MONTHYEARIR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 LR-N24-0038, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities 2024-09-25
[Table view] Category:Inspection Report
MONTHYEARIR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 IR 05000272/20230012023-05-0303 May 2023 Integrated Inspection Report 05000272/2023001 and 05000311/2023001 IR 05000272/20233012023-05-0101 May 2023 Initial Operator Licensing Examination Report 05000272/2023301 and 05000311/2023301 IR 05000272/20230112023-03-0707 March 2023 Comprehensive Engineering Team Inspection Report 05000272/2023011 and 05000311/2023011 IR 05000272/20220062023-03-0101 March 2023 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022006 and 05000311/2022006) IR 05000272/20220042023-01-31031 January 2023 Integrated Inspection Report 05000272/2022004 and 05000311/2022004 IR 05000272/20220112023-01-0606 January 2023 Design Basis Assurance Inspection (Programs) Inspection Report 05000272/2022011 and 05000311/2022011 IR 05000272/20220032022-11-0909 November 2022 Integrated Inspection Report 05000272/2022003 and 05000311/2022003 IR 05000272/20224022022-10-14014 October 2022 Cyber Security Report 05000272/2022402 and 05000311/2022402 - Cover Letter Only IR 05000272/20220052022-08-31031 August 2022 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2022005 and 05000311/2022005) IR 05000272/20220022022-08-0808 August 2022 Integrated Inspection Report 05000272/2022002 and 05000311/2022002 IR 05000272/20224012022-07-21021 July 2022 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2022401, 05000272/2022401, and 05000311/2022401 (Cover Letter Only) IR 05000272/20225012022-06-14014 June 2022 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2022501, 05000272/2022501, and 05000311/2022501 IR 05000272/20220012022-05-0404 May 2022 Integrated Inspection Report 05000272/2022001 and 05000311/2022001 IR 05000272/20223012022-04-27027 April 2022 Initial Operator Licensing Examination Report 05000272/2022301 and 05000311/2022301 IR 05000272/20210132022-03-10010 March 2022 Evaluation of Changes, Tests, and Experiments Baseline IR 05000354/2021013, 05000272/2021013 and 05000311/2021013 & ISFSI IR 07200048/2021001 Related to PSEG Evals of Stations & Planned Wind Port Manufacturing Facility IR 05000272/20210062022-03-0202 March 2022 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2021006 and 05000311/2021006) IR 05000272/20210042022-02-10010 February 2022 Integrated Inspection Report 05000272/2021004 and 05000311/2021004 IR 05000272/20215012021-11-30030 November 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2021501, 05000272/2021501 and 05000311/2021501 IR 05000272/20214022021-11-19019 November 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2021402, 05000272/2021402 and 05000311/2021402 IR 05000272/20210032021-11-0202 November 2021 Integrated Inspection Report 05000272/2021003 and 05000311/2021003 IR 05000272/20214032021-10-28028 October 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Biennial Problem Identification and Resolution Inspection Report (Security-Related Information) 05000354/2021403, 05000272/2021403 and 05000311/2021403 (Cover Letter Only IR 05000272/20210122021-10-28028 October 2021 and Salem Nuclear Generating Station, Units 1 and 2 - Biennial Problem Identification and Resolution Inspection Report 05000354/2021012, 05000272/2021012 and 05000311/2021012 IR 05000272/20210112021-09-30030 September 2021 Temporary Instruction 2515/194 Inspection Report 05000272/2021011 and 05000311/2021011 IR 05000272/20210052021-09-0101 September 2021 Updated Inspection Plan for the Salem Nuclear Generating Station (Report 05000272/2021005 and 05000311/2021005) IR 05000272/20210022021-08-18018 August 2021 Reissued Integrated Inspection Report 05000272/2021002 and 05000311/2021002 ML21222A1402021-08-11011 August 2021 Integrated Inspection Report 05000272/2021002 and 05000311/2021002 IR 05000272/20210012021-05-0505 May 2021 Integrated Inspection Report 05000272/2021001 and 05000311/2021001 IR 05000272/20210102021-03-0909 March 2021 Triennial Fire Protection Inspection Report 05000272/2021010 and 05000311/2021010 IR 05000272/20200062021-03-0303 March 2021 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2020006 and 05000311/2020006) IR 05000272/20214012021-02-23023 February 2021 and Salem Nuclear Generating Station, Units 1 and 2: Security Baseline Inspection Report 05000354/2021401, 05000272/2021401 and 05000311/2021401 (Letter Only) IR 05000272/20200042021-02-0909 February 2021 Generating Station, Units 1 and 2: Integrated Inspection Report 05000272/2020004 and 05000311/2020004 ML21008A5092021-01-21021 January 2021 Inspection Report 2024-09-25
[Table view] |
See also: IR 05000272/2010009
Text
October 28, 2010 Docket No. 05000272License No. DPR-70
05000311 DPR-75
07200048
Thomas P. Joyce
President and Chief Nuclear Officer
PSEG Nuclear LLC
P.O. Box 236
Hancocks Bridge, NJ 08038
SUBJECT: NRC INDEPENDENT SPENT FUEL STORAGE INSTALLATION INSPECTION REPORT NOS. 05000272/2010009, 05000311/2010009, AND
07200048/2010001, SALEM NUCLEAR GENERATING STATION, PSEG
NUCLEAR LLC, HANCOCKS BRIDGE, NEW JERSEY
Dear Mr. Joyce:
On September 20, 2010, the NRC completed an inspection of the Salem Nuclear Generating
Station Independent Spent Fuel Storage Installation (ISFSI) pre-operational activities and initial
loading of spent fuel into the ISFSI facility. The ins
pection period began August 9, 2010. The findings were discussed with Lou Menoscal, Nuclear Project Manager, and other members of
your staff during a preliminary exit meeting on September 17, 2010. At the preliminary exit
meeting, Mr. Menoscal was informed the inspection would remain open until the initial
multipurpose canister (MPC) was successfully stored at the ISFSI pad. This was accomplished
on September 20, 2010. A final exit meeting was conducted, via telephone, on
September 20, 2010, with Tom Wallender, ISFSI Project Manager. The enclosed report
presents the results of this inspection.
The inspection examined activities associated with the preparation, movement and placement of
spent fuel from the spent fuel pool into the ISFSI facility. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, no findings were identified.
In accordance with 10 CFR Part 2.390 of the NRC's "Rules of Practice," a copy of this letter, its
enclosure, and your response (if any) will be available electronically for public ins
pection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's
document system (ADAMS). ADAMS is accessible from the NRC Web Site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electric Reading Room).
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415
T. Joyce 2
Thank you for your cooperation during this inspection.
Sincerely,
Original signed by Judith A. Joustra
Judith A. Joustra, Chief
Decommissioning Branch
Division of Nuclear Materials Safety
Enclosure:
Inspection Report Nos. 05000272/2010009, 05000311/2010009, and 07200048/2010001
w/Attachment: Supplemental Information
cc:
State of New Jersey
State of Delaware
2 T. Joyce
Thank you for your cooperation during this inspection.
Sincerely,
Judith A. Joustra, Chief
Decommissioning Branch
Division of Nuclear Materials Safety
Enclosure:
Inspection Report Nos. 05000272/2010009, 05000311/2010009, and 07200048/2010001
w/Attachment: Supplemental Information
cc:
State of New Jersey
State of Delaware
Distribution w/encl
- W. Dean, RA (R1ORAMAIL Resource)
M. Dapas, DRA (R1ORAMAIL Resource)
J. Kinneman, DNMS (R1DNMSMAIL Resource)
P. Henderson, DNMS (R1DNMSMAIL Resource)
D. Lew, DRP (R1DRPMAIL Resource)
J. Clifford, DRP (R1DRPMAIL Resource) D. Roberts, DRS (R1DRSMail Resource) P. Wilson, DRS (R1DRSMail Resource)
A. Burritt, DRP J. Joustra, DNMS
S. Hammann, DNMS
M. Roberts, DNMS
J. Pearson, NMSS E. Love, NMSS S. Chaudhary, DRS
L. Cline, DRP
A. Turilin, DRP
C. Douglas, DRP
D. Schroeder, DRP, SRI
P. McKenna, DRP, RI
K. McKenzie, Resident OA
D. Garner, NSIR
G. Miller, RI OEDO
D. Bearde, DRS RidsNrrPMSalem Resourc
e DOCUMENT NAME: G:\WordDocs\D&LB_ISFSI_IRs\LDPR-70.2010009.doc
SUNSI Review Complete: SHammann
After declaring this document
AAn Official Agency Record
@ it will be released to the Public.
To receive a copy of this document, indicate in the box:
A C@ = Copy w/o attach/encl
A E@ = Copy w/ attach/encl
A N@ = No copy
OFFICE DNMS/RI
N DNMS/RI N DRP/RI N
NAME SHammann MCR For JJoustra JAJ ABurritt LC For
DATE 10/27/10 10/28/10 10/27/10 ML103010268 - Ltr ML103010290 - Rpt
OFFICIAL RECORD COPY