4-9-2007 | On February 9, 2007, SCE concluded that Unit 3 Train B Component Cooling Water ( CCW) system may have been inoperable between November 24, 2006 and December 15, 2006 due to entrained gas. During this period, Unit 3 was being returned to service following a refueling outage.
entered Mode 4 on December 7, 2006. On December 15, 2006, with Unit 3 in Mode 1, plant operators vented CCW Train B returning Train B to operable status. Because this period exceeds the allowable out of service time limit of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> as specified by TS 3.7.7, SCE is reporting this occurrence in accordance with 10CFR50.73(a)(2)(i)(B).
The source of the entrained gas is not yet fully understood and remains under investigation. SCE is continuing to vent the CCW system in both Units to ensure the systems remain operable. |
---|
LER-2006-006, One train of Component Cooling Water considered inoperable for longer than allowed by Technical Specification 3.7.7 due to gas entrainment.Docket Number |
Event date: |
12-15-2006 |
---|
Report date: |
4-9-2007 |
---|
Reporting criterion: |
10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
---|
3622006006R00 - NRC Website |
|
Event Date: December 15, 2006 Reactor Vendor: Combustion Engineering Mode: Mode 1 — Power Operation Power: 0.95 percent
A. BACKGROUND INFORMATION
The Component Cooling Water [CC] (CCW) System consists of two independent critical trains and one non-critical loop (NCL). (Critical trains provide cooling for safety related equipment.) The non critical loop can be aligned to either one of the critical loops. Each CCW train is provided with a dedicated pump and a surge tank. A third, swing pump is also provided and can be aligned to either CCW train. The surge tanks are pressurized with a nitrogen blanket.
Technical Specification (TS) 3.7.7, Component Cooling Water System, requires two trains of CCW to be operable when the plant is in Modes 1-4. When one train is inoperable, the TS require SCE to restore the inoperable train within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, or place the plant in Mode 3 within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and Mode 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. TS Bases B3.7.7 states that in Modes 5 and 6, the operability requirements of the CCW System are determined by the systems it supports.
Consistent with 10 CFR 50, Appendix A, General Design Criteria (GDC) 2 and 44, the design basis of the CCW system includes the requirement to be capable of performing its safety function following a Design Basis Earthquake (DBE) concurrent with a single active failure.
B. DESCRIPTION OF EVENT
On March 8, 2006, during routine activities, engineering personnel observed unexpected changes in the Unit 2 CCW Train A surge tank level indication. SCE's troubleshooting efforts concluded surge tank fluctuations were being caused by entrained gas. SCE initiated periodic venting at Unit 2. At was not affected. As a preventative measure, SCE initiated venting at Unit 3 as well. Venting history is provided in the Additional Information section.
On December 15, 2006, 120 gallons was vented from Unit 3 Train B return from the letdown heat exchanger. As a result, SCE contracted with outside consultants (Fauske and Associates) to analyze the potential effects of the gas on Unit 3 CCW system Train B.
SCE received the Fauske and Associates report on February 9, 2007 [Discovery date]. The consultants' report concluded that due to the location of the bubble, it could potentially migrate with the inadvertent opening of the letdown temperature control valve on the output of the letdown heat exchanger which varies CCW flow through the heat exchanger. They determined that should the following conditions occur:
1) Train B is aligned to the non-critical loop and 2) the non-critical loop becomes isolated and 3) the letdown temperature control valve fails fully open, a gas volume of 120 gallons in Train B could result in a void fraction (VF) at the CCW pump suction of 9 percent for 3.5 seconds (the average VF would be about 6 percent for 7.5 seconds, which is the time required for the void to travel through the pump). Generally accepted industry guidance indicates that a void fraction of about 5-6 percent would not permanently degrade pump performance. Because the calculated void fraction was outside the 5-6 percent range, SCE conservatively concluded that Unit 3 CCW Train B was inoperable from the time it was returned to service in Mode 6 following the cycle 14 refueling outage [November 24, 2006] through the initial start up in Mode 4 [December 7, 2006] until the system was vented [December 11 and December 15, 2006], about 21 days.
TS 3.7.7 requires the CCW system to be operable in modes 1 through 4. Unit 3 entered Mode 4 on December 7, 2006. On December 15, 2006, with Unit 3 in Mode 1, SCE vented CCW Train B returning Train B to operable status. Because this period (about 8 days) exceeds the allowable out of service time limit of TS 3.7.7, SCE is reporting this occurrence in accordance with 10CFR50.73(a)(2)(i)(B).
Cause of the Event:
The CCW system is a closed loop system, pressurized by a nitrogen blanket on the surge tank and treated with corrosion inhibitors. SCE believes gas in the system can most likely be attributed to one of three sources: absorption of the nitrogen blanket into the cooling water, air entrained when the system is open during maintenance, or as a product of a chemical reaction. SCE is investigating each of these sources but has not yet been able to determine definitively the source of the entrained gas and our investigation is ongoing.
Corrective Actions:
SCE has taken and is taking the following interim corrective actions:
1. Operating procedures have been changed to perform daily venting on both trains of Unit 3 and Train A of Unit 2. This action ensures that the systems remain operable. As a conservative measure, Unit 2 Train B is vented periodically.
2. Vent extensions are being added to better quantify venting amounts through a more standardized venting procedure.
3. SCE plans to revise the fill and vent procedure before the next planned outage on Unit 3.
SCE may identify and implement additional corrective actions.
Safety Significance
The SONGS Unit 3 Component Cooling Water system has two independent safety-related trains.
During the time Train B CCW was declared inoperable, Train A remained operable. (Amounts vented from Train A were below the amounts determined to be of concern.) Therefore, Train A was available to provide a heat sink for the removal of process and operating heat from safety related components during a Design Basis Accident or transient.
An assessment of the incremental core damage probability (ICDP) and the incremental large early release probability (ILERP) for the inoperability of Train B CCW determined that the Unit 3 ICDP and ILERP were 5E-7 and 2E-8, respectively. Therefore the safety significance of this event was minimal. The assessment was based on the reported component unavailability and operating NRC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION (7-2001) conditions that existed from the time the train was declared operable on November 24, 2006 through the venting of gas on December 15, 2006.
Additional Information:
Although no abnormal CCW surge tank fluctuations had been observed prior to March 3, 2006, it is uncertain whether a similar condition occurred on Unit 3 or at some time in the past. The CCW system configuration has not been changed for many years. Consequently, it is possible that some gas accumulation has occurred in the past. Because it is not possible to quantify any gas volumes that might have accumulated, their potential effect on system operability cannot be assessed.
Venting History Date Unit 2 Train A Unit 2 Train B Unit 3 Train A Unit 3 Train B 8/03/06-9/29/06 No venting No ventingg 9/29/06-10/17/06 Periodic venting Periodic venting Periodic venting Once (9/29/06) 10/16/06-10/24/06 No venting 10/25/06-11/09/06 Daily venting 11/10/06-11/22/06 Daily venting Refueling Outage 11/23/06-12/15/06 Daily venting No venting 12/15/06-2/28/07 Monthly venting Daily venting Previous Events:
In the past three years, SCE has not reported any occurrences where entrained gas caused a plant system to be considered inoperable.
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|