ML100550505
| ML100550505 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 02/02/2010 |
| From: | Tennessee Valley Authority |
| To: | Office of Nuclear Reactor Regulation |
| References | |
| Download: ML100550505 (102) | |
Text
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 (continued)
Watts Bar - Unit 2 B 3.4-1 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.1 RCS Pressure, Temperature, and Flow Departure from Nucleate Boiling (DNB) Limits
BASES BACKGROUND These Bases address requirements for maintaining RCS pressure, temperature, and flow rate within limits assumed in the safety analyses.
The safety analyses (Ref. 1) of normal operating conditions and
anticipated operational occurrences assume initial conditions within the
normal steady state envelope. The limits placed on RCS pressure, temperature, and flow rate ensure that the minimum departure from
nucleate boiling ratio (DNBR) will be met for each of the transients
analyzed.
The RCS pressure limit is consistent with operation within the nominal
operational envelope. Pressurizer pressure indications are averaged to
come up with a value for comparison to the limit. A lower pressure will
cause the reactor core to approach DNB limits.
The RCS coolant average temperature limit is consistent with full power
operation within the nominal operational envelope. Indications of
temperature are averaged to determine a value for comparison to the
limit. A higher average temperature will cause the core to approach DNB
limits.
The RCS flow rate normally remains constant during an operational fuel
cycle with all pumps running. The minimum RCS flow limit corresponds
to that assumed for DNB analyses. Flow rate indications are averaged to
come up with a value for comparison to the limit. A lower RCS flow will
cause the core to approach DNB limits.
Operation for significant periods of time outside these DNB limits
increases the likelihood of a fuel cladding failure in a DNB limited event.
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-2 (developmental)
A APPLICABLE SAFETY ANALYSES The requirements of this LCO represent the initial conditions for DNB
limited transients analyzed in the plant safety analyses (Ref. 1). The
safety analyses have shown that transients initiated from the limits of this
LCO will result in meeting the DNBR criterion. This is the acceptance
limit for the RCS DNB parameters. Changes to the unit that could impact
these parameters must be assessed for their impact on the DNBR
criteria. The transients analyzed for include loss of coolant flow events
and dropped or stuck rod events. A key assumption for the analysis of
these events is that the core power distribution is within the limits of LCO 3.1.7, "Control Bank Insertion Limits;" LCO 3.2.3, "AXIAL FLUX
DIFFERENCE (AFD);" and LCO 3.2.4, "QUADRANT POWER TILT
RATIO (QPTR)."
The pressurizer pressure limit of 2214 psig and the RCS average
temperature limit of 593.2°F correspond to analytical limits of 2185 psig
and 594.2°F used in the safety analyses, with allowance for measurement
uncertainty.
The RCS DNB parameters satisfy Criterion 2 of the NRC Policy
Statement.
LCO This LCO specifies limits on the monitored process variables - pressurizer pressure, RCS average temperature, and RCS total flow rate - to ensure
the core operates within the limits assumed in the safety analyses.
Operating within these limits will result in meeting the DNBR criterion in
the event of a DNB limited transient.
RCS total flow rate contains a measurement error of 1.6% (process
computer) or 1.8% (control board indication) based on performing a
precision heat balance and using the result to calibrate the RCS flow rate
indicators. Potential fouling of the feedwater venturi, which might not be
detected, could bias the result from the precision heat balance in a
nonconservative manner. Therefore, a penalty of 0.1% for undetected fouling of the feedwater venturi raises the nominal flow measurement
allowance to 1.7% (process computer) or 1.9% (control board indication).
Any fouling that might bias the flow rate measurement greater than 0.1%
can be detected by monitoring and trending various plant performance
parameters. If detected, either the effect of the fouling shall be quantified
and compensated for in the RCS flow rate measurement or the venturi
shall be cleaned to eliminate the fouling. The LCO numerical values for
pressure, temperature, and flow rate are given for the measurement
location and have been adjusted for instrument error.
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 BASES (continued)
Watts Bar - Unit 2 B 3.4-3 (developmental)
B APPLICABILITY In MODE 1, the limits on pressurizer pressure, RCS coolant average temperature, and RCS flow rate must be maintained during steady state
operation in order to ensure DNBR criteria will be met in the event of an
unplanned loss of forced coolant flow or other DNB limited transient. In
all other MODES, the power level is low enough that DNB is not a
concern.
A Note has been added to indicate the limit on pressurizer pressure is not
applicable during short term operational transients such as a THERMAL
POWER ramp increase > 5% RTP per minute or a THERMAL POWER
step increase > 10% RTP. These conditions represent short term
perturbations where actions to control pressure variations might be
counterproductive. Also, since they represent transients initiated from
power levels < 100% RTP, an increased DNBR margin exists to offset the
temporary pressure variations.
Another set of limits on DNB related parameters is provided in SL 2.1.1, "Reactor Core SLs." Those limits are less restrictive than the limits of this
LCO, but violation of a Safety Limit (SL) merits a stricter, more severe
Required Action. Should a violation of this LCO occur, the operator must
check whether or not an SL may have been exceeded.
ACTIONS A.1
RCS pressure and RCS average temperature are controllable and
measurable parameters. With one or both of these parameters not within
LCO limits, action must be taken to restore parameter(s).
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 BASES (continued)
Watts Bar - Unit 2 B 3.4-4 (developmental)
A ACTIONS A.1 (continued)
RCS total flow rate is not a controllable parameter and is not expected to
vary during steady state operation. If the indicated RCS total flow rate is
below the LCO limit, power must be reduced, as required by Required
Action B.1, to restore DNB margin and eliminate the potential for violation
of the accident analysis bounds.
The 2-hour Completion Time for restoration of the parameters provides
sufficient time to adjust plant parameters, to determine the cause for the
off normal condition, and to restore the readings within limits, and is
based on plant operating experience.
B.1 If Required Action A.1 is not met within the associated Completion Time, the plant must be brought to a MODE in which the LCO does not apply.
To achieve this status, the plant must be brought to at least MODE 2
within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. In MODE 2, the reduced power condition eliminates the
potential for violation of the accident analysis bounds. The Completion
Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable to reach the required plant conditions in an
orderly manner.
SURVEILLANCE
REQUIREMENTS SR 3.4.1.1
- Since Required Action A.1 allows a Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to restore
parameters that are not within limits, the 12-hour Surveillance Frequency
for verifying that the pressurizer pressure is sufficient to ensure the
pressure can be restored to a normal operation, steady state condition
following load changes and other expected transient operations. The 12-
hour interval has been shown by operating practice to be sufficient to
regularly assess for potential degradation and to verify operation is within
safety analysis assumptions.
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 BASES Watts Bar - Unit 2 B 3.4-5 (developmental)
B SURVEILLANCE REQUIREMENTS (continued)
- Since Required Action A.1 allows a Completion Time of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to restore
parameters that are not within limits, the 12-hour Surveillance Frequency
for verifying RCS average temperature is sufficient to ensure the
temperature can be restored to a normal operation, steady state condition
following load changes and other expected transient operations. The
12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval has been shown by operating practice to be sufficient to
regularly assess for potential degradation and to verify operation is within
safety analysis assumptions.
- The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Surveillance Frequency to verify the RCS total flow rate is
performed using the installed flow instrumentation. The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> interval
has been shown by operating practice to be sufficient to regularly assess
potential degradation and to verify operation within safety analysis
assumptions.
- Measurement of RCS total flow rate by performance of a precision
calorimetric heat balance once every 18 months allows the installed RCS flow instrumentation to be calibrated and verifies the actual RCS flow rate
is greater than or equal to the minimum required RCS flow rate.
The Frequency of 18 months reflects the importance of verifying flow after
a refueling outage when the core has been altered, which may have
caused an alteration of flow resistance.
This SR is modified by a Note that allows entry into MODE 1, without
having performed the SR, and placement of the unit in the best condition
for performing the SR. The Note states that the SR is not required to be
performed until 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after 90% RTP. This exception is appropriate since the heat balance method requires the plant to be at a minimum of 90% RTP to obtain the stated RCS flow accuracies. The Surveillance
shall be performed within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after reaching 90% RTP.
- Note: The accuracy of the instruments used for monitoring RCS pressure, temperature and flow rate is discussed in this Bases
section under LCO.
RCS Pressure, Temperature, and Flow DNB Limits B 3.4.1 BASES Watts Bar - Unit 2 B 3.4-6 (developmental)
B REFERENCES 1. Watts Bar FSAR, Section 15.0, "Accident Analysis," Section 15.2, "Condition II - Faults of Moderate Frequency," and Section 15.3.4, "Complete Loss Of Forced Reactor Coolant Flow."
RCS Minimum Temperature for Criticality B 3.4.2 (continued)
Watts Bar - Unit 2 B 3.4-7 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.2 RCS Minimum Temperature for Criticality
BASES BACKGROUND This LCO is based upon meeting several major considerations before the reactor can be made critical and while the reactor is critical.
The first consideration is moderator temperature coefficient (MTC),
LCO 3.1.4, "Moderator Temperature Coefficient (MTC)." In the transient
and accident analyses, the MTC is assumed to be in a range from slightly
positive to negative, and the operating temperature is assumed to be
within the nominal operating envelope while the reactor is critical. The
LCO on minimum temperature for criticality helps ensure the plant is
operated consistent with these assumptions.
The second consideration is the protective instrumentation. Because
certain protective instrumentation (e.g., excore neutron detectors) can be
affected by moderator temperature, a temperature value within the
nominal operating envelope is chosen to ensure proper indication and
response while the reactor is critical.
The third consideration is the pressurizer operating characteristics. The
transient and accident analyses assume that the pressurizer is within its
normal startup and operating range (i.e., saturated conditions and steam
bubble present). It is also assumed that the RCS temperature is within its
normal expected range for startup and power operation. Since the
density of the water, and hence the response of the pressurizer to
transients, depends upon the initial temperature of the moderator, a
minimum value for moderator temperature within the nominal operating
envelope is chosen.
The fourth consideration is that the reactor vessel is above its minimum
nil ductility reference temperature when the reactor is critical.
RCS Minimum Temperature for Criticality B 3.4.2 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-8 (developmental)
A APPLICABLE SAFETY ANALYSES Although the RCS minimum temperature for criticality is not itself an initial
condition assumed in Design Basis Accidents (DBAs), the closely aligned
temperature for hot zero power (HZP) is a process variable that is an
initial condition of DBAs, such as the rod cluster control assembly (RCCA)
withdrawal, RCCA ejection, and main steam line break accidents
performed at zero power that either assumes the failure of, or presents a
challenge to, the integrity of a fission product barrier.
All low power safety analyses assume initial RCS loop temperatures the HZP temperature of 557 F (Ref. 1). The minimum temperature for criticality limitation provides a small band, 6 F, for critical operation below HZP. This band allows critical operation below HZP during plant
startup and does not adversely affect any safety analyses since the MTC
is not significantly affected by t he small temperature difference between
HZP and the minimum temperature for criticality.
The RCS minimum temperature for criticality satisfies Criterion 2 of the
NRC Policy Statement.
LCO Compliance with the LCO ensures that the reactor will not be made or maintained critical (k eff 1.0) at a temperature less than a small band below the HZP temperature, which is assumed in the safety analysis.
Failure to meet the requirements of this LCO may produce initial
conditions inconsistent with the initial conditions assumed in the safety
analysis.
APPLICABILITY In MODE 1 and MODE 2, with k eff 1.0, LCO 3.4.2 is applicable since the reactor can only be critical (k eff 1.0) in these MODES.
The special test exception of LCO 3.1.10, "PHYSICS TESTS Exceptions
- MODE 2," permits PHYSICS TESTS to be performed at 5% RTP with RCS loop average temperatures slightly lower than normally allowed so
that fundamental nuclear characteristics of the core can be verified. In
order for nuclear characteristics to be accurately measured, it may be
necessary to operate outside the normal restrictions of this LCO. For
example, to measure the MTC at beginning of cycle, it is necessary to
allow RCS loop average temperatures to fall below T no load , which may cause RCS loop average temperatures to fall below the temperature limit
of this LCO.
RCS Minimum Temperature for Criticality B 3.4.2 BASES (continued)
Watts Bar - Unit 2 B 3.4-9 (developmental)
B ACTIONS A.1 If the parameters that are outside the limit cannot be restored, the plant
must be brought to a MODE in which the LCO does not apply. To
achieve this status, the plant must be brought to MODE 3 within
30 minutes. Rapid reactor shutdown can be readily and practically
achieved within a 30-minute period. The allowed time is reasonable, based on operating experience, to reach MODE 3 in an orderly manner
and without challenging plant systems.
SURVEILLANCE
REQUIREMENTS SR 3.4.2.1
RCS loop average temperature is required to be verified at or above
551 F (value does not account for instrument error) every 30 minutes when the Tavg - T ref deviation alarm is not reset and any RCS loop Tavg < 561 F.
The Note modifies the SR. When any RCS loop average temperature is
< 561 F and the Tavg - T ref deviation alarm is alarming, RCS loop average temperatures could fall below the LCO requirement without additional
warning. The SR to verify RCS loop average temperatures every
30 minutes is frequent enough to prevent the inadvertent violation of the
LCO.
REFERENCES 1. Watts Bar FSAR, Section 15.0, "Accident Analysis."
RCS P/T Limits B 3.4.3 (continued)
Watts Bar - Unit 2 B 3.4-10 (developmental)
B B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.3 RCS Pressure and Temperature (P/T) Limits
BASES
BACKGROUND All components of the RCS are designed to withstand effects of cyclic loads due to system pressure and temperature changes. These loads
are introduced by startup (heatup) and shutdown (cooldown) operations, power transients, and reactor trips. This LCO limits the pressure and
temperature changes during RCS heatup and cooldown, within the design
assumptions and the stress limits for cyclic operation.
The PTLR contains P/T limit curves for heatup, cooldown, inservice leak
and hydrostatic (ISLH) testing, and data for the maximum rate of change
of reactor coolant temperature (Ref. 1).
Each P/T limit curve defines an acceptable region for normal operation.
The usual use of the curves is operational guidance during heatup or
cooldown maneuvering, when pressure and temperature indications are
monitored and compared to the applicable curve to determine that
operation is within the allowable region.
The LCO establishes operating limits that provide a margin to brittle
failure of the reactor vessel and piping of the reactor coolant pressure
boundary (RCPB). The vessel is the component most subject to brittle
failure, and the LCO limits apply mainly to the vessel. The limits do not
apply to the pressurizer, which has different design characteristics and
operating functions.
10 CFR 50, Appendix G (Ref. 2), requires the establishment of P/T limits
for specific material fracture toughness requirements of the RCPB
materials. Reference 2 requires an adequate margin to brittle failure
during normal operation, anticipated operational occurrences, and system
hydrostatic tests. It mandates the use of the American Society of Mechanical Engineers (ASME) Code,Section XI, Appendix G (Ref. 3).
The neutron embrittlement effect on the material toughness is reflected by
increasing the nil ductility reference temperature (RT NDT) as exposure to neutron fluence increases.
RCS P/T Limits B 3.4.3 BASES (continued)
Watts Bar - Unit 2 B 3.4-11 (developmental)
A BACKGROUND (continued)
The actual shift in the RT NDT of the vessel material will be established periodically by removing and evaluating the irradiated reactor vessel material specimens, in accordance with ASTM E 185 (Ref. 4) and
Appendix H of 10 CFR 50 (Ref. 5). The operating P/T limit curves will be
adjusted, as necessary, based on the evaluation findings and the
recommendations of Regulatory Guide 1.99 (Ref. 6).
The P/T limit curves are composite curves established by superimposing limits derived from stress analyses of those portions of the reactor vessel
and head that are the most restrictive. At any specific pressure, temperature, and temperature rate of change, one location within the
reactor vessel will dictate the most restrictive limit. Across the span of the
P/T limit curves, different locations are more restrictive, and, thus, the
curves are composites of the most restrictive regions.
The heatup curve represents a different set of restrictions than the
cooldown curve because the directions of the thermal gradients through
the vessel wall are reversed. The thermal gradient reversal alters the
location of the tensile stress between the outer and inner walls.
The criticality limit curve includes the Reference 2 requirement that it be 40 F above the heatup curve or the cooldown curve, and not less than the minimum permissible temperature for ISLH testing. However, the
criticality curve is not operationally limit ing; a more restrictive limit exists in LCO 3.4.2, "RCS Minimum Temperature for Criticality."
The consequence of violating the LCO limits is that the RCS has been
operated under conditions that can result in brittle failure of the RCPB, possibly leading to a nonisolable leak or loss of coolant accident. In the
event these limits are exceeded, an evaluation must be performed to
determine the effect on the structural integrity of the RCPB components.
The ASME Code,Section XI, Appendix E (Ref. 7), provides a
recommended methodology for evaluating an operating event that causes
an excursion outside the limits.
RCS P/T Limits B 3.4.3 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-12 (developmental)
B APPLICABLE SAFETY ANALYSES The P/T limits are not derived from Design Basis Accident (DBA)
analyses. They are prescribed during normal operation to avoid
encountering pressure, temperature, and temperature rate of change
conditions that might cause undetected flaws to propagate and cause
nonductile failure of the RCPB, an unanalyzed condition. Reference 8 establishes the methodology for determining the P/T limits. Although the
P/T limits are not derived from any DBA, the P/T limits are acceptance limits since they preclude operation in an unanalyzed condition.
RCS P/T limits satisfy Criterion 2 of the NRC Policy Statement.
LCO The two elements of this LCO are:
- a. The limit curves for heatup, cooldown, and ISLH testing; and b. Limits on the rate of change of temperature.
The LCO limits apply to all components of the RCS, except the
pressurizer. These limits define allowable operating regions and permit a
large number of operating cycles while providing a wide margin to
nonductile failure.
The limits for the rate of change of temperature control and the thermal
gradient through the vessel wall are used as inputs for calculating the
heatup, cooldown, and ISLH testing P/T limit curves. Thus, the LCO for
the rate of change of temperature restricts stresses caused by thermal
gradients and also ensures the validity of the P/T limit curves.
Violating the LCO limits places the reactor vessel outside of the bounds of
the stress analyses and can increase stresses in other RCPB
components. The consequences depend on several factors, as follow:
- a. The severity of the departure from the allowable operating P/T regime or the severity of the rate of change of temperature; b. The length of time the limits were violated (longer violations allow the temperature gradient in the thick vessel walls to become more
pronounced); and c. The existences, sizes, and orientations of flaws in the vessel material.
RCS P/T Limits B 3.4.3 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-13 (developmental)
A APPLICABILITY The RCS P/T limits LCO provides a definition of acceptable operation for prevention of nonductile failure in accordance with 10 CFR 50, Appendix G (Ref. 2). Although the P/T limits were developed to provide
guidance for operation during heatup or cooldown (MODES 3, 4, and 5)
or ISLH testing, their Applicability is at all times in keeping with the
concern for nonductile failure. The limits do not apply to the pressurizer.
During MODES 1 and 2, other Technical Specifications provide limits for
operation that can be more restrictive than or can supplement these P/T
limits. LCO 3.4.1, "RCS Pressure, Temperature, and Flow Departure
from Nucleate Boiling (DNB) Limits"; LCO 3.4.2, "RCS Minimum
Temperature for Criticality"; and Safety Limit 2.1, "Safety Limits," also
provide operational restrictions for pressure and temperature and
maximum pressure. Furthermore, MODES 1 and 2 are above the
temperature range of concern for nonductile failure, and stress analyses
have been performed for normal maneuvering profiles, such as power
ascension or descent.
ACTIONS A.1 and A.2
Operation outside the P/T limits during MODE 1, 2, 3, or 4 must be
corrected so that the RCPB is returned to a condition that has been
verified by stress analyses.
The 30 minute Completion Time reflects the urgency of restoring the
parameters to within the analyzed range. Most violations will not be
severe, and the activity can be accomplished in this time in a controlled
manner.
Besides restoring operation within limits, an evaluation is required to
determine if RCS operation can continue. The evaluation must verify the
RCPB integrity remains acceptable and must be completed before
continuing operation. Several methods may be used, including
comparison with pre-analyzed transients in the stress analyses, new
analyses, or inspection of the components.
ASME Code,Section XI, Appendix E (Ref. 7), may be used to support the
evaluation. However, its use is restricted to evaluation of the vessel
beltline.
RCS P/T Limits B 3.4.3 BASES (continued)
Watts Bar - Unit 2 B 3.4-14 (developmental)
A ACTIONS A.1 and A.2 (continued)
The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is reasonable to accomplish the evaluation.
The evaluation for a mild violation is possible within this time, but more
severe violations may require special, event specific stress analyses or
inspections. A favorable evaluation must be completed before continuing
to operate.
Condition A is modified by a Note requiring Required Action A.2 to be
completed whenever the Condition is entered. The Note emphasizes the
need to perform the evaluation of the effects of the excursion outside the
allowable limits. Restoration alone per Required Action A.1 is insufficient
because higher than analyzed stresses may have occurred and may have
affected the RCPB integrity.
B.1 and B.2
If a Required Action and associated Completion Time of Condition A are
not met, the plant must be placed in a lower MODE because either the
RCS remained in an unacceptable P/T region for an extended period of
increased stress or a sufficiently severe event caused entry into an
unacceptable region. Either possibility indicates a need for more careful
examination of the event, best accomplished with the RCS at reduced
pressure and temperature. In reduced pressure and temperature
conditions, the possibility of propagation with undetected flaws is
decreased.
If the required restoration activity cannot be accomplished within
30 minutes, Required Action B.1 and Required Action B.2 must be
implemented to reduce pressure and temperature.
If the required evaluation for continued operation cannot be accomplished
within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> or the results are indeterminate or unfavorable, action
must proceed to reduce pressure and temperature as specified in
Required Action B.1 and Required Action B.2. A favorable evaluation
must be completed and documented before returning to operating
pressure and temperature conditions.
Pressure and temperature are reduced by bringing the plant to MODE 3
within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to MODE 5 with RCS pressure < 500 psig within
36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
RCS P/T Limits B 3.4.3 BASES (continued)
Watts Bar - Unit 2 B 3.4-15 (developmental)
A ACTIONS B.1 and B.2 (continued)
The allowed Completion Times are reasonable, based on operating
experience, to reach the required plant conditions from full power
conditions in an orderly manner and without challenging plant systems.
C.1 and C.2
Actions must be initiated immediately to correct operation outside of the
P/T limits at times other than when in MODE 1, 2, 3, or 4, so that the
RCPB is returned to a condition that has been verified by stress analysis.
The immediate Completion Time reflects the urgency of initiating action to
restore the parameters to within the analyzed range. Most violations will
not be severe, and the activity can be accomplished in this time in a
controlled manner.
Besides restoring operation within limits, an evaluation is required to
determine if RCS operation can continue. The evaluation must verify that
the RCPB integrity remains acceptable and must be completed prior to
entry into MODE 4. Several methods may be used, including comparison
with pre-analyzed transients in the stress analyses, or inspection of the
components.
ASME Code,Section XI, Appendix E (Ref. 7), may be used to support the
evaluation. However, its use is restricted to evaluation of the vessel
beltline.
Condition C is modified by a Note requiring Required Action C.2 to be
completed whenever the Condition is entered. The Note emphasizes the
need to perform the evaluation of the effects of the excursion outside the
allowable limits. Restoration alone per Required Action C.1 is insufficient
because higher than analyzed stresses may have occurred and may have
affected the RCPB integrity.
RCS P/T Limits B 3.4.3 BASES (continued)
Watts Bar - Unit 2 B 3.4-16 (developmental)
B SURVEILLANCE REQUIREMENTS SR 3.4.3.1
Verification that operation is within the PTLR limits is required every
30 minutes when RCS pressure and temperature conditions are
undergoing planned changes. This Frequency is considered reasonable
in view of the control room indication available to monitor RCS status.
Also, since temperature rate of change limits are specified in hourly increments, 30 minutes permit assessment and correction for minor
deviations within a reasonable time.
Surveillance for heatup, cooldown, or ISLH testing may be discontinued
when the definition given in the relevant plant procedure for ending the
activity is satisfied.
This SR is modified by a Note that only requires this SR to be performed
during system heatup, cooldown, and ISLH testing. No SR is given for
criticality operations because LCO 3.4.2 contains a more restrictive
requirement.
REFERENCES 1. Appendix "B" to RCS System Description N3-68-4001, "Watts Bar Unit 2 RCS Pressure and Temperature Limits Report." 2. Title 10, Code of Federal Regulations, Part 50, Appendix G, "Fracture Toughness Requirements." 3. ASME Boiler and Pressure Vessel Code,Section XI, Appendix G, "Fracture Toughness Criteria for Protection Against Failure." 4. ASTM E 185-82, "Standard Practice for Conducting Surveillance Tests for Light-Water Cooled Nuclear Power Reactor Vessels,"
July 1982.
- 5. Title 10, Code of Federal Regulations, Part 50, Appendix H, "Reactor Vessel Material Surveillance Program Requirements." 6. Regulatory Guide 1.99, Revision 2, "Radiation Embrittlement of Reactor Vessel Materials," May 1988.
RCS P/T Limits B 3.4.3 BASES (continued)
Watts Bar - Unit 2 B 3.4-17 (developmental)
B REFERENCES (continued) 7. ASME Boiler and Pressure Vessel Code,Section XI, Appendix E, "Evaluation of Unanticipated Operating Events." 8. WCAP-14040-A, Revision 4, "Methodology Used to Develop Cold Overpressure Mitigating System Setpoints and RCS Heatup and Cooldown Limit Curves," May 2004.
RCS Loops - MODES 1 and 2 B 3.4.4 (continued)
Watts Bar - Unit 2 B 3.4-18 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.4 RCS Loops - MODES 1 and 2
BASES BACKGROUND The primary function of the RCS is removal of the heat generated in the fuel due to the fission process, and transfer of this heat, via the steam
generators (SGs), to the secondary plant.
The secondary functions of the RCS include:
- a. Moderating the neutron energy level to the thermal state, to increase the probability of fission;
- b. Improving the neutron economy by acting as a reflector;
- c. Carrying the soluble neutron poison, boric acid;
- d. Providing a second barrier against fission product release to the environment; and
- e. Removing the heat generated in the fuel due to fission product decay following a unit shutdown.
The reactor coolant is circulated through four loops connected in parallel
to the reactor vessel, each containing an SG, a reactor coolant pump (RCP), and appropriate flow and temperature instrumentation for both
control and protection. The reactor vessel contains the clad fuel. The
SGs provide the heat sink to the isolated secondary coolant. The RCPs
circulate the coolant through the reactor vessel and SGs at a sufficient
rate to ensure proper heat transfer and prevent fuel damage. This forced
circulation of the reactor coolant ensures mixing of the coolant for proper
boration and chemistry control.
APPLICABLE
SAFETY ANALYSES Safety analyses contain various assumptions for the design bases
accident initial conditions including RCS pressure, RCS temperature, reactor power level, core parameters, and safety system setpoints. The
important aspect for this LCO is the reactor coolant forced flow rate, which is represented by the number of RCS loops in service.
RCS Loops - MODES 1 and 2 B 3.4.4 BASES (continued)
Watts Bar - Unit 2 B 3.4-19 (developmental)
A APPLICABLE SAFETY ANALYSES (continued)
Both transient and steady state analyses have been performed to
establish the effect of flow on the departure from nucleate boiling (DNB).
The transient and accident analyses for the plant have been performed
assuming four RCS loops are in operation. The majority of the plant
safety analyses are based on initial conditions at high core power or zero
power. The accident analyses that are most important to RCP operation
are the four pump coastdown, single pump locked rotor, single pump (broken shaft or coastdown), and rod withdrawal events (Ref. 1).
Steady state DNB analysis has been performed for the four RCS loop
operation. For four RCS loop operation, the steady state DNB analysis, which generates the pressure and temperature Safety Limit (SL) (i.e., the
departure from nucleate boiling ratio (DNBR) limit) assumes a maximum
power level of 118% RTP. This is the design overpower condition for four
RCS loop operation. The value for the accident analysis setpoint of the nuclear overpower (high flux) trip is 118% and is based on an analysis assumption that bounds possible instrumentation errors. The DNBR limit
defines a locus of pressure and temperature points that result in a
minimum DNBR greater than or equal to the critical heat flux correlation
limit.
The plant is designed to operate with all RCS loops in operation to
maintain DNBR above the SL, during all normal operations and
anticipated transients. By ensuring heat transfer in the nucleate boiling
region, adequate heat transfer is provided between the fuel cladding and
the reactor coolant.
RCS Loops - MODES 1 and 2 satisfy Criterion 2 of the NRC Policy
Statement.
LCO The purpose of this LCO is to require an adequate forced flow rate for core heat removal. Flow is represented by the number of RCPs in
operation for removal of heat by the SGs. To meet safety analysis
acceptance criteria for DNB, four pumps are required at rated power.
An OPERABLE RCS loop consists of an OPERABLE RCP in operation
providing forced flow for heat transport and an OPERABLE SG.
RCS Loops - MODES 1 and 2 B 3.4.4 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-20 (developmental)
A APPLICABILITY In MODES 1 and 2, the reactor is critical and thus has the potential to produce maximum THERMAL POWER. Thus, to ensure that the assumptions of the accident analyses remain valid, all RCS loops are
required to be OPERABLE and in operation in these MODES to prevent
DNB and core damage.
The decay heat production rate is much lower than the full power heat
rate. As such, the forced circulation flow and heat sink requirements are
reduced for lower, noncritical MODES as indicated by the LCOs for
MODES 3, 4, and 5.
Operation in other MODES is covered by:
LCO 3.4.5, "RCS Loops - MODE 3";
LCO 3.4.6, "RCS Loops - MODE 4";
LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled";
LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled";
LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level" (MODE 6); and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation -
Low Water Level" (MODE 6).
ACTIONS A.1 If the requirements of the LCO are not met, the Required Action is to
reduce power and bring the plant to MODE 3. This lowers power level
and thus reduces the core heat removal needs and minimizes the
possibility of violating DNB limits.
The Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable, based on operating
experience, to reach MODE 3 from full power conditions in an orderly
manner and without challenging safety systems.
RCS Loops - MODES 1 and 2 B 3.4.4 BASES (continued)
Watts Bar - Unit 2 B 3.4-21 (developmental)
A SURVEILLANCE REQUIREMENTS SR 3.4.4.1
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that each RCS loop is in
operation. Verification includes flow rate, temperature, or pump status
monitoring, which help ensure that forced flow is providing heat removal
while maintaining the margin to DNB. The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is
sufficient considering other indications and alarms available to the
operator in the control room to monitor RCS loop performance.
REFERENCES
- 1. Watts Bar FSAR, Section 15.0, "Accident Analysis."
RCS Loops - MODE 3 B 3.4.5 (continued)
Watts Bar - Unit 2 B 3.4-22 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.5 RCS Loops - MODE 3
BASES BACKGROUND In MODE 3, the primary function of the reactor coolant is removal of decay heat and transfer of this heat, via the steam generators (SGs), to
the secondary plant fluid. The secondary function of the reactor coolant
is to act as a carrier for soluble neutron poison, boric acid.
The reactor coolant is circulated through four RCS loops, connected in
parallel to the reactor vessel, each containing an SG, a reactor coolant
pump (RCP), and appropriate flow, pressure, level, and temperature
instrumentation for control, protection, and indication. The reactor vessel
contains the clad fuel. The SGs provide the heat sink. The RCPs
circulate the water through the reactor vessel and SGs at a sufficient rate
to ensure proper heat transfer and prevent fuel damage.
In MODE 3, RCPs are used to provide forced circulation for heat removal
during heatup and cooldown. The MODE 3 decay heat removal
requirements are low enough that a single RCS loop with one RCP
running is sufficient to remove core decay heat. However, two RCS loops
are required to be OPERABLE to ensure redundant capability for decay
heat removal.
APPLICABLE
SAFETY ANALYSES Whenever the reactor trip breakers (RTBs) are in the closed position and the control rod drive mechanisms (CRDMs) are energized, an inadvertent
rod withdrawal from subcritical, resulting in a power excursion, is
possible. Such a transient could be caused by a malfunction of the rod
control system. In addition, the possibility of a power excursion due to the
ejection of an inserted control rod is possible with the breakers closed or
open. Such a transient could be caused by the mechanical failure of a
CRDM.
RCS Loops - MODE 3 B 3.4.5 BASES (continued)
Watts Bar - Unit 2 B 3.4-23 (developmental)
A APPLICABLE SAFETY ANALYSES (continued)
Therefore, in MODE 3 with RTBs in the closed position and Rod Control
System capable of rod withdrawal, accidental control rod withdrawal from
subcritical is postulated and requires at least two RCS loops to be
OPERABLE and in operation to ensure that the accident analyses limits
are met. For those conditions when the Rod Control System is not
capable of rod withdrawal, two RCS loops are required to be OPERABLE, but only one RCS loop is required to be in operation to be consistent with
MODE 3 accident analyses.
Failure to provide decay heat removal may result in challenges to a
fission product barrier. The RCS loops are part of the primary success
path that functions or actuates to prevent or mitigate a Design Basis
Accident or transient that either assumes the failure of, or presents a
challenge to, the integrity of a fission product barrier.
RCS Loops - MODE 3 satisfy Criterion 3 of the NRC Policy Statement.
LCO The purpose of this LCO is to require that at least two RCS loops be OPERABLE. In MODE 3 with the RTBs in the closed position and Rod
Control System capable of rod withdrawal, two RCS loops must be in
operation. Two RCS loops are required to be in operation in MODE 3
with RTBs closed and Rod Control System capable of rod withdrawal due
to the postulation of a power excursion because of an inadvertent control
rod withdrawal. The required number of RCS loops in operation ensures
that the Safety Limit criteria will be met for all of the postulated accidents.
With the RTBs in the open position, or the CRDMs de-energized, the Rod
Control System is not capable of rod withdrawal; therefore, only one RCS
loop in operation is necessary to ensure removal of decay heat from the
core and homogenous boron concentration throughout the RCS. An
additional RCS loop is required to be OPERABLE to ensure adequate
decay heat removal capability.
The Note permits all RCPs to be de-energized for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> per 8 hour9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> period. The purpose of the Note is to perform tests that are designed to
validate various accident analyses values. One of these tests is
validation of the pump coastdown curve used as input to a number of
accident analyses including a loss of flow accident. This test is generally
performed in MODE 3 during the initial startup testing program, and as
such should only be performed once.
RCS Loops - MODE 3 B 3.4.5 BASES (continued)
Watts Bar - Unit 2 B 3.4-24 (developmental)
A LCO (continued)
If, however, changes are made to the RCS that would cause a change to the flow characteristics of the RCS, the input values of the coastdown
curve must be revalidated by conducting the test again. The 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> time
period specified is adequate to perform the desired tests, and operating
experience has shown that boron stratification is not a problem during this
short period with no forced flow.
Utilization of the Note is permitted provided the following conditions are
met, along with any other conditions imposed by initial startup test
procedures:
- a. No operations are permitted that would dilute the RCS boron concentration, thereby maintaining the margin to criticality. Boron
reduction is prohibited because a uniform concentration distribution
throughout the RCS cannot be ensured when in natural circulation;
and
- b. Core outlet temperature is maintained at least 10 F below saturation temperature, so that no vapor bubble may form and possibly cause a
natural circulation flow obstruction.
An OPERABLE RCS loop consists of one OPERABLE RCP and one
OPERABLE SG, which has the minimum water level specified in
SR 3.4.5.2. An RCP is OPERABLE if it is capable of being powered and
is able to provide forced flow if required.
RCS Loops - MODE 3 B 3.4.5 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-25 (developmental)
A APPLICABILITY In MODE 3, this LCO ensures forced circulation of the reactor coolant to remove decay heat from the core and to provide proper boron mixing.
The most stringent condition of the LCO, that is, two RCS loops
OPERABLE and two RCS loops in operation, applies to MODE 3 with
RTBs in the closed position. The least stringent condition, that is, two
RCS loops OPERABLE and one RCS loop in operation, applies to
MODE 3 with the RTBs open.
Operation in other MODES is covered by:
LCO 3.4.4, "RCS Loops - MODES 1 and 2";
LCO 3.4.6, "RCS Loops - MODE 4";
LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled";
LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled";
LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level" (MODE 6); and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation -
Low Water Level" (MODE 6).
ACTIONS A.1
If one required RCS loop is inoperable, redundancy for heat removal is
lost. The Required Action is restoration of the required RCS loop to
OPERABLE status within the Completion Time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. This time
allowance is a justified period to be without the redundant, non-operating
loop because a single loop in operation has a heat transfer capability
greater than that needed to remove the decay heat produced in the
reactor core and because of the low probability of a failure in the
remaining loop occurring during this period.
B.1 If restoration is not possible within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, the unit must be brought to
MODE 4. In MODE 4, the unit may be placed on the Residual Heat
Removal System. The additional Completion Time of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is
compatible with required operations to achieve cooldown and
depressurization from the existing plant conditions in an orderly manner
and without challenging plant systems.
RCS Loops - MODE 3 B 3.4.5 BASES (continued)
Watts Bar - Unit 2 B 3.4-26 (developmental)
A ACTIONS (continued)
C.1 and C.2 If the required RCS loop is not in operation, and the RTBs are closed and
Rod Control System capable of rod withdrawal, the Required Action is
either to restore the required RCS loop to operation or to de-energize all
CRDMs by opening the RTBs or de-energizing the motor generator (MG)
sets. When the RTBs are in the closed position and Rod Control System
capable of rod withdrawal, it is postulated that a power excursion could
occur in the event of an inadvertent control rod withdrawal. This
mandates having the heat transfer capacity of two RCS loops in
operation. If only one loop is in operation, the RTBs must be opened.
The Completion Times of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to restore the required RCS loop to
operation or de-energize all CRDMs is adequate to perform these
operations in an orderly manner without exposing the unit to risk for an
undue time period.
D.1, D.2, and D.3
If all RCS loops are inoperable or no RCS loop is in operation, except as
during conditions permitted by the Note in the LCO section, all CRDMs
must be de-energized by opening the RTBs or de-energizing the MG
sets. All operations involving a reduction of RCS boron concentration
must be suspended, and action to restore one of the RCS loops to
OPERABLE status and operation must be initiated. Boron dilution
requires forced circulation for proper mixing, and opening the RTBs or
de-energizing the MG sets removes the possibility of an inadvertent rod
withdrawal. The immediate Completion Time reflects the importance of
maintaining operation for heat removal. The action to restore must be
continued until one loop is restored to OPERABLE status and operation.
SURVEILLANCE
REQUIREMENTS SR 3.4.5.1
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that the required loops are in
operation. Verification includes flow rate, temperature, and pump status
monitoring, which help ensure that forced flow is providing heat removal.
The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient considering other indications and
alarms available to the operator in the control room to monitor RCS loop
performance.
RCS Loops - MODE 3 B 3.4.5 BASES Watts Bar - Unit 2 B 3.4-27 (developmental)
B SURVEILLANCE REQUIREMENTS (continued)
SR 3.4.5.2 requires verification of SG OPERABILITY. SG OPERABILITY
is verified by ensuring that the secondary side narrow range water level is 6 % (value does not account for instrument error) for required RCS loops. If the SG secondary side narrow range water level is less than
6 %, the tubes may become uncovered and the associated loop may not
be capable of providing the heat sink for removal of the decay heat. The
12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Frequency is considered adequate in view of other indications
available in the control room to alert the operator to a loss of SG level.
Verification that the required RCPs are OPERABLE ensures that safety
analyses limits are met. The requirement also ensures that an additional
RCP can be placed in operation, if needed, to maintain decay heat
removal and reactor coolant circulation. Verification is performed by
verifying proper breaker alignment and power availability to the required
RCPs.
REFERENCES None RCS Loops - MODE 4 B 3.4.6 (continued)
Watts Bar - Unit 2 B 3.4-28 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.6 RCS Loops - MODE 4
BASES BACKGROUND In MODE 4, the primary function of the reactor coolant is the removal of decay heat and the transfer of this heat to either the steam generator (SG) secondary side coolant or the component cooling water via the
residual heat removal (RHR) heat exchangers. The secondary function of
the reactor coolant is to act as a carrier for soluble neutron poison, boric
acid.
The reactor coolant is circulated through four RCS loops connected in
parallel to the reactor vessel, each loop containing an SG, a reactor
coolant pump (RCP), and appropriate flow, pressure, level, and
temperature instrumentation for control, protection, and indication. The
RCPs circulate the coolant through the reactor vessel and SGs at a
sufficient rate to ensure proper heat transfer and to prevent boric acid
stratification.
In MODE 4, with the reactor trip breakers open and the rods not capable
of withdrawal, either RCPs or RHR loops can be used to provide forced
circulation. The intent in this case is to provide forced flow from at least
one RCP or one RHR loop for decay heat removal and transport. The
flow provided by one RCP loop or RHR loop is adequate for decay heat
removal. The other intent is to require that two paths be available to
provide redundancy for decay heat removal.
In MODE 4, with the reactor trip breakers closed and the rods capable of
withdrawal, two RCPs must be OPERABLE and in operation to provide
forced circulation.
APPLICABLE
SAFETY ANALYSES In MODE 4, with the reactor trip breakers open and the rods not capable
of withdrawal, RCS circulation is considered in determination of the time
available for mitigation of the accidental boron dilution event. The RCS
and RHR loops provide this circulation.
RCS Loops - MODE 4 B 3.4.6 BASES (continued)
Watts Bar - Unit 2 B 3.4-29 (developmental)
A APPLICABLE SAFETY ANALYSES (continued)
Whenever the reactor trip breakers (RTBs) are in the closed position and
the control rod drive mechanisms (CRDMs) are energized, an inadvertent
rod withdrawal from subcritical, resulting in a power excursion, is
possible. Such a transient could be caused by a malfunction of the rod
control system. In addition, the possibility of a power excursion due to the
ejection of an inserted control rod is possible with the breakers closed or
open. Such a transient could be caused by the mechanical failure of a
CRDM.
Therefore, in MODE 4 with RTBs in the closed position and Rod Control
System capable of rod withdrawal, accidental control rod withdrawal from
subcritical is postulated and requires at least two RCS loops to be
OPERABLE and in operation to ensure that the accident analyses limits
are met. For those conditions when the Rod Control System is not
capable of rod withdrawal, any combination of two RCS or RHR loops are
required to be OPERABLE, but only one loop is required to be in
operation to meet decay heat removal requirements.
RCS Loops - MODE 4 have been identified in the NRC Policy Statement
as important contributors to risk reduction.
LCO The purpose of this LCO is to require that at least two loops be OPERABLE. In MODE 4 with the RTBs in the closed position and Rod
Control System capable of rod withdrawal, two RCS loops must be
OPERABLE and in operation. Two RCS loops are required to be in
operation in MODE 4 with RTBs closed and Rod Control System capable
of rod withdrawal due to the postulation of a power excursion because of
an inadvertent control rod withdrawal. The required number of RCS loops
in operation ensures that the Safety Limit criteria will be met for all of the
postulated accidents.
With the RTBs in the open position, or the CRDMs de-energized, the Rod
Control System is not capable of rod withdrawal; therefore, only one loop
in operation is necessary to ensure removal of decay heat from the core
and homogenous boron concentration throughout the RCS. In this case, the LCO allows the two loops that are required to be OPERABLE to
consist of any combination of RCS loops and RHR loops. An additional
loop is required to be OPERABLE to provide redundancy for heat
removal.
RCS Loops - MODE 4 B 3.4.6 BASES (continued)
Watts Bar - Unit 2 B 3.4-30 (developmental)
B LCO (continued)
The Note requires that the secondary side water temperature of each SG be 50 F above each of the RCS cold leg temperatures before the start of an RCP with any RCS cold leg temperature the COMS arming temperature as specified in the PTLR. This restraint is to prevent a low temperature overpressure event due to a thermal transient when an RCP
is started.
An OPERABLE RCS loop comprises an OPERABLE RCP and an
OPERABLE SG, which has the minimum water level specified in
Similarly for the RHR System, an OPERABLE RHR loop comprises an
OPERABLE RHR pump capable of providing forced flow to an
OPERABLE RHR heat exchanger. RCPs and RHR pumps are
OPERABLE if they are capable of being powered and are able to provide
forced flow if required.
APPLICABILITY In MODE 4, this LCO ensures forced circulation of the reactor coolant to remove decay heat from the core and to provide proper boron mixing.
One loop of either RCS or RHR provides sufficient circulation for these
purposes. However, two loops consisting of any combination of RCS and
RHR loops are required to be OPERABLE to meet single failure
considerations.
Operation in other MODES is covered by:
LCO 3.4.4, "RCS Loops - MODES 1 and 2";
LCO 3.4.5, "RCS Loops - MODE 3";
LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled";
LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled";
LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level" (MODE 6); and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation -
Low Water Level" (MODE 6).
RCS Loops - MODE 4 B 3.4.6 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-31 (developmental)
A ACTIONS A.1 If only one RCS loop is OPERABLE and both RHR loops are inoperable, redundancy for heat removal is lost. Action must be initiated to restore a
second RCS or RHR loop to OPERABLE status. The immediate
Completion Time reflects the importance of maintaining the availability of
two paths for heat removal.
B.1 If one required RHR loop is OPERABLE and in operation and there are
no RCS loops OPERABLE, an inoperable RCS or RHR loop must be
restored to OPERABLE status to provide a redundant means for decay
heat removal.
If the parameters that are outside the limits cannot be restored, the plant
must be brought to MODE 5 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Bringing the plant to
MODE 5 is a conservative action with regard to decay heat removal. With
only one RHR loop OPERABLE, redundancy for decay heat removal is
lost and, in the event of a loss of the remaining RHR loop, it would be
safer to initiate that loss from MODE 5 ( 200 F) rather than MODE 4 (200 to 350 F). The Completion Time of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is a reasonable time, based on operating experience, to reach MODE 5 from MODE 4 in an
orderly manner and without challenging plant systems.
C.1 and C.2
If one required RCS loop is not in operation, and the RTBs are closed and
Rod Control System capable of rod withdrawal, the Required Action is
either to restore the required RCS loop to operation or to de-energize all
CRDMs by opening the RTBs or de-energizing the motor generator (MG)
sets. When the RTBs are in the closed position and Rod Control System
capable of rod withdrawal, it is postulated that a power excursion could
occur in the event of an inadvertent control rod withdrawal. This
mandates having the heat transfer capacity of two RCS loops in
operation. If only one loop is in operation, the RTBs must be opened.
The Completion Times of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to restore the required RCS loop to
operation or de-energize all CRDMs is adequate to perform these
operations in an orderly manner without exposing the unit to risk for an
undue time period.
RCS Loops - MODE 4 B 3.4.6 BASES (continued)
Watts Bar - Unit 2 B 3.4-32 (developmental)
A ACTIONS (continued)
D.1, D.2 and D.3 If no loop is OPERABLE or in operation, all CRDMs must be
de-energized by opening the RTBs or de-energizing the MG sets. All
operations involving a reduction of RCS boron concentration must be
suspended, and action to restore one RCS or RHR loop to OPERABLE
status and operation must be initiated. Boron dilution requires forced
circulation for proper mixing, and the margin to criticality must not be
reduced in this type of operation. Opening the RTBs or de-energizing the
MG sets removes the possibility of an inadvertent rod withdrawal. The
immediate Completion Times reflect the importance of maintaining
operation for decay heat removal. The action to restore must be
continued until one loop is restored to OPERABLE status and operation.
SURVEILLANCE
REQUIREMENTS SR 3.4.6.1
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that two RCS loops are in
operation when the rod control system is capable of rod withdrawal.
Verification includes flow rate, temperature, or pump status monitoring, which help ensure that forced flow is providing heat removal. The
Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient considering other indications and
alarms available to the operator in the control room to monitor RCS and
RHR loop performance.
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that one RCS or RHR loop is
in operation when the rod control system is not capable of rod withdrawal.
Verification includes flow rate, temperature, or pump status monitoring, which help ensure that forced flow is providing heat removal. The
Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient considering other indications and
alarms available to the operator in the control room to monitor RCS and
RHR loop performance.
RCS Loops - MODE 4 B 3.4.6 BASES Watts Bar - Unit 2 B 3.4-33 (developmental)
B SURVEILLANCE REQUIREMENTS (continued)
SR 3.4.6.3 requires verification of SG OPERABILITY. SG OPERABILITY
is verified by ensuring that the secondary side narrow range water level is 6% (value does not account for instrument error). If the SG secondary side narrow range water level is < 6%, the tubes may become uncovered
and the associated loop may not be capable of providing the heat sink
necessary for removal of decay heat. The 12-hour Frequency is
considered adequate in view of other indications available in the control
room to alert the operator to the loss of SG level.
Verification that the required pump is OPERABLE ensures that an
additional RCS or RHR pump can be placed in operation, if needed, to
maintain decay heat removal and reactor coolant circulation. Verification
is performed by verifying proper break er alignment and power available to the required pump. The Frequency of 7 days is considered reasonable in
view of other administrative controls available and has been shown to be
acceptable by operating experience.
REFERENCES None RCS Loops - MODE 5, Loops Filled B 3.4.7 (continued)
Watts Bar - Unit 2 B 3.4-34 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.7 RCS Loops - MODE 5, Loops Filled
BASES BACKGROUND In MODE 5 with the RCS loops filled, the primary function of the reactor coolant is the removal of decay heat and the transfer of this heat to either
the steam generator (SG) secondary side coolant or the component
cooling water via the residual heat removal (RHR) heat exchangers.
While the principal means for decay heat removal is via the RHR System, the SGs are specified as a backup means for redundancy. Even though
the SGs cannot produce steam in this MODE, they are capable of being a
heat sink due to their large contained volume of secondary water. As
long as the SG secondary side water is at a lower temperature than the
reactor coolant, heat transfer will occur. The rate of heat transfer is
directly proportional to the temperature difference. The secondary
function of the reactor coolant is to act as a carrier for soluble neutron
poison, boric acid.
In MODE 5 with RCS loops filled, the reactor coolant is circulated by
means of two RHR loops connected to the RCS, each loop containing an
RHR heat exchanger, an RHR pump, and appropriate flow and
temperature instrumentation for control, protection, and indication.
One RHR pump circulates the water through the RCS at a sufficient rate
to prevent boric acid stratification.
The number of loops in operation can vary to suit the operational needs.
The intent of this LCO is to provide forced flow from at least one RHR
loop for decay heat removal and transport. The flow provided by one
RHR loop is adequate for decay heat removal. The other intent of this
LCO is to require that a second path be available to provide redundancy
for heat removal.
The LCO provides for redundant paths of decay heat removal capability.
The first path can be an RHR loop that must be OPERABLE and in
operation. The second path can be another OPERABLE RHR loop or
maintaining two SGs with secondary side water levels greater than or
equal to 6% narrow range to provide an alternate method for decay heat
removal.
RCS Loops - MODE 5, Loops Filled B 3.4.7 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-35 (developmental)
B APPLICABLE SAFETY ANALYSES In MODE 5, RCS circulation is considered in the determination of the time
available for mitigation of the accidental boron dilution event. The RHR
loops provide this circulation.
RCS Loops - MODE 5 (Loops Filled) have been identified in the NRC
Policy Statement as important contributors to risk reduction.
LCO The purpose of this LCO is to require that at least one of the RHR loops be OPERABLE and in operation with an additional RHR loop OPERABLE
or two SGs with secondary side water level greater than or equal to
6% narrow range. One RHR loop provides sufficient forced circulation to
perform the safety functions of the reactor coolant under these conditions.
An additional RHR loop is required to be OPERABLE to meet single
failure considerations. However, if the standby RHR loop is not
OPERABLE, an acceptable alternate method is two SGs with their
secondary side water levels greater than or equal to 6% narrow range.
Should the operating RHR loop fail, the SGs could be used to remove the
decay heat.
Note 1 allows one RHR loop to be inoperable for a period of up to
2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, provided that the other RHR loop is OPERABLE and in
operation. This permits periodic surveillance tests to be performed on the
inoperable loop during the only time when such testing is safe and
possible.
Note 2 requires that the secondary side water temperature of each SG be 50 F above each of the RCS cold leg temperatures before the start of a reactor coolant pump (RCP) with an RCS cold leg temperature the COMS arming temperature specified in the PTLR. This restriction is to prevent a low temperature overpressure event due to a thermal transient
when an RCP is started.
Note 3 provides for an orderly transition from MODE 5 to MODE 4 during
a planned heatup by permitting removal of RHR loops from operation
when at least one RCS loop is in operation. This Note provides for the
transition to MODE 4 where an RCS loop is permitted to be in operation
and replaces the RCS circulation function provided by the RHR loops.
RHR pumps are OPERABLE if they are capable of being powered and
are able to provide flow if required. An SG can perform as a heat sink
when it has an adequate water level and is OPERABLE.
RCS Loops - MODE 5, Loops Filled B 3.4.7 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-36 (developmental)
A APPLICABILITY In MODE 5 with RCS loops filled, this LCO requires forced circulation of the reactor coolant to remove decay heat from the core and to provide proper boron mixing. One loop of RHR provides sufficient circulation for
these purposes. However, one additional RHR loop is required to be
OPERABLE, or the secondary side water level of at least two SGs is
required to be 6% narrow range.
Operation in other MODES is covered by:
LCO 3.4.4, "RCS Loops - MODES 1 and 2";
LCO 3.4.5, "RCS Loops - MODE 3";
LCO 3.4.6, "RCS Loops - MODE 4";
LCO 3.4.8, "RCS Loops - MODE 5, Loops Not Filled";
LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level" (MODE 6); and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation -
Low Water Level" (MODE 6).
ACTIONS A.1 and A.2
If one RHR loop is inoperable and the required SGs have secondary side
water levels < 6% narrow range, redundancy for heat removal is lost.
Action must be initiated immediately to restore a second RHR loop to
OPERABLE status or to restore the required SG secondary side water
levels. Either Required Action A.1 or Required Action A.2 will restore
redundant heat removal paths. The immediate Completion Time reflects
the importance of maintaining the availability of two paths for heat
removal.
B.1 and B.2
If no RHR loop is in operation, except during conditions permitted by
Note 1, or if no loop is OPERABLE, all operations involving a reduction of
RCS boron concentration must be suspended and action to restore one
RHR loop to OPERABLE status and operation must be initiated. To
prevent boron dilution, forced circulation is required to provide proper
mixing and preserve the margin to criticality in this type of operation. The
immediate Completion Times reflect the importance of maintaining
operation for heat removal.
RCS Loops - MODE 5, Loops Filled B 3.4.7 BASES (continued)
Watts Bar - Unit 2 B 3.4-37 (developmental)
B SURVEILLANCE REQUIREMENTS SR 3.4.7.1
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that the required loop is in
operation. Verification includes flow rate, temperature, or pump status
monitoring, which help ensure that forced flow is providing heat removal.
The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient considering other indications and
alarms available to the operator in the control room to monitor RHR loop
performance.
Verifying that at least two SGs are OPERABLE by ensuring their
secondary side narrow range water levels are greater than or equal to 6%
(value does not account for instrument error) narrow range ensures an alternate decay heat removal method in the event that the second RHR
loop is not OPERABLE. If both RHR loops are OPERABLE, this
Surveillance is not needed. The 12-hour Frequency is considered
adequate in view of other indications available in the control room to alert
the operator to the loss of SG level.
Verification that a second RHR pump is OPERABLE ensures that an
additional pump can be placed in operation, if needed, to maintain decay
heat removal and reactor coolant circulation. Verification is performed by
verifying proper breaker alignment and power available to the RHR pump.
If secondary side water level is greater than or equal to 6% narrow range
in at least two SGs, this Surveillance is not needed. The Frequency of
7 days is considered reasonable in view of other administrative controls
available and has been shown to be acceptable by operating experience.
REFERENCES None RCS Loops - MODE 5, Loops Not Filled B 3.4.8 (continued)
Watts Bar - Unit 2 B 3.4-38 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.8 RCS Loops - MODE 5, Loops Not Filled
BASES
BACKGROUND In MODE 5 with the RCS loops not filled, the primary function of the reactor coolant is the removal of decay heat generated in the fuel, and the
transfer of this heat to the component cooling water via the residual heat
removal (RHR) heat exchangers. The steam generators (SGs) are not
available as a heat sink when the loops are not filled. The secondary
function of the reactor coolant is to act as a carrier for the soluble neutron
poison, boric acid.
In MODE 5 with loops not filled, only RHR pumps can be used for coolant
circulation. The number of pumps in operation can vary to suit the operational needs. The intent of this LCO is to provide forced flow from at least one RHR pump for decay heat removal and transport and to require
that two paths be available to provide redundancy for heat removal.
APPLICABLE
SAFETY ANALYSES In MODE 5, RCS circulation is considered in the determination of the time
available for mitigation of the accidental boron dilution event. The RHR
loops provide this circulation. The flow provided by one RHR loop is
adequate for heat removal and for boron mixing.
RCS loops in MODE 5 (loops not filled) have been identified in the NRC
Policy Statement as important contributors to risk reduction.
LCO The purpose of this LCO is to require that at least two RHR loops be OPERABLE and one of these loops be in operation. An OPERABLE loop
is one that has the capability of transferring heat from the reactor coolant
at a controlled rate. Heat cannot be removed via the RHR System unless
forced flow is used. A minimum of one running RHR pump meets the
LCO requirement for one loop in operation. An additional RHR loop is
required to be OPERABLE to meet single failure considerations.
RCS Loops - MODE 5, Loops Not Filled B 3.4.8 BASES (continued)
Watts Bar - Unit 2 B 3.4-39 (developmental)
A LCO (continued)
Note 1 permits all RHR pumps to be de-energized for 15 minutes when switching from one loop to another. The circumstances for stopping both RHR pumps are to be limited to situations when the outage time is short
and core outlet temperature is maintained > 10 F below saturation temperature. The Note prohibits boron dilution or draining operations
when RHR forced flow is stopped.
Note 2 allows one RHR loop to be inoperable for a period of 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />, provided that the other loop is OPERABLE and in operation. This permits
periodic surveillance tests to be performed on the inoperable loop during
the only time when these tests are safe and possible.
An OPERABLE RHR loop is comprised of an OPERABLE RHR pump
capable of providing forced flow to an OPERABLE RHR heat exchanger.
RHR pumps are OPERABLE if they are capable of being powered and are able to provide flow if required.
APPLICABILITY In MODE 5 with loops not filled, this LCO requires core heat removal and coolant circulation by the RHR System.
Operation in other MODES is covered by:
LCO 3.4.4, "RCS Loops - MODES 1 and 2;" LCO 3.4.5, "RCS Loops - MODE 3;"
LCO 3.4.6, "RCS Loops - MODE 4;"
LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled;"
LCO 3.9.5, "Residual Heat Removal (RHR) and Coolant Circulation - High Water Level" (MODE 6); and LCO 3.9.6, "Residual Heat Removal (RHR) and Coolant Circulation - Low Water Level" (MODE 6).
RCS Loops - MODE 5, Loops Not Filled B 3.4.8 BASES (continued)
Watts Bar - Unit 2 B 3.4-40 (developmental)
A ACTIONS A.1 If only one RHR loop is OPERABLE and in operation, redundancy for
RHR is lost. Action must be initiated to restore a second loop to
OPERABLE status. The immediate Completion Time reflects the
importance of maintaining the availability of two paths for heat removal.
B.1 and B.2
If no required RHR loops are OPERABLE or in operation, except during
conditions permitted by Note 1, all operations involving a reduction of
RCS boron concentration must be suspended and action must be initiated
immediately to restore an RHR loop to OPERABLE status and operation.
Boron dilution requires forced circulation for uniform dilution, and the
margin to criticality must not be reduced in this type of operation. The
immediate Completion Time reflects the importance of maintaining
operation for heat removal. The action to restore must continue until one
loop is restored to OPERABLE status and operation.
SURVEILLANCE
REQUIREMENTS SR 3.4.8.1
This SR requires verification every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> that one loop is in operation.
Verification includes flow rate, temperature, or pump status monitoring, which help ensure that forced flow is providing heat removal. The
Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient considering other indications and
alarms available to the operator in the control room to monitor RHR loop
performance.
Verification that the required number of pumps are OPERABLE ensures
that additional pumps can be placed in operation, if needed, to maintain
decay heat removal and reactor coolant circulation. Verification is
performed by verifying proper breaker alignment and power available to the required pumps. The Frequency of 7 days is considered reasonable
in view of other administrative controls available and has been shown to
be acceptable by operating experience.
REFERENCES None.
Pressurizer B 3.4.9 (continued)
Watts Bar - Unit 2 B 3.4-41 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.9 Pressurizer
BASES BACKGROUND The pressurizer provides a point in the RCS where liquid and vapor are maintained in equilibrium under saturated conditions for pressure control
purposes to prevent bulk boiling in the remainder of the RCS. Key
functions include maintaining required primary system pressure during
steady state operation, and limiting the pressure changes caused by
reactor coolant thermal expansion and contraction during normal load
The pressure control components addressed by this LCO include the
pressurizer water level, the required heaters, and their controls.
Pressurizer safety valves and pressurizer power operated relief valves
are addressed by LCO 3.4.10, "Pressurizer Safety Valves," and
LCO 3.4.11, "Pressurizer Power Operated Relief Valves (PORVs),"
respectively.
The intent of the LCO is to ensure that a steam bubble exists in the
pressurizer prior to power operation to minimize the consequences of
potential overpressure transients. The presence of a steam bubble is
consistent with analytical assumptions. Relatively small amounts of
noncondensible gases can inhibit the condensation heat transfer between
the pressurizer spray and the steam, and diminish the spray effectiveness
for pressure control.
Electrical immersion heaters, located in the lower section of the
pressurizer vessel, keep the water in the pressurizer at saturation
temperature and maintain a constant operating pressure. A minimum
required available capacity of pressurizer heaters ensures that the RCS
pressure can be maintained. The capability to maintain and control
system pressure is important for maintaining subcooled conditions in the
RCS and ensuring the capability to remove core decay heat by either
forced or natural circulation of reactor coolant. Unless adequate heater
capacity is available, the hot, high pressure condition cannot be
maintained indefinitely and still provide the required subcooling margin in
the primary system. Inability to control the system pressure and maintain
subcooling under conditions of natural circulation flow in the primary
system could lead to a loss of single phase natural circulation and
decreased capability to remove core decay heat.
Pressurizer B 3.4.9 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-42 (developmental)
A APPLICABLE SAFETY ANALYSES In MODES 1, 2, and 3, the LCO requirement for a steam bubble is
reflected implicitly in the accident analyses. Safety analyses performed
for lower MODES are not limiting. All analyses performed from a critical
reactor condition assume the existence of a steam bubble and saturated
conditions in the pressurizer. In making this assumption, the analyses
neglect the small fraction of noncondensible gases normally present.
Safety analyses presented in the FSAR (Ref. 1) do not take credit for
pressurizer heater operation; however, an implicit initial condition
assumption of the safety analyses is that the RCS is operating at normal
pressure.
The maximum pressurizer water level limit satisfies Criterion 2 of the NRC
Policy Statement. Although the heaters are not specifically used in
accident analysis, the need to maintain subcooling in the long term during
loss of offsite power, as indicated in NUREG-0737 (Ref. 2), is the reason
for providing an LCO.
LCO The LCO requirement for the pressurizer to be OPERABLE with a water volume 1656 cubic feet, which is equivalent to 92%, ensures that a steam bubble exists. Limiting the LCO maximum operating water level
preserves the steam space for pressure control. The LCO has been
established to ensure the capability to establish and maintain pressure
control for steady state operation and to minimize the consequences of
potential overpressure transients. Requiring the presence of a steam
bubble is also consistent with analytical assumptions.
The LCO requires two groups of OPERABLE pressurizer heaters, each
with a capacity 150 kW. The minimum heater capacity required is sufficient to maintain the RCS near normal operating pressure when
accounting for heat losses through the pressurizer insulation. By
maintaining the pressure near the operating conditions, a wide margin to
subcooling can be obtained in the loops. The design value of 150 kW per
group is exceeded by the use of fifteen heaters in a group rated at
23.1 kW each. The amount needed to maintain pressure is dependent on
the heat losses.
Pressurizer B 3.4.9.BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-43 (developmental)
A APPLICABILITY The need for pressure control is most pertinent when core heat can cause the greatest effect on RCS temperature, resulting in the greatest effect on pressurizer level and RCS pressure control. Thus, applicability has been
designated for MODES 1 and 2. The applicability is also provided for
MODE 3. The purpose is to prevent solid water RCS operation during
heatup and cooldown to avoid rapid pressure rises caused by normal
operational perturbation, such as reactor coolant pump startup.
In MODES 1, 2, and 3, there is need to maintain the availability of
pressurizer heaters. In the event of a loss of offsite power, the initial
conditions of these MODES give the greatest demand for maintaining the
RCS in a hot pressurized condition with loop subcooling for an extended
period. For MODE 4, 5, or 6, it is not necessary to control pressure (by
heaters) to ensure loop subcooling for heat transfer when the Residual
Heat Removal (RHR) System is in service, and therefore, the LCO is not
applicable.
ACTIONS A.1 and A.2
Pressurizer water level control malfunctions or other plant evolutions may
result in a pressurizer water level above the nominal upper limit, even
with the plant at steady state conditions. Normally the plant will trip in this
event since the upper limit of this LCO is the same as the Pressurizer
Water Level - High Trip.
If the pressurizer water level is not within the limit, action must be taken to
restore the plant to operation within the bounds of the safety analyses. To
achieve this status, the plant must be brought to MODE 3, with the
reactor trip breakers open, within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.
This takes the plant out of the applicable MODES and restores the plant
to operation within the bounds of the safety analyses.
The allowed Completion Times are reasonable, based on operating
experience, to reach the required plant conditions from full power
conditions in an orderly manner and without challenging plant systems.
Pressurizer B 3.4.9.BASES (continued)
Watts Bar - Unit 2 B 3.4-44 (developmental)
B ACTIONS (continued)
B.1 If one required group of pressurizer heaters is inoperable, restoration is
required within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. The Completion Time of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is reasonable
considering the anticipation that a demand caused by loss of offsite
power would be unlikely in this period.
C.1 and C.2
If one group of pressurizer heaters is inoperable and cannot be restored
in the allowed Completion Time of Required Action B.1, the plant must be
brought to a MODE in which the LCO does not apply. To achieve this
status, the plant must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to
MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions
from full power conditions in an orderly manner and without challenging
plant systems.
SURVEILLANCE
REQUIREMENTS SR 3.4.9.1
This SR requires that during steady state operation, pressurizer level is
maintained below the nominal upper level limit of 92% (value does not account for instrument error) to provide a minimum space for a steam bubble. The Surveillance is performed by observing the indicated level.
The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> corresponds to verifying the parameter each
shift. The 12-hour interval has been shown by operating practice to be
sufficient to regularly assess level for any deviation and verify that
operation is within safety analyses assumptions. Alarms are also
available for early detection of abnormal level indications.
The SR is satisfied when the power supplies are demonstrated to be
capable of producing the minimum power and the associated pressurizer
heaters are verified to be at their design rating. This may be done by
testing the power supply output and by performing an electrical check on
heater element continuity and resistance. The Frequency of 92 days is
considered adequate to detect heater degradation and has been shown
by operating experience to be acceptable.
Pressurizer B 3.4.9.BASES (continued)
Watts Bar - Unit 2 B 3.4-45 (developmental)
B REFERENCES 1. Watts Bar FSAR, Section 15.0, "Accident Analyses." 2. NUREG-0737, "Clarification of TMI Action Plan Requirements," November 1980.
Pressurizer Safety Valves B 3.4.10 (continued)
Watts Bar - Unit 2 B 3.4-46 (developmental)
B B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.10 Pressurizer Safety Valves
BASES BACKGROUND The pressurizer safety valves pr ovide, in conjunction with the Reactor Protection System, overpressure protection for the RCS. The pressurizer
safety valves are totally enclosed pop type, spring loaded, self actuated
valves with backpressure compensation. The safety valves are designed
to prevent the system pressure from exceeding the system Safety Limit (SL), 2735 psig, which is 110% of the design pressure.
Because the safety valves are totally enclosed and self actuating, they
are considered independent components. The relief capacity for each
valve, 420,000 lb/hr, is based on postulated overpressure transient
conditions resulting from a complete loss of steam flow to the turbine.
This event results in the maximum surge rate into the pressurizer, which
specifies the minimum relief capacity for the safety valves. The discharge
flow from the pressurizer safety valves is directed to the pressurizer relief
tank. This discharge flow is indicated by an increase in temperature
downstream of the pressurizer safety valves or increase in the pressurizer
relief tank temperature or level.
Overpressure protection is required in MODES 1, 2, 3, 4, and 5; however, in MODE 4 with any RCS cold leg temperature <
the COMS arming temperature specified in the PTLR, MODE 5, and MODE 6 with the reactor vessel head on, overpressure protection is provided by operating
procedures and by meeting the requirements of LCO 3.4.12, "Cold
Overpressure Mitigation System (COMS)."
The upper and lower pressure limits are based on a 3% tolerance. The lift setting is for the ambient conditions associated with MODES 1, 2, 3, and MODE 4 with all RCS cold leg temperatures > the COMS arming temperature specified in the PTLR. This requires either that the valves be set hot or that a correlation between hot and cold settings be established.
The pressurizer safety valves are part of the primary success path and
mitigate the effects of postulated accidents. OPERABILITY of the safety
valves ensures that the RCS pressure will be limited to 110% of design
pressure.
Pressurizer Safety Valves B 3.4.10 BASES (continued)
Watts Bar - Unit 2 B 3.4-47 (developmental)
A BACKGROUND (continued)
The consequences of exceeding the American Society of Mechanical Engineers (ASME) pressure limit (Ref. 1) could include damage to RCS
components, increased leakage, or a requirement to perform additional
stress analyses prior to resumption of reactor operation.
APPLICABLE
SAFETY ANALYSES All accident and safety analyses in the FSAR (Ref. 2) that require safety
valve actuation assume operation of three pressurizer safety valves to
limit increases in RCS pressure. The overpressure protection analysis (Ref. 3) is also based on operation of three safety valves. Accidents that
could result in overpressurization if not properly terminated include:
- a. Uncontrolled rod withdrawal from full power;
- b. Loss of reactor coolant flow;
- c. Loss of external electrical load;
- d. Loss of normal feedwater;
- e. Loss of all AC power to station auxiliaries;
- f. Locked rotor; and
- g. Feedwater line break.
Detailed analyses of the above transients are contained in Reference 2.
Safety valve actuation is required in events c, d, e, f, and g (above) to
limit the pressure increase. Compliance with this LCO is consistent with
the design bases and accident analyses assumptions.
Pressurizer safety valves satisfy Criterion 3 of the NRC Policy Statement.
Pressurizer Safety Valves B 3.4.10 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-48 (developmental)
B LCO The three pressurizer safety valves are set to open at the RCS design pressure (2485 psig), and within the specified tolerance, to avoid exceeding the maximum design pressure SL, to maintain accident
analyses assumptions, and to comply with ASME requirements. The
upper and lower pressure tolerance limits are based on a 3% tolerance.
The limit protected by this Specification is the reactor coolant pressure
boundary (RCPB) SL of 110% of design pressure. Inoperability of one or
more valves could result in exceeding the SL if a transient were to occur.
The consequences of exceeding the ASME pressure limit could include
damage to one or more RCS components, increased leakage, or
additional stress analysis being required prior to resumption of reactor
operation.
APPLICABILITY In MODES 1, 2, 3, and MODE 4 with all RCS cold leg temperatures > the COMS arming temperature specified in the PTLR, OPERABILITY of three valves is required because the combined capacity is required to keep
reactor coolant pressure below 110% of its design value during certain
accidents. MODE 3 is conservatively included, although the listed
accidents may not require the safety valves for protection.
The LCO is not applicable in MODE 4 when all RCS cold leg
temperatures are the COMS arming temperature as specified in the PTLR, in MODE 5, or in MODE 6 (with the reactor vessel head on) because COMS is provided. Overpressure protection is not required in
MODE 6 with reactor vessel head detensioned.
The Note allows entry into MODE 3 and MODE 4 with all RCS cold leg temperatures > the COMS arming temperature specified in the PTLR, with the lift settings outside the LCO limits. This permits testing and
examination of the safety valves at high pressure and temperature near
their normal operating range, but only after the valves have had a
preliminary cold setting. The cold setting gives assurance that the valves
are OPERABLE near their design condition. Only one valve at a time will
be removed from service for testing. The 54-hour exception is based on
18 hour2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> outage time for each of the three valves. The 18 hour2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> period is
derived from operating experience that hot testing can be performed in
this timeframe.
Pressurizer Safety Valves B 3.4.10 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-49 (developmental)
B ACTIONS A.1 With one pressurizer safety valve inoperable, restoration must take place
within 15 minutes. The Completion Time of 15 minutes reflects the
importance of maintaining the RCS Overpressure Protection System. An
inoperable safety valve coincident with an RCS overpressure event could
challenge the integrity of the pressure boundary.
B.1 and B.2
If the Required Action of A.1 cannot be met within the required
Completion Time or if two or more pressurizer safety valves are
inoperable, the plant must be brought to a MODE in which the
requirement does not apply. To achieve this status, the plant must be
brought to at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to MODE 4 with any RCS cold leg temperature <
the COMS arming temperature specified in the PTLR within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions
from full power conditions in an orderly manner and without challenging
plant systems. With any RCS cold leg temperatures at or below the COMS arming temperature as specified in the PTLR, overpressure protection is provided by the COMS System. The change from MODE 1, 2, or 3 to MODE 4 with any RCS cold leg temperature <
the COMS arming temperature specified in the PTLRreduces the RCS energy (core power and pressure), lowers the potential for large pressurizer insurges, and thereby removes the need for overpressure protection by three pressurizer safety valves.
SURVEILLANCE
REQUIREMENTS SR 3.4.10.1
SRs are specified in the Inservice Testing Program. Pressurizer safety
valves are to be tested in accordance with the requirements of the ASME
OM Code (Ref. 4), which provides the activities and Frequencies
necessary to satisfy the SRs. No additional requirements are specified.
The pressurizer safety valve setpoint is 3% for OPERABILITY, however, the valves are reset to 1% during the surveillance to allow for drift.
Pressurizer Safety Valves B 3.4.10 BASES (continued)
Watts Bar - Unit 2 B 3.4-50 (developmental)
B REFERENCES 1. ASME Boiler and Pressure Vessel Code,Section III, NB 7000, 1971 Edition through Summer 1973.
- 2. Watts Bar FSAR, Section 15.0, "Accident Analyses." 3. WCAP-7769, Rev. 1, "Topical Report on Overpressure Protection for Westinghouse Pressurized Water Reactors," June 1972.
- 4. American Society of Mechanical Engineers (ASME) OM Code, "Code for Operation and Maintenance of Nuclear Power Plants."
Pressurizer PORVs B 3.4.11 (continued)
Watts Bar - Unit 2 B 3.4-51 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.11 Pressurizer Power Operated Relief Valves (PORVs)
BASES BACKGROUND The pressurizer is equipped with two types of devices for pressure relief:
pressurizer safety valves and PORVs. The PORVs are pilot-operated
solenoid valves that are controlled to open at a specific set pressure
when the pressurizer pressure increases and close when the pressurizer
pressure decreases. The PORVs may also be manually operated from
the control room.
Block valves, which are normally open, are located between the
pressurizer and the PORVs. The block valves are used to isolate the
PORVs in case of excessive leakage or a stuck open PORV. Block valve closure is accomplished manually using controls in the control room. A stuck open PORV is, in effect, a small break loss of coolant accident (LOCA). As such, block valve closure terminates the RCS
depressurization and coolant inventory loss.
The PORVs and their associated block valves may be used by plant
operators to depressurize the RCS to recover from certain transients if
normal pressurizer spray is not available. Additionally, the series
arrangement of the PORVs and their block valves permit performance of
surveillances on the valves during power operation.
The PORVs may also be used for feed and bleed core cooling in the case
of multiple equipment failure events that are not within the design basis, such as a total loss of feedwater.
The PORVs, their block valves, and their controls are powered from the
vital buses that normally receive power from offsite power sources, but
are also capable of being powered from emergency power sources in the
event of a loss of offsite power. Two PORVs and their associated block
valves are powered from two separate safety trains (Ref. 1).
Pressurizer PORVs B 3.4.11 BASES (continued)
Watts Bar - Unit 2 B 3.4-52 (developmental)
A BACKGROUND (continued)
The plant has two PORVs, each having a relief capacity of 210,000 lb/hr at 2485 psig. The functional design of the PORVs is based on
maintaining pressure below the Pressurizer Pressure - High reactor trip
setpoint following a step reduction of 50% of full load with steam dump.
In addition, the PORVs minimize challenges to the pressurizer safety
valves and also may be used for low temperature overpressure protection (LTOP). See LCO 3.4.12, "Cold Overpressure Mitigation System (COMS)."
APPLICABLE
SAFETY ANALYSES Plant operators employ the PORVs to depressurize the RCS in response
to certain plant transients if normal pressurizer spray is not available. For
the Steam Generator Tube Rupture (SGTR) event, the safety analysis
assumes that manual operator actions are required to mitigate the event.
A loss of offsite power is assumed to accompany the event, and thus, normal pressurizer spray is unavailable to reduce RCS pressure. The
PORVs are assumed to be used for RCS depressurization, which is one
of the steps performed to equalize the primary and secondary pressures
in order to terminate the primary to secondary break flow and the
radioactive releases from the affected steam generator.
The PORVs are modeled in safety analyses for events that result in
increasing RCS pressure for which departure from nucleate boiling ratio (DNBR), pressurizer filling, or reactor coolant saturation criteria are critical (Ref. 2). By assuming PORV actuation, the primary pressure remains
below the high pressurizer pressure trip setpoint; thus, the DNBR
calculation is more conservative. As such, this actuation is not required
to mitigate these events, and PORV automatic operation is, therefore, not
an assumed safety function.
Pressurizer PORVs satisfy Criterion 3 of the NRC Policy Statement.
Pressurizer PORVs B 3.4.11 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-53 (developmental)
A LCO The LCO requires the PORVs and their associated block valves to be OPERABLE for manual operation to mitigate the effects associated with an SGTR.
By maintaining two PORVs and their associated block valves
OPERABLE, the single failure criterion is satisfied. An OPERABLE block
valve may be either open and energized with the capability to be closed, or closed and energized with the capability to be opened, since the
required safety function is accomplished by manual operation, the block
valves may be OPERABLE when closed to isolate the flow path of an
inoperable PORV that is capable of being manually cycled (e.g., as in the
case of excessive PORV leakage). Similarly, isolation of an OPERABLE
PORV does not render that PORV or block valve inoperable provided the
relief function remains available with manual action.
An OPERABLE PORV is required to be capable of manually opening and closing and not experiencing excessive seat leakage. Excessive seat
leakage although not associated with a specific acceptance criteria, exists
when conditions dictate closure of block valve to limit leakage.
Satisfying the LCO helps minimize challenges to fission product barriers.
APPLICABILITY In MODES 1, 2, and 3, the PORV and its block valve are required to be OPERABLE to limit the potential for a small break LOCA through the flow
path. The most likely cause for a PORV small break LOCA is a result of a
pressure increase transient that causes the PORV to open. Imbalances
in the energy output of the core and heat removal by the secondary
system can cause the RCS pressure to increase to the PORV opening
setpoint. The most rapid increases will occur at the higher operating
power and pressure conditions of MODES 1 and 2. The PORVs are also
required to be OPERABLE in MODES 1, 2, and 3 for manual actuation to
mitigate a steam generator tube rupture event.
Pressure increases are less prominent in MODE 3 because the core input energy is reduced, but the RCS pressure is high. Therefore, the LCO is
applicable in MODES 1, 2, and 3. The LCO is not applicable in MODE 4, 5, and 6 with the reactor vessel head in place when both pressure and
core energy are decreased and the pressure surges become much less
significant. LCO 3.4.12 addresses the PORV requirements in these
MODES.
Pressurizer PORVs B 3.4.11 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-54 (developmental)
A ACTIONS A Note has been added to clarify that all pressurizer PORVs are treated as separate entities, each with separate Completion Times (i.e., the Completion Time is on a component basis).
A.1 PORVs may be inoperable and capable of being manually cycled (e.g., due to excessive seat leakage). In this condition, either the PORV
must be restored or the flow path isolated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. The associated
block valve is required to be closed, but power must be maintained to the
associated block valve, since removal of power would render the block
valve inoperable. This permits operation of the plant until the next
refueling outage (MODE 6) so that maintenance can be performed on the
PORVs to eliminate the problem condition.
Quick access to the PORV for pressure control can be made when power
remains on the closed block valve. The Completion Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is
based on plant operating experience that has shown that minor problems
can be corrected or closure accomplished in this time period.
B.1, B.2, and B.3
If one PORV is inoperable and not capable of being manually cycled, it
must be either restored or isolated by closing the associated block valve
and removing the power to the associated block valve. The Completion
Times of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> are reasonable, based on challenges to the PORVs
during this time period, and provide the operator adequate time to correct
the situation. If the inoperable valve cannot be restored to OPERABLE
status, it must be isolated within the specified time. Because there is at
least one PORV that remains OPERABLE, an additional 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is
provided to restore the inoperable PORV to OPERABLE status. If the PORV cannot be restored within this additional time, the plant must be brought to a MODE in which the LCO does not apply, as required by
Condition D.
C.1 and C.2
If one block valve is inoperable, then it is necessary to either restore the
block valve to OPERABLE status within the Completion Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or
place the associated PORV in manual control. The prime importance for
the capability to close the block valve is to isolate a stuck open PORV.
Therefore, if the block valve cannot be restored to OPERABLE status
within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, the Required Action is to place the PORV in manual control Pressurizer PORVs B 3.4.11 BASES (continued)
Watts Bar - Unit 2 B 3.4-55 (developmental)
A ACTIONS C.1 and C.2 (continued)
to preclude its automatic opening for an overpressure event and to avoid
the potential for a stuck open PORV at a time that the block valve is
inoperable. The Completion Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is reasonable, based on the
small potential for challenges to the system during this time period, and
provides the operator time to correct the situation. Because at least one
PORV remains OPERABLE, the operator is permitted a Completion Time
of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore the inoperable block valve to OPERABLE status.
The time allowed to restore the block valve is based upon the Completion
Time for restoring an inoperable PORV in Condition B, since the PORVs may not be capable of mitigating an event if the inoperable block valve is not full open. If the block valve is restored within the Completion Time of
72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, the PORV may be restored to automatic operation. If it cannot
be restored within this additional time, the plant must be brought to a
MODE in which the LCO does not apply, as required by Condition D.
D.1 and D.2
If the Required Action of Condition A, B, or C is not met, then the plant
must be brought to a MODE in which the LCO does not apply. To
achieve this status, the plant must be brought to at least MODE 3 within
6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and to MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times
are reasonable, based on operating experience, to reach the required
plant conditions from full power conditions in an orderly manner and
without challenging plant systems. In MODES 4 and 5, automatic PORV
OPERABILITY may be required. See LCO 3.4.12.
E.1, E.2, E.3, and E.4 If both PORVs are inoperable and not capable of being manually cycled, it is necessary to either restore at least one valve within the Completion
Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> or isolate the flow path by closing and removing the power
to the associated block valves. The Completion Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> is
reasonable, based on the small potential for challenges to the system
during this time and provides the operator time to correct the situation. If
no PORVs are restored within the Completion Time, then the plant must
be brought to a MODE in which the LCO does not apply. To achieve this
status, the plant must be brought to at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and
to MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions from full power conditions in an orderly manner and without
challenging plant systems. In MODES 4 and 5, automatic PORV
OPERABILITY may be required. See LCO 3.4.12.
Pressurizer PORVs B 3.4.11 BASES (continued)
Watts Bar - Unit 2 B 3.4-56 (developmental)
A ACTIONS (continued)
F.1 and F.2 If both block valves are inoperable, it is necessary to either restore the
block valves within the Completion Time of 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, or place the
associated PORVs in manual control and restore at least one block valve
within 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. The Completion Times are reasonable, based on the
small potential for challenges to the system during this time and provide
the operator time to correct the situation.
G.1 and G.2
If the Required Actions of Condition F are not met, then the plant must be
brought to a MODE in which the LCO does not apply. To achieve this
status, the plant must be brought to at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and
to MODE 4 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The allowed Completion Times are
reasonable, based on operating experience, to reach the required plant
conditions from full power conditions in an orderly manner and without
challenging plant systems. In MODES 4 and 5, automatic PORV
OPERABILITY may be required. See LCO 3.4.12.
SURVEILLANCE
REQUIREMENTS SR 3.4.11.1
Block valve cycling verifies that the valve(s) can be opened and closed if
needed. The basis for the Frequency of 92 days is the ASME OM Code (Ref. 3). If the block valve is closed to isolate a PORV that is capable of
being manually cycled, the OPERABILITY of the block valve is of
importance, because opening the block valve is necessary to permit the
PORV to be used for manual control of reactor pressure. If the block
valve is closed to isolate an inoperable PORV that is incapable of being
manually cycled, the maximum Completion Time to restore the PORV and
open the block valve is 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, which is well within the allowable limits (25%) to extend the block valve Frequency of 92 days. Furthermore, these test requirements would be completed by the reopening of a
recently closed block valve upon restoration of the PORV to OPERABLE
status.
The Note modifies this SR by stating that it is not required to be met with
the block valve closed, in accordance with the Required Action of this
LCO.
Pressurizer PORVs B 3.4.11 BASES Watts Bar - Unit 2 B 3.4-57 (developmental)
A SURVEILLANCE REQUIREMENTS (continued)
SR 3.4.11.2 requires a complete cycle of each PORV. Operating a
PORV through one complete cycle ensures that the PORV can be
manually actuated for mitigation of an SGTR. The Frequency of
18 months is based on a typical refueling cycle and industry accepted
practice.
REFERENCES
- 1. Regulatory Guide 1.32, "Criteria for Safety Related Electric Power Systems for Nuclear Power Plants," U.S. Nuclear Regulatory
Commission, February 1977.
- 2. Watts Bar FSAR, Section 15.2, "Condition II - Faults of Moderate
Frequency." 3. American Society of Mechanical Engineers (ASME) OM Code, "Code for Operation and Maintenance of Nuclear Power Plants."
COMS B 3.4.12 (continued)
Watts Bar - Unit 2 B 3.4-58 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.12 Cold Overpressure Mitigation System (COMS)
BASES BACKGROUND The COMS controls RCS pressure at low temperatures so the integrity of the reactor coolant pressure boundary (RCPB) is not compromised by
violating the pressure and temperature (P/T) limits of 10 CFR 50, Appendix G (Ref. 1). The reactor vessel is the limiting RCPB component
for demonstrating such protection. The PTLR provides the maximum
allowable actuation logic setpoints for the power operated relief valves (PORVs) and the maximum RCS pressure for the existing RCS cold leg
temperature during cooldown, shutdown, and heatup to meet the
Reference 1 requirements during the COMS MODES.
The reactor vessel material is less tough at low temperatures than at
normal operating temperature. As the vessel neutron exposure
accumulates, the material toughness decreases and becomes less
resistant to pressure stress at low temperatures (Ref. 2). RCS pressure, therefore, is maintained low at low temperatures and is increased only as
temperature is increased.
The potential for vessel overpressurization is most acute when the RCS is
water solid, occurring only while shutdown; a pressure fluctuation can
occur more quickly than an operator can react to relieve the condition.
Exceeding the RCS P/T limits by a significant amount could cause brittle
cracking of the reactor vessel. LCO 3.4.3, "RCS Pressure and
Temperature (P/T) Limits," requires administrative control of RCS
pressure and temperature during heatup and cooldown to prevent
exceeding the PTLR limits.
This LCO provides RCS overpressure protection by having a minimum
coolant input capability and having adequate pressure relief capacity.
Limiting coolant input capability requires all safety injection pumps and all
but one charging pump incapable of injection into the RCS and isolating
the accumulators. The pressure relief capacity requires either two
redundant RCS relief valves or a depressurized RCS and an RCS vent of
sufficient size. One RCS relief valve or the open RCS vent is the
overpressure protection device that acts to terminate an increasing
pressure event.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-59 (developmental)
A BACKGROUND (continued)
With minimum coolant input capability, the ability to provide core coolant addition is restricted. The LCO does not require the makeup control
system deactivated or the safety injection (SI) actuation circuits blocked.
Due to the lower pressures in the COMS MODES and the expected core
decay heat levels, the makeup system can provide adequate flow via the
makeup control valve. If conditions require the use of more than one
charging pump or safety injection pump for makeup in the event of loss of
inventory, then pumps can be made available through manual actions.
The COMS for pressure relief consists of two PORVs with reduced lift
settings, or one PORV and the Residual Heat Removal (RHR) suction
relief valve, or a depressurized RCS and an RCS vent of sufficient size.
Two RCS relief valves are required for redundancy. One RCS relief valve
has adequate relieving capability to keep from overpressurization for the
required coolant input capability.
PORV Requirements
As designed for the COMS, each PORV is signaled to open if the RCS
pressure approaches a limit determined by the COMS actuation logic.
The COMS actuation logic monitors both RCS temperature and RCS
pressure and determines when a condition not acceptable in the PTLR
limits is approached. The wide range RCS temperature indications are
auctioneered to select the lowest temperature signal.
The lowest temperature signal is processed through a function generator
that calculates a pressure limit for that temperature. The calculated
pressure limit is then compared with the indicated RCS pressure from a
wide range pressure channel. If the indicated pressure meets or exceeds
the calculated value, a PORV is signaled to open.
The PTLR presents the PORV setpoints for COMS. The setpoints are
normally staggered so only one valve opens during a low temperature
overpressure transient. Having the setpoints of both valves within the
limits in the PTLR ensures that the Reference 1 limits will not be
exceeded in any analyzed event.
When a PORV is opened in an increasing pressure transient, the release
of coolant will cause the pressure increase to slow and reverse. As the
PORV releases coolant, the RCS pressure decreases until a reset
pressure is reached and the valve is signaled to close. The pressure
continues to decrease below the reset pressure as the valve closes.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-60 (developmental)
B BACKGROUND (continued)
RHR Suction Relief Valve Requirements
During COMS MODES, the RHR System is operated for decay heat
removal and low pressure letdown control. Therefore, the RHR suction
isolation valves are open in the piping from the RCS hot leg to the inlet
header of the RHR pumps. While these valves are open, the RHR
suction relief valve is exposed to the RCS and is able to relieve pressure
transients in the RCS.
The RHR suction isolation valves must be open to make the RHR suction
relief valve OPERABLE for RCS overpressure mitigation. Autoclosure
interlocks are not permitted to cause the RHR suction isolation valves to
close. The RHR suction relief valve is a spring loaded, bellows type
water relief valve with pressure tolerances and accumulation limits
established by Section III of the American Society of Mechanical
Engineers (ASME) Code (Ref. 3) for Class 2 relief valves.
RCS Vent Requirements
Once the RCS is depressurized, a vent exposed to the containment
atmosphere will maintain the RCS at containment ambient pressure in an
RCS overpressure transient, if the relieving requirements of the transient
do not exceed the capabilities of the vent. Thus, the vent path must be
capable of relieving the flow resulting from the limiting COMS mass or
heat input transient, and maintaining pressure below the P/T limits. The
required vent capacity may be provided by one or more vent paths.
For an RCS vent to meet the flow capacity requirement, it requires
removing a pressurizer safety valve, removing a PORV, and disabling its
block valve in the open position, or opening the pressurizer manway. The
vent path(s) must be above the level of reactor coolant, so as not to drain
the RCS when open.
APPLICABLE
SAFETY ANALYSES Safety analyses (Ref. 4) demonstrate that the reactor vessel is
adequately protected against exceeding the Reference 1 P/T limits. In
MODES 1, 2, 3, and MODE 4 with all RCS cold leg temperatures > the COMS arming temperature specified in the PTLR, the pressurizer safety valves will prevent RCS pressure from exceeding the Reference 1 limits.
Below the COMS arming temperature specified in the PTLR, overpressure prevention falls to two OPERABLE RCS relief valves or to a
depressurized RCS and a sufficient sized RCS vent. Each of these
means has a limited overpressure relief capability.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-61 (developmental)
A APPLICABLE SAFETY ANALYSES (continued)
The actual temperature at which the pressure in the P/T limit curve falls
below the pressurizer safety valve setpoint increases as the reactor
vessel material toughness decreases due to neutron embrittlement. Each
time the PTLR curves are revised, the COMS must be re-evaluated to
ensure its functional requirements can still be met using the RCS relief
valve method or the depressurized and vented RCS condition.
The PTLR contains the acceptance limits that define the COMS
requirements. Any change to the RCS must be evaluated against the
Reference 4 analyses to determine the impact of the change on the
COMS acceptance limits.
Transients that are capable of overpressurizing the RCS are categorized
as either mass or heat input transients, examples of which follow:
Mass Input Type Transients
- a. Inadvertent safety injection; or
- b. Charging/letdown flow mismatch.
Heat Input Type Transients
- a. Inadvertent actuation of pressurizer heaters;
- b. Loss of RHR cooling; or
- c. Reactor coolant pump (RCP) startup with temperature asymmetry within the RCS or between the RCS and steam generators.
The following are required during the COMS MODES to ensure that mass
and heat input transients do not occur, which either of the COMS
overpressure protection means cannot handle:
- a. Rendering all safety injection pumps and all but one charging pump incapable of injection;
- b. Deactivating the accumulator discharge isolation valves in their closed positions; and
- c. Disallowing start of an RCP if secondary temperature is more than 50 F above primary temperature in any one loop. LCO 3.4.6, "RCS Loops - MODE 4," and LCO 3.4.7, "RCS Loops - MODE 5, Loops
Filled," provide this protection.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-62 (developmental)
B APPLICABLE SAFETY ANALYSES (continued)
The Reference 4 analyses demonstrate that either one RCS relief valve
or the depressurized RCS and RCS vent can maintain RCS pressure
below limits when no safety injection pumps and only one centrifugal
charging pump is actuated. Thus, the LCO allows only one charging
pump OPERABLE during the COMS MODES. Since neither one RCS
relief valve nor the RCS vent can handle the pressure transient induced
from accumulator injection, when RCS temperature is low, the LCO also
requires the accumulators be isolated when accumulator pressure is
greater than or equal to the maximum RCS pressure for the existing RCS
cold leg temperature allowed in the PTLR.
The isolated accumulators must have their discharge valves closed and
the valve power supply breakers fixed in their open positions. Fracture mechanics analyses established the temperature of COMS Applicability
at as specified in the PTLR.
The consequences of a small break loss of coolant accident (LOCA) in
COMS MODE 4 conform to 10 CFR 50.46 and 10 CFR 50, Appendix K (Refs. 5 and 6) requirements by having a maximum of one charging pump
OPERABLE and SI actuation enabled.
PORV Performance
The fracture mechanics analyses show that the vessel is protected when
the PORVs are set to open at or below the limit shown in the PTLR. The
setpoints are derived by analyses that model the performance of the
COMS, assuming the mass injection COMS transient of no safety
injection pumps and only one centrifugal charging pump injecting into the
RCS and the heat injection COMS transient of starting a RCP with the
RCS 50 F colder than the secondary side. These analyses consider pressure overshoot and undershoot beyond the PORV opening and
closing, resulting from signal processing and valve stroke times. The
PORV setpoints at or below the derived limit ensures the Reference 1 P/T
limits will be met.
The PORV setpoints in the PTLR will be updated when the revised P/T
limits conflict with the COMS analysis limits. The P/T limits are
periodically modified as the reactor vessel material toughness decreases
due to neutron embrittlement caused by neutron irradiation. Revised
limits are determined using neutron fluence projections and the results of
examinations of the reactor vessel material irradiation surveillance
specimens. The Bases for LCO 3.4.3, "RCS Pressure and Temperature (P/T) Limits," discuss these examinations.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-63 (developmental)
A APPLICABLE SAFETY ANALYSES PORV Performance (continued)
The PORVs are considered active components. Thus, the failure of one
PORV is assumed to represent the worst case, single active failure.
RHR Suction Relief Valve Performance
The RHR suction relief valve does not have variable pressure and
temperature lift setpoints like the PORVs. Analyses must show that the
RHR suction relief valve with a setpoint at or between 436.5 psig and
463.5 psig will pass flow greater than that required for the limiting COMS
transient while maintaining RCS pressure less than the P/T limit curve.
Assuming all relief flow requirements during the limiting COMS event, the
RHR suction relief valve will maintain RCS pressure to within the valve
rated lift setpoint, plus an accumulation <
3% of the rated lift setpoint.
The RHR suction relief valve inclusion and location within the RHR
System does not allow it to meet single failure criteria when spurious
RHR suction isolation valve closure is postulated. Also, as the RCS P/T
limits are decreased to reflect the loss of toughness in the reactor vessel
materials due to neutron embrittlement, the RHR suction relief valves
must be analyzed to still accommodate the design basis transients for
COMS.
The RHR suction relief valve is considered an active component. Thus, the failure of this valve is assumed to represent the worst case single
active failure.
RCS Vent Performance
With the RCS depressurized, analyses show a vent capable of relieving
> 475 gpm water flow is capable of mitigating the allowed COMS
overpressure transient. The capacity of 475 gpm is greater than the flow
of the limiting transient for the COMS configuration, with one centrifugal
charging pump OPERABLE, maintaining RCS pressure less than the
maximum pressure on the P/T limit curve.
Three vent flow paths have been identified in the RCS which could serve
as pressure release (vent) paths. With one safety or PORV removed, the
open line could serve as one vent path. The pressurizer manway could
serve as an alternative vent path with the manway cover removed. These flow paths are capable of discharging 475 gpm at low pressure in the
RCS. Thus, any one of the openings can be used for relieving the
pressure to prevent violating the P/T limits.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-64 (developmental)
A APPLICABLE SAFETY ANALYSES RCS Vent Performance (continued)
The RCS vent size will be re-evaluated for compliance each time the P/T
limit curves are revised based on the results of the vessel material
surveillance. The RCS vent is passive and is not subject to active failure.
The COMS satisfies Criterion 2 of the NRC Policy Statement.
LCO This LCO requires that the COMS is OPERABLE. The COMS is OPERABLE when the minimum coolant input and pressure relief
capabilities are OPERABLE. Violation of this LCO could lead to the loss
of low temperature overpressure mitigation and violation of the
Reference 1 limits as a result of an operational transient.
To limit the coolant input capability, the LCO requires no safety injection
pumps and a maximum of one charging pump be capable of injecting into
the RCS, and all accumulator discharge isolation valves be closed and
immobilized when accumulator pressure is greater than or equal to the
maximum RCS pressure for the existing RCS cold leg temperature
allowed in the PTLR.
The LCO is modified by two Notes. Note 1 allows two charging pumps to
be made capable of injecting for less than or equal to 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> during pump
swap operations. One hour provides sufficient time to safely complete
the actual transfer and to complete the administrative controls and
surveillance requirements associated with the swap. The intent is to
minimize the actual time that more than one charging pump is physically
capable of injection.
Note 2 states that accumulator isolation is only required when the
accumulator pressure is more than or at the maximum RCS pressure for
the existing temperature, as allowed by the P/T limit curves. This Note permits the accumulator discharge isolation valve Surveillance to be
performed only under these pressure and temperature conditions.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-65 (developmental)
B LCO (continued)
The elements of the LCO that provide low temperature overpressure mitigation through pressure relief are:
A PORV is OPERABLE for COMS when its block valve is open, its lift setpoint is set to the limit required by the PTLR and testing
proves its ability to open at this setpoint, and motive power is
available to the valve and its control circuit.
An RHR suction relief valve is OPERABLE for COMS when both
RHR suction isolation valves are open, its setpoint is at or
between 436.5 psig and 463.5 psig, and testing has proven its
ability to open at this setpoint.
An RCS vent is OPERABLE when capable of relieving > 475 gpm
water flow.
Each of these methods of overpressure prevention is capable of
mitigating the limiting COMS transient.
APPLICABILITY This LCO is applicable in MODE 4 with any RCS cold leg temperature
< the COMS arming temperature specified in the PTLR, MODE 5, and MODE 6 when the reactor vessel head is on. The pressurizer safety
valves provide overpressure protection that meets the Reference 1 P/T
limits above the COMS arming temperature specified in the PTLR. When the reactor vessel head is off, overpressurization cannot occur.
LCO 3.4.3 provides the operational P/T limits for all MODES.
LCO 3.4.10, "Pressurizer Safety Valves," requires the OPERABILITY of
the pressurizer safety valves that provide overpressure protection during
MODES 1, 2, and 3 and MODE 4 with all RCS cold leg temperatures
> the COMS arming temperature specified in the PTLR.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-66 (developmental)
B APPLICABILITY (continued)
Low temperature overpressure prevention is most critical during shutdown when the RCS is water solid, and a mass or heat input
transient can cause a very rapid increase in RCS pressure when little or
no time allows operator action to mitigate the event.
ACTIONS A Note prohibits the application of LCO 3.0.4.b to an inoperable COMS.
There is an increased risk associated with entering MODE 4 from
MODE 5 with COMS inoperable and the provisions of LCO 3.0.4.b, which
allow entry into a MODE or other specified condition in the Applicability
with the LCO not met after performance of a risk assessment addressing
inoperable systems and components, should not be applied in this
circumstance.
A.1 and B.1
With two or more charging pumps or any safety injection pumps capable
of injecting into the RCS, RCS overpressurization is possible.
To immediately initiate action to restore restricted coolant input capability
to the RCS reflects the urgency of removing the RCS from this condition.
C.1, D.1, and D.2
An unisolated accumulator requires isolation within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This is only
required when the accumulator pressure is at or more than the maximum
RCS pressure for the existing temperature allowed by the P/T limit curves.
If isolation is needed and cannot be accomplished in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />, Required
Action D.1 and Required Action D.2 provide two options, either of which
must be performed in the next 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. By increasing the RCS
temperature to > the COMS arming temperature specified in the PTLR, an accumulator pressure specified in WAT-D-0863 (Ref. 8) cannot exceed the COMS limits if the accumulators are fully injected.
Depressurizing the accumulators below the COMS limit from the PTLR
also gives this protection.
The Completion Times are based on operating experience that these
activities can be accomplished in these time periods and on engineering
evaluations indicating that an event requiring COMS is not likely in the
allowed times.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-67 (developmental)
A ACTIONS (continued)
E.1 In MODE 4 with one required RCS relief valve inoperable, the RCS relief
valve must be restored to OPERABLE status within a Completion Time of
7 days. Two RCS relief valves are required to provide low temperature
overpressure mitigation while withstanding a single failure of an active
component.
The Completion Time considers the facts that only one of the RCS relief
valves is required to mitigate an overpressure transient and that the
likelihood of an active failure of the remaining valve path during this time
period is very low.
F.1 The consequences of operational events that will overpressurize the RCS
are more severe at lower temperature (Ref. 7). Thus, with one of the two
RCS relief valves inoperable in MODE 5 or in MODE 6 with the head on, the Completion Time to restore two valves to OPERABLE status is
24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
The Completion Time represents a reasonable time to investigate and
repair several types of relief valve failures without exposure to a lengthy
period with only one OPERABLE RCS relief valve to protect against
overpressure events.
G.1 The RCS must be depressurized and a vent must be established within
8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> when:
- a. Both required RCS relief valves are inoperable; or
- b. A Required Action and associated Completion Time of Condition A, B, D, E or F is not met; or
- c. The COMS is inoperable for any reason other than Condition A, B, C, D, E or F.
This action is needed to protect the RCPB from a low temperature
overpressure event and a possible brittle failure of the reactor vessel.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-68 (developmental)
A ACTIONS G.1 (continued)
The Completion Time considers the time required to place the plant in this
Condition and the relatively low probability of an overpressure event
during this time period due to increased operator awareness of
administrative control requirements.
SURVEILLANCE
REQUIREMENTS SR 3.4.12.1, SR 3.4.12.2, and SR 3.4.12.3
To minimize the potential for a low temperature overpressure event by
limiting the mass input capability, no safety injection pumps and all but
one charging pump are verified incapable of injecting into the RCS and
the accumulator discharge isolation valves are verified closed and locked
out.
The safety injection pumps and charging pump are rendered incapable of
injecting into the RCS through removing the power from the pumps by
racking the breakers out under administrative control. Alternative
methods of low temperature overpressure protection control may be
employed using at least two independent means such that a single failure
or single action will not result in an injection into the RCS. This may be
accomplished through the pump control switch being placed in pull to lock
and at least one valve in the discharge flow path being closed, or closing
discharge MOV(s) and de-energizing the motor operator(s) under
administrative control, or locking closed and tagging manual valve(s) in
the discharge flow path.
The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is sufficient, considering other indications and
alarms available to the operator in the control room, to verify the required
status of the equipment. The additional Frequency for SR 3.4.12.1 and
SR 3.4.12.2 is necessary to allow time during the transition from MODE 3
to MODE 4 to make the pumps inoperable.
The RCS vent capable of relieving > 475 gpm water flow is proven
OPERABLE by verifying its open condition either:
- a. Once every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for a vent path that cannot be locked.
- b. Once every 31 days for a vent path that is locked, sealed, or secured in position. A removed safety or PORV fits this category.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-69 (developmental)
A SURVEILLANCE REQUIREMENTS SR 3.4.12.4 (continued)
The passive vent arrangement must only be open to be OPERABLE.
This Surveillance is required to be performed if the vent is being used to
satisfy the pressure relief requirements of the LCO 3.4.12b.
The PORV block valve must be verified open every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to provide
the flow path for each required PORV to perform its function when
actuated. The valve must be remotely verified open in the main control
room. This Surveillance is performed if the PORV satisfies the LCO.
The block valve is a remotely controlled, motor operated valve. The
power to the valve operator is not required removed, and the manual
operator is not required locked in the inactive position. Thus, the block
valve can be closed in the event the PORV develops excessive leakage
or does not close (sticks open) after relieving an overpressure situation.
The 72-hour Frequency is considered adequate in view of other
administrative controls available to the operator in the control room, such
as valve position indication, that verify that the PORV block valve remains
open.
The required RHR suction relief valve shall be demonstrated OPERABLE
by verifying both RHR suction isolation valves are open and by testing it
in accordance with the Inservice Testing Program. This Surveillance is
only performed if the RHR suction relief valve is being used to satisfy this
LCO.
Every 31 days both RHR suction isolation valves are verified locked open, with power to the valve operator removed, to ensure that accidental
closure will not occur. The "locked open" valves must be locally verified
in the open position with the manual actuator locked. The 31 day
Frequency is based on engineering judgment, is consistent with the
procedural controls governing valve operation, and ensures correct valve
position.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-70 (developmental)
B SURVEILLANCE REQUIREMENTS (continued)
The COT is required to be in frequency prior to decreasing RCS
temperature to the COMS arming temperature specified in the PTLR or be performed within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after decreasing RCS temperature to the COMS arming temperature specified in the PTLR on each required PORV to verify and, as necessary, adjust its lift setpoint. The COT will verify the
setpoint is within the PTLR allowed maximum limits in the PTLR. PORV
actuation could depressurize the RCS and is not required. The COT is
required to be performed every 31 days when RCS temperature is the COMS arming temperature specified in the PTLR with the reactor head in place.
The 12-hour allowance to meet the requirement considers the
unlikelihood of a low temperature overpressure event during this time.
A Note has been added indicating that this SR is required to be met within
12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after decreasing RCS cold leg temperature to the COMS arming temperature specified in the PTLR.
Performance of a CHANNEL CALIBRATION on each required PORV
actuation channel is required every 18 months to adjust the whole
channel so that it responds and the valve opens within the required range
and accuracy to known input.
COMS B 3.4.12 BASES (continued)
Watts Bar - Unit 2 B 3.4-71 (developmental)
B REFERENCES 1. Title 10, Code of Federal Regulations, Part 50, Appendix G, "Fracture Toughness Requirements." 2. Generic Letter 88-11, "NRC Position on Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operation." 3. ASME Boiler and Pressure Vessel Code,Section III.
- 4. Watts Bar FSAR, Section 15.2, "Condition II - Faults of Moderate Frequency." 5. Title 10, Code of Federal Regulations, Part 50.46, "Acceptance Criteria for Emergency Core Cooling Systems for Light Water Nuclear Power Reactors." 6. Title 10, Code of Federal Regulations, Part 50, Appendix K, "ECCS Evaluation Models." 7. Generic Letter 90-06, "Resolution of Generic Issue 70,
'Power-Operated Relief Valve and Block Valve Reliability, and
Generic Issue 94, 'Additional Low-Temperature Overpressure
Protection for Light Water Reactors,' pursuant to 10 CFR 50.44(f)." 8. Westinghouse Letter to TVA, WBT-D-0863, "WBS 5.6.10 Cold Overpressure Mitigation System Setpoint Analysis," July 2009.
RCS Operational LEAKAGE B 3.4.13 (continued)
Watts Bar - Unit 2 B 3.4-72 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.13 RCS Operational LEAKAGE
BASES BACKGROUND Components that contain or transport the coolant to or from the reactor core make up the RCS. Component joints are made by welding, bolting, rolling, or pressure loading, and valves isolate connecting systems from
the RCS.
During plant life, the joint and valve interfaces can allow varying amounts
of reactor coolant LEAKAGE, through either normal operational wear or
mechanical deterioration. The purpose of the RCS Operational
LEAKAGE LCO is to limit system operation in the presence of LEAKAGE
from these sources to amounts that do not compromise safety. This LCO specifies the types and amounts of LEAKAGE.
10 CFR 50, Appendix A, GDC 30 (Ref. 1), requires means for detecting
and, to the extent practical, identifying the source of reactor coolant
LEAKAGE. Regulatory Guide 1.45 (Ref. 2) describes acceptable
methods for selecting leakage detection systems.
The safety significance of RCS LEAKAGE varies widely depending on its
source, rate, and duration. Therefore, detecting and monitoring reactor
coolant LEAKAGE into the containment area is necessary. Quickly
separating the identified LEAKAGE from the unidentified LEAKAGE is
necessary to provide quantitative information to the operators, allowing
them to take corrective action should a leak occur that is detrimental to
the safety of the facility and the public.
A limited amount of leakage inside cont ainment is expected from auxiliary systems that cannot be made 100% leaktight. Leakage from these
systems should be detected, located, and isolated from the containment
atmosphere, if possible, to not interfere with RCS leakage detection.
This LCO deals with protection of the reactor coolant pressure boundary (RCPB) from degradation and the core from inadequate cooling, in addition to preventing the accident analyses radiation release assumptions from being exceeded. The consequences of violating this
LCO include the possibility of a loss of coolant accident (LOCA) or steam
generator tube rupture (SGTR).
RCS Operational LEAKAGE B 3.4.13 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-73 (developmental)
A APPLICABLE SAFETY ANALYSES Except for primary to secondary LEAKAGE, the safety analyses do not
address operational LEAKAGE. However, other operational LEAKAGE is
related to the safety analyses for LOCA; the amount of leakage can affect
the probability of such an event. The safety analysis for a main steam
line break (MSLB) assumes that the pre-accident primary-to-secondary
LEAKAGE from three steam generators is 150 gallons per day (gpd) per
steam generator and 1 gallon per minute (gpm) from one steam
generator. This leakage assumption remains the same after the accident.
For an SGTR accident, the accident analysis assumes a primary-to-
secondary leakage of 150 gpd per steam generator prior to the accident.
Subsequent to the SGTR a leakage of 150 gpd is assumed in each of
three intact steam generators and RCS blowdown flow through the
ruptured tube in the faulted steam generator. Consequently, the LCO
requirement to limit primary-to-secondary LEAKAGE through any one
steam generator to less than or equal to 150 gpd is acceptable.
The safety analysis for the SLB accident assumes the entire 1 gpm
primary-to-secondary LEAKAGE is through the affected steam generator
as an initial condition. The dose consequences resulting from the SLB
accident are within the limits defined in 10 CFR 100 or the staff approved
licensing basis (i.e., a small fraction of these limits).
The RCS operational LEAKAGE satisfies Criterion 2 of
LCO RCS operational LEAKAGE shall be limited to:
No pressure boundary LEAKAGE is allowed, being indicative of an
off-normal condition. LEAKAGE of this type is unacceptable as the
leak itself could cause further deterioration, resulting in higher
LEAKAGE. Violation of this LCO could result in continued
degradation of the RCPB. LEAKAGE past seals and gaskets is not
RCS Operational LEAKAGE B 3.4.13 BASES (continued)
Watts Bar - Unit 2 B 3.4-74 (developmental)
A LCO (continued)
- b. Unidentified LEAKAGE One gallon per minute (gpm) of unidentified LEAKAGE is allowed as
a reasonable minimum detectable amount that the containment air
monitoring and containment pocket sump level monitoring equipment
can detect within a reasonable time period. Violation of this LCO
could result in continued degradation of the RCPB, if the LEAKAGE
is from the pressure boundary.
- c. Identified LEAKAGE Up to 10 gpm of identified LEAKAGE is considered allowable
because LEAKAGE is from known sources that do not interfere with
detection of unidentified LEAKAGE and is well within the capability of
the RCS Makeup System. Identified LEAKAGE includes LEAKAGE
to the containment from specifically known and located sources, but
does not include pressure boundary LEAKAGE or controlled reactor
coolant pump (RCP) seal leakoff (a normal function not considered
LEAKAGE). Violation of this LCO could result in continued
degradation of a component or system.
- d. Primary to Secondary LEAKAGE through ANY One SG The limit of 150 gallons per day (gpd) per SG (600 gpd total for all
SGs) is based on the operational LEAKAGE performance criteria in
NEI 97-06, Steam Generator Program Guidelines (Reference 4).
The Steam Generator Program operational LEAKAGE performance
criterion in NEI 97-06 states, "The RCS operational primary to
secondary leakage through any one SG shall be limited to
150 gallons per day." The limit is based on operating experience with
SG tube degradation mechanisms that result in tube leakage. The
operational leakage rate criterion in conjunction with the implementation of the Steam Gener ator Program is an effective measure for minimizing the frequency of steam generator tube
ruptures.
RCS Operational LEAKAGE B 3.4.13 BASES (continued)
Watts Bar - Unit 2 B 3.4-75 (developmental)
A APPLICABILITY In MODES 1, 2, 3, and 4, the potential for RCPB LEAKAGE is greatest when the RCS is pressurized.
In MODES 5 and 6, LEAKAGE limits are not required because the reactor
coolant pressure is far lower, resulting in lower stresses and reduced
potentials for LEAKAGE.
ACTIONS A.1 Unidentified LEAKAGE or identified LEAKAGE in excess of the LCO
limits must be reduced to within limits within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. This Completion
Time allows time to verify leakage rates and either identify unidentified
LEAKAGE or reduce LEAKAGE to within limits before the reactor must be
shut down. This action is necessary to prevent further deterioration of the
RCPB.
B.1 and B.2
If any pressure boundary LEAKAGE exists, or primary-to-secondary
LEAKAGE is not within limits, or if unidentified LEAKAGE or identified
LEAKAGE cannot be reduced to within limits within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />, the reactor
must be brought to lower pressure conditions to reduce the severity of the
LEAKAGE and its potential consequences. It should be noted that
LEAKAGE past seals and gaskets is not pressure boundary LEAKAGE.
The reactor must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and MODE 5
within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. This action reduces the LEAKAGE and also reduces the
factors that tend to degrade the pressure boundary.
The allowed Completion Times are reasonable, based on operating experience, to reach the required plant conditions from full power conditions in an orderly manner and without challenging plant systems.
In MODE 5, the pressure stresses acting on the RCPB are much lower, and further deterioration is much less likely.
RCS Operational LEAKAGE B 3.4.13 BASES (continued)
Watts Bar - Unit 2 B 3.4-76 (developmental)
A SURVEILLANCE REQUIREMENTS SR 3.4.13.1
Verifying RCS LEAKAGE to be within the LCO limits ensures the integrity
of the RCPB is maintained. Pressure boundary LEAKAGE would at first
appear as unidentified LEAKAGE and can only be positively identified by
inspection. It should be noted that LEAKAGE past seals and gaskets is
not pressure boundary LEAKAGE. Unidentified LEAKAGE and identified
LEAKAGE are determined by performance of an RCS water inventory
balance.
The RCS water inventory balance must be met with the reactor at steady state operating conditions and near operating pressure. The SR is modified by 2 Notes. Note 1 states that this SR is not required to be
performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after establishing steady state operation. The
12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> allowance provides sufficient time to collect and process all
necessary data after stable plant conditions are established.
Steady state operation is required to perform a proper inventory balance;
calculations during maneuvering are not useful. For RCS operational
LEAKAGE determination by water inventory balance, steady state is
defined as stable RCS pressure, temperature, power level, pressurizer
and makeup tank levels, makeup and letdown, and RCP seal injection
and return flows.
An early warning of pressure boundary LEAKAGE or unidentified
LEAKAGE is provided by the automat ic systems that monitor the
containment atmosphere radioactivity and the containment pocket sump
level. It should be noted that LEAKAGE past seals and gaskets is not
pressure boundary LEAKAGE. These leakage detection systems are
specified in LCO 3.4.15, "RCS Leakage Detection Instrumentation."
Note 2 states that this SR is not applicable to primary-to-secondary
LEAKAGE because LEAKAGE of 150 gallons per day cannot be measured accurately by an RCS water inventory balance.
The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Frequency is a reasonable interval to trend LEAKAGE and
recognizes the importance of early leakage detection in the prevention of
accidents.
RCS Operational LEAKAGE B 3.4.13 BASES (continued)
Watts Bar - Unit 2 B 3.4-77 (developmental)
A SURVEILLANCE REQUIREMENTS (continued)
This SR verifies that primary-to-secondary LEAKAGE is less than or
equal to 150 gallons per day through any one SG. Satisfying the primary-
to-secondary LEAKAGE limit ensures that the operational LEAKAGE
performance criterion in the Steam Generator Program is met. If this SR
is not met, compliance with LCO 3.4.17 "Steam Generator Tube Integrity,"
should be evaluated. The 150 gallons per day limit is measured at room temperature as described in Ref. 5. The operational LEAKAGE rate limit
applies to LEAKAGE through any one SG. If it is not practical to assign
the LEAKAGE to an individual SG, all the primary-to-secondary LEAKAGE should be conservatively assumed to be from one SG.
The Surveillance is modified by a NOTE which states that the
Surveillance is not required to be performed until 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after
establishment of steady state operation. For RCS primary-to-secondary
LEAKAGE determination, steady state is defined as stable RCS pressure, temperature, power level, pressurizer and makeup tank levels, makeup
and letdown, and RCP seal injection and return flows.
The Surveillance Frequency of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> is a reasonable interval to trend
primary-to-secondary LEAKAGE and recognizes the importance of early
leakage detection in the prevention of accidents. The primary-to-
secondary LEAKAGE is determined using continuous process radiation
monitors or radiochemical grab sampling in accordance with EPRI
guidelines (Ref. 5)
REFERENCES
- 1. Title 10, Code of Federal Regulations, Part 50, Appendix A, General Design Criteria 30, "Quality of Reactor Coolant Boundary." 2. Regulatory Guide 1.45, "Reactor Coolant Pressure Boundary Leakage Detection Systems," May 1973.
- 3. Watts Bar FSAR, Section 15.4, "Condition IV - Limiting Faults." 4. NEI 97-06, "Steam Generator Program Guidelines."
- 5. EPRI Pressurized Water Reactor Primary-to-Secondary Leak Guidelines.
RCS PIV Leakage B 3.4.14 (continued)
Watts Bar - Unit 2 B 3.4-78 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.14 RCS Pressure Isolation Valve (PIV) Leakage
BASES BACKGROUND 10 CFR 50.2, 10 CFR 50.55a(c), and GDC 55 of 10 CFR 50, Appendix A (Refs. 1, 2, and 3), define RCS PIVs as any two normally closed valves in
series within the reactor coolant pressure boundary (RCPB), which
separate the high pressure RCS from an attached low pressure system.
During their lives, these valves can produce varying amounts of reactor
coolant leakage through either normal operational wear or mechanical
deterioration. The RCS PIV Leakage LCO allows RCS high pressure
operation when leakage through these valves exists in amounts that do
not compromise safety.
The PIV leakage limit applies to each individual valve.
Although this specification provides a limit on allowable PIV leakage rate, its main purpose is to prevent overpressure failure of the low pressure
portions of connecting systems. The leakage limit is an indication that the
PIVs between the RCS and the connecting systems are degraded or
degrading. PIV leakage could lead to overpressure of the low pressure
piping or components. Failure consequences could be a loss of coolant
accident (LOCA) outside of containment, an unanalyzed accident, that
could degrade the ability for low pressure injection.
The basis for this LCO is the 1975 NRC "Reactor Safety Study" (Ref. 4)
that identified potential intersystem LOCAs as a significant contributor to
the risk of core melt. A subsequent study (Ref. 5) evaluated various PIV
configurations to determine the probability of intersystem LOCAs.
PIVs are provided to isolate the RCS from the following typically
connected systems:
- a. Residual Heat Removal (RHR) System;
- b. Safety Injection System; and
- c. Chemical and Volume Control System.
The PIVs are listed in the FSAR, Section 3.9 (Ref. 6).
RCS PIV Leakage B 3.4.14 BASES (continued)
Watts Bar - Unit 2 B 3.4-79 (developmental)
A BACKGROUND (continued)
Violation of this LCO could result in continued degradation of a PIV, which could lead to overpressurization of a low pressure system and the loss of
the integrity of a fission product barrier.
APPLICABLE
SAFETY ANALYSES Reference 4 identified potential intersystem LOCAs as a significant
contributor to the risk of core melt. The dominant accident sequence in
the intersystem LOCA category is the failure of the low pressure portion
of the RHR System outside of containment. The accident is the result of
a postulated failure of the PIVs, which are part of the RCPB, and the
subsequent pressurization of the RHR System downstream of the PIVs
from the RCS. Because the low pressure portion of the RHR System is
typically designed for 600 psig, overpressurization failure of the RHR low
pressure line would result in a LOCA outside containment and subsequent risk of core melt.
Reference 5 evaluated various PIV configurations, leakage testing of the
valves, and operational changes to determine the effect on the probability
of intersystem LOCAs. This study concluded that periodic leakage testing
of the PIVs can substantially reduce the probability of an intersystem
LOCA.
RCS PIV leakage satisfies Criterion 2 of the NRC Policy Statement.
LCO RCS PIV leakage is LEAKAGE into closed systems connected to the RCS. Isolation valve leakage is usually on the order of drops per minute.
Leakage that increases significantly suggests that something is
operationally wrong and corrective action must be taken.
The LCO PIV leakage limit is 0.5 gpm per nominal inch of valve size with
a maximum limit of 5 gpm. The previous criterion of 1 gpm for all valve
sizes imposed an unjustified penalty on the larger valves without
providing information on potential valve degradation and resulted in
higher personnel radiation exposures. A study concluded a leakage rate limit based on valve size was superior to a single allowable value.
RCS PIV Leakage B 3.4.14 BASES (continued)
Watts Bar - Unit 2 B 3.4-80 (developmental)
A LCO (continued)
Reference 7 permits leakage testing at a lower pressure differential than between the specified maximum RCS pressure and the normal pressure
of the connected system during RCS operation (the maximum pressure differential) in those types of valves in which the higher service pressure will tend to diminish the overall leakage channel opening. In such cases, the observed rate may be adjusted to the maximum pressure differential
by assuming leakage is directly proportional to the pressure differential to
the one half power.
APPLICABILITY In MODES 1, 2, 3, and 4, this LCO applies because the PIV leakage potential is greatest when the RCS is pressurized. In MODE 4, valves in
the RHR flow path are not required to meet the requirements of this LCO
when in or during the transition to or from the RHR mode of operation.
In MODES 5 and 6, leakage limits are not provided because the lower
reactor coolant pressure results in a reduced potential for leakage and for
a LOCA outside the containment.
ACTIONS The Actions are modified by two Notes. Note 1 provides clarification that each flow path allows separate entry into a Condition. This is allowed
based upon the functional independence of the flow path. Note 2
requires an evaluation of affected systems if a PIV is inoperable. The
leakage may have affected system operability, or isolation of a leaking
flow path with an alternate valve may have degraded the ability of the
interconnected system to perform its safety function.
A.1 and A.2
The flow path must be isolated. Required Actions A.1 and A.2 are
modified by a Note that the valve used for isolation must meet the same
leakage requirements as the PIVs and must be within the RCPB.
Required Action A.1 requires that the isolation with one valve must be
performed within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />. Four hours provides time to reduce leakage in
excess of the allowable limit and to isolate the affected system if leakage
cannot be reduced. The 4-hour Completion Time allows the actions and
restricts the operation with leaking isolation valves.
RCS PIV Leakage B 3.4.14 BASES (continued)
Watts Bar - Unit 2 B 3.4-81 (developmental)
A ACTIONS A.1 and A.2 (continued)
The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time after exceeding the limit allows for the
restoration of the leaking PIV to OPERABLE status. This timeframe
considers the time required to complete this Action and the low probability
of a second valve failing during this period.
B.1 and B.2
If leakage cannot be reduced, or the system isolated, the plant must be
brought to a MODE in which the requirement does not apply. To achieve
this status, the plant must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and
MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. This Action may reduce the leakage and also
reduces the potential for a LOCA outside the containment. The allowed
Completion Times are reasonable, based on operating experience, to
reach the required plant conditions from full power conditions in an
orderly manner and without challenging plant systems.
SURVEILLANCE
REQUIREMENTS SR 3.4.14.1
Performance of leakage testing on each RCS PIV or isolation valve used
to satisfy Required Action A.1 and Required Action A.2 is required to
verify that leakage is below the specified limit and to identify each leaking
valve. The leakage limit of 0.5 gpm per inch of nominal valve diameter up to 5 gpm maximum applies to each valve. Leakage testing requires a
stable pressure condition.
For the two PIVs in series, the leakage requirement applies to each valve
individually and not to the combined leakage across both valves. If the
PIVs are not individually leakage tested, one valve may have failed completely and not be detected if the other valve in series meets the leakage requirement. In this situation, the protection provided by
redundant valves would be lost.
RCS PIV Leakage B 3.4.14 BASES (continued)
Watts Bar - Unit 2 B 3.4-82 (developmental)
A SURVEILLANCE REQUIREMENTS SR 3.4.14.1 (continued)
Testing is to be performed every 18 months, a typical refueling cycle, if
the plant does not go into MODE 5 for at least 7 days. The 18 month
Frequency is consistent with 10 CFR 50.55a(g) (Ref. 8) as contained in
the Inservice Testing Program, is within the frequency allowed by the
American Society of Mechanical Engineers (ASME) OM Code (Ref. 7),
and is based on the need to perform such surveillances under the
conditions that apply during an outage and the potential for an unplanned
transient if the Surveillance were performed with the reactor at power.
In addition, testing must be performed once after the valve has been opened by flow or exercised to ensure tight reseating. PIVs disturbed in
the performance of this Surveillance should also be tested unless
documentation shows that an infinite testing loop cannot practically be
avoided. Testing must be performed within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> after the valve has
been reseated. Within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> is a reasonable and practical time limit
for performing this test after opening or reseating a valve.
The leakage limit is to be met at the RCS pressure associated with
MODES 1 and 2. This permits leakage testing at high differential
pressures with stable conditions not possible in the MODES with lower
pressures.
Entry into MODES 3 and 4 is allowed to establish the necessary
differential pressures and stable conditions to allow for performance of
this Surveillance. The Note that allows this provision is complementary to
the Frequency of prior to entry into MODE 2 whenever the unit has been
in MODE 5 for 7 days or more, if leakage testing has not been performed
in the previous 9 months. In addition, this Surveillance is not required to
be performed on the RHR System when the RHR System is aligned to the
RCS in the shutdown cooling mode of operation. PIVs contained in the
RHR shutdown cooling flow path must be leakage rate tested after RHR is secured and stable unit conditions and the necessary differential pressures are established.
RCS PIV Leakage B 3.4.14 BASES (continued)
Watts Bar - Unit 2 B 3.4-83 (developmental)
A REFERENCES
- 1. Title 10, Code of Federal Regulations, Part 50, Section 50.2, "Definitions - Reactor Coolant Pressure Boundary." 2. Title 10, Code of Federal Regulations, Part 50, Section 50.55a, "Codes and Standards," Subsection (c), "Reactor Coolant Pressure Boundary." 3. Title 10, Code of Federal Regulations, Part 50, Appendix A,Section V, "Reactor Containment," General Design Criterion 55, "Reactor Coolant Pressure Boundary Penetrating Containment." 4. U.S. Nuclear Regulatory Commission (NRC), "Reactor Safety Study - An Assessment of Accident Risks in U.S. Commercial Nuclear
Power Plants," Appendix V, WASH-1400 (NUREG-75/014),
October 1975.
- 5. U.S. NRC, "The Probability of Intersystem LOCA: Impact Due to Leak Testing and Operational Changes," NUREG-0677, May 1980.
- 6. Watts Bar FSAR, Section 3.9, "Mechanical Systems and Components" (Table 3.9-17).
- 7. American Society of Mechanical Engineers (ASME) OM Code, "Code for Operation and Maintenance of Nuclear Power Plants."
- 8. Title 10, Code of Federal Regulations, Part 50, Section 50.55a, "Codes and Standards," Subsection (g), "Inservice Inspection
Requirements."
RCS Leakage Detection Instrumentation B 3.4.15 (continued)
Watts Bar - Unit 2 B 3.4-84 (developmental)
B B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.15 RCS Leakage Detection Instrumentation
BASES BACKGROUND GDC 30 of Appendix A to 10 CFR 50 (Ref. 1) requires means for detecting and, to the extent practical, identifying the location of the source
of RCS LEAKAGE. Regulatory Guide 1.45 (Ref. 2) describes acceptable
methods for selecting leakage detection systems.
Leakage detection systems must have the capability to detect significant
reactor coolant pressure boundary (RCPB) degradation as soon after
occurrence as practical to minimize the potential for propagation to a
gross failure. Thus, an early indication or warning signal is necessary to
permit proper evaluation of all unidentified LEAKAGE.
Industry practice has shown that water flow changes of 0.5 gpm to
1.0 gpm can be readily detected in contained volumes by monitoring
changes in water level, in flow rate, or in the operating frequency of a
pump. The containment pocket sump used to collect unidentified
LEAKAGE is instrumented to alarm for increases of 0.5 gpm to 1.0 gpm in
the normal flow rates. This sensitivity is acceptable for detecting
increases in unidentified LEAKAGE.
The reactor coolant contains radioactivity that, when released to the
containment, can be detected by radiation monitoring instrumentation.
Reactor coolant radioactivity levels will be low during initial reactor startup
and for a few weeks thereafter, until activated corrosion products have
been formed and fission products appear from fuel element cladding
contamination or cladding defects. Instrument sensitivity of 10
-9 µCi/cc radioactivity for particulate monitoring is practical for this leakage detection system. A radioactivity detection system is included for monitoring particulate activity because of its sensitivity and rapid response to RCS LEAKAGE.
RCS Leakage Detection Instrumentation B 3.4.15 BASES (continued)
Watts Bar - Unit 2 B 3.4-85 (developmental)
B BACKGROUND (continued)
An atmospheric gaseous radioactivity monitor will provide a positive indication of leakage in the event that high levels of reactor coolant gaseous activity exist due to fuel cladding defects. The effectiveness of the atmospheric gaseous radioactivity monitors depends primarily on the activity of the reactor coolant and also, in part, on the containment volume and the background activity level. Shortly after startup and also during steady state operation with low levels of fuel defects, the level of radioactivity in the reactor coolant may be too low for the containment atmosphere gaseous radiation monitors to detect a reactor coolant leak of 1 gpm within one hour. Atmospheric gaseous radioactivity monitors are not required by this LCO.
The sample lines supplying the radioactivity monitoring instrumentation are heated (heat traced) to ensure that a representative sample can be
obtained. During periods when the heat tracing is inoperable, the
particulate channel of the radioactivity monitoring instrumentation is
inoperable and grab samples for particulates may not be taken using the
sample lines.
An increase in humidity of the containment atmosphere would indicate
release of water vapor to the containment. Dew point temperature
measurements can thus be used to monitor humidity levels of the
containment atmosphere as an indicator of potential RCS LEAKAGE.
A 1°F increase in dew point is well within the sensitivity range of available instruments.
Since the humidity level is influenced by several factors, a quantitative
evaluation of an indicated leakage rate by this means may be
questionable and should be compared to observed increases in liquid
flow into or from the containment pocket sump. Humidity level monitoring
is considered most useful as an indirect alarm or indication to alert the
operator to a potential problem. Humidity monitors are not required by
this LCO.
RCS Leakage Detection Instrumentation B 3.4.15 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-86 (developmental)
B BACKGROUND (continued)
Air temperature and pressure monitoring methods may also be used to
infer unidentified LEAKAGE to the containment. Containment
temperature and pressure fluctuate slightly during plant operation, but a
rise above the normally indicated range of values may indicate RCS
leakage into the containment. The relevance of temperature and
pressure measurements are affected by containment free volume and, for
temperature, detector location. Alarm signals from these instruments can
be valuable in recognizing rapid and sizable leakage to the containment.
Temperature and pressure monitors are not required by this LCO.
APPLICABLE
SAFETY ANALYSES The need to evaluate the severity of an alarm or an indication is important
to the operators, and the ability to compare and verify with indications from other systems is necessary. The system response times and
sensitivities are described in the FSAR (Ref. 3).
The safety significance of RCS LEAKAGE varies widely depending on its
source, rate, and duration. Therefore, detecting and monitoring RCS
LEAKAGE into the containment area is necessary. Quickly separating
the identified LEAKAGE from the unidentified LEAKAGE provides
quantitative information to the operators, allowing them to take corrective
action should a leak detrimental to the safety of the unit and the public
occur. RCS leakage detection instrumentation satisfies Criterion 1 of the
NRC Policy Statement.
LCO One method of protecting against large RCS leakage derives from the ability of instruments to rapidly detect extremely small leaks. This LCO
requires instruments of diverse monitoring principles to be OPERABLE to
provide a high degree of confidence that extremely small leaks are
detected in time to allow actions to place the plant in a safe condition
when RCS LEAKAGE indicates possible RCPB degradation.
The LCO is satisfied when monitors of diverse measurement means are
available. Thus, the containment pocket sump level monitor, in
combination with a particulate radioactivity monitor, provides an acceptable minimum.
The sample lines supplying the radioactivity monitoring instrumentation
are heated (heat traced) to ensure that a representative sample can be
obtained.
RCS Leakage Detection Instrumentation B 3.4.15 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-87 (developmental)
B APPLICABILITY Because of elevated RCS temperature and pressure in MODES 1, 2, 3, and 4, RCS leakage detection instrumentation is required to be OPERABLE.
In MODE 5 or 6, the temperature is to be 200°F and pressure is maintained low or at atmospheric pressure. Since the temperatures and
pressures are far lower than those for MODES 1, 2, 3, and 4, the
likelihood of leakage and crack propagation are much smaller. Therefore, the requirements of this LCO are not applicable in MODES 5 and 6.
ACTIONS A.1 and A.2
With the required containment pocket sump level monitor inoperable, no
other form of sampling can provide the equivalent information; however, the containment atmosphere particulate radioactivity monitor will provide indications of changes in leakage. Together with the atmosphere
monitor, the periodic surveillance for RCS water inventory balance, SR 3.4.13.1, must be performed at an increased frequency of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> to
provide information that is adequate to detect leakage.
Restoration of the required containment pocket sump level monitor to
OPERABLE status within a Completion Time of 30 days is required to
regain the function after the monitor's failure. This time is acceptable, considering the Frequency and adequacy of the RCS water inventory
balance required by Required Action A.1.
RCS Leakage Detection Instrumentation B 3.4.15 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-88 (developmental)
B ACTIONS (continued)
B.1.1, B.1.2, and B.2 With the particulate containment atmosphere radioactivity monitoring instrumentation channel inoperable, alternative action is required. Either grab samples of the containment atmosphere must be taken and
analyzed or water inventory balances, in accordance with SR 3.4.13.1, must be performed to provide alternate periodic information.
During periods when the heat tracing is inoperable for the sample lines
supplying the radioactivity monitoring instrumentation, the particulate
channel of the instrumentation is inoperable and grab samples for
particulates may not be taken using the sample lines.
With a sample obtained and analyzed or water inventory balance
performed every 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, the reactor may be operated for up to 30 days
to allow restoration of the required containment atmosphere particulate radioactivity monitor.
The 24-hour interval provides periodic information that is adequate to
detect leakage. The 30-day Completion Time recognizes at least one
other form of leakage detection is available.
C.1 and C.2
If a Required Action of Condition A or B cannot be met, the plant must be
brought to a MODE in which the requirement does not apply. To achieve
this status, the plant must be brought to at least MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
and to MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />. The allowed Completion Times are
reasonable, based on operating experience, to reach the required plant
conditions from full power conditions in an orderly manner and without
challenging plant systems.
D.1 With all required monitors inoperable, no automatic means of monitoring
leakage are available, and immediate plant shutdown in accordance with
LCO 3.0.3 is required.
RCS Leakage Detection Instrumentation B 3.4.15 BASES (continued)
Watts Bar - Unit 2 B 3.4-89 (developmental)
B SURVEILLANCE REQUIREMENTS SR 3.4.15.1
SR 3.4.15.1 requires the performance of a CHANNEL CHECK of the
required containment atmosphere particulate radioactivity monitor. The check gives reasonable confidence that the channel is operating properly.
The Frequency of 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> is based on instrument reliability and is
reasonable for detecting off normal conditions.
SR 3.4.15.2 requires the performance of a COT on the required
containment atmosphere particulate radioactivity monitor. The test ensures that the monitor can perform its function in the desired manner.
The test verifies the alarm setpoint and the relative accuracy of the
instrument string. The Frequency of 92 days considers instrument
reliability, and operating experience has shown that it is proper for
detecting degradation.
These SRs require the performance of a CHANNEL CALIBRATION for
each of the RCS leakage detection instrumentation channels. The
calibration verifies the accuracy of the instrument string, including the
instruments located inside containment. The Frequency of 18 months is
a typical refueling cycle and considers channel reliability. Again, operating experience has proven that this Frequency is acceptable.
REFERENCES 1. 10 CFR 50, Appendix A, General Design Criterion 30, "Quality of Reactor Coolant Pressure Boundary." 2. Regulatory Guide 1.45, "Reactor Coolant Pressure Boundary Leakage Detection Systems," Revision 0, May 1973.
RCS Specific Activity B 3.4.16 (continued)
Watts Bar - Unit 2 B 3.4-90 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.16 RCS Specific Activity
BASES BACKGROUND The maximum dose to the whole body and the thyroid that an individual at the site boundary can receive for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> during an accident is specified
in 10 CFR 100 (Ref. 1). The maximum dose to the whole body and the
thyroid that an individual occupying the Main Control Room can receive
for the accident duration is specified in 10 CFR 50, Appendix A, GDC 19.
The limits on specific activity ensure that the doses are held to a small
fraction of the 10 CFR 100 limits and within the 10 CFR 50, Appendix A, GDC 19 limits during analyzed transients and accidents.
The RCS specific activity LCO limits the allowable concentration level of
radionuclides in the reactor coolant. The LCO limits are established to
minimize the offsite and Main Control Room radioactivity dose
consequences in the event of a steam generator tube rupture (SGTR) or
main steam line break (MSLB) accident.
The LCO contains specific activity limits for both DOSE EQUIVALENT
I-131 and gross specific activity. The allowable levels are intended to
limit the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> dose at the site boundary to a small fraction of the
10 CFR 100 dose guideline limits, and ensure the Main Control Room
accident dose is within the appropriate 10 CFR 50, Appendix A, GDC 19
dose guideline limits.
The evaluations showed the potential offsite and Main Control Room
dose levels for a SGTR and MSLB accident were within the appropriate
10 CFR 100 and GDC 19 guideline limits.
RCS Specific Activity B 3.4.16 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-91 (developmental)
B APPLICABLE SAFETY ANALYSES The LCO limits on the specific activity of the reactor coolant ensures that
the resulting 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> doses at the site boundary and Main Control Room
accident doses will not exceed the appropriate 10 CFR 100 dose
guideline limits and 10 CFR 50, Appendix A, GDC 19 dose guideline limits following a SGTR or MSLB accident. The SGTR and MSLB safety
analysis (Ref. 2) assumes the specific activity of the reactor coolant at the LCO limit and an existing reactor coolant steam generator (SG) tube
leakage rate of 150 gallons per day (GPD). The safety analysis assumes
the specific activity of the secondary coolant at its limit of 0.1 Ci/gm DOSE EQUIVALENT I-131 from LCO 3.7.14, "Secondary Specific
Activity."
The analysis for the SGTR and MSLB accidents establish the acceptance
limits for RCS specific activity. Reference to these analyses is used to
assess changes to the unit that could affect RCS specific activity, as they
relate to the acceptance limits.
The analyses are for two cases of reactor coolant specific activity. One
case assumes specific activity at 0.265 Ci/gm DOSE EQUIVALENT I-131 with an iodine spike immediately after the accident that increases
the iodine activity in the reactor coolant by a factor of 500 times the iodine
production rate necessary to maintain a steady state iodine concentration
of 0.265 Ci/gm DOSE EQUIVALENT I-131. The second case assumes the initial reactor coolant iodine activity at 21 Ci/gm DOSE EQUIVALENT I-131 due to a pre-accident iodine spike caused by an
RCS transient. In both cases, the noble gas activity in the reactor coolant
equals the LCO limit of 100/ E Ci/gm for gross specific activity.
The analysis also assumes a loss of offsite power at the same time as the
SGTR and MSLB event. The SGTR causes a reduction in reactor coolant
inventory. The reduction initiates a reactor trip from a low pressurizer
pressure signal or an RCS overtemperature T signal. The MSLB results in a reactor trip due to low steam pressure.
The coincident loss of offsite power causes the steam dump valves to
close to protect the condenser. The rise in pressure in the ruptured SG
discharges radioactively contaminated steam to the atmosphere through
the SG power operated relief valves and the main steam safety valves.
The unaffected SGs remove core decay heat by venting steam to the
atmosphere until the cooldown ends.
RCS Specific Activity B 3.4.16 BASES (continued)
Watts Bar - Unit 2 B 3.4-92 (developmental)
A APPLICABLE SAFETY ANALYSES (continued)
The safety analysis shows the radiological consequences of an SGTR
and MSLB accident are within the appropriate 10 CFR 100 and
10 CFR 50, Appendix A, GDC 19 dose guideline limits. Operation with
iodine specific activity levels greater than the LCO limit is permissible, if
the activity levels do not exceed 21 Ci/gm DOSE EQUIVALENT I-131, in the applicable specification, for more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. The safety analysis
has concurrent and pre-accident iodine spiking levels up to 21 Ci/gm DOSE EQUIVALENT I-131.
The limits on RCS specific activity are also used for establishing
standardization in radiation shielding and plant personnel radiation
protection practices.
RCS specific activity satisfies Criterion 2 of the NRC Policy Statement.
LCO The specific iodine activity is limited to 0.265 Ci/gm DOSE EQUIVALENT I-131, and the gross specific activity in the reactor coolant
is limited to the number of Ci/gm equal to 100 divided by E (average disintegration energy of the sum of the average beta and gamma
energies of the coolant nuclides). The limit on DOSE EQUIVALENT I-131
ensures the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> thyroid dose to an individual at the site boundary and
accident dose to personnel in the Main Control Room during the Design
Basis Accident (DBA) will be within the allowed thyroid dose. The limit on
gross specific activity ensures the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> whole body dose to an
individual at the site boundary and accident dose to personnel in the Main
Control Room during the DBA will be within the allowed whole body dose.
The SGTR and MSLB accident analysis (Ref. 2) shows that the 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />
site boundary dose levels and Main Control Room accident dose are
within acceptable limits. Violation of the LCO may result in reactor
coolant radioactivity levels that could, in the event of a SGTR or MSLB, lead to site boundary doses that exceed the 10 CFR 100 dose guideline
limits, or Main Control Room accident dose that exceed the 10 CFR 50, Appendix A, GDC 19 dose limits.
RCS Specific Activity B 3.4.16 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-93 (developmental)
A APPLICABILITY In MODES 1 and 2, and in MODE 3 with RCS average temperature 500 F, operation within the LCO limits for DOSE EQUIVALENT I-131 and gross specific activity are necessary to contain the potential consequences of an accident to within the acceptable Main Control Room
and site boundary dose values.
For operation in MODE 3 with RCS average temperature < 500 F, and in MODES 4 and 5, the release of radioactivity in the event of a SGTR is
unlikely since the saturation pressure of the reactor coolant is below the
lift pressure settings of the main steam safety valves.
ACTIONS A.1 and A.2
With the DOSE EQUIVALENT I-131 greater than the LCO limit, samples
at intervals of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> must be taken to demonstrate that the limit of
21 Ci/gm is not exceeded. The Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is required to obtain and analyze a sample. Sampling is done to continue to provide
a trend.
The DOSE EQUIVALENT I-131 must be restored to within limits within
48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. The Completion Time of 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> is required, if the limit
violation resulted from normal iodine spiking.
A Note permits the use of the provisions of LCO 3.0.4.c. This allowance
permits entry into the applicable MODE(S) while relying on the ACTIONS.
This allowance is acceptable due to the significant conservatism
incorporated into the specific activity limit, the low probability of an event
which is limiting due to exceeding this limit, and the ability to restore
transient specific activity excursions while the plant remains at, or
proceeds to power operation.
RCS Specific Activity B 3.4.16 BASES (continued)
Watts Bar - Unit 2 B 3.4-94 (developmental)
A ACTIONS (continued)
B.1 and B.2 With the gross specific activity in excess of the allowed limit, an analysis
must be performed within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> to determine DOSE EQUIVALENT
I-131. The Completion Time of 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> is required to obtain and analyze
a sample.
The change within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> to MODE 3 and RCS average temperature
< 500 F lowers the saturation pressure of the reactor coolant below the setpoints of the main steam safety valves and prevents venting the SG to
the environment in an SGTR event. The allowed Completion Time of
6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable, based on operating experience, to reach MODE 3
below 500 F from full power conditions in an orderly manner and without challenging plant systems.
C.1 If a Required Action and the associated Completion Time of Condition A
is not met or if the DOSE EQUIVALENT I-131 is greater than 21 Ci/gm, the reactor must be brought to MODE 3 with RCS average temperature
< 500 F within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />. The Completion Time of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> is reasonable, based on operating experience, to reach MODE 3 below 500 F from full power conditions in an orderly manner and without challenging plant systems.
SURVEILLANCE
REQUIREMENTS SR 3.4.16.1
SR 3.4.16.1 requires performing a gamma isotopic analysis as a measure
of the gross specific activity of the reactor coolant at least once every
7 days. While basically a quantitative measure of radionuclides with half
lives longer than 15 minutes, excluding iodines, this measurement is the
sum of the degassed gamma activities and the gaseous gamma activities
in the sample taken. This Surveillance provides an indication of any
increase in gross specific activity.
Trending the results of this Surveillance allows proper remedial action to
be taken before reaching the LCO limit under normal operating
conditions. The Surveillance is applicable in MODES 1 and 2, and in
MODE 3 with Tavg at least 500 F. The 7-day Frequency considers the unlikelihood of a gross fuel failure during the time.
RCS Specific Activity B 3.4.16 BASES Watts Bar - Unit 2 B 3.4-95 (developmental)
A SURVEILLANCE REQUIREMENTS (continued)
This Surveillance is performed in MODE 1 only to ensure iodine remains
within limit during normal operation and following rapid power changes
when fuel failure is more apt to occur. The 14-day Frequency is adequate
to trend changes in the iodine activity level, considering gross activity is
monitored every 7 days. The Frequency, between 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> and 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
after a power change 15% RTP within a 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> period, is established because the iodine levels peak during this time following fuel failure;
samples at other times would provide inaccurate results.
A radiochemical analysis for E determination is required every 184 days (6 months) with the plant operating in MODE 1 equilibrium conditions.
The E determination directly relates to the LCO and is required to verify plant operation within the specified gross activity LCO limit. The analysis
for E is a measurement of the average energies per disintegration for isotopes with half lives longer than 15 minutes, excluding iodines. The
Frequency of 184 days recognizes E does not change rapidly.
This SR has been modified by a Note that indicates sampling is required
to be performed within 31 days after a minimum of 2 effective full power
days and 20 days of MODE 1 operation have elapsed since the reactor
was last subcritical for at least 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br />. This ensures that the
radioactive materials are at equilibrium so the analysis for E is representative and not skewed by a crud burst or other similar abnormal
event.
REFERENCES 1. Title 10, Code of Federal Regulations, Part 100.11, "Determination of Exclusion Area, Low Population Zone, and Population Center
Distance," 1973.
- 2. Watts Bar FSAR, Section 15.4, "Condition IV - Limiting Faults."
SG TUBE INTEGRITY B 3.4.17 (continued)
Watts Bar - Unit 2 B 3.4-96 (developmental)
A B 3.4 REACTOR COOLANT SYSTEM (RCS)
B 3.4.17 STEAM GENERATOR (SG) TUBE INTEGRITY
BASES BACKGROUND Steam generator (SG) tubes are small diameter, thin walled tubes that carry primary coolant through the primary to secondary heat exchangers.
The SG tubes have a number of impor tant safety functions. Steam generator tubes are an integral part of the reactor coolant pressure
boundary (RCPB) and, as such, are relied on to maintain the primary
system's pressure and inventory. The SG tubes isolate the radioactive
fission products in the primary coolant from the secondary system. In
addition, as part of the RCPB, the SG tubes are unique in that they act as
the heat transfer surface between the primary and secondary systems to
remove heat from the primary system. This Specification addresses only the RCPB integrity function of the SG. The SG heat removal function is addressed by LCO 3.4.4, "RCS Loops - MODES 1 and 2," LCO 3.4.5, "RCS Loops - MODE 3," LCO 3.4.6, "RCS Loops - MODE 4," and
LCO 3.4.7, "RCS Loops - MODE 5, Loops Filled."
SG tube integrity means that the tubes are capable of performing their
intended RCPB safety function consistent with the licensing basis, including applicable regulatory requirements.
Steam generator tubing is subject to a variety of degradation
mechanisms. Steam generator tubes may experience tube degradation
related to corrosion phenomena, such as wastage, pitting, intergranular
attack, and stress corrosion cracking, along with other mechanically
induced phenomena such as denting and wear. These degradation
mechanisms can impair tube integrity if they are not managed effectively.
The SG performance criteria are used to manage SG tube degradation.
Specification 5.7.2.12, "Steam Generator (SG) Program," requires that a
program be established and implemented to ensure that SG tube integrity
is maintained. Pursuant to Specification 5.7.2.12, tube integrity is
maintained when the SG performance criteria are met. There are three
SG performance criteria: structural integrity, accident induced leakage, and operational LEAKAGE. The SG performance criteria are described in Specification 5.7.2.12. Meeting the SG performance criteria provides
reasonable assurance of maintaining tube integrity at normal and
accident conditions.
SG TUBE INTEGRITY B 3.4.17 BASES (continued)
Watts Bar - Unit 2 B 3.4-97 (developmental)
A BACKGROUND (continued)
The processes used to meet the SG performance criteria are defined by the Steam Generator Program Guidelines (Ref. 1).
APPLICABLE
SAFETY ANALYSES The steam generator tube rupture (SGTR) accident is the limiting design
basis event for SG tubes and avoiding an SGTR is the basis for this
Specification. The analysis of an SGTR event assumes a bounding
primary to secondary LEAKAGE rate equal to the operational LEAKAGE
rate limits in LCO 3.4.13, "RCS Operational LEAKAGE," plus the leakage
rate associated with a double-ended rupture of a single tube. The
accident analysis for a SGTR assumes the contaminated secondary fluid
is only briefly released to the atmosphere via safety valves and the
majority is discharged to the main condenser.
The analysis for design basis accidents and transients other than an SGTR assume the SG tubes retain their structural integrity (i.e., they are assumed not to rupture). In these analyses, the steam discharge to the
atmosphere is based on the total primary to secondary LEAKAGE from
150 gallons per day (gpd) per steam generator and 1 gallon per minute (gpm) in the faulted steam generator. For accidents that do not involve
fuel damage, the primary coolant activity level of DOSE EQUIVALENT
I-131 is assumed to be equal to the LCO 3.4.16, "RCS Specific Activity,"
limits. For accidents that assume fuel damage, the primary coolant
activity is a function of the amount of activity released from the damaged
fuel. The dose consequences of these events are within the limits of
GDC 19 (Ref. 2), and 10 CFR 100 (Ref. 3) or the NRC approved licensing
basis.
Steam generator tube integrity satisfies Criterion 2 of
LCO The LCO requires that SG tube integrity be maintained. The LCO also requires that all SG tubes that satisfy the repair criteria be plugged in
accordance with the Steam Generator Program.
During an SG inspection, any inspected tube that satisfies the Steam
Generator Program repair criteria is removed from service by plugging. If a tube was determined to satisfy the repair criteria but was not plugged, the tube may still have tube integrity.
SG TUBE INTEGRITY B 3.4.17 BASES (continued)
Watts Bar - Unit 2 B 3.4-98 (developmental)
A LCO (continued)
In the context of this Specification, an SG tube is defined as the entire length of the tube, including the tube wall, between the tube-to-tubesheet
weld at the tube inlet and the tube-to-tubesheet weld at the tube outlet.
The tube-to-tubesheet weld is not considered part of the tube.
An SG tube has tube integrity when it satisfies the SG performance
criteria. The SG performance criteria are defined in Specification
5.7.2.12, "Steam Generator Program," and describe acceptable SG tube
performance. The Steam Generator Program also provides the
evaluation process for determining conformance with the SG performance
criteria.
There are three SG performance criteria: structural integrity, accident
induced leakage, and operational LEAKAGE. Failure to meet any one of
these criteria is considered failure to meet the LCO.
The structural integrity performance criterion provides a margin of safety
against tube burst or collapse under normal and accident conditions, and
ensures structural integrity of the SG tubes under all anticipated
transients included in the design specification. Tube burst is defined as, "The gross structural failure of the tube wall. The condition typically
corresponds to an unstable opening displacement (e.g., opening area
increased in response to constant pressure) accompanied by ductile (plastic) tearing of the tube material at the ends of the degradation." Tube
collapse is defined as, "For the load displacement curve for a given
structure, collapse occurs at the top of the load versus displacement
curve where the slope of the curve becomes zero." The structural
integrity performance criterion provides guidance on assessing loads that
have a significant effect on burst or collapse. In that context, the term
"significant" is defined as "An accident loading condition other than
differential pressure is considered significant when the addition of such
loads in the assessment of the structural integrity performance criterion
could cause a lower structural limit or limiting burst/collapse condition to
be established." For tube integrity evaluations, except for circumferential
degradation, axial thermal loads are classified as secondary loads. For
circumferential degradation, the classification of axial thermal loads as
primary or secondary loads will be evaluated on a case-by-case basis.
The division between primary and secondary classifications will be based on detailed analysis and/or testing.
SG TUBE INTEGRITY B 3.4.17 BASES (continued)
Watts Bar - Unit 2 B 3.4-99 (developmental)
A LCO (continued)
Structural integrity requires that the primary membrane stress intensity in a tube not exceed the yield strength for all ASME Code,Section III, Service Level A (normal operating conditions), and Service Level B (upset
or abnormal conditions) transients included in the design specification.
This includes safety factors and applicable design basis loads based on
ASME Code,Section III, Subsection NB (Ref. 4) and Draft Regulatory
Guide 1.121 (Ref. 5).
The accident induced leakage performance criterion ensures that the
primary to secondary LEAKAGE caused by a design basis accident, other
than an SGTR, is within the accident analysis assumptions. The accident
analysis assumes that accident induced leakage does not exceed 1 gpm
in the faulted SG. The accident induced leakage rate includes any
primary-to-secondary LEAKAGE existing prior to the accident in addition
to primary-to-secondary LEAKAGE induced during the accident.
The operational LEAKAGE performance criterion provides an observable
indication of SG tube conditions during plant operation. The limit on
operational LEAKAGE is contained in LCO 3.4.13, "RCS Operational
LEAKAGE," and limits primary-to-secondary LEAKAGE through any one
SG to 150 gallons per day. This limit is based on the assumption that a
single crack leaking this amount would not propagate to an SGTR under
the stress conditions of a LOCA or a main steam line break. If this
amount of LEAKAGE is due to more than one crack, the cracks are very
small, and the above assumption is conservative.
APPLICABILITY Steam generator tube integrity is challenged when the pressure differential across the tubes is large. Large differential pressures across
SG tubes can only be experienced in MODE 1, 2, 3, or 4.
RCS conditions are far less challenging in MODES 5 and 6 than during
MODES 1, 2, 3, and 4. In MODES 5 and 6, primary-to-secondary
differential pressure is low, resulting in lower stresses and reduced
potential for LEAKAGE.
ACTIONS The ACTIONS are modified by a Note that the Conditions may be entered independently for each SG tube. This is acceptable because the
Required Actions provide appropriate compensatory actions for each
affected SG tube. Complying with the Required Actions may allow for
continued operation, and subsequent affected SG tubes are governed by
subsequent Condition entry, and application of associated Required
Actions.
SG TUBE INTEGRITY B 3.4.17 BASES (continued)
Watts Bar - Unit 2 B 3.4-100 (developmental)
A ACTIONS (continued)
A.1 and A.2 Condition A applies if it is discovered that one or more SG tubes
examined in an inservice inspection satisfy the tube repair criteria but
were not plugged in accordance with the Steam Generator Program as
required by SR 3.4.17.2. An evaluation of SG tube integrity of the
affected tube(s) must be made. Steam generator tube integrity is based
on meeting the SG performance criteria described in the Steam
Generator Program. The SG repair criteria define limits on SG tube
degradation that allow for flaw growth between inspections while still
providing assurance that the SG performance criteria will continue to be met. In order to determine if an SG tube that should have been plugged, has tube integrity, an evaluation must be completed that demonstrates
that the SG performance criteria will continue to be met until the next
refueling outage or SG tube inspection. The tube integrity determination
is based on the estimated condition of the tube at the time the situation is
discovered and the estimated growth of the degradation prior to the next
SG tube inspection. If it is determined that tube integrity is not being
maintained, Condition B applies.
A Completion Time of 7 days is sufficient to complete the evaluation while
minimizing the risk of plant operation with a SG tube that may not have
tube integrity.
If the evaluation determines that the affected tube(s) have tube integrity, Required Action A.2 allows plant operation to continue until the next
refueling outage or SG inspection provided the inspection interval
continues to be supported by an operational assessment that reflects the
affected tubes. However, the affected tube(s) must be plugged prior to
entering MODE 4 following the next refueling outage or SG inspection.
This Completion Time is acceptable since operation until the next
inspection is supported by the operational assessment.
B.1 and B.2
If the Required Actions and associated Completion Times of Condition A
are not met or if SG tube integrity is not being maintained, the reactor
must be brought to MODE 3 within 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and MODE 5 within 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.
The allowed Completion Times are reasonable, based on operating
experience, to reach the desired plant conditions from full power
conditions in an orderly manner and without challenging plant systems.
SG TUBE INTEGRITY B 3.4.17 BASES (continued)
(continued)
Watts Bar - Unit 2 B 3.4-101 (developmental)
A SURVEILLANCE REQUIREMENTS SR 3.4.17.1
During shutdown periods the SGs are inspected as required by this SR
and the Steam Generator Program. NEI 97-06, Steam Generator
Program Guidelines (Ref. 1), and its referenced EPRI Guidelines, establish the content of the Steam Generator Program. Use of the Steam
Generator Program ensures that the inspection is appropriate and
consistent with accepted industry practices.
During SG inspections a condition monitoring assessment of the
SG tubes is performed. The condition monitoring assessment determines the "as found" condition of the SG tubes. The purpose of the condition monitoring assessment is to ensure t hat the SG performance criteria have been met for the previous operating period.
The Steam Generator Program determines the scope of the inspection
and the methods used to determine whether the tubes contain flaws
satisfying the tube repair criteria. Inspection scope (i.e., which tubes or
areas of tubing within the SG are to be inspected) is a function of existing
and potential degradation locations. The Steam Generator Program also
specifies the inspection methods to be used to find potential degradation.
Inspection methods are a function of degradation morphology, nondestructive examination (NDE) technique capabilities, and inspection
locations.
The Steam Generator Program defines the Frequency of SR 3.4.17.1.
The Frequency is determined by the operational assessment and other
limits in the SG examination guideli nes (Ref. 6). The Steam Generator Program uses information on existing degradations and growth rates to
determine an inspection Frequency that provides reasonable assurance
that the tubing will meet the SG performance criteria at the next
scheduled inspection. In addition, Specification 5.7.2.12 contains
prescriptive requirements concerning inspection intervals to provide added assurance that the SG performance criteria will be met between scheduled inspections.
SG TUBE INTEGRITY B 3.4.17 BASES Watts Bar - Unit 2 B 3.4-102 (developmental)
A SURVEILLANCE REQUIREMENTS (continued)
During an SG inspection, any inspected tube that satisfies the Steam
Generator Program repair criteria is removed from service by plugging.
The tube repair criteria delineated in Specification 5.7.2.12 are intended
to ensure that tubes accepted for continued service satisfy the
SG performance criteria with allowance for error in the flaw size
measurement and for future flaw growth. In addition, the tube repair
criteria, in conjunction with other elements of the Steam Generator
Program, ensure that the SG performance criteria will continue to be met
until the next inspection of the subject tube(s). Reference 1 provides guidance for performing operational assessments to verify that the tubes remaining in service will continue to meet the SG performance criteria.
The Frequency of prior to entering MODE 4 following an SG inspection
ensures that the Surveillance has been completed and all tubes meeting
the repair criteria are plugged prior to subjecting the SG tubes to
significant primary-to-secondary pressure differential.
REFERENCES
- 1. NEI 97-06, "Steam Generator Program Guidelines."
- 2. 10 CFR 50 Appendix A, GDC 19, Control Room.
- 3. 10 CFR 100, Reactor Site Criteria.
- 4. ASME Boiler and Pressure Vessel Code,Section III, Subsection NB. 5. Draft Regulatory Guide 1.121, "Basis for Plugging Degraded Steam Generator Tubes," August 1976.
- 6. EPRI, "Pressurized Water Reactor Steam Generator Examination Guidelines."