05000368/FIN-2014005-01
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Failure to Develop Adequate Guidance for Extreme Damage Mitigation |
| Description | The inspectors identified a noncited violation of 10 CFR 50.54(hh)(2) for the failure to develop mitigating strategy guidance that would successfully maintain or restore Unit 2 core cooling after the loss of large areas of the plant. Specifically, the guidance did not ensure the capability of the mitigating strategy because an unisolated flow diversion could have prevented water from reaching the steam generators and cooling the core. The issue was documented in Condition Report CR-ANO-2-2014-03277, and the procedure was revised to correct the condition. The licensees failure to develop mitigating strategy guidance that would successfully maintain or restore Unit 2 core cooling after loss of large areas of the plant, as required by 10 CFR 50.54(hh)(2), was a performance deficiency. The performance deficiency was more than minor, and therefore a finding, because it was associated with the procedure quality attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems. Specifically, the guidance did not ensure the capability of the mitigating strategy because an unisolated flow diversion could have prevented water from reaching the steam generators and cooling the core. Using NRC Manual Chapter 0609, Attachment 4, Initial Characterization of Findings, dated June 19, 2012, and NRC Manual Chapter 0609, Appendix L, B.5.b Significance Determination Process, dated December 24, 2009, Table 1, SDP Screening Worksheet for B.5.b, the finding was determined to be of very low safety significance because the performance deficiency represented the unrecoverable unavailability of an individual mitigating strategy; other core cooling mitigating strategies were available. This finding has a human performance crosscutting aspect associated with avoid complacency, in that the licensee failed to recognize and plan for the possibility of latent issues, even while expecting successful outcomes [H.12]. |
| Site: | Arkansas Nuclear |
|---|---|
| Report | IR 05000368/2014005 Section 1R04 |
| Date counted | Dec 31, 2014 (2014Q4) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.04 |
| Inspectors (proximate) | B Tindell G Guerra J Drake J Melfi J Rollins M Young P Elkmann R Lantz S Hedger |
| Violation of: | 10 CFR 50.54 |
| CCA | H.12, Avoid Complacency |
| INPO aspect | QA.4 |
| ' | |