Finding | |
---|---|
Title | Failure to Correctly Translate the Design Basis for the Containment Spray System |
Description | The team identified a finding of very low safety significance involving a non-cited violation of Title 10 CFR Part 50, Appendix B, Criterion III, Design Control, in that, design control measures did not assure that the design basis for safety related systems were correctly translated into procedures. Specifically, the licensee failed to correctly translate the design basis of the containment spray system into Technical Basis Document Procedure TBD-EOP-05, Uncontrolled Heat Extraction. After identification, the licensee entered this issue in the corrective action program as Condition Report 2011-06802. The failure to correctly translate the design basis of the containment spray system into an emergency operating procedure technical basis document is a performance deficiency. It is more than minor and therefore a finding because it adversely affects the procedure quality attribute of the barrier integrity cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. The incorrect guidance in the emergency operating procedure basis document could result in a licensed operator taking incorrect action to secure containment spray based on a faulty understanding of the expected system response. Securing containment spray during a main steam line break would challenge the safety function of the containment building, increasing the risk to public health and safety. Traditional enforcement does not apply because the issue did not have any actual safety consequences or potential for impacting the NRC\'s regulatory function, and was not the result of any willful violation of NRC requirements. In accordance with Inspection Manual Chapter 0609, Attachment 4, Phase 1 Initial Screening and Characterization of Findings, a phase 1 screening was performed and the finding was determined to be of very low safety significance (Green) because the finding: (1) did not represent only a degradation of the radiological barrier function provided for the control room, or auxiliary building, or spent fuel pool; (2) did not represent a degradation of the barrier function of the control room against smoke or a toxic atmosphere; (3) did not represent an actual open pathway in the physical integrity of reactor containment system, containment isolation system, and heat removal components; and (4) did not involve an actual reduction in function of hydrogen ignitors in the reactor containment. There was no cross-cutting aspect assigned to this performance deficiency because it was not indicative of current plant performance. |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2012301 Section 4OA5 |
Date counted | Jun 30, 2012 (2012Q2) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | NRC identified |
Inspection Procedure: | |
Inspectors (proximate) | B Larson D Strickland K Clayton M Haire N Hernandez T Buchanan |
INPO aspect | |
' | |
Finding - Fort Calhoun - IR 05000285/2012301 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2012Q2
Self-Identified List (Fort Calhoun)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||