MONTHYEARIR 05000245/20164032016-09-29029 September 2016 Millstone Power Station, Units 2 and 3 - Security Inspection Report 05000336/2016403 and 05000423/2016403. Letter Only IR 05000336/20164032016-09-29029 September 2016 Security Inspection Report 05000336/2016403 and 05000423/2016403. Letter Only ML0902800902009-01-27027 January 2009 Notification of Inspection and Request for Information ML0820504522008-07-23023 July 2008 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000336/20052022007-10-0303 October 2007 Letter to Mr. D. Christian - Millstone Power Station, Units 2 and 3 - NRC Material Control and Accounting Program Inspection Report No. 05000336/2005202 and 05000423/2005202 ML0631102852006-11-0606 November 2006 Response to Evaluation of a Non-cited Violation (NRC Integrated Inspection Report Numbers 05000336/2006006 and 05000423/2006006 IR 05000336/20060122006-10-0404 October 2006 IR 05000336-06-012, IR 05000423-06-012, 08/21/2006 - 08/25/2006, Millstone Power Station, Units 2 and 3, Physical Protection IR 05000336/20060152006-08-25025 August 2006 IR 05000336/2006015 and 05000423/2006015; Millstone Power Station, Units 2 and 3; Ti 2515/168 IR 05000336/20050022005-08-10010 August 2005 EA-05-156; Response Letter to Mr. Grecheck (Dominion) from NRC Disputed Violation in Inspection Report 05000336-05-002 and 05000423-05-002 ML0515803152004-10-0404 October 2004 Review of Millstone Unit 2 Steam Generator Tube Inspection Reports for Their 2003 Outage IR 05000336/20040132004-06-0303 June 2004 IR 05000336-04-013, IR 05000423-04-013, on 05/03/2004-05/06/2004; for Millstone Power Station, Physical Security Baseline Inspection Report. Cover Letter ML0412604612004-05-0505 May 2004 Assessment Follow-up Letter-Millstone Power Station, Unit 2 IR 05000336/20020032002-06-13013 June 2002 IR 05000336-02-03; on 03/31-05/11/02; Dominion Nuclear Connecticut, Inc., Millstone Power Station; Unit 2; Resident Inspection. No Violations Identified IR 05000336/20020112002-06-0707 June 2002 IR 05000423-02-011, IR 05000336-02-011, on 04/30-05/03/2002, Dominion Nuclear Connecticut, Inc, Millstone Power Station Units 2 & 3. Emergency Preparedness Exercise & Performance Indicator Review IR 05000336/20020022002-04-24024 April 2002 IR 05000336/2002-002; on 02/10-03/30/02; Dominion Nuclear Connecticut, Inc., Millstone Power Station; Unit 2; Resident Inspection. No Violations Identified IR 05000336/20010152002-03-18018 March 2002 IR 05000336/2001-015 and 05000423/01-015, Millstone Power Station, Inspection on 02/01/02 Related to Biennial Baseline Inspection of Id and Resolution of Problems, Corrective Action Program. Two Violations Were Identified IR 05000336/20010142002-03-0808 March 2002 IR 05000336/2001-014, IR 05000423/2001-014, Dominion Nuclear Connecticut, Inc., Millstone Power Station, Unit 2, Resident Inspection on 12/30/2001-02/09/2002 Re Unit 3, Maintenance Rule Implementation ML0206602472002-03-0707 March 2002 Notification of Conduct of a Triennial Fire Protection Baseline Inspection 2016-09-29
[Table view] Category:Letter
MONTHYEARML24030A7522024-01-30030 January 2024 Technical Specification Bases Pages IR 05000336/20234022024-01-30030 January 2024 Security Baseline Inspection Report 05000336/2023402 and 05000423/2023402 (Cover Letter Only) ML23341A0172024-01-12012 January 2024 Issuance of Amendment No. 288 Revision to Applicability Term for Reactor Coolant System Heatup and Cooldown Pressure-Temperature Limitations Figures IR 05000336/20234402024-01-11011 January 2024 Special Inspection Report 05000336/2023440 and 05000423/2023440 (Cover Letter Only) ML24004A1052024-01-0404 January 2024 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000336/2024010 & 05000423/2024010 ML23361A0942023-12-21021 December 2023 Response to Request for Additional Information Regarding Proposed License Amendment Request to Revise Technical Specifications for Reactor Core Safety Limits, Fuel Assemblies and Core Operating Limits Report . ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23361A0312023-12-20020 December 2023 Intent to Pursue Subsequent License Renewal ML23352A0202023-12-18018 December 2023 Senior Reactor and Reactor Operator Initial License Examinations ML23334A2242023-11-30030 November 2023 Request for Exemption from Enhanced Weapons Firearms Background Checks, and Security Event Notifications Implementation ML23324A4222023-11-20020 November 2023 Reactor Vessel Internals Inspections Aging Management Program Submittal Related to License Renewal Commitment 13 ML23324A4302023-11-20020 November 2023 Alloy 600 Aging Management Program Submittal Related to License Renewal Commitment 15 ML23317A2702023-11-13013 November 2023 Core Operating Limits Report, Cycle 23 IR 05000336/20230032023-11-0606 November 2023 Integrated Inspection Report 05000336/2023003 and 05000423/2023003 ML23298A1652023-10-26026 October 2023 Requalification Program Inspection IR 05000336/20234202023-10-0404 October 2023 Security Inspection Report 05000336/2023420 and 05000423/2023420 ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23226A0052023-09-26026 September 2023 Issuance of Amendment No. 287 Supplement to Spent Fuel Pool Criticality Safety Analysis IR 05000245/20230012023-09-19019 September 2023 Safstor Inspection Report 05000245/2023001 IR 05000336/20230102023-09-0808 September 2023 Commercial Grade Dedication Report 05000336/2023010 and 05000423/2023010 IR 05000336/20230052023-08-31031 August 2023 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Report 05000336/2023005 and 05000423/2023005) ML23248A2132023-08-30030 August 2023 Response to Request for Additional Information Regarding Proposed License Amendment Request to Revise the Applicability Term for Reactor Coolant System Heatup and Cooldown Pressure-Temperature. ML23242A0142023-08-30030 August 2023 Operator Licensing Examination Approval ML23223A0552023-08-18018 August 2023 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specifications for Reactor Core Safety Limits, Fuel Assemblies, and COLR Related to Framatome Gaia Fuel ML23223A0482023-08-18018 August 2023 Request for Withholding Information from Public Disclosure for License Amendment Request to Use Framatome Small Break and Realistic Large Break LOCA Evaluation Methodologies for Establishing COLR Limits IR 05000336/20230022023-08-0909 August 2023 Integrated Inspection Report 05000336/2023002 and 05000423/2023002 ML23188A0432023-07-31031 July 2023 Authorization and Safety Evaluation for Alternative Request No. IR-04-11 ML23208A0922023-07-26026 July 2023 Request for Approval of Appendix F of Fleet Report DOM-NAF-2-P Qualification of Framatome ORFEO-GAIA and OORFE-NMGRID CHF Correlations in the Dominion Energy Vipre-D Computer Code Response ML23188A0202023-07-26026 July 2023 Closeout of Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors ML23207A1102023-07-26026 July 2023 NRC Regulatory Issues Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations IR 05000336/20234012023-07-17017 July 2023 Material Control and Accounting Program Inspection Report 05000336/2023401 and 05000423/2023401 - (Cover Letter Only) ML23175A0052023-07-12012 July 2023 Alternative Request P-07 for Pump Periodic Verification Testing Program for Containment Recirculation Spray System Pumps ML23193A8562023-06-28028 June 2023 Submittal of Updates to the Final Safety Analysis Reports ML23178A1682023-06-26026 June 2023 2022 Annual Report of Emergency Core Cooling System (ECCS) Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML23153A1732023-06-16016 June 2023 Correction to Amendment Nos. 346 & 286 Millstone, 294 & 277 North Anna, 311 & 311 Surry, and 225 Summer to Revise Technical Specifications to Adopt TSTF-554,Rev Reactor Coolant Leakage Requirement ML23151A0742023-06-12012 June 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23159A2202023-06-0808 June 2023 Associated Independent Spent Fuel Storage Installation Revision to Emergence Plan - Report of Changes IR 07200047/20234012023-06-0808 June 2023 NRC Independent Spent Fuel Storage Installation Security Inspection Report No. 07200047/2023401 2024-01-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION ust 25, 2006
SUBJECT:
MILLSTONE POWER STATION, UNITS 2 AND 3 - NRC INSPECTION REPORT 05000336/2006015 and 05000423/2006015
Dear Mr. Christian:
On July 20, 2006, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Millstone Power Station, Units 2 and 3. The enclosed inspection report documents the inspection results, which were discussed on July 20, 2006, with Mr. Bill Watson, Millstone B.5.b Project Manager, and other members of your staff.
The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.
The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.
No findings of significance were identified.
In accordance with 10 CFR 2.390 and the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system, ADAMS. ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room). However, because of the security-related concerns contained in the enclosure, and in accordance with 10 CFR 2.390, a copy of this letters enclosure will not be available for public inspection.
Warning: Violation of Section 147 of the Atomic Energy DETERMINATION Act, Safeguards Information, is subject to civil and MADE BY:
criminal penalties. NAME/TITLE: Barry C. Westreich, Chief ORGANIZATION: NSIR/DNS/SOS BASIS: 2/25/02 NRC Order SIGNATURE: /RA/ 5/12/06 In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response, if any. This practice will ensure that your response will not be made available electronically for public inspection in the NRC Public Document Room or from the NRCs document system, ADAMS. If Safeguards Information is necessary to provide an acceptable I response, please provide the level of protection described in 10 CFR 73.21.
Sincerely,
/RA/
Paul Krohn, Chief Projects Branch 6 Division of Reactor Projects Docket No. 50-336, 50-423 License No. DPR-65, NPF-49 Enclosure: NRC Inspection Report 05000336/2006015 and 05000423/2006015 ( )
cc w/o encl:
J.A. Price, Site Vice President, Millstone D.W. Dodson, Supervisor, Station Licensing cc w/encl; w/SGI:
J. Campbell, Site Security Manager, Millstone E. Wilds, Director, State of Connecticut State Liaison Officer Designee J. Spath, State of New York, State Liaison Officer PGK SUNSI Review Complete: (Reviewers Initials)
DOCUMENT NAME: TI2515-168Millstone wo enclwpd.wpd After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME MSchneider/PGK PKrohn DATE 08/25/06 08/25/06 OFFICIAL RECORD COPY