Letter Sequence Request |
---|
CAC:MF7294, Generic Letter 2008-01, Managing Gas Accumulation (Approved, Closed) |
|
|
Similar Documents at Cook |
---|
Category:Letter
MONTHYEARIR 05000315/20230042024-01-31031 January 2024 Integrated Inspection Report 05000315/2023004 and 05000316/2023004 ML24004A1582024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0039 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) AEP-NRC-2024-01, Emergency Plan Revision 482024-01-0808 January 2024 Emergency Plan Revision 48 AEP-NRC-2023-56, Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor2023-12-20020 December 2023 Report Per Technical Specification 5.6.6 for Inoperability of Unit 1 Post Accident Monitoring Reactor Coolant (Loop 3 Cold Leg) Wide Range Temperature Recorder Thermal Sensor ML23352A3502023-12-19019 December 2023 Dc. Cook Nuclear Power Plant, Units 1 Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination AEP-NRC-2023-45, Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 Unit 2 - Schedular Exemption for Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Implementation IR 05000315/20234042023-11-0606 November 2023 Cyber Security Inspection Report 05000315/2023404 and 05000316/2023404 ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 IR 05000315/20234032023-09-19019 September 2023 Security Baseline Inspection Report 05000315/2023403 and 05000316/2023403 IR 05000315/20230112023-08-31031 August 2023 Functional Engineering Inspection - Commercial Grade Dedication Report 05000315/2023011 and 05000316/2023011 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 AEP-NRC-2023-40, Annual Report of Loss-of-Coolant Accident Evaluation Model Changes2023-08-29029 August 2023 Annual Report of Loss-of-Coolant Accident Evaluation Model Changes IR 05000315/20234022023-08-11011 August 2023 Security Baseline Inspection Report 05000315/2023402 and 05000316/2023402 AEP-NRC-2023-34, Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation2023-08-0202 August 2023 Supplement to Request for Approval of Change Regarding Neutron Flux Instrumentation IR 05000315/20230022023-07-24024 July 2023 Integrated Inspection Report 05000315/2023002 and 05000316/2023002 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III IR 05000315/20230122023-06-22022 June 2023 Biennial Problem Identification and Resolution Inspection Report 05000315/2023012 and 05000316/2023012 IR 05000315/20235012023-06-21021 June 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000315/2023501 and 05000316/2023501 AEP-NRC-2023-29, Core Operating Limits Report2023-06-19019 June 2023 Core Operating Limits Report ML23159A0192023-06-13013 June 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Donald C. Cook Nuclear Plant, Units 1 and 2 AEP-NRC-2023-32, Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations2023-06-0606 June 2023 Response to NRC Regulatory Issue Summary 2023-1 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2023-33, Renewable Operating Permit2023-06-0505 June 2023 Renewable Operating Permit AEP-NRC-2023-30, Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump2023-06-0101 June 2023 Follow-Up Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-27, Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Annual Radiological Environmental Operating Report ML23131A3282023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 IR 05000315/20230012023-05-0303 May 2023 Integrated Inspection Report 05000315/2023001 and 05000316/2023001 AEP-NRC-2023-19, Annual Radioactive Effluent Release Report2023-04-30030 April 2023 Annual Radioactive Effluent Release Report ML23117A0062023-04-27027 April 2023 Review of the Spring 2022 Steam Generator Tube Inspections Report ML23114A1142023-04-25025 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection AEP-NRC-2023-23, Annual Report of Individual Monitoring for 20222023-04-24024 April 2023 Annual Report of Individual Monitoring for 2022 AEP-NRC-2023-24, Notification of Ph Non-Compliance for Turbine Room Sump2023-04-12012 April 2023 Notification of Ph Non-Compliance for Turbine Room Sump AEP-NRC-2023-20, Annual Report of Property Insurance2023-04-0303 April 2023 Annual Report of Property Insurance AEP-NRC-2023-15, Decommissioning Funding Status Report2023-03-28028 March 2023 Decommissioning Funding Status Report ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 IR 05000315/20234012023-03-16016 March 2023 Security Baseline Inspection Report 05000315/2023401 and 05000316/2023401 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220042023-02-0101 February 2023 Integrated Inspection Report 05000315/2022004 and 05000316/2022004 and Exercise of Enforcement Discretion AEP-NRC-2023-11, Form OAR-1, Owner'S Activity Report2023-01-31031 January 2023 Form OAR-1, Owner'S Activity Report IR 05000315/20230102023-01-31031 January 2023 Phase 4 Post-Approval License Renewal Inspection Report 05000315/2023010 and 05000316/2023010 AEP-NRC-2023-02, Request for Approval of Change Regarding Neutron Flux Instrumentation2023-01-26026 January 2023 Request for Approval of Change Regarding Neutron Flux Instrumentation ML22363A5622023-01-0404 January 2023 Relief Request ISIR-5-06 Related to ASME Code Case N-729-6 Supplemental Examination Requirements of Reactor Vessel Closure Head Penetration Nozzles AEP-NRC-2022-66, Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring2022-12-15015 December 2022 Report Per Technical Specification 5.6.6 for Inoperability of Unit 2 Post Accident Monitoring Neutron Flux Monitoring AEP-NRC-2022-46, Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in2022-12-12012 December 2022 Notification of Deviation from Electric Power Research Institute (EPRI) Materials Reliability Program 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in ML22340A1392022-11-30030 November 2022 Submittal of Revision 31 to Updated Final Safety Analysis Report and 10CFR50.71(e) Updated and Related Site Change Reports IR 05000315/20220112022-11-0404 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000315/2022011 and 05000316/2022011 IR 05000315/20220032022-10-28028 October 2022 Integrated Inspection Report 05000315/2022003 and 05000316/2022003 AEP-NRC-2022-58, U1C31 Steam Generator Tube Inspection Report2022-10-24024 October 2022 U1C31 Steam Generator Tube Inspection Report AEP-NRC-2022-61, Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-062022-10-24024 October 2022 Request for Relief Related to American Society of Mechanical Engineers (ASME) Code Case N-729-6 Supplemental Examination Requirements, ISIR-5-06 2024-01-08
[Table view] |
Text
INDIANA Indiana Michigan Power MICHIGAN Cook Nuclear Plant POIWER One Cook Place Bridgman, MI 49106 A unit ofAmerican Electric Power IndianaMichiganPower.com June 24, 2015 AEP-NRC-2015-37 10 CFR 50.4 Docket Nos. 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Donald C. Cook Nuclear Plant Unit 1 and Unit 2 COMMITMENT SCHEDULE CHANGE RELATED TO TECHNICAL SPECIFICATION TASK FORCE-523
References:
- 1. U. S. Nuclear Regulatory Commission (NRC) Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, dated January 11, 2008, Agencywide Documents Access and Management System (ADAMS) Accession No. ML072910759.
- 2. Letter from L. J. Weber, Indiana Michigan Power Company (A&M), to NRC, Nine-Month Response to NRC Generic Letter 2008-01 issued pursuant to 10 CFR 50.54(f), "Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated October 14, 2008, ADAMS Accession No. ML082950467.
- 3. Letter from J. P. Gebbie, I&M, to NRC, Evaluation of TSTF-523 "Generic Letter 2008-01, Managing Gas Accumulation," dated March 7, 2014, ADAMS Accession No. ML14070A344.
- 4. NRC Memorandum from J. Holonich to A.J. Mendiola re: Minutes From Aug 19, 2014 Meeting on Gas Voids NEI Version, dated October 1, 2014, ADAMS Accession No. ML14266A168.
Indiana Michigan Power Company (I&M), the licensee for Donald C. Cook Nuclear Plant (CNP), Units 1 and 2, is providing notification of a change to a regulatory commitment that was documented in Reference
- 3. I&M has revised the completion date to submit a license amendment request (LAR)for technical specification (TS) revisions related to Technical Specification Task Force (TSTF)-523, Generic Letter 2008-01, Managing Gas Accumulation.
In Reference 1, the U. S. Nuclear Regulatory Commission (NRC) requested information from licensees regarding how they protect certain safety systems from the accumulation of air, nitrogen, or other gases that could cause the systems to become inoperable.
The Generic Letter (GL) requested U. S. Nuclear Regulatory Commission AEP-NRC-2015-37 Page 2 licensees to evaluate their emergency core cooling system (ECCS), residual heat removal (RHR), and containment spray (CTS) systems in order to determine how their licensing basis, design, testing, and corrective actions ensure that gas accumulation is maintained less than the amount that challenges operability of these systems, and that appropriate action is taken when conditions adverse to quality are identified.
In addition, the NRC requested licensees to provide a statement regarding which corrective actions were completed, the schedule for completing the remaining corrective actions, and the basis for that schedule.
I&M provided a response to Reference 1 for CNP in Reference
- 2. Reference 2 contained the following commitment to provide an evaluation of TSTF-523 within 60 days of NRC approval of TSTF-523: "Evaluate the TSTF Traveler for gas accumulation to either supplement or replace the current TS requirements." Notice of Availability for adopting TSTF-523 under the Consolidated Line Item Improvement Process was provided in 79 FR 2700 on January 15, 2014. I&M satisfied the Reference 2 commitment by letter dated March 7, 2014 (Reference 3), which concluded that additional analysis is required to determine the actions necessary to ensure the ECCS, RHR, and CTS systems are capable of performing their specified safety functions and that these systems are in compliance with their licensing basis with respect to the concerns outlined in GL 2008-01. As a result, a new commitment was made in Reference 3 related to TSTF-523, as stated below: "Conduct additional technical evaluation of Emergency Core Cooling Systems, Residual Heat Removal System, and Containment Spray System for gas accumulation.
Upon completion of the evaluation, submit a license amendment request to adopt the appropriate portions of TSTF-523." The commitment change identified in this letter applies only to extension of the completion date.The commitment wording is unchanged and continues to specify TSTF-523 as the basis of the proposed license amendment.
In Reference 3, I&M committed to perform additional analysis of gas accumulation issues at CNP and submit a LAR by June 30, 2015. However, as recognized in the memorandum dated October 1, 2014, to Licensing Processes Branch Chief Anthony J. Mendiola (Reference 4), there is uncertainty in the industry regarding the NRC endorsed guidance for implementing TSTF-523 (i.e., RIS .2013-09 and NEI 09-10 Revision 1a-A). Concurrently, I&M was evaluating bids from various vendors for performing site-specific analysis of the potentially affected systems. Although industry resolution of the uncertainties detailed in Reference 4 has not occurred, I&M has determined that the necessary analysis should be performed notwithstanding the uncertainties.
I&M has recently chosen a vendor to perform the analysis and the schedule for completion of the analysis would not allow for a June 30, 2015, LAR submittal.
Therefore, I&M is submitting this letter to notify the NRC that the commitment to submit a LAR has been extended to January 29, 2016, to allow time for additional analysis to be performed prior to implementing TSTF-523.
U. S. Nuclear Regulatory Commission AEP-NRC-2015-37 Page 3 This letter contains no new regulatory commitments and one revised regulatory commitment due date, as summarized in the enclosure to this letter. Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.Sincerely, Joel P. Gebbie Site Vice President TLC/ams
Enclosure:
Donald C. Cook Nuclear Plant Regulatory Commitment c: A. W. Dietrich, NRC, Washington, D.C.J. T. King -MPSC MDEQ -RMD/RPS NRC Resident Inspector C. D. Pederson, NRC, Region III A. J. Williamson, AEP Ft. Wayne, w/o enclosures Enclosure to AEP-NRC-2015-37 Donald C. Cook Nuclear Plant Regulatory Commitment The following table identifies the action committed to by Indiana Michigan Power Company for implementation of Technical Specification Task Force (TSTF)-523 at Donald C. Cook Nuclear Plant. Any other actions discussed in this submittal represent intended or planned actions by I&M. They are described to the U. S. Nuclear Regulatory Commission (NRC) for the NRC's information and are not regulatory commitments.
Commitment Completion Date Conduct additional technical evaluation of Emergency Core Cooling Systems, Residual Heat Removal System, and Containment Spray System for gas accumulation.
Upon January 29, 2016 completion of the evaluation, submit a license amendment request to adopt the appropriate portions of TSTF-523.