1482. This program will NIT one valve each refueling outage, on a rotating schedule, while partial flow testing the other three valves.

If any degradation is detected that interferes with a valve's operability then the valve will be disassembled, internally inspected, and manually full stroke exercised during the same outage. In addition, the other three valves in this group will be NIT during the same outage.

Justification:

Preapproved per NUREG-1482, section 4.1.2.

10006618.1ST 40MIS 128 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 7 OF 10 NO. V-RR7 Valves:

RHR-2-8740A, RHR to Hot Leg #1 Check Valve (Unit Two only)

RHR-2-8740B, RHR to Hot Leg #2 Check Valve (Unit Two only)

Category:

A,C Code Class: 1 Test Reqt:

Part 10 does not provide for sampling.

Function:

These valves have a safety function in the open direction of allowing RHR pumps to discharge to the RCS hot legs during safety injection. They have a safety function in the closed direction of protecting the lower pressure rated RHR piping from overpressurization by back leakage from the RCS.

Basis:

These valves cannot be exercised during power operation because the RHR pumps do not develop sufficient head to overcome RCS pressure.

These valves cannot be exercised during cold shutdown because this would result in short cycling the core, thereby not removing decay heat.

These valves cannot be adequately tested during refueling outages using flow because the only available flow path would result in testing the valves in parallel and the hot leg injection lines are not equipped with individual flow indicators. The Non-Intrusive testing (NIT) method cannot be used for the unit two valves because the valve discs failed to consistently impact the back stop during non-intrusive tests performed during refueling outages. The unit one valves do provide consistent NIT results.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure indication.

These valves will be disassembled, internally inspected, and manually full stroke exercised on a rotational basis, one valve each refueling outage. If any degradation is detected that interferes with the valve's operability, then the opposite train valve will also be disassembled, internally inspected, and manual full stroke exercised during the same outage.

Justification:

Disassembly and inspection each refueling outage is per Part 10, paragraph 4.3.2.4.c.

Disassembly and inspection sampling program is preapproved per NRC Generic Letter 89-04,, position 2.

10006618.1ST 40MIS 129 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 8 OF 10 NO. V-RR8 Valves:

9011 A, Containment Spray Header A Isolation Check Valve (IC) 9011 B, Containment Spray Header B Isolation Check Valve (IC)

Category:

A,C Code Class: 2 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves have an active safety function to open to allow full containment spray flow following an accident. They also have a safety function in the closed position (back leakage) to provide containment isolation.

Basis:

These valves cannot be exercised during power operations, cold shutdown, or refueling outages because flow through these valves would result in spraying containment.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation.

These valves will be disassembled, internally inspected, and manually full stroke exercised on a rotational basis, one valve each refueling outage. If any degradation is detected that interferes with the valve's operability, then the opposite train valve will also be disassembled, internally inspected, and manual full stroke exercised during the same outage.

Justification:

Disassembly and inspection each refueling outage is per Part 10, paragraph 4.3.2.4(c).

Disassembly and inspection sampling program is preapproved per NRC Generic Letter 89-04,, position 2.

10006618.1ST 40MIS 130 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 9 OF 10 NO. V-RR10 Valves:

9002A Containment Spray Pump #1 Discharge Check Valve 9002B Containment Spray Pump #2 Discharge Check Valve Category:

C Code Class: 2 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves function to allow full-flow during containment spray following a LOCA.

They close to prevent backflow of recirculating post-LOCA sump water back to the RWST in the event that valve 9001A or 9001B is open.

Basis:

These check valves cannot be exercised during power operation because the system alignment for testing would require a containment entry to manually isolate the spray headers for testing and require placing the RHR system in an unanalyzed condition.

It is impractical to test these valves during shutdowns as the flowpath through these valves disables a train of the RHR system. The shutdown test alignment for partial or full stroking the valves places the RHR system in a degraded and precarious operating configuration, and creates the potential for inadvertent spraying of containment, inadequate RHR flow to the RCS, or overfilling of the reactor vessel or refueling cavity. The valves are located in essentially dry pipe and are not subject to cycling; therefore, potential degradation mechanisms are minimal.

These valves will be disassembled, internally inspected, and manually full stroke exercised, one valve each refueling outage. If any degradation is detected that interferes with the valve's operability, then the remaining valve will also be disassembled, internally inspected, and manually full stroke exercised during the same outage.

Justification:

Disassembly and inspection each refueling outage is per Part 10, paragraph 4.3.2.4(c).

Disassembly and inspection sampling program is preapproved per NRC Generic Letter 89-04,, position 2.

10006618.1ST 40MIS 131 DIABLO CANYON POWER PLANT - UNITS 1 & 2 PACIFIC GAS & ELECTRIC COMPANY

DIABLO CANYON POWER PLANT - UNITS 1 & 2 INSERVICE TESTING PROGRAM PLAN - PUMPS AND VALVES TABLE 2.3 ASME/ANSI OM-1987 (INCLUDING OMa-1988 ADDENDA)

REV 18 (2002)

REQUESTS FOR RELIEF FROM CODE REQUIREMENTS PAGE 10 OF 10 NO. V-RR11 Valves:

MS-5166, SG-2 Steam to Auxiliary Feedwater Pump #1 Check Valve MS-5167, SG-3 Steam to Auxiliary Feedwater Pump #1 Check Valve Category:

C Code Class: 2 Test Reqt:

Part 10 does not provide for sampling.

Function:

These check valves function to supply steam to the turbine driven auxiliary feedwater pump. The valves also have a safety function in the closed (reverse-flow) position to prevent an intact steam generator from blowing down to containment through the turbine driven AFW pump steam supply line following a MSLB.

Basis:

Full stroke opening is verified on a cold shutdown basis, but valve reclosure capability cannot be verified.

These valves are not equipped with mechanical exercisers, position indicators or differential pressure instrumentation. There are no test connections or taps installed that would allow reverse-flow seating verification for these check valves. Alternatively, the ability of the valve to close following actuation will be verified by disassembly and internal inspection on a rotational basis, one valve each refueling outage.

If any degradation is detected that interferes with the valve's operability, then the opposite train valve will also be disassembled and internally inspected during the same outage. The valves will be part stroke tested after reassembly.

Justification:

Disassembly and inspection each refueling outage is per Part 10, paragraph 4.3.2.4(c).

Disassembly and inspection sampling program is preapproved per NRC Generic Letter 89-04,, position 2.

10006618.1ST 40MIS 132 PACIFIC GAS & ELECTRIC COMPANY