05000387/FIN-2013003-02
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | |
Description | Inspectors identified a Green NCV of 10 CFR 50, Appendix B, Criterion XI, Test Control, because PPL staff performed unacceptable preconditioning by performing corrective maintenance prior to recording the as-found time response of the reactor protection system (RPS) and end-of-cycle recirculation pump trip (EOC-RPT) for the turbine control valve (TCV) fast closure function. Specifically, corrective maintenance was performed with the potential to improve the time response of the system without verifying that the as-found condition was within the acceptance criteria assumed in the accident analysis. PPL entered the issue into their CAP as CR 1712564 and verified as-left data was verified to be within acceptance criteria which provided reasonable assurance that the SSC would perform satisfactorily during the subsequent operational period. Inspectors determined the performance deficiency is more than minor because it was associated with the equipment performance attribute of the Mitigating Systems cornerstone and affected the objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences (i.e., core damage). Specifically, the failure to collect as-found data could result in the inability to verify the operability of structures, systems, and components (SSC). Additionally, in this case, the test had exhibited low margin and unreliable performance during its previous surveillance test. The inspectors determined, through a review of IMC 0609, Appendix A, Exhibit 2, that the finding was Green because the finding was not related to a design or qualification deficiency, did not represent a loss of a mitigating system safety function, and did not screen as potentially risk significant due to external initiating events. The finding is related to the cross-cutting area of PI&R, CAP, in that PPL did not take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. Specifically, though degraded performance was identified during previous testing, PPL staff did not take timely and effective corrective actions to ensure the required maintenance did not unacceptably precondition the following 24-month surveillance test. |
Site: | Susquehanna |
---|---|
Report | IR 05000387/2013003 Section 1R15 |
Date counted | Jun 30, 2013 (2013Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71111.15 |
Inspectors (proximate) | J Greives A Bolger M Gray F Arner J Laughlin P Finney D Orr S Barber R Rolph D Dodson |
Violation of: | 10 CFR 50 Appendix B Criterion XI |
CCA | P.3, Resolution |
INPO aspect | PI.3 |
' | |
Finding - Susquehanna - IR 05000387/2013003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Susquehanna) @ 2013Q2
Self-Identified List (Susquehanna)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||