04-16-2007 | A emergency diesel generator, a previously identified minor fuel oil leak (approximately 1 drop/minute) increased and required an unplanned engine shutdown. The emergency diesel generator had been declared inoperable at the start of the surveillance test and remained so following the leak. At its maximum, the leakrate was estimated at between 0.12 and 0.25 gpm.
By 05:53 on 8/18/06, the leak had been repaired, the surveillance test completed, and the emergency diesel generator restored to OPERABLE status.
The fuel oil leak was initially identified on 6/28/06 at 16:48. Between that initial discovery and the engine shutdown on 8/17/06, the emergency diesel generator had been operated four times with a cumulative run time of approximately 3.9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />.
On 10/26/06, the leak was determined to be from an approximately 350 degree circumferential crack in the copper tubing of the fuel supply line inside a 3/8" fitting to a pressure gauge. On 12/15/06, the cracked tubing was tested on a similar diesel generator. The tubing fully severed after approximately one hour of diesel generator operation at rated load. Thus it is concluded that the EDG was not capable of meeting its design basis between the originally identified leak on 6/28/06 and its return to operability on 8/18/06. |
---|
FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 PAGE (3) Kewaunee Power Station 05000305 YEAR
EVENT DESCRIPTION
At 17:35 on 8/17/06, after approximately 10 minutes of operation during a planned surveillance test on the train A emergency diesel generator (EDG) [DG], a previously identified minor fuel oil leak increased and required an unplanned engine shutdown. The EDG had been declared inoperable at the start of the surveillance test and remained so following the leak. At its maximum, the leakrate was estimated at between 0.12 and 0.25 gpm. The leak did not atomize.
By 05:53 on 8/18/06, the leak had been repaired, the surveillance test completed, and the EDG restored to OPERABLE.
The fuel oil leak (approximately 1 drop/minute) was initially identified on a copper tubing Swagelock fitting (downstream of the engine-driven fuel oil pump [P] and the fuel priming pump), on 6/28/06 and a Work Order was written to repair it. Between initial discovery on 6/28/06 and the engine shutdown on 8/17/06, the EDG had been operated four times with a cumulative run time of approximately 3.9 hours1.041667e-4 days <br />0.0025 hours <br />1.488095e-5 weeks <br />3.4245e-6 months <br />.
On 10/26/06, the leak failure mechanism was determined to be an approximately 350 degree circumferential crack in the copper tubing of the fuel supply line inside a 3/8" fitting to a pressure gauge. On 12/15/06, the cracked tubing was tested on a similar diesel generator. The tubing fully severed after approximately one hour of diesel generator operation at rated load. Thus it is concluded that the EDG was not capable of meeting its design basis between the originally identified leak on 6/28/06 and its return to operability on 8/18/06.
EVENT ANALYSIS
This event is being reported under 10 CFR 50.73(a)(2)(v)(B) and (D) as a condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to remove residual heat and mitigate the consequences of an accident.
This event is also being reported under 10 CFR 50.73(a)(2)(i)(B) as an operation which was prohibited by the plant's Technical Specifications.
The following train B safety equipment was also inoperable between 6/28/06 at 16:48 and 8/18/06 @ 05:53:
Equip Inoperable Operable Duration (hrs) Total (hrs) EDG B 6/29/06 @ 9:27 6/30/06 @ 00:56 15.48 EDG B 7/27/06 @ 7:00 7/27/06 @ 15:49 8.82 29.97 EDG B 8/13/06 @ 8:54 8/13/06 @ 14:34 5.67 SW [BI] Train B 7/23/06 @ 12:30 7/23/06 @ 22:00 9.50 SW Train B 7/26/06 @ 3:47 7/27/06 @ 4:35 24.80 39.77 SW Train B 8/9/06 @ 7:46 8/9/06 @ 11:49 4.05 SW Train B 8/13/06 @ 8:55 8/13/06 @ 10:20 1.42 FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6 PAGE (3) Equip Inoperable Operable Duration (hrs) Total (hrs) RHR [BP] Pmp B 7/13/06 @ 8:43 7/14/06 @ 00:41 15.97 RHR Pump B 7/12/06 @ 15:51 7/12/06 @ 16:33 0.70 RHR Pump B 7/27/06 @ 13:35 7/27/06 @ 16:31 2.93 20.52 RHR Train B 7/12/06 @ 14:54 7/12/06 @ 15:25 0.52 RHR Train B 8/13/06 @ 13:12 8/13/06 @ 13:36 0.4 ICS [BE] Pump B 7/12/06 @ 14:46 7/12/06 @ 15:37 0.85 0.85 SI [BQ] Pump B 7/14/06 @ 1:03 7/14/06 @ 1:04 0.02 1.42 SI Train B 8/10/06 @ 9:41 8/10/06 @ 11:05 1.4 Chg [CB] Pump B 7/11/06 @ 7:04 7/11/06 @ 15:58 8.9 19.3 Chg Pump B 8/8/06 @ 7:09 8/8/06 @ 17:35 10.4 CC [CC] Pump B 7/02/06 @ 10:15 7/02/06 @ 10:30 0.25 CC Pump B 7/28/06 @ 23:40 7/28/06 @ 23:45 0.08 CC Train B 7/30/06 @ 21:39 7/30/06 @ 23:30 1.85 3.98 CC Train B 8/13/06 @ 00:04 8/13/06 @ 00:10 0.10 CC Train B 8/13/06 @ 10:21 8/13/06 @ 12:03 1.7 TDAFW [BA] Pmp 7/3/06 @ 8:58 7/3/06@ 9:07 0.15 TDAFW Pump 7/10/06 @ 9:18 7/10/06 @ 9:26 0.13 0.65 TDAFW Pump 8/3/06 @ 12:32 8/3/06 @ 12:45 0.22 TDAFW Pump 8/7/06 @ 10:24 8/7/06 @ 10:33 0.15 AFW [BA] Pmp B 7/10/06 @ 8:49 7/10/06 @ 8:56 0.12 AFW Train B 7/27/06 @ 10:15 7/27/06 @ 10:45 0.5 2.16 AFW Pump B 8/7/06 @ 10:00 8/7/06 @ 10:07 0.12 AFW Pump 8/13/06 @ 8:55 8/13/06 @ 10:20 1.42 Sfgds [JE] Train B 7/11/06 @ 9:18 7/11/06 @ 11:11 1.88 5.43 Sfgds Train B 8/8/06 @ 9:29 8/8/06 @ 13:02 3.55 With train A EDG inoperable, the plant should have entered Tech Spec LCO 3.7.b.2, which states: "One diesel generator may be inoperable for a period not exceeding 7 days provided the other diesel is tested daily to ensure OPERABILITY and the engineered safety features associated with this diesel generator are OPERABLE." During this event, train A EDG was inoperable in exceess of 7 days and train B EDG was never tested for operability under this LCO.
FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6) PAGE (3) Kewaunee Power Station 05000305 YEAR Exceeding the 7 day LCO for train A EDG, and each of the occasions above involving concurrently inoperable train B engineered safety features, should have resulted in entry into Tech Spec LCO 3.0.c, which did not occur. Tech Spec LCO 3.0.c states:
When a LIMITING CONDITION FOR OPERATION is not met, and a plant shutdown is required except as provided in the associated ACTION requirements, within one hour action shall be initiated to place the unit in a MODE in which the specification does not apply by placing it, as applicable, in:
1. At least HOT STANDBY within the next 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, 2. At least HOT SHUTDOWN within the following 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />, and 3. At least COLD SHUTDOWN within the subsequent 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
SAFETY SIGNIFICANCE
The overall incremental core damage probability (IDCP) for the time period in question is 2.2E-5, which is categorized in the NRC Significance Determination Process as Substantial safety significance.
CAUSE
The direct cause of the leak was determined to be circumferential cracking due to vibration induced fatigue.
The root cause for the event was that critical information was not known by decision makers - as evidenced by the following:
- Failure to initiate a CAP for the initial leak on 6/28/06 (missed opportunity for equipment operability evaluation)
- Training does not cover common industry-known tubing failure mechanisms.
- Managers and supervisors were not knowledgeable of OE from this type of failure event.
- The work request screen team did not walk down the equipment deficiency or recognize the need to do so, and did not communicate the proper sense of urgency to the rest of the organization.
FACILITY NAME (1) DOCKET NUMBER (2) LER NUMBER (6) PAGE (3) Kewaunee Power Station 05000305 YEAR
CORRECTIVE ACTIONS
For the direct cause, the leak was repaired, an operability test was performed, and the EDG was restored to OPERABLE status.
For the root cause, critical information will be made available to decision makers via the following changes:
- New software, (MAXIMO and CRS), will be implemented to ensure equipment issues are always captured within the corrective action system.
0 Until CRS and MAXIMO are implemented, the following interim corrective actions have been taken:
- On a daily basis, Outage and Planning reviews all new work requests to ensure CAPs are written when required.
- If a CAP was not generated, the work request initiator is contacted to write a CAP and include the CAP number on the work request.
- The CAP & Work Order process has been reiterated several times in the following:
- The daily Plan Of the Day meetings
- Material will be added to Lesson Plans to assure workers are aware of failure mechanisms of tubing compression fittings, signs of failure and interpretation of those signs.
- Supervisors and managers will receive training on this event.
- Work request screen team members will receive training on this event.
PREVIOUS SIMILAR EVENTS
sets
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|