MONTHYEARCPSES-200600627, Updated Response to Requested Information Part 2 of NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors.2006-03-31031 March 2006 Updated Response to Requested Information Part 2 of NRC Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized Water Reactors. Project stage: Request CPSES-200601177, Supplement to License Amendment Request (LAR) 05-010 Revision to Technical Specification 3.3.2, ESFAS Instrumentation, 3.5.2, ECCS-Operating, and 3.6.7, Spray Additive System.2006-06-23023 June 2006 Supplement to License Amendment Request (LAR) 05-010 Revision to Technical Specification 3.3.2, ESFAS Instrumentation, 3.5.2, ECCS-Operating, and 3.6.7, Spray Additive System. Project stage: Supplement ML0624404202006-08-25025 August 2006 Supplement to License Amendment Request (LAR) 05-010 and Response to Request for Information Project stage: Supplement CPSES-200601743, Supplement to License Amendment Request (LAR) 05-010 and Response to Request for Information2006-09-0505 September 2006 Supplement to License Amendment Request (LAR) 05-010 and Response to Request for Information Project stage: Supplement CPSES-200601951, Supplement to License Amendment Request (LAR) 05-010 and Response to Request for Information2006-09-28028 September 2006 Supplement to License Amendment Request (LAR) 05-010 and Response to Request for Information Project stage: Supplement ML0625500762006-10-0505 October 2006 Issuance of Amendments Revisions to TS 3.3.2, ESFAS (Engineered Safety Features Actuation System) Instrumentation; and TS 3.5.2, ECCS (Emergency Core Cooling System) - Operating Project stage: Approval ML0628401022006-10-0505 October 2006 Technical Specification, Revisions to TS 3.3.2, ESFAS Instrumentation; and TS 3.5.2, ECCS - Operating Project stage: Other 2006-06-23
[Table View] |
|
---|
Category:Letter type:CPSES
MONTHYEARCPSES-201001000, Operator Licensing Examination Data, Form 5362010-07-28028 July 2010 Operator Licensing Examination Data, Form 536 CPSES-200901377, Operator Licensing Examination Data2009-09-29029 September 2009 Operator Licensing Examination Data CPSES-200701127, Response to Request for Additional Information Related to License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times.2007-11-15015 November 2007 Response to Request for Additional Information Related to License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times. CPSES-200701495, Withdrawal of License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-10-22022 October 2007 Withdrawal of License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200701530, Additional Information in Connection with the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments2007-10-0909 October 2007 Additional Information in Connection with the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments CPSES-200701496, Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments2007-10-0202 October 2007 Information Required by Order Approving the Indirect Transfer of Facility Operating Licenses and Conforming License Amendments CPSES-200701351, Transmittal of First-Half 2007 Fitness-for-Duty Program Performance Data2007-08-29029 August 2007 Transmittal of First-Half 2007 Fitness-for-Duty Program Performance Data CPSES-200701076, Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt2007-08-28028 August 2007 Revision to the Operating License and Technical Specifications 1.0, Use and Application and 3.7.17, Spent Fuel Assembly Storage to Revise Rated Thermal Power from 3458 Mwt to 3612 Mwt CPSES-200701302, Relief Request B-4 to the Unit 2 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date - August 03, 2004, Second Interval)2007-08-22022 August 2007 Relief Request B-4 to the Unit 2 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date - August 03, 2004, Second Interval) CPSES-200701324, Supplement to License Amendment Request (LAR) 07-003 Revision to Technical Specification 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, and 5.6.5 B, Core Operating Limits2007-08-16016 August 2007 Supplement to License Amendment Request (LAR) 07-003 Revision to Technical Specification 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, and 5.6.5 B, Core Operating Limits CPSES-200701323, License Amendment Request 07-006, Revision to Technical Specification 3.1.4, Rod Group Alignment Limits, Table 3.3.1-1, Reactor Trip System Instrumentation, Table 3.3.2-1, Engineered Safety Feature Actuation System..2007-08-16016 August 2007 License Amendment Request 07-006, Revision to Technical Specification 3.1.4, Rod Group Alignment Limits, Table 3.3.1-1, Reactor Trip System Instrumentation, Table 3.3.2-1, Engineered Safety Feature Actuation System.. CPSES-200701279, Mitigation of Alloy 82/182 Pressurizer Butt Welds in 20082007-08-0303 August 2007 Mitigation of Alloy 82/182 Pressurizer Butt Welds in 2008 CPSES-200701284, (Cpses), Operator Licensing Examination Data2007-08-0202 August 2007 (Cpses), Operator Licensing Examination Data CPSES-200701238, Submittal of the CPSES Units 1 and 2 Large and Small Break LOCA Analyses2007-07-31031 July 2007 Submittal of the CPSES Units 1 and 2 Large and Small Break LOCA Analyses CPSES-200701178, Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 72007-07-20020 July 2007 Supplement to Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change (TAC Nos. MD5289 and MD5280), Enclosures 1, 4, 5, 6 & 7 CPSES-200701126, Response to Request for Additional Information to License Amendment Request (LAR) 06-007 Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-07-18018 July 2007 Response to Request for Additional Information to License Amendment Request (LAR) 06-007 Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200701174, Submittal of Twelfth Refueling Outage (1RF12) Inservice Inspection Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/03/2000, Second Interval)2007-07-17017 July 2007 Submittal of Twelfth Refueling Outage (1RF12) Inservice Inspection Summary Report (1998 Edition of ASME Code Section XI Through 2000 Addenda, Interval Start Date - 08/03/2000, Second Interval) CPSES-200701065, Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients.2007-06-21021 June 2007 Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients. CPSES-200700951, (Cpses), Unit 1, Pressurizer Weld Overlay 60 Day Report and Update for Unit 1 Reactor Pressure Vessel Head Replacement Regarding Revised Order EA-03-0092007-06-19019 June 2007 (Cpses), Unit 1, Pressurizer Weld Overlay 60 Day Report and Update for Unit 1 Reactor Pressure Vessel Head Replacement Regarding Revised Order EA-03-009 CPSES-200701059, Submittal of Startup Report, Cycle 132007-06-13013 June 2007 Submittal of Startup Report, Cycle 13 CPSES-200700738, License Amendment Request (LAR) 07-001 Revision to Technical Requirements Surveillance 13.3.33.2 Frequency for the Turbine Stop and Control Valves2007-05-22022 May 2007 License Amendment Request (LAR) 07-001 Revision to Technical Requirements Surveillance 13.3.33.2 Frequency for the Turbine Stop and Control Valves CPSES-200700915, Supplemental Response to Request for Information on Generic Letter 2003-01, Control Room Habitability2007-05-0707 May 2007 Supplemental Response to Request for Information on Generic Letter 2003-01, Control Room Habitability CPSES-200700871, Transmittal of Year 2006 Radioactive Effluent Release Report2007-04-30030 April 2007 Transmittal of Year 2006 Radioactive Effluent Release Report CPSES-200700859, Submittal of the Annual Non-Radiological Environmental Operating Report for 20062007-04-27027 April 2007 Submittal of the Annual Non-Radiological Environmental Operating Report for 2006 CPSES-200700517, Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change2007-04-18018 April 2007 Application for Order Approving Indirect Transfer of Control of Licenses and License Amendments to Reflect Proposed Licensee Name Change CPSES-200700719, Nuclear Liability Insurance2007-04-10010 April 2007 Nuclear Liability Insurance CPSES-200700605, License Amendment Request (LAR) 07-003, Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, & 5.6.5b, Core Operating Limits Report2007-04-10010 April 2007 License Amendment Request (LAR) 07-003, Revision to Technical Specifications 3.1, Reactivity Control Systems, 3.2, Power Distribution Limits, 3.3, Instrumentation, & 5.6.5b, Core Operating Limits Report CPSES-200700708, Evaluation of Pressurizer Weld Overlay Confirmatory Analyses2007-04-0505 April 2007 Evaluation of Pressurizer Weld Overlay Confirmatory Analyses CPSES-200700691, Core Operating Limits Report, Cycle 132007-04-0404 April 2007 Core Operating Limits Report, Cycle 13 CPSES-200700663, Transmittal of the Annual Radiological Environmental Operating Report for 20062007-03-30030 March 2007 Transmittal of the Annual Radiological Environmental Operating Report for 2006 CPSES-200700607, Property Damage Insurance2007-03-29029 March 2007 Property Damage Insurance CPSES-200700606, Decommissioning Report2007-03-29029 March 2007 Decommissioning Report CPSES-200700573, Request to Withdraw Relief Request A-72007-03-22022 March 2007 Request to Withdraw Relief Request A-7 CPSES-200700571, Supplement to License Amendment Request (LAR) 05-06; Revision to Technical Specification 5.6.5 Revise Listing of LOCA and Non-LOCA Analysis Methodologies (TAC Nos. MD0185/0186)2007-03-19019 March 2007 Supplement to License Amendment Request (LAR) 05-06; Revision to Technical Specification 5.6.5 Revise Listing of LOCA and Non-LOCA Analysis Methodologies (TAC Nos. MD0185/0186) CPSES-200700515, Day Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients.2007-03-0909 March 2007 Day Response to NRC Generic Letter 2007-01, Inaccessible or Underground Power Cable Failures That Disable Accident Mitigation Systems or Cause Plant Transients. CPSES-200700454, Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data2007-02-28028 February 2007 Transmittal of Second-Half 2006 Fitness-For-Duty Program Performance Data CPSES-200700451, Annual Operating Report for 20062007-02-28028 February 2007 Annual Operating Report for 2006 CPSES-200700422, Response to Request for Additional Information Related to Txu Power'S Request for Review of Previously Submitted Topical Reports2007-02-22022 February 2007 Response to Request for Additional Information Related to Txu Power'S Request for Review of Previously Submitted Topical Reports CPSES-200700414, Transmittal of Inservice Inspection Program Plan, Revision 5 (Unit 1: ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date - 08/13/200, Second Interval)2007-02-22022 February 2007 Transmittal of Inservice Inspection Program Plan, Revision 5 (Unit 1: ASME Code Section XI 1998 Edition, 1999 and 2000 Addenda, Interval Start Date - 08/13/200, Second Interval) CPSES-200700391, Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds2007-02-20020 February 2007 Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds CPSES-200700346, Guarantees of Payment of Deferred Premiums, Submits Form 10-Q for the Period Ending September 30, 20062007-02-0808 February 2007 Guarantees of Payment of Deferred Premiums, Submits Form 10-Q for the Period Ending September 30, 2006 CPSES-200700229, Comanche, Response to Request for Additional Information, Relief Request B-6 for the Unit 1 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date..2007-02-0202 February 2007 Comanche, Response to Request for Additional Information, Relief Request B-6 for the Unit 1 Inservice Inspection (ISI) Program Plan from the 1998 Edition of ASME Code, Section XI, Through 2000 Addenda (Interval Start Date.. CPSES-200700169, Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds2007-01-30030 January 2007 Inspection and Mitigation of Alloy 82/182 Pressurizer Butt Welds CPSES-200700147, Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power2007-01-29029 January 2007 Response to Request for Additional Information Regarding Resolution of Generic Letter 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power CPSES-200700127, Submittal of Unit 2 Ninth Refueling Outage (2RF09) Inservice Inspection (ISI) Summary Report (Unit 2: 1998 Edition of ASME Code Section XI, Through 2000 Addenda, Interval Start Date - August 3, 2004, Second Interval)2007-01-24024 January 2007 Submittal of Unit 2 Ninth Refueling Outage (2RF09) Inservice Inspection (ISI) Summary Report (Unit 2: 1998 Edition of ASME Code Section XI, Through 2000 Addenda, Interval Start Date - August 3, 2004, Second Interval) CPSES-200700146, License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits2007-01-18018 January 2007 License Amendment Request (LAR) 06-007, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Offsite Circuits CPSES-200700130, License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators2007-01-18018 January 2007 License Amendment Request (LAR) 06-009, Revision to Technical Specification (TS) 3.8.1, AC Sources - Operating, Extension of Completion Times for Diesel Generators CPSES-200700099, Annual Report of Changes in Peak Cladding Temperature2007-01-10010 January 2007 Annual Report of Changes in Peak Cladding Temperature CPSES-200602339, License Amendment Request (LAR) 06-010, Revision to Technical Specification 5.5.16, Containment Leakage Rate Testing Program.2006-12-19019 December 2006 License Amendment Request (LAR) 06-010, Revision to Technical Specification 5.5.16, Containment Leakage Rate Testing Program. CPSES-200602340, License Amendment Request (LAR) 06-012, Revision to Technical Specification 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources - Operating, & TS 3.8.9, Distribution Systems - Operating.2006-12-19019 December 2006 License Amendment Request (LAR) 06-012, Revision to Technical Specification 3.7.5, Auxiliary Feedwater System, TS 3.8.1, AC Sources - Operating, & TS 3.8.9, Distribution Systems - Operating. 2010-07-28
[Table view] |
Text
dft TXU
'vAC>wPower TXU Power Mike Blevins Comanche Peak Steam Electric Station Senior Vice President &
Chief Nuclear Officer P. O. Box 1002 (EO1)
Glen Rose, TX 76043 Tel: 254 897 5209 Ref: #10CFR50.54(f)
Fax: 254 897 6652 mike.blevins~txu.com CPSES-200600627 Log # TXX-06062 March 31, 2006 U. S. Nuclcar Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 UPDATED RESPONSE TO REQUESTED INFORMATION PART 2 OF NRC GENERIC LETTER 2004-02, "POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN BASIS ACCIDENTS AT PRESSURIZED-WATER REACTORS" REF: 1. Letter Logged TXX-05162 from M. Blevins to the NRC dated September 1, 2005, "RESPONSE TO REQUESTED INFORMATION PART 2 OF NRC GENERIC LETTER 2004-02, POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN BASIS ACCIDENTS AT PRESSURIZED-WATER REACTORS"
- 2. NRC letter from M. Thadani (NRC) to M. Blevins dated February 9, 2006, Requesting Additional Information Re: Response to Generic Letter 2004-02
- 3. NEI Letter from Anthony R. Pietrangelo (NEI) to Dr. Brian Sheron (NRC) dated February 28, 2006, Regarding NRC Requests for Additional Information to PWR Licensees Regarding Responses to Generic Letter 2004-02
- 4. NRC Letter from Dr. Brian Sheron (NRC) to Anthony R. Pietrangelo (NEI) dated March 3, 2006, Responding to the NEI letter regarding NRC Requests for Additional Information to PWR Licensees Regarding Responses to Generic Letter 2004-02 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Caflaway . Comanche Peak
/SfIo
TXX-06062 Page 2 of 5 Gentlemen:
The US Nuclear Regulatory Commission (NRC) issued Generic Letter 2004-02 on September 13, 2004 to 1) request that addressees perform an evaluation of the emergency core cooling system (ECCS) and containment spray system (CSS) recirculation functions in light of the information provided in the generic letter and, if appropriate, take additional actions to ensure system function, and 2) require addressees to provide the NRC a written response in accordance with I OCFR50.54(f).
Additionally the NRC requested that addressees submit information specified in part 2 of the generic letter to the NRC. The request was based on identified potential susceptibility of the pressurized water reactor (PWR) recirculation sump screens to debris blockage during design basis accidents requiring recirculation operation of ECCS or CSS and on the potential for additional adverse effects due to debris blockage of flow paths necessary for ECCS and CSS recirculation and containment drainage. Reference I provided the available information requested in part 2 of the generic letter as of September 1, 2005 and committed to update the information in the first quarter of 2006.
Subsequently, the NRC issued a request for additional information, Reference 2 (RAI) regarding the information provided in Reference 1. These RAls cover a broad range of topics and are intended to support the NRC staffs ongoing review of industry activities to resolve Generic Safety Issue 191. Responses to the RAls were requested within 60 days of the date of the letter transmitting the information requests. Subsequently] NEI requested (Reference 3) NRC consideration and acceptance of an alternative set of actions and schedule.
The NRC responded to the NEI request on March 3, 2006 via Reference 4 and agreed to the proposed alternative actions and schedule. The NRC agreed that for units completing their outage to incorporate strainer modifications in 2006, infonnation needed to fully address GL 2004-02 will be provided to the staff by December 31, 2006. The NRC further agreed that for units installing strainers after 2006, information needed to fully address GL 2004-02 will be provided to the staff withi.n 90 days of outage completion but not later than December 31, 2007.
TXU Generation Company, LP (TXU Power) is providing an update to the information that was submitted per Reference I and is revising commitment 27370 provided in Reference 1. The following information is being provided in accordance with IOCFR50.54(f).
TXX-06062 Page 3 of 5 Updates:
NRC Requested Information 2(a):
IProvidel Confirmation that the ECCS and CSS recirculation functions under debris loading conditions are or will be in compliance with the regulatory requirements listed in the Applicable Regulatory Requiremcnts section of this generic letter. This submittal should address the configuration of the plant that
,will exist once all modifications required for regulatory compliance have beert made and this licensing basis has been updated to reflect the results of the analysis described above.
Update to CPSES Response 2(a):
Activities are proceeding as described in Ref.1 with two changes.
- 1) In lieu of modifications to and replacement of Min-K insulation under pipe whip restraints, a sample of the welded, stainless steel encapsulated, high efficiency insulation was obtained and is undergoing structural analysis and comparison to insulation types that have been tested. A Zone of Influence (ZOI) based on this comparison will be used in a revision to the debris generation analysis.
- 2) As an alternative to the replacement of the containment spray chemical additive NaOH with Tri-sodium phosphate (TSP), CPSES is evaluating a reduction in the quantity of NaOH. A license amendment request was submitted in December 2005 to change Technical Specifications to allow either of these design options.
Design activities for the new sump strainers are in progress. A prototype has been built and tested in a flume with the conservative debris loads described in Ref. 1. In addition, manufactured chemical byproducts based on the Westinghouse Owner's Group methodology were added to the debris loads. CPSES does not utilize Calcium Silicate or any other insulation which reacts with TSP, and exposed bare concrete is minimal. Therefore, only aluminum byproducts were used in the strainer testing.
Bypass testing was also included. The testing was conducted March 6, 7, 8, and 9, 2006. A member of the NRC staff witnessed the testing on March 8. A range of tests was performed from very low fiber (latent fiber only), to thin bed, to thick bed.
Because CPSES is a low fiber reflective metal insulation (RMI) plant, the thick bed test was beyond the design basis; however, the strainer head loss was lower than fir the thin bed case. All tests included a very high particulate debris load. In each test, debris was introduced at (i.e. within 3 feet of) the strainer. During each test, continuous mixing of the flume upstream of the debris injection point was provided by overhead nozzles. The analysis of the bypass testing samples and the formal test report have not yet been completed; however, preliminary data and observations a7-e very positive with respect to strainer performance.
TXX-06062 Page 4 of 5 NRC Requested Information 2(b):
IProvidel A general description of and implementation schedule for all corrective actions, including any plant modifications, that you identified while responding to this generic letter. Efforts to implement the identified actions should be initiated no later than the first refueling outage starting after April 1, 2006. All actions should be completed by December 31, 2007. Provide justification for not implementing the identified actions during the first refueling outage starting after April 1, 2006. If all corrective actions vill not be completed by December 31, 2007, describe howv the regulatory requirements discussed in the Applicable Regulatory Requirements section will be met until the corrective actions are completed.
CPSES Response 2(b):
Activities are proceeding as described in Ref.l with the exception of some intermediate estimated completion dates (ECDs). The completion of these activities will support the update and response to RAIs for Unit 2 scheduled by the end of 2006.
NRC Requested Information 2(c):
[Provide] A description of the methodology that was used to perform the analysis of the susceptibility of the ECCS and CSS recirculation functions to the adverse effects of post-accident debris blockage and operation with debris-laden fluids. The submittal may reference a guidance document (e.g., Regulatory Guide 1.82, Rev. 3, industry guidance) or other methodology previously submitted to the NRC. (The submittal may also reference the response to Item I of the Requested Information described above. The documents to be submitted or referenced should include the results of any supporting containment walkdown surveillance performed to identify potential debris sources and other pertinent containment characteristics.)
CPSES Response 2(c):
Due to range and complexity of issues with respect to downstream and chemical effects, testing and analysis to support the update and revision of the analyses described in Ref. 1 to reflect the final CPSES design will not be completed by the end of the second quarter of 2006 as projected in Ref. 1. We expect these to be compleyed to support the update and response to RAls for Unit 2 scheduled by the end of 2006.
NRC Requested Information 2(d). 2(e). 2(f):
At this time, there are no updates to the NRC requested information in 2(d), 2(e), or 2(f) other than ones described by the above updates.
TXX-06062 Page 5 of 5 This letter contains one revised licensing commitment regarding CPSES Units I and 2.
Description of Commitment 27370 As a result of analyses, testing, and design evaluations not being fully (Revised) completed, an update to this response (modifications and maintenance actions) will be provided no later than Dccember 31, 2006for Unit 2 and 90 davs after completion of the Unit 1 refiueling outage in ihC Spring of2007.
Should you have any questions, please contact Mr. J. D. Seawright at (254) 897-0140.
I state under penalty of perjury that the foregoing is true and correct.
Executed on March 31, 2006.
Sincerely, TXU Generation Company LP By: TXU Generation Management Company LLC Its General Partner Mike Blevins By:Aa 21-
/i'redW. addcen Director, Regulatory Affairs JDS c - B. S. Mallett, Region IV M. C. Thadani, NRR Resident Inspectors, CPSES