Finding | |
---|---|
Title | Failure to Adequately Plan and Control Work Activities to Maintain ALARA |
Description | The inspector reviewed a self-revealing finding of very low safety significance because during the refueling outage 18 extended power upgrade, the licensee did not adequately plan and control work activities for the design and replacement of the new fuel pool cooling heat exchangers. Specifically, outage personnel did not perform adequate pre-outage walkdowns, which resulted in significant unplanned collective exposure. Actual collective dose and hours for Radiation Work Permit 2012-1086, Fuel Pool Cooling & Cleanup Heat Exchanger Replacement, was 23.9 person-rem and 12,237 RWP-hours, respectively. This is compared to the initial planned estimate of 3.74 person-rem and 1,905 RWP-hours. This finding and procedural concern was entered into the corrective action program as Condition Reports CR-GGNS-2012-09011 and CR-GGNS-2012-12398. The failure to appropriately use ALARA planning and controls procedures to prevent unplanned and unintended collective doses was a performance deficiency. This performance deficiency was more than minor because it affected the Occupational Radiation Safety Cornerstone attribute of Program and Process in that the failure to adequately implement ALARA procedures caused the collective radiation dose for the job activity to exceed the planned dose by more than 50 percent. In addition, this type of issue is addressed in Example 6.j of IMC 0612, Appendix E, Examples of Minor Issues. Using the Occupational Radiation Safety Significance Determination Process, the inspector determined this performance deficiency to be a finding of very low safety significance because although it involved ALARA planning and controls, the licensee s latest rolling three-year average does not exceed 240 person-rem. This finding has a cross-cutting aspect in the human performance area, work control component, because the licensee failed to evaluate the impact of work scope change on human performance and interdepartmental communication and coordination prior to commencing work activities. Specifically, there was inappropriate coordination and communication of work activities between work groups |
Site: | Grand Gulf |
---|---|
Report | IR 05000416/2012005 Section 2RS2 |
Date counted | Dec 31, 2012 (2012Q4) |
Type: | Finding: Green |
cornerstone | Or Safety |
Identified by: | Self-revealing |
Inspection Procedure: | IP 71124.02 |
Inspectors (proximate) | B Rice D Proulx G George J Laughlin L Carson N Okonkwo R Kumana R Smith S Achen S Makord Proulxg George J Laughlin L Carson N Okonkwo R Kumana R Smith S Achen S Makor B Rice |
CCA | H.5, Work Management |
INPO aspect | WP.1 |
' | |