05000285/FIN-2012007-05
From kanterella
Jump to navigation
Jump to search
Finding | |
---|---|
Title | Untimely Corrective Actions Related to Revising a Post- Fire Safe Shutdown Procedure |
Description | The inspectors identified a non-cited violation of License Condition 3.D and the Quality Assurance Plan for failure to take timely corrective action. Specifically, the licensee revised procedure steps to open the breakers for the reactor coolant gas vent system valves in response to Non-cited Violation 05000285/2008009-02; however, the licensee did not revise the procedures until March 24, 2012, after the inspectors requested to review the corrective actions for the 2008 violation. The failure to take timely corrective action to address inadequate procedure guidance to safely shutdown the plant following a fire was a performance deficiency. The finding was more than minor because it was associated with the protection against external events (fire) attribute of the Mitigating Systems Cornerstone and it adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. This finding was evaluated using the Fire Protection Significance Determination Process and was determined to be of very low safety significance because of the design of the vent system valves (i.e., three spurious actuations needed to exceed charging pump capability), availability of reliable reactor coolant system pressure and pressurizer level indications in the control room, and the ability of the operator to compensate for the deficiency because of their experience and familiarity. This finding had a cross-cutting aspect in the area of human performance associated with decision making because the licensee did not use a systematic process to correct fire protection procedure deficiencies in response to a violation in 2008. |
Site: | Fort Calhoun |
---|---|
Report | IR 05000285/2012007 Section 4OA2 |
Date counted | Jun 30, 2012 (2012Q2) |
Type: | NCV: Green |
cornerstone | Mitigating Systems |
Identified by: | NRC identified |
Inspection Procedure: | IP 71152 |
Inspectors (proximate) | G Miller G Pick J Mateychick J Watkins S Makor |
CCA | H.13, Consistent Process |
INPO aspect | DM.1 |
' | |
Finding - Fort Calhoun - IR 05000285/2012007 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Fort Calhoun) @ 2012Q2
Self-Identified List (Fort Calhoun)
| |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||