Letter Sequence Request |
---|
|
|
MONTHYEARCP-201200552, License Amendment Request (LAR) 2012-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-12012-07-12012 July 2012 License Amendment Request (LAR) 2012-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-1 Project stage: Request ML12234A6412012-08-21021 August 2012 Acceptance of Application - License Amendment Request 12-001 Email for Revision to Technical Specification (TS) 5.7 and TS Table 3.3.3 - 1 Project stage: Acceptance Review CP-201201253, Supplement to License Amendment Request (LAR) 12-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-1, Post Accident Monitoring Instrumentation.2012-10-23023 October 2012 Supplement to License Amendment Request (LAR) 12-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-1, Post Accident Monitoring Instrumentation. Project stage: Supplement ML13156A2482013-07-11011 July 2013 Issuance of Amendment Nos. 159 and 159, Revise Technical Specification (TS) 5.7, High Rad Area, and TS Table 3.3.3-1, Post Accident Monitoring Instrumentation Project stage: Approval 2012-07-12
[Table View] |
|
---|
Category:Letter type:CP
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202300144, (CPNPP) - Decommissioning Report2023-03-30030 March 2023 (CPNPP) - Decommissioning Report CP-202300139, (CPNPP) - Property Damage Insurance2023-03-30030 March 2023 (CPNPP) - Property Damage Insurance CP-202300098, (Cpnpp), Annual Report of Changes in Peak Cladding Temperature2023-03-16016 March 2023 (Cpnpp), Annual Report of Changes in Peak Cladding Temperature CP-202200481, Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST)2022-12-0707 December 2022 Response to Request for Additional Information - Relief Request Application P-1, Inservice Testing (IST) CP-202200454, (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 .2022-12-0101 December 2022 (Cpnpp), Reply to a Notice of Violation Transmitted Via NRC Letter from Gregory Werner to Ken Peters Dated 11/01/2022, Comanche Peak Nuclear Power Plant, Units 1 and 2 Integrated Inspection Report 05000445/2022003 . CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200450, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2022-11-16016 November 2022 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202200435, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2022-11-0808 November 2022 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202200419, (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report2022-11-0303 November 2022 (CPNPP) - Unit 1 Refueling Outage 22 (1RF22) Steam Generator 180 Day Report CP-202200357, (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report2022-09-14014 September 2022 (CPNPP) Unit 2 - Response to Request for Additional Information, Fall 2021 (2RF19) Steam Generator Tube Inspection Report CP-202200358, (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46)2022-09-14014 September 2022 (CPNPP) - Transmittal of Revised Emergency Plan (Revision 46) CP-202200246, Evacuation Time Estimate Analysis2022-08-25025 August 2022 Evacuation Time Estimate Analysis CP-202200306, (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22)2022-08-11011 August 2022 (CPNPP) - Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 22 (1RF22) CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200276, (CPNPP) - Relief Request Application P-1, Inservice Testing (IST)2022-07-20020 July 2022 (CPNPP) - Relief Request Application P-1, Inservice Testing (IST) CP-202200247, (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 0172022-06-30030 June 2022 (CPNPP) - 10CFR50.59 Evaluation Summary Report 023, 10CFR72.48 Evaluation Summary Report 008 and Commitment Material Change Evaluation Report 017 2024-01-31
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARCP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 ML24023A0242024-01-24024 January 2024 Correction to Amendment Nos. 185 and 185 Regarding Implementation of Full Spectrum Loss-of-Coolant Accident Methodology CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300293, (CPNPP) - License Amendment Request Proposing Changes to Technical Specifications to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days2023-09-14014 September 2023 (CPNPP) - License Amendment Request Proposing Changes to Technical Specifications to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator from 72 Hours to 14 Days L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300096, License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements2023-04-20020 April 2023 License Amendment Request (LAR) 23-002 Application Regarding GDC-5 Shared Systems Requirements CP-202300140, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-0012023-04-19019 April 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors. LAR 23-001 CP-202300157, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-14014 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, and ISFSI, Application for Order Consenting to Transfer of Licenses and Conforming License Amendments CP-202300135, License Renewal Application Revision 0 - Supplement 12023-04-0606 April 2023 License Renewal Application Revision 0 - Supplement 1 CP-202200380, (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications2022-11-21021 November 2022 (CPNPP) - Non-Voluntary License Amendment Request to Revise Technical Specifications 3.2.1, Fq(Z), to Implement Methodology from WCAP-17661, Revision 1, Improved RAOC and CAOC Fq Surveillance Technical Specifications CP-202200355, Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-0022022-11-21021 November 2022 Application to Revise Technical Specifications to Apply the Westinghouse Full Spectrum Loss of Coolant Accident Evaluation Model LAR 22-002 CP-202200350, Facility Operating License Numbers NPF-87 and NPF-89 - License Renewal Application - Appendix E, Environmental Report2022-10-0303 October 2022 Facility Operating License Numbers NPF-87 and NPF-89 - License Renewal Application - Appendix E, Environmental Report ML22192A0072022-08-22022 August 2022 Issuance of Amendment Nos. 183 and 183 Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2 CP-202200273, Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative2022-07-20020 July 2022 Third Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative CP-202200006, (CPNPP) - Second Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended.2022-02-17017 February 2022 (CPNPP) - Second Supplement to License Amendment Request (LAR) 20-006 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended. CP-202200075, Third Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2022-02-15015 February 2022 Third Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections CP-202100575, (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2021-08-31031 August 2021 (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections CP-202100251, (CPNPP) - Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections2021-07-27027 July 2021 (CPNPP) - Application to Revise Technical Specifications to Adopt TSTF 577, Revised Frequencies for Steam Generator Tube Inspections CP-202100394, Supplement to License Amendment Request (LAR) 20-0062021-07-13013 July 2021 Supplement to License Amendment Request (LAR) 20-006 CP-202100065, Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2021-05-11011 May 2021 Application to Revise Technical Specifications to Adopt Risk Informed Completion Times, TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b CP-202000585, (CPNPP) - Supplement to License Amendment Request (LAR) 20-005, Revision to Technical Specification (TS) 3.6.8, Containment Sump2021-01-27027 January 2021 (CPNPP) - Supplement to License Amendment Request (LAR) 20-005, Revision to Technical Specification (TS) 3.6.8, Containment Sump CP-202000584, (CPNPP) - Supplement to License Amendment Request (LAR) 15-001, Revision to Technical Specification (TS) 3.8.l, AC SOURCES-OPERATING2020-12-0909 December 2020 (CPNPP) - Supplement to License Amendment Request (LAR) 15-001, Revision to Technical Specification (TS) 3.8.l, AC SOURCES-OPERATING CP-202000575, (CPNPP) - Exigent License Amendment Request (LAR) 20-007 Revision to Technical Specification (TS) 3.7.8, Station Service Water System and TS 3.8.1, AC Sources - Operating2020-11-19019 November 2020 (CPNPP) - Exigent License Amendment Request (LAR) 20-007 Revision to Technical Specification (TS) 3.7.8, Station Service Water System and TS 3.8.1, AC Sources - Operating CP-202000365, Luminant, Comamche Leak Nuclear Power Plant, License Amendment Request 20-005, New Technical Specification 3.6.8, Containment Sump2020-08-31031 August 2020 Luminant, Comamche Leak Nuclear Power Plant, License Amendment Request 20-005, New Technical Specification 3.6.8, Containment Sump CP-202000401, (CPNPP) - Supplement to Exigent License Amendment Request (LAR) 20-002, Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water2020-07-28028 July 2020 (CPNPP) - Supplement to Exigent License Amendment Request (LAR) 20-002, Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water CP-202000388, (CPNPP) - Supplement to Exigent License Amendment Request (LAR) 20-002, Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water2020-07-16016 July 2020 (CPNPP) - Supplement to Exigent License Amendment Request (LAR) 20-002, Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water CP-202000321, (CPNPP) - License Amendment Request (LAR) 20-001 Technical Specification (TS) 1.1, Definitions - ESP & RTS Response Time2020-07-0202 July 2020 (CPNPP) - License Amendment Request (LAR) 20-001 Technical Specification (TS) 1.1, Definitions - ESP & RTS Response Time CP-202000305, (CPNPP) - Exigent License Amendment Request (LAR) 20-002 Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water2020-06-24024 June 2020 (CPNPP) - Exigent License Amendment Request (LAR) 20-002 Revision to Technical Specification (TS) 3.7.19, Safety Chilled Water TXX-2002, Exigent License Amendment Request (LAR) 20-003 Revision to Technical Specification (TS) 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator Program2020-04-10010 April 2020 Exigent License Amendment Request (LAR) 20-003 Revision to Technical Specification (TS) 5.5.9, Unit 1 Model D76 and Unit 2 Model D5 Steam Generator Program CP-201900368, Revision to Technical Specifications 3.8.1, AC Sources - Operating2020-03-31031 March 2020 Revision to Technical Specifications 3.8.1, AC Sources - Operating CP-202000016, Editorial Correction to License Amendment Request (LAR) 19-002 Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program.2020-01-16016 January 2020 Editorial Correction to License Amendment Request (LAR) 19-002 Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program. CP-201900393, License Amendment Request (LAR) 19-001, Application to Adopt TSTF-513-A, Revision 3, PWR Operability Requirements and Actions for RCS Leakage Instrumentation2019-11-0707 November 2019 License Amendment Request (LAR) 19-001, Application to Adopt TSTF-513-A, Revision 3, PWR Operability Requirements and Actions for RCS Leakage Instrumentation CP-201900415, License Amendment Request (LAR) 19-002, Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2019-11-0707 November 2019 License Amendment Request (LAR) 19-002, Application to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program CP-201800115, License Amendment Request 17-001 Revision to Technical Specification 3.3.2. ESFAS Instrumentation2018-03-29029 March 2018 License Amendment Request 17-001 Revision to Technical Specification 3.3.2. ESFAS Instrumentation ML17074A4942017-04-13013 April 2017 Issuance of Amendment Nos. 168 and 168 Adoption of TSTF-545, Revision 3, TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing ML16351A2002016-12-14014 December 2016 Submittal of License Amendment Request 16-003, Administrative Change to License Name CP-201600216, License Amendment Request 16-001, Application to Revise Technical Specifications to Adopt TSF-545, Revision 3, TS Inservice Testing Program Removal and Clarify SR Usage Rule Application to Section 5.5 Testing.2016-04-27027 April 2016 License Amendment Request 16-001, Application to Revise Technical Specifications to Adopt TSF-545, Revision 3, TS Inservice Testing Program Removal and Clarify SR Usage Rule Application to Section 5.5 Testing. CP-201501062, ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments2015-11-12012 November 2015 ISFSI - Application for Order Approving Transfer of Licenses and Conforming License Amendments CP-201400165, (CPNPP) - Redacted Version of License Amendment Request (LAR) 13-003, for Approval of the Revised CPNPP Cyber Security Plan Implementation Schedule2014-02-0404 February 2014 (CPNPP) - Redacted Version of License Amendment Request (LAR) 13-003, for Approval of the Revised CPNPP Cyber Security Plan Implementation Schedule CP-201301322, License Amendment Request (LAR) 13-003, for Approval of the Revised CPNPP Cyber Security Plan Implementation Schedule2013-11-21021 November 2013 License Amendment Request (LAR) 13-003, for Approval of the Revised CPNPP Cyber Security Plan Implementation Schedule CP-201301065, Revision to Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item Improvement Process2013-08-29029 August 2013 Revision to Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item Improvement Process CP-201300738, License Amendment Request 13-002, Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item..2013-07-10010 July 2013 License Amendment Request 13-002, Application to Revise Technical Specifications to Adopt TSTF-510, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection, Using the Consolidated Line Item.. CP-201300257, License Amendment Request (LAR) 13-01, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.3, Fuel Storage, and 5.5 Programs & Manuals.2013-03-28028 March 2013 License Amendment Request (LAR) 13-01, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage, 4.3, Fuel Storage, and 5.5 Programs & Manuals. CP-201300083, License Amendment Request 12-06, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage and 5.5 Programs and Manuals.2013-01-15015 January 2013 License Amendment Request 12-06, Revision to Technical Specifications 3.7.16, Fuel Storage Pool Boron Concentration, 3.7.17, Spent Fuel Assembly Storage and 5.5 Programs and Manuals. CP-201200518, License Amendment Request (LAR) 12-004, Revision to Technical Specification 3.8.1, Ac Sources - Operating, for Two, 14-Day Completion Times for Offsite Circuits2012-10-0202 October 2012 License Amendment Request (LAR) 12-004, Revision to Technical Specification 3.8.1, Ac Sources - Operating, for Two, 14-Day Completion Times for Offsite Circuits CP-201200552, License Amendment Request (LAR) 2012-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-12012-07-12012 July 2012 License Amendment Request (LAR) 2012-001, Revision to Technical Specification 5.7, High Radiation Area and Technical Specifications Table 3.3.3-1 CP-201200012, (Cpnpp), Revision to Technical Specification (TS) 5.5.9, Unit 1 D76 and Unit 2 D5 Steam Generator (SG) Program, and TS 5.6.9, Unit 1 D76 and Unit 2 D5 Steam Generator Tube Inspection Report, for a Permanent ....2012-03-28028 March 2012 (Cpnpp), Revision to Technical Specification (TS) 5.5.9, Unit 1 D76 and Unit 2 D5 Steam Generator (SG) Program, and TS 5.6.9, Unit 1 D76 and Unit 2 D5 Steam Generator Tube Inspection Report, for a Permanent .... CP-201101038, License Amendment Request (LAR) 11-001, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled2011-08-0101 August 2011 License Amendment Request (LAR) 11-001, Application for Technical Specification Change Regarding Risk-Informed Justification for the Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled 2024-01-31
[Table view] |
Text
11 Rafael Flores Luminant Power Senior Vice President P.O. Box 1002
& Chief Nuclear Officer 6322 North FM 56 rafael.flores@luminant.com Glen Rose, TX 76043 Lum inant T 254 897 5590 C 8175590403 F 254 897 6652 CP-201200552 Ref: 10 CFR 50.90 TXX-12092 July 12, 2012 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT (CPNPP)
DOCKET NOS. 50-445 AND 50-446 LICENSE AMENDMENT REQUEST (LAR)12-001, REVISION TO TECHNICAL SPECIFICATION 5.7, "HIGH RADIATION AREA" AND TECHNICAL SPECIFICATIONS TABLE 3.3.3-1"
Dear Sir or Madam:
Pursuant to 10CFR50.90, Luminant Generation Company LLC (Luminant Power) hereby requests an amendment to the CPNPP Unit I Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89) by incorporating the attached change into the Comanche Peak Nuclear Power Plant (CPNPP)
Unit 1 and 2 Technical Specifications. This change request applies to both Units.
The proposed change will revise Technical Specifications 5.7.1 entitled "High Radiation Areas with Dose Rates not Exceeding 1.0 rem/hour at 30 Centimeters from the Radiation Source or from any Surface Penetrated by the Radiation." This License Amendment Request proposes to allow entry into High Radiation Areas by personnel continuously escorted by individuals qualified in radiation protection procedures. Also, the proposed change will incorporate an unrelated editorial change to Table 3.3.3-1. provides a detailed description of the proposed changes, a technical analysis of the proposed changes, Luminant Power's determination that the proposed changes do not involve a significant hazard consideration, a regulatory analysis of the proposed changes, and an environmental evaluation. Attachment 2 provides the affected Technical Specification pages marked-up to reflect the proposed changes. Attachment 3 provides retyped Technical Specification pages for review. These changes will be processed per CPNPP site procedures.
Luminant Power requests approval of the proposed License Amendment by July 15, 2013, to be implemented within 120 days of the issuance of the license amendment. The approval date was administratively selected to allow for NRC review, but the plant does not require this amendment to allow continued safe full power operations.
A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway - Comanche Peak
- Diablo Canyon - Palo Verde - San Onofre
- South Texas Project - Wolf Creek 40c)
Nuclear Regulatory Commission 07/12/2012 TXX-12092 Page 2 of 2 In accordance with 10CFR50.91(b), Luminant Power is providing the State of Texas with a copy of this proposed amendment.
This communication contains no new or revised commitments.
Should you have any questions, please contact Mr. Steve Dixon at (254) 897-5482.
I state under penalty of perjury that the foregoing is true and correct.
Executed on July 12, 2012, Sincerely, Luminant Generation Company, LLC Rafael Flores By: FIŽW 2f2' ,h.&
Ffd W. Madden Director, Oversight and Regulatory Affairs Attachments 1. Description and Assessment
- 2. Proposed Technical Specifications Changes (Marked Up Pages)
- 3. Retyped Technical Specification Pages (for information) c - E. E. Collins, Region IV W. C. Walker, Region IV B. K. Singal, NRR Resident Inspectors, CPNPP Alice Hamilton Rogers, P.E.
Inspection Unit Manager Texas Department of State Health Services Mail Code 1986 P. 0. Box 149347 Austin TX 78714-9347 A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Callaway
- Comanche Peak - Diablo Canyon
- South Texas Project Wolf Creek
ATTACHMENT 1 to TXX-12092 DESCRIPTION AND ASSESSMENT
Attachment i to TXX-12092 Page 2 of 7 07/12/2012 LICENSEE'S EVALUATION
1.0 DESCRIPTION
2.0 PROPOSED CHANGE
3.0 BACKGROUND
4.0 TECHNICAL ANALYSIS
5.0 REGULATORY ANALYSIS
5.1 No Significant Hazards Consideration 5.2 Applicable Regulatory Requirements/Criteria
6.0 ENVIRONMENTAL CONSIDERATION
7.0 PRECEDENTS
8.0 REFERENCES
Attachment I to TXX-12092 Page 3 of 7 07/12/2012
1.0 DESCRIPTION
By this letter, Luminant Generation Company LLC (Luminant Power) requests an amendment to the CPNPP Unit I Operating License (NPF-87) and CPNPP Unit 2 Operating License (NPF-89) by incorporating the attached change into the CPNPP Unit 1 and 2 Technical Specifications.
Proposed change LAR 12-001 is a request to revise Technical Specifications (TS) 5.7.1, "High Radiation Area" for Comanche Peak Nuclear Power Plant (CPNPP) Units 1 and 2. Also, the proposed change would correct an error in the the column header of Table 3.3.3-1.
No changes to the CPNPP Final Safety Analysis report are anticipated at this time as a result of this License Amendment Request. Luminant Power requests approval of the proposed License Amendment by July 15, 2013, to be implemented within 120 days of the issuance of the license amendment.
2.0 PROPOSED CHANGE
The proposed change would revise TS 5.7.1e to allow access to high radiation areas by personnel under continuous escort by personnel qualified in radiation protection procedures. This proposed change is consistent with the entry requirements of TS 5.7.2 e and would ease potential restrictions on emergency responders who could require entry into a high radiation area. The change to Table 3.3.3-1 will incorporate an editorial correction.
TS 5.7.1e currently states:
"e. Except for individuals qualified in radiation protection procedures, entry into such areas shall be made only after dose rates in the area have been determined and entry personnel are knowledgeable of them."
TS 5.7.1e would be revised as follows:
"e. Except for individuals qualified in radiation protection procedures, or personnel continuously escorted by such individuals, entry into such areas shall be made only after dose rates have been determined and entry personnel are knowledgeable of them."
Table 3.3.3-1 currently states:
"Condition Referenced from Required Action E.1."
Table 3.3.3-1 would be revised to state:
"Condition Referenced from Required Action D.1."
In summary, the proposed change to TS 5.7.1e ensures that entry into high radiation areas with dose rates not exceeding 1.0 rem/hour is not more restrictive than entry into high radiation areas with dose rates greater than 1.0 rem/hour and corrects the error in Table 3.3.3-1 colunu information.
to TXX-12092 Page 4 of 7 07/12/2012
3.0 BACKGROUND
On May 21, 1991, the NRC issued a revision to its standards for protection against ionizing radiation, 10CFR20. The purpose of the revision was to modify the Radiation Protection Standards to reflect developments in the principles and scientific knowledge underlying radiation protection. The new 10CFR20 became effective on June 20, 1991 and required implementation on or before January 1, 1994. The new 10CFR20 regulations were programmatically implemented at CPNPP effective January 1, 1993.
On May 15, 1997, Luminant requested and was granted License Amendment 64 which implemented the Improved Technical Specifications. This License Amendment provided high radiation area access control alternatives pursuant to 10 CFR 20.203(c)(2) and met the requirements in 10 CFR Part 20 and the guidance in NRC RG 8.3.8, on such access controls.
The proposed change to TS 5.7.1 is being requested by Luminant to facilitate entry into High Radiation Areas with dose rates not exceeding 1.0 rem/hour by individuals under the continuous escort of personnel qualified in radiation protection procedures. This option for entry is currently stated in TS section 5.7.2 concerning entry into High Radiation Areas with dose rates greater than 1.0 rem/hour. This requested change will correct this inconsistency in control of radiation areas.
4.0 TECHNICAL ANALYSIS
In May, 2006, the Nuclear Regulatory Commission issued Regulatory Guide 8.38, "Control of Access to High and Very High Radiation Areas in Nuclear Power Plants." In section 2.4 of the Regulatory Guide, the following methods of controlling access to these areas were deemed acceptable by the NRC staff:
"Each high radiation area, as defined in 10 CFR Part 20, should be barricaded and conspicuously posted as a high radiation area, and entrance thereto should be controlled by requiring issuance of an RWP or equivalent. Individuals trained and qualified in radiation protection procedures (e.g., a health physics technician) or personnel continuously escorted by such individuals may be exempted from this RWP requirement while performing their assigned duties in high radiation areas where radiation doses could be received that are equal to or less than 1.0 rem (0.01 Sv) in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> [measured at 30 centimeters (11.8 in.) from any source of radiation] provided that they are otherwise following plant radiation protection procedures, or a general radiation protection RWP, for entry into such high radiation areas. Any individual or group of individuals permitted to enter such areas should be provided with or accompanied by one or more of the following:
(1) a radiation monitoring device that continuously indicates the radiation dose rate in the area (2) a radiation monitoring device that continuously integrates the radiation dose rate in the area and alarms when a preset integrated dose is received; entry into such areas with this monitoring device may be made after the dose rates in the area have been determined and personnel have been made knowledgeable of them (3) an individual qualified in radiation protection procedures with a radiation dose rate monitoring device; this individual is responsible for providing positive radiation protection control over the activities within the area and should perform periodic radiation surveillance at the frequency specified in the radiation protection procedures or the applicable RWP."
CPNPP is requesting this change to the Technical Specifications to align the entry requirements
Attachment I to TXX-12092 Page 5 of 7 07/12/2012 with the allowed control methods of Regulatory Guide 8.38.
5.0 REGULATORY ANALYSIS
5.1 No Significant Hazards Consideration Luminant Power has evaluated whether or not a significant hazards consideration is involved with the proposed amendment(s) by focusing on the three standards set forth in 10CFR50.92, "Issuance of amendment," as discussed below:
- 1. Do the proposed changes involve a significant increase in the probability or consequences of an accident previously evaluated?
Response: No The proposed change to the Technical Specifications has no impact on accident initiation or mitigation. Therefore, the proposed changes do not involve a significant increase in the probability or consequences of an accident previously evaluated.
- 2. Do the proposed changes create the possibility of a new or different kind of accident from any accident previously evaluated?
Response: No The proposed change to the Technical Specifications has no impact on accident initiation or mitigation. Therefore, the proposed change does not create the possibility of a new or different kind of accident from any previously evaluated.
- 3. Do the proposed changes involve a significant reduction in a margin of safety?
Response: No The proposed change to the Technical Specifications has no impact on accident initiation or mitigation. The proposed change will allow for the positive radiation protection control of activities in High Radiation Areas. This is consistent with the requirements of 10CFR20.1601(a) and 10CFR20.1601(c).
Therefore the proposed change does not involve a reduction in a margin of safety.
Based on the above evaluations, Luminant Power concludes that the proposed amendment(s) present no significant hazards under the standards set forth in 10CFR50.92(c) and, accordingly, a finding of no significant hazards consideration is justified.
5.2 Applicable Regulatory Requirements/Criteria 10CFR20.1601 describes the applicable regulatory requirements associated with the proposed amendment. 10CFR20.1601 states:
"(a) The licensee shall ensure that each entrance or access point to a high radiation area has one or more of the following features--
Attachment I to TXX-12092 Page 6 of 7 07/12/2012 (1) A control device that, upon entry into the area, causes the level of radiation to be reduced below that level at which an individual might receive a deep-dose equivalent of 0.1 rem (1 mSv) in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> at 30 centimeters from the radiation source or from any surface that the radiation penetrates; (2) A control device that energizes a conspicuous visible or audible alarm signal so that the individual entering the high radiation area and the supervisor of the activity are made aware of the entry; or (3) Entryways that are locked, except during periods when access to the areas is required, with positive control over each individual entry.
(b) In place of the controls required by paragraph (a) of this section for a high radiation area, the licensee may substitute continuous direct or electronic surveillance that is capable of preventing unauthorized entry.
(c) A licensee may apply to the Commission for approval of alternative methods for controlling access to high radiation areas.
(d) The licensee shall establish the controls required by paragraphs (a) and (c) of this section in a way that does not prevent individuals from leaving a high radiation area.
(e) Control is not required for each entrance or access point to a room or other area that is a high radiation area solely because of the presence of radioactive materials prepared for transport and packaged and labeled in accordance with the regulations of the Department of Transportation provided that--
(1) The packages do not remain in the area longer than 3 days; and (2) The dose rate at 1 meter from the external surface of any package does not
. exceed 0.01 rem (0.1 mSv) per hour.
(f) Control of entrance or access to rooms or other areas in hospitals is not required solely because of the presence of patients containing radioactive material, provided that there are personnel in attendance who will take the necessary precautions to prevent the exposure of individuals to radiation or radioactive material in excess of the limits established in this part and to operate within the ALARA provisions of the licensee's radiation protection program."
CPNPP is requesting this License Amendment Request under the requirements of 10CFR20.1601 (b) and (c) listed above.
In conclusion, based on the considerations discussed above, (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) such activities will be conducted in compliance with the Commission's regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
6.0 ENVIRONMENTAL CONSIDERATION
The proposed amendment is confined to (i) changes to surety, insurance, and/or indemnity requirements, or (ii) changes to recordkeeping, reporting, or administrative procedures or requirements. Accordingly, the proposed amendment meets the eligibility criterion for categorical exclusion set forth in 10CFR51.22(c)(10). Therefore, pursuant to 10CFR51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the proposed amendment.
Attachment I to TXX-12092 Page 7 of 7 07/12/2012 7.0 PRECEDENTS 7.1 On January 4, 2010, the NRC approved and issued License Amendment No. 241 to the Facility Operating License for the Vermont Yankee Nuclear Power Station to revise the Technical Specifications that governs the administrative controls of High Radiation Areas (HRA) to incorporate the HRA administrative controls contained within the Standard Technical Specifications, NUREG 1433, Revision 3.
7.2 On June 27, 2002, the NRC approved and issued License Amendment No. 58 to the Facility Possession Only License for the Three Mile Island Nuclear Station, Unit 2 to revise the referenced control requirements for access to high radiation areas with the actual requirements of 10CFR20.
8.0 REFERENCES
8.1 Regulatory Guide 8.38, "Control of Access to High and Very High Radiation Areas in Nuclear Power Plants."
8.2 10 CFR Part 20 - Standards for Protection Against Radiation 8.3 Standard Technical Specifications, NUREG 1433, Revision 3
ATTACHMENT 2 to TXX-12092 PROPOSED TECHNICAL SPECIFICATION CHANGES (MARK-UP)
Pages 3.3-37 5.7-2
PAM Instrumentation 3.3.3 Table 3.3.3-1 (page 1 of 1)
Post Accident Monitoring Instrumentation CONDITION REFERENCED FROM FUNCTION REQUIRED CHANNELS REQUIRED ACTION E-.1
- 1. Refueling Water Storage Tank Level 2 E
- 2. Subcooling Monitors 2 E
- 3. Reactor Coolant System (RCS) Hot Leg 1 per loop E Temperature (Wide Range) (Thot)
- 4. RCS Cold Leg Temperature (Wide Range) 1 per loop E (Tcold)
- 5. RCS Pressure (Wide Range) 2 E
- 6. Reactor Vessel Water Level 2 (a)
F
- 7. Containment Sump Water Level (Wide Range) 2 E
- 8. Containment Pressure (Intermediate Range) 2 E
- 9. Steam Line Pressure 2 per steam line E
- 10. Containment Area Radiation (High Range) 2 F
- 11. Deleted
- 12. Pressurizer Water Level 2 E
- 13. Steam Generator Water Level (Narrow Range) 2 per steam generator E
- 14. Condensate Storage Tank Level 2 E
- 15. Core Exit Temperature - Quadrant 1 2 (c) E
- 16. Core Exit Temperature - Quadrant 2 2 (c) E
- 17. Core Exit Temperature - Quadrant 3 2 (c)
E
- 18. Core Exit Temperature - Quadrant 4 2(c) E
- 19. Auxiliary Feedwater Flow
- a. AFW Flow 2 per steam generator E OR
- b. AFW Flow and Steam Generator Water 1 each per steam E Level (Wide Range) generator (a) A channel is eight sensors in a probe. A channel is OPERABLE if four or more sensors, one or more in the upper section and three or more in the lower section, are OPERABLE.
(b) Deleted (c) A channel consists of two core exit thermocouples (CETs).
COMANCHE PEAK - UNITS 1 AND 2 3.3-37 Amendment No. 150
High Radiation Area 5.7 5.7 High Radiation Area 5.7.1 Hiah Radiation Areas with Dose Rates not Exceeding 1.0 rem/hour at 30 Centimeters from the Radiation Source or from any Surface Penetrated by the Radiation (continued) or personnel ii. Be under the surveillance as specified in the RWP or cequivalent, while in the area, by means of closed circuit continuously - television, of personnel qualified in radiation protection escorted by such pro s, responsible for controlling personnel radiation individuals, exposure in t and with the means to communicate with individuals in the area w overed by such surveillance.
- e. Except for individuals qualified in radiation protection procedur , entry into such areas shall be made only after dose rates in the area have been determined and entry personnel are knowledgeable of them.
5.7.2 High Radiation Areas with Dose Rates Greater than 1.0 rem/hour at 30 Centimeters from the Radiation Source or from any Surface Penetrated by the Radiation, but less than 500 rads/hour at 1 Meter from the Radiation Source or from any Surface Penetrated by the Radiation:
- a. Each entryway to such an area shall be conspicuously posted as a high radiation area and shall be provided with a locked or continuously guarded door or gate that prevents unauthorized entry, and, in addition:
- 1. All such door and gate keys shall be maintained under the administrative control of the [shift manager], or his or her designee.
- 2. Doors and gates shall remain locked except during periods of personnel or equipment entry or exit.
- b. Access to, and activities in, each such area shall be controlled by means of an RWP or equivalent that includes specification of radiation dose rates in the immediate work area(s) and other appropriate radiation protection equipment and measures.
- c. Individuals qualified in radiation protection procedures may be exempted from the requirement for an RWP or equivalent while performing radiation surveys in such areas provided that they are otherwise following plant radiation protection procedures for entry to, exit from, and work in such areas.
- d. Each individual or group entering such an area shall possess:
- 1. A radiation monitoring device that continuously integrates the radiation rates in the area and alarms when the device's dose alarm setpoint is reached, with an appropriate alarm setpoint, or COMANCHE PEAK - UNITS 1 AND 2 5.7-2 Amendment No. 150
ATTACHMENT 3 to TXX-12092 RETYPED TECHNICAL SPECIFICATION PAGES Pages 3.3-37 5.7-2
PAM Instrumentation 3.3.3 Table 3.3.3-1 (page 1 of 1)
Post Accident Monitoring Instrumentation CONDITION REFERENCED FROM FUNCTION REQUIRED CHANNELS REQUIRED ACTION D.1
- 1. Refueling Water Storage Tank Level 2 E
- 2. Subcooling Monitors 2 E
- 3. Reactor Coolant System (RCS) Hot Leg 1 per loop E Temperature (Wide Range) (Thot)
- 4. RCS Cold Leg Temperature (Wide Range) 1 per loop E (Tcold)
- 5. RCS Pressure (Wide Range) 2 E
- 6. Reactor Vessel Water Level 2(a) F
- 7. Containment Sump Water Level (Wide Range) 2 E
- 8. Containment Pressure (Intermediate Range) 2 E
- 9. Steam Line Pressure 2 per steam line E
- 10. Containment Area Radiation (High Range) 2 F
- 11. Deleted
- 12. Pressurizer Water Level 2 E
- 13. Steam Generator Water Level (Narrow Range) 2 per steam generator E
- 14. Condensate Storage Tank Level 2 E
- 15. Core Exit Temperature - Quadrant 1 2 (c) E
- 16. Core Exit Temperature - Quadrant 2 2 (c) E
- 17. Core Exit Temperature - Quadrant 3 2(c) E
- 18. Core Exit Temperature - Quadrant 4 2(c) E
- 19. Auxiliary Feedwater Flow
- a. AFW Flow 2 per steam generator E OR
- b. AFW Flow and Steam Generator Water 1 each per steam E Level (Wide Range) generator (a) A channel is eight sensors in a probe. A channel is OPERABLE if four or more sensors, one or more in the upper section and three or more in the lower section, are OPERABLE.
(b) Deleted (c) A channel consists of two core exit thermocouples (CETs).
COMANCHE PEAK- UNITS 1 AND 2 3.3-37 Amendment No. 4&G-,
High Radiation Area 5.7 5.7 High Radiation Area 5.7.1 High Radiation Areas with Dose Rates not Exceeding 1.0 rem/hour at 30 Centimeters from the Radiation Source or from any Surface PFenetrated by the Radiation (continued) ii. Be under the surveillance as specified in the RWP or equivalent, while in the area, by means of closed circuit television, of personnel qualified in radiation protection procedures, responsible for controlling personnel radiation exposure in the area, and with the means to communicate with individuals in the area who are covered by such surveillance.
- e. Except for individuals qualified in radiation protection procedures, or personnel continuously escorted by such individuals, entry into such areas shall be made only after dose rates in the area have been determined and entry personnel are knowledgeable of them.
5.7.2 High Radiation Areas with Dose Rates Greater than 1.0 rem/hour at 30 Centimeters from the Radiation Source or from any Surface Penetrated by the Radiation, but less than 500 rads/hour at 1 Meter from the Radiation Source or from any Surface Penetrated by the Radiation:
- a. Each entryway to such an area shall be conspicuously posted as a high radiation area and shall be provided with a locked or continuously guarded door or gate that prevents unauthorized entry, and, in addition:
- 1. All such door and gate keys shall be maintained under the administrative control of the [shift manager], or his or her designee.
- 2. Doors and gates shall remain locked except during periods of personnel or equipment entry or exit.
- b. Access to, and activities in, each such area shall be controlled by means of an RWP or equivalent that includes specification of radiation dose rates in the immediate work area(s) and other appropriate radiation protection equipment and measures.
- c. Individuals qualified in radiation protection procedures may be exempted from the requirement for an RWP or equivalent while performing radiation surveys in such areas provided that they are otherwise following plant radiation protection procedures for entry to, exit from, and work in such areas.
- d. Each individual or group entering such an area shall possess:
- 1. A radiation monitoring device that continuously integrates the radiation rates in the area and alarms when the device's dose alarm setpoint is reached, with an appropriate alarm setpoint, or COMANCHE PEAK - UNITS 1 AND 2 5.7-2 Amendment No. 4,50-,