IR 05000413/2023004 | 2 February 2024 | Integrated Inspection Report 05000413-2023004 and 05000414-2023004 | |
RA-23-0288, End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report | 16 November 2023 | End of Cycle 27 (C1 R27) Steam Generator Tube Inspection Report | Nondestructive Examination |
IR 05000413/2023010 | 11 October 2023 | NRC Inspection Report 05000413/2023010 and 05000414/2023010 | Aging Management Missed surveillance License Renewal Fire Protection Program |
IR 05000413/2023005 | 25 August 2023 | Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2023005 and 05000414/2023005) | |
IR 05000413/2023002 | 25 July 2023 | Integrated Inspection Report 05000413/2023002 and 05000414/2023002 | Boric Acid High Radiation Area Fire Barrier Enforcement Discretion Nondestructive Examination Functionality Assessment Operability Determination Liquid penetrant Fire Protection Program Coast down Unidentified leakage |
IR 05000413/2023001 | 5 May 2023 | Integrated Inspection Report 05000413/2023001 and 05000414/2023001 | Enforcement Discretion Functionality Assessment Condition Adverse to Quality Aging Management Significance Determination Process Operability Determination Fire Protection Program Coast down |
IR 05000413/2023011 | 25 April 2023 | Focused Engineering Inspection Report 05000413/2023011 and 05000414/2023011 | Commercial Grade Dedication |
IR 05000413/2022006 | 1 March 2023 | Annual Assessment Letter for Catawba Nuclear Station, Units 1 and 2 (NRC Inspection Report 05000413/2022006 and 05000414/2022006) | Commercial Grade Dedication Cyber Security License Renewal Exemption Request COVID-19 |
IR 05000413/2023401 | 1 March 2023 | Security Baseline Inspection Report 05000413 2023401 and 05000414 2023401 | |
IR 05000413/2023301 | 17 February 2023 | Operator Licensing Examination Approval 05000413/2023301 and 05000414/2023301 | |
IR 05000413/2022004 | 31 January 2023 | Integrated Inspection Report 05000413/2022004 and 05000414/2022004 | Boric Acid Enforcement Discretion Functionality Assessment Operability Determination |
IR 05000413/2022011 | 15 December 2022 | Biennial Problem Identification and Resolution Inspection Report 05000413/2022011 and 05000414/2022011 | Boric Acid Fitness for Duty Enforcement Discretion |
IR 05000413/2022403 | 17 November 2022 | Cyber Security Inspection Report 05000413/2022403 and 05000414/2022403 (Public) | Cyber Security Affidavit |
IR 05000414/2022003 | 31 October 2022 | Integrated Inspection Report 05000414/2022003 and 05000414/2022003 | Safe Shutdown Boric Acid High Radiation Area Internal Flooding Temporary Modification VT-2 Functionality Assessment Locked High Radiation Area Operability Determination Liquid penetrant Fire Protection Program Power change Siren |
IR 05000413/2022402 | 28 October 2022 | Security Baseline Inspection Report 05000413 2022402 and 05000414 2022402 | |
IR 05000413/2022005 | 26 August 2022 | Updated Inspection Plan for Catawba Nuclear Station, Units 1 and 2 - NRC Inspection Report 05000413/2022005 and 05000414/2022005 | Commercial Grade Dedication Cyber Security License Renewal Exemption Request COVID-19 |
IR 05000413/2022002 | 29 July 2022 | Integrated Inspection Report 05000413/2022002 and 05000414/2022002 | Safe Shutdown Internal Flooding Enforcement Discretion Temporary Modification Functionality Assessment FLEX Operability Determination Fire Protection Program Siren |
IR 07200045/2022001 | 26 July 2022 | Operation of an Independent Spent Fuel Storage Installation Report 07200045/2022001 | |
IR 05000413/2022010 | 21 July 2022 | Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2022010 and 05000414/2022010 | Stroke time Operability Determination Power-Operated Valves Weak link |
IR 05000414/2022001 | 28 April 2022 | Integrated Inspection Report 05000413/ 2022001 and 05000414/2022001 | Enforcement Discretion Met Tower Temporary Modification Functionality Assessment Significance Determination Process Large early release frequency Operability Determination Fire Protection Program Siren |
IR 05000413/2022420 | 7 April 2022 | Security Inspection Report 05000413/2022420 and 05000414/2022420 | |
RA-22-0080, Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System | 7 April 2022 | Independent Spent Fuel Storage Installation, McGuire, Units 1 & 2, Independent Spent Fuel Storage Installation, Request for an Exemption to the Requirements of Certificate of Compliance No. 1031 for the NAC Magnastor Storage System | Tornado Missile Commercial Grade Dedication Condition Adverse to Quality Tornado-Generated Missile Design basis earthquake Exemption Request Liquid penetrant |
IR 05000413/2021006 | 2 March 2022 | Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 (Report 05000413/2021006 and 05000414/2021006) | Cyber Security License Renewal Exemption Request Power-Operated Valves COVID-19 |
IR 05000413/2022401 | 18 February 2022 | Security Baseline Inspection Report 05000413/2022401 and 05000414/2022401 | Affidavit |
IR 05000413/2021004 | 26 January 2022 | Integrated Inspection Report 05000413/2021004 and 05000414/2021004 | Safe Shutdown Boric Acid High Radiation Area Internal Flooding Temporary Modification Functionality Assessment Locked High Radiation Area Aging Management Significance Determination Process Operability Determination License Renewal Liquid penetrant Fire Protection Program |
ML22011A180 | 18 January 2022 | Review of the Spring 2021 Steam Generator Tube Inspection Report | |
IR 05000413/2021301 | 8 November 2021 | Operator Licensing Examination Report 05000413/2021301 and 05000414/2021301 | Job Performance Measure |
IR 05000413/2021402 | 3 November 2021 | Security Baseline Inspection Report 05000413/2021402 and 05000414/2021402 | Contraband |
IR 05000413/2021003 | 28 October 2021 | Integrated Inspection Report 05000413/2021003 and 05000414/2021003 | Safe Shutdown Internal Flooding Enforcement Discretion Temporary Modification Functionality Assessment FLEX Operability Determination Coronavirus COVID-19 Fire Protection Program Power change |
IR 05000413/2021010 | 27 September 2021 | Design Basis Assurance Inspection (Teams) Inspection Report 05000413/2021010 and 05000414/2021010 | Significance Determination Process Large early release frequency Coronavirus COVID-19 |
IR 05000413/2021404 | 26 August 2021 | Material Control and Accounting Program Inspection Report 05000413/2021404 and 05000414/2021404 (OUO Removed) | Affidavit |
IR 05000413/2021002 | 5 August 2021 | Integrated Inspection Report 05000413/2021002 and 05000414/2021002 | Safe Shutdown Boric Acid Temporary Modification Functionality Assessment Aging Management Process Control Program Operability Determination License Renewal Coronavirus COVID-19 Pressure Boundary Leakage Fire Protection Program |
IR 05000413/2021001 | 29 April 2021 | Integrated Inspection Report 05000413/2021001 and 05000414/2021001 | Internal Flooding Enforcement Discretion Operator Manual Action Temporary Modification Functionality Assessment Open Phase Condition Operability Determination Coronavirus COVID-19 Fire Protection Program |
IR 05000413/2021011 | 23 April 2021 | NRC Fire Protection Team Inspection Report 05000413/2021011 and 05000414/2021011 | Safe Shutdown Probabilistic Risk Assessment Temporary Modification Aging Management Fire Protection Program |
IR 05000413/2020006 | 3 March 2021 | Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2020006 and 05000414/2020006 | Fitness for Duty Open Phase Condition License Renewal Exemption Request Power-Operated Valves COVID-19 |
IR 05000413/2021401 | 26 February 2021 | Security Baseline Inspection Report 05000413/2021401 and 05000414/2021401 | Coronavirus COVID-19 |
IR 05000413/2020004 | 28 January 2021 | Integrated Inspection Report 05000413/2020004 and 05000414/2020004 | Internal Flooding Enforcement Discretion Functionality Assessment Operability Determination Coronavirus COVID-19 Fire Protection Program Downpower |
IR 05000413/2020011 | 18 December 2020 | Biennial Problem Identification and Resolution Inspection Report 05000413/2020011 and 05000414/2020011 Dated December 18, 2020 | Condition Adverse to Quality Operability Determination Maintenance Rule Program |
IR 05000413/2020401 | 23 November 2020 | Security Aseline Inspection Report 05000413/2020401 and 05000414/2020401 | Affidavit |
IR 05000413/2020003 | 30 October 2020 | Integrated Inspection Report 05000413/2020003, 05000414/2020003 and 07200045/2020002 | Safe Shutdown High Radiation Area Stroke time Temporary Modification Functionality Assessment FLEX Operability Determination Earthquake Coronavirus COVID-19 Fire Protection Program Power change |
IR 05000413/2020005 | 17 August 2020 | Updated Inspection Plan for Catawba Nuclear Station Units 1 and 2 (NRC Inspection Report 05000413/2020005 and 05000414/2020005) | Fitness for Duty Operator Manual Action Cyber Security Open Phase Condition License Renewal Exemption Request Power-Operated Valves COVID-19 |
IR 05000413/2020002 | 3 August 2020 | Integrated Inspection Report 05000413/2020002, 05000414/2020002 and 07200045/2020001 | Safe Shutdown Boric Acid High winds Enforcement Discretion Nondestructive Examination Temporary Modification Functionality Assessment Significance Determination Process Operability Determination Coronavirus COVID-19 Liquid penetrant Fire Protection Program |
IR 05000413/2020001 | 28 April 2020 | Integrated Inspection Report 05000413/2020001 and 05000414/2020001 | Safe Shutdown Enforcement Discretion Temporary Modification Functionality Assessment Condition Adverse to Quality Significance Determination Process Operability Determination Earthquake Coronavirus COVID-19 Fire Protection Program |
IR 05000413/2020010 | 10 March 2020 | Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000413/2020010 and 05000414/2020010 | Weak link |
IR 05000413/2019006 | 3 March 2020 | Annual Assessment Letter for Catawba Nuclear Station Units 1 and 2 - NRC Inspection Report 05000413/2019006 and 05000414/2019006 | Operator Manual Action Open Phase Condition |
IR 05000413/2019004 | 27 January 2020 | Integrated Report 05000413/2019004 and 05000414/2019004 | |
IR 05000413/2019010 | 9 January 2020 | Reissue Catawba - Design Basis Assurance Inspection (Programs) Inspection Report 05000413/2019010 and 05000414/2019010 | Significance Determination Process Moisture barrier License Renewal |
ML19354A856 | 20 December 2019 | Design Basis Assurance Inspection (Programs) Inspection Report 0500413/2019010 and 05000414/2019010 | Significance Determination Process Moisture barrier |
IR 05000413/2019411 | 26 November 2019 | U.S. Nuclear Regulatory Commission Security Inspection Report 05000413/2019411 and 05000414/2019411 | |
IR 05000413/2019003 | 7 November 2019 | Integrated Inspection Report 05000413/2019003 and 05000414/2019003 | |