At 0651 on May 22, 2006, Service Air ( SA) pressure began lowering for an unknown reason. Additional Service Air Compressors (SAC's) could not be started in time to recover SA pressure. Following a rapid power reduction the reactor was manually scrammed at 0701 as a mitigating action. All automatic systems functioned as expected, and the plant entered and remained in Mode 3, Hot Shutdown. This event was not risk significant. Analysis revealed the most likely cause to be the SAC automatic control system failed to respond to system pressure changes. SAC's were placed in local control mode to operate independently based on individual start-stop-unload setpoints. The plant subsequently started up on May 24, 2006. The cause was a single point failure mode introduced into the newly installed SAC compressor controller that was unrecognized in the design process. A standing order now prevents SAC's from operation in other than local control until an evaluation of failure modes on the automatic control system has been performed. Action remaining includes revising applicable plant configuration change procedures to perform failure mode evaluation for Maintenance Rule ( MR) Risk Significant control systems; revising the SAC operating procedure to normally operate in local mode, except when controlled methods retain at least two SAC's to supply plant air; determining which of the past three years plant modifications require a failure mode evaluation; and performing evaluations for those modifications. |
PLANT STATUS
Cooper Nuclear Station (CNS) was at 100% power in Mode 1 at the time of the event.
BACKGROUND
The Plant Air System is comprised of both the Service Air (SA) System [EIIS:LF] and the Instrument Air (IA) System [EIIS:LD]. SA System includes three air compressors [EllS:CMP], air receivers [EIIS:RCV], and other equipment necessary to generate the compressed air supply to the SA distribution header and the IA Dryers[EllS:DRYJ. Air compressors are rotary type compressors rated to deliver 822 cfm at 125 psig. Each compressor is driven by a 480 VAC motor. Compressors A and B are powered from critical buses and Compressor C is powered from a non-critical bus. The three compressors operate in parallel and one of the three will be available on a demand basis with the other two in standby mode ready to operate as required. Compressor operation is controlled by a control system [EIIS:PMC] that brings additional units on-line when operating units reach a fully loaded condition and there is a further increase in demand. Normally, one air compressor will maintain sufficient pressure in the air receivers to provide the desired instrument air header pressure. The second and third compressors serve as standby units.
Actuation of standby units is automatic.
A plant modification had provided for replacement of antiquated, unreliable reciprocating air compressors to provide air to the Plant Air Systems. In addition, the controls for operation of the air compressors were upgraded to provide higher overall reliability, reduced maintenance labor, and simplified operation. The Plant Air System provides a normal air supply to essential operating instrumentation and valves and serves the operational needs for motive and maintenance air of the plant on a continuous basis.
EVENT DESCRIPTION
At 0651 on May 22, 2006, SA pressure began lowering for an unknown reason. Additional Service Air Compressors (SAC's) could not be started in time to recover SA pressure. A rapid power reduction was performed, and at 0701, the reactor was manually scrammed as a mitigating action due to lowering SA pressure. All control rods fully inserted and a Group 2 isolation occurred due to low Reactor Vessel level as expected immediately following the scram. Minimum reactor level during the scram was noted to be 20 inches below Instrument Zero. Steady shutdown conditions were achieved with reactor level restored to its normal range being controlled by the Feedwater System and reactor pressure at 900 psig being controlled by Steam Bypass Valves to the Main Condenser. All automatic systems functioned as expected, and the plant remained in Mode 3, Hot Shutdown, while the cause of the SA pressure lowering was investigated.
Based on the post-trip analysis of SAC operation, the loss of Plant Air was most likely caused by the integrated portion of the SAC automatic control system failing to respond to system pressure changes.
Consequently, the compressors were placed in local control mode to operate independently based on their individual start-stop-unload setpoints. This results in all 3 air compressors running with "B" SAC loading and unloading to control SA pressure, and with 'A' and 'C' SAC's running unloaded. The plant was subsequently started up on May 24, 2006.
BASIS FOR REPORT
Both the actuation of Reactor Protection System (RPS) and the Group 2 isolation are reportable under 10 CFR 50.73(a)(2)(iv), System Actuation.
SAFETY SIGNIFICANCE
This condition is not risk significant, because design mitigation capabilities dependent on critical air remained available to support safety functions for the duration of the condition and as a result of prompt local operator action to restore air header pressure. In addition, the transition from online full power conditions to shutdown occurred without further equipment or human error complications.
This condition did not challenge a fuel, reactor coolant pressure, primary containment, or secondary containment boundary. The condition did not impact the plant's ability to safely shut down or maintain the reactor in a safe shutdown condition.
Therefore, the impact of this condition is considered negligible. As a result, the event is bounded by the baseline PSA model and has negligible risk significance.
CAUSE
A single point failure mode was introduced into the newly installed compressor controller for the SAC that was unrecognized in the CNS design process.
CORRECTIVE ACTION
The following actions have been completed.
1. SAC control has been placed in local control mode to operate independently based on the individual SAC start-stop-unload setpoints to prevent recurrence of this event.
2. A standing order was put in place on June 29, 2006 that prevents SAC's from being operated in other than local control until an engineering evaluation of failure modes on the automatic control system has been performed. Exceptions are limited to formal troubleshooting or other methods that retain at least 2 SAC's, permanent or temporary, to supply plant air and are not controlled by the automatic control system.
The following corrective actions are being tracked in the CNS corrective action program.
1. Revise applicable CNS configuration and control procedures to perform failure mode evaluation of plant configuration changes for Maintenance Rule Risk Significant control systems. Examples of acceptable methodologies for digital control systems refer to EPRI Topical Reports TR-102348 and TR-108831. Examples of acceptable methodologies for other systems include standard failure mode evaluation assessment, functional fault tree analysis, or cause-consequences analysis.
2. Revise the SAC operating procedure such that the SAC's are normally operated in local mode, except when testing, formal troubleshooting or other controlled methods are used that retain at least two SAC's, permanent or temporary, to supply plant air not controlled by automatic mode.
3. Based upon Maintenance Rule Risk Significance, determine which of the past three years of installed plant modifications require a failure mode evaluation, and perform a failure mode evaluation for those modifications as required.
4. Based upon Maintenance Rule Risk Significance, determine which of the plant modifications currently in work or completed but not installed require a failure mode evaluation, and perform a failure mode evaluation for those modifications as required.
PREVIOUS EVENTS
None
|
---|
|
|
| | Reporting criterion |
---|
05000305/LER-2006-010 | | | 05000456/LER-2006-001 | Unit 1 Reactor Coolant System Pressure Boundary Leakage Due To Inter-Granular Stress Corrosion Cracking of a Pressurizer Heater Sleeve | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded | 05000454/LER-2006-001 | Technical Specification Required Action Completion Time Exceeded for Inoperable Containment Isolation Valves Due to Untimely Operability Determination | | 05000423/LER-2006-001 | Loss Of Safety Function Of The Control Room Emergency Ventilation System | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | 05000369/LER-2006-001 | Ice Condenser and Floor Cooling System Containment Isolation Valve inoperable longer than allowed by Technical Specification 3.6.3. | | 05000353/LER-2006-001 | HPCI Ramp Generator Signal Converter Failure | 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000352/LER-2006-001 | Loss Of One Offsite Circuit Due To Invalid Actuation Of Fire Suppression System | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000336/LER-2006-001 | | 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor | 05000316/LER-2006-001 | Failure to Comply with Technical Specification 3.6.2, Containment Air Locks | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-001 | Plant Shutdown Required by Technical Specification Action 3.6.5.B.1 | | 05000293/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv), System Actuation | 05000289/LER-2006-001 | | | 05000287/LER-2006-001 | Actuation of Emergency Generator due to Spurious Transformer Lockout | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000251/LER-2006-001 | Turkey Point Unit 4 05000251 1 OF 6 | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000247/LER-2006-001 | Manual Reactor Trip Due to Multiple Dropped Control Rods Caused by Loss of Control Rod Power Due to Personnel Error | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000440/LER-2006-001 | Incorrect Wiring in the Remote Shutdown Panel Results in a Fire Protection Program Violation | | 05000413/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000368/LER-2006-001 | Completion of a Plant Shutdown Required by Technical Specifications Due to Loss of Motive Power to Certain Containment Isolation Valves as a Result of a Phase to Ground Short Circuit in a Motor Control Cubicle | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000306/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000298/LER-2006-001 | Cooper Nuclear Station 05000298 1 of 4 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000286/LER-2006-001 | I | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-001 | | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000266/LER-2006-001 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function | 05000261/LER-2006-001 | Manual Reactor Trip Due to Failure of a Turbine Governor Valve Electro-Hydraulic Control Card | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000255/LER-2006-001 | | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000461/LER-2006-002 | Turbine Bypass Function Lost Due to Circuit Card Maintenance Frequency | | 05000458/LER-2006-002 | Loss of Safety Function of High Pressure Core Spray Due to Manual Deactivation | | 05000456/LER-2006-002 | Units 1 and 2 Entry into Limiting Condition for Operation 3.0.3 due to Main Control Room Ventilation Envelope Low Pressure | | 05000443/LER-2006-002 | Noncompliance with the Requirements of Technical Specification 6.8.1.2.a | | 05000387/LER-2006-002 | DMissed Technical Specification surveillance requirement | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000362/LER-2006-002 | Unit 3 Shutdown to Inspect Safety Injection Tank Spiral Wound Gaskets | | 05000336/LER-2006-002 | Manual Reactor Trip Due To Trip Of Both Feed Pumps Following A Loss Of Instrument Air | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000316/LER-2006-002 | | 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000315/LER-2006-002 | Failure to Comply with Technical Specification Requirement 3.6.13, Divider Barrier Integrity | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000293/LER-2006-002 | | | 05000289/LER-2006-002 | | | 05000251/LER-2006-002 | Intermediate Range High Flux Trip Setpoint Exceeded Technical Specification Allowable Value | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000440/LER-2006-002 | Scaffold Built in the Containment Pool Swell Region | 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition | 05000413/LER-2006-002 | Safe Shutdown Potentially Challenged by an External Flooding Event and Inadequate Design and Configuration Control | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000388/LER-2006-002 | Missed Technical Specification LCO 3.8.1 Entry for Unit 2 During Unit 1 ESS Bus Testing | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000348/LER-2006-002 | Main Steam Isolation Valve Failure to Close | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000305/LER-2006-002 | | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000301/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000286/LER-2006-002 | 450 Broadway, GSB P.O. Box 249 Buchanan, N.Y. 10511-0249Entergy Tel (914) 734-6700 Fred Dacimo Site Vice President Administration September 13, 2006 Indian Point Unit No. 3 Docket No. 50-286 N L-06-084 Document Control Desk U.S. Nuclear Regulatory Commission Mail Stop O-P1-17 Washington, DC 20555-0001 Subject:L Licensee Event Report # 2006-002-00, "Manual Reactor Trip as a Result of Arcing Under the Main Generator Between Scaffolding and Phase A&B of the Isophase Bus Housing" Dear Sir: The attached Licensee Event Report (LER) 2006-002-00 is the follow-up written report submitted in accordance with 10 CFR 50.73. This event is of the type defined in 10 CFR 50.73(a)(2)(iv)(A) for an event recorded in the Entergy corrective action process as Condition Report CR-IP3-2006-02255. There are no commitments contained in this letter. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing, Indian Point Energy Center at (914) 734-6668. Fred R. Dacimo Site Vice President Indian Point Energy Center Docket No. 50-286 NL-06-084 Page 2 of 2 Attachment: LER-2006-002-00 CC: Mr. Samuel J. Collins Regional Administrator — Region I U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Resident Inspector's Office Resident Inspector Indian Point Unit 3 Mr. Paul Eddy State of New York Public Service Commission INPO Record Center NRC FORM 366 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES: 06/30/2007
(6-2004)
. Estimated burden per response to comply with this mandatory collection request: 50 hours.DReported lessons learned are incorporated into the licensing process and fed back to industry. Send comments regarding burden estimate to the Records and FOIA/Privacy Service Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internetLICENSEE EVENT REPORT (LER) e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection. ■ 1. FACILITY NAME 2. DOCKET NUMBER I 3. PAGE
INDIAN POINT 3 05000-286 1 OF 6
4.TITLE: Manual Reactor Trip as a Result of Arcing Under the Main Generator Between
Scaffolding and Phase A&B of the Iso-phase Bus Housing | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000282/LER-2006-002 | | 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000269/LER-2006-002 | High Energy Line Breaks Outside Licensing Basis May Result in Loss of Safety Function | | 05000263/LER-2006-002 | | | 05000255/LER-2006-002 | | 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications | 05000254/LER-2006-002 | Quad Cities Nuclear Power Station Unit 1 05000254 1 of 3 | 10 CFR 50.73(a)(2)(iv)(A), System Actuation | 05000483/LER-2006-003 | Unexpected Inoperability of the Emergency Exhaust System due to Inoperable Pressure Boundary | 10 CFR 50.73(a)(2)(v)(C), Loss of Safety Function - Release of Radioactive Material 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications |
|