IR 05000388/2013009
| ML13092A011 | |
| Person / Time | |
|---|---|
| Site: | Susquehanna |
| Issue date: | 04/01/2013 |
| From: | Darrell Roberts Division Reactor Projects I |
| To: | Rausch T Susquehanna |
| gray, mel | |
| References | |
| IR-13-009 | |
| Download: ML13092A011 (3) | |
Text
April 1, 2013
SUBJECT:
ASSESSMENT FOLLOW-UP LETTER SUSQUEHANNA STEAM ELECTRIC STATION, UNlT 2 (05000388/2013009)
Dear Mr. Rausch:
As a result of its continuous review of plant performance, the U. S. Nuclear Regulatory Commission (NRC) updated its assessment of Susquehanna Steam Electric Station (Susquehanna) Unit 2. The NRCs evaluation consisted of a review of performance indicators and inspection results. This letter informs you of the NRCs assessment of and its plans for a future inspection at your facility. This letter supplements, but does not supersede, the annual assessment letter issued on March 4, 2013.
As discussed in the annual assessment letter, the NRC determined the performance of Susquehanna Unit 2 during 2012 was within the Licensee Response column of the NRCs Reactor Oversight Process (ROP) Action Matrix. Subsequently on March 20, 2013, PPL staff submitted a revision for the Unplanned Scrams with Complications Performance Indicator (PI).
The revision reported the December 16, 2012 automatic plant shutdown (scram) as complicated because operators re-entered emergency operating procedures after the scram had occurred.
The NRCs review of Susquehanna Unit 2 identified the revised Unplanned Scrams with Complications PI crossed the green-to-white threshold (i.e., greater than one complicated scram). Specifically, Unit 2 had complicated scrams on November 9, 2012 and December 16, 2012. As a result, the NRC revised its assessment of Susquehanna Unit 2 to conclude that during the fourth quarter 2012, performance of Susquehanna Unit 2 is in the Regulatory Response column of the NRCs ROP Action Matrix because the Unplanned Scrams with Complications PI is in the white band. Therefore, the NRC plans to schedule and perform a supplemental inspection using Inspection Procedure (IP) 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area. The NRC requests that your staff provide notification of your readiness for the NRC to conduct this supplemental inspection.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Mr. Mel Gray at 610-337-5209 with any questions you have regarding this letter.
Sincerely,
/RA/
Darrell J. Roberts, Director Division of Reactor Projects
Docket Nos.
50-388 License No.
cc: Distribution via ListServ
ML13092A011 SUNSI Review
Non-Sensitive
Sensitive
Publicly Available
Non-Publicly Available
OFFICE RI/DRP RI/DRP RI/DRP
NAME JAyala/JA MGray/MG DRoberts/DJR
DATE 03/26/13 03/26/13 04/01/13