|
---|
Category:Letter
MONTHYEARIR 05000416/20240112024-10-16016 October 2024 – Fire Protection Team Inspection Report 05000416/2024011 ML24263A2712024-09-19019 September 2024 Application to Revise Technical Specifications to Adopt TSTF-592, Revise Automatic Depressurization System (ADS) Instrumentation Requirements ML24257A0172024-09-17017 September 2024 Request for Withholding Information from Public Disclosure Unit 1 IR 05000416/20240122024-09-17017 September 2024 License Renewal Post Approval Phase 2 Inspection Report 05000416/2024012 ML24254A3602024-09-10010 September 2024 Pre-Submittal Slides for License Amendment Request, Criticality Safety Analysis, Technical Specification 4.3.1, Criticality and Technical Specification 5.5.14, Spent Fuel Storage Rack Neutron Absorber Monitoring Program IR 05000416/20244022024-09-0909 September 2024 Security Baseline Inspection Report 05000416/2024402 05000416/LER-2024-003, Feedwater Inlet Check Valve Incorrectly Determined Operable2024-08-26026 August 2024 Feedwater Inlet Check Valve Incorrectly Determined Operable ML24235A0832024-08-22022 August 2024 Evaluations Performed in Accordance with 10 CFR 50.54(q) for Changes to Emergency Planning Documents IR 05000416/20240052024-08-21021 August 2024 Updated Inspection Plan for Grand Gulf Nuclear Station (Report 05000416/2024005) ML24220A2642024-08-20020 August 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24185A1522024-08-13013 August 2024 Issuance of Amendment Nos. 334, 235, and 215, Respectively, to Revise TSs to Adopt TSTF-205 ML24176A1202024-07-29029 July 2024 Issuance of Amendment 234 Revision to Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b IR 05000416/20240022024-07-29029 July 2024 Integrated Inspection Report 05000416/2024002 ML24172A2502024-07-29029 July 2024 – Issuance of Amendment No. 233 Adoption of 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML24204A2432024-07-23023 July 2024 Notification of Cyber Security Baseline Inspection and Request for Information (05000416/2024403) ML24191A2432024-07-0909 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operations IR 05000416/20240102024-06-27027 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000416/2024010 ML24156A1762024-06-24024 June 2024 Regulatory Audit Summary in Support of License Amendment Requests to Adopt TSTF-505, Revision 2 and 10 CFR 50.69 (Epids L-2023-LLA-0081 and L-2023-LLA-0080) ML24165A1512024-06-13013 June 2024 Second Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times – RITSTF Initiative 4b and Application to Adopt 10 CFR 50.69, Risk-Informe ML24163A2652024-06-11011 June 2024 Inservice Inspection Summary Report ML24060A2192024-05-30030 May 2024 Authorization of Alternative to Use EN-RR-01 Concerning Proposed Alternative to Adopt Code Case N-752 05000416/LER-2024-002, Automatic Actuation of Reactor Protection System2024-05-28028 May 2024 Automatic Actuation of Reactor Protection System ML24130A0912024-05-0909 May 2024 Request for Information Letter License Renewal Phase 2 Inspection ML24128A1512024-05-0909 May 2024 Project Manager Assignment ML24128A0422024-05-0707 May 2024 License Amendment Request to Remove Obsolete License Conditions IR 05000416/20240012024-05-0202 May 2024 Integrated Inspection Report 05000416 2024001 ML24122C6112024-05-0101 May 2024 Supplement to License Amendment Request to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - Ritstf. ML24116A0372024-04-25025 April 2024 Report of Technical Specification Bases Changes ML24113A0952024-04-22022 April 2024 Annual Radioactive Effluent Release Report for 2023 ML24113A0972024-04-22022 April 2024 Annual Report of Individual Monitoring - NRC Form 5 for 2023 Per 1 0 CFR 20.2206 ML24107B0402024-04-16016 April 2024 Notification by Entergy Operations, Inc., of Proposed Economic Performance Incentive and Reliance on Post-Event Improvements in Plant Procedures And/Or Methods of Operation in FERC ML24107A8872024-04-16016 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) ML24101A3882024-04-10010 April 2024 Response to Request for Confirmation of Information by the Office of Nuclear Reactor Regulation Proposed Alternative Request EN-RR-22-001 Risk-Informed Categorization and Treatment for Repair ML24100A0692024-04-0909 April 2024 Report of Changes or Errors to 10 CFR 50.46 Analysis ML24094A0992024-04-0303 April 2024 (GGNS) Core Operating Limits Report (COLR) Cycle 25, Revision O ML24089A2262024-03-29029 March 2024 Entergy Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Exams ML24087A1962024-03-27027 March 2024 High Pressure Core Spray Inoperable Due to Minimum Flow Valve Failure to Close IR 05000416/20220042024-03-19019 March 2024 – Amended Integrated Inspection Report 05000416/2022004 and Exercise of Enforcement Discretion ML24075A1712024-03-15015 March 2024 Nuclear Onsite Property Damage Insurance (10 CFR 50.54(w)(3)) ML24074A2892024-03-14014 March 2024 Proof of Financial Protection (10 CFR 140.15) ML24058A3512024-02-28028 February 2024 Notification of Biennial Problem Identification and Resolution Inspection and Request for Information IR 05000416/20230062024-02-28028 February 2024 Annual Assessment Letter for Grand Gulf Nuclear Station - Report 05000416/2023006 IR 05000416/20233012024-02-26026 February 2024 NRC Examination Report 05000416-2023301 ML24043A1892024-02-12012 February 2024 Spent Fuel Storage Radioactive Effluent Release Report for 2023 ML24012A1422024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0051 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24043A0732024-01-29029 January 2024 2024-01 Post Examination Comments IR 05000416/20230042024-01-25025 January 2024 Integrated Inspection Report 5000416/2023004 IR 05000416/20234012024-01-18018 January 2024 Cyber Security Inspection Report 05000416/2023401 (Public) ML24018A0222024-01-18018 January 2024 Core Operating Limits Report (COLR) Cycle 24, Revision 2 IR 05000416/20243012024-01-16016 January 2024 NRC Initial Operator Licensing Examination Approval 05000416/2024301 2024-09-09
[Table view] Category:Schedule and Calendars
MONTHYEARML23130A2732023-05-10010 May 2023 and Waterford 3 Steam Electric Station - Response to Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML21354A7512021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 6 of 18 ML21354A7522021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 7 of 18 ML21354A7532021-12-20020 December 2021 Recertification of Foreign Ownership Control or Influence and Request for FOCI Redetermination - Part 8 of 18 ML21126A3032021-05-10010 May 2021 Entergy Operations, Inc. Pre-Submittal Meeting - Grand Gulf Nuclear Station, Unit 1 Relief Request to Adopt Performance-based Testing for Pressure Isolation Valves (Pivs) ML21083A1422021-03-22022 March 2021 Strategy 4 ML21083A1372021-03-22022 March 2021 NEIMA Reporting ML21083A1382021-03-22022 March 2021 Rulemaking ML21083A1392021-03-22022 March 2021 Strategy 1 ML21083A1402021-03-22022 March 2021 Strategy 2 ML21083A1412021-03-22022 March 2021 Strategy 3 ML21083A1432021-03-22022 March 2021 Strategy 5 ML21083A1442021-03-22022 March 2021 Strategy 6 ML20365A0702020-12-30030 December 2020 Schedule Change to Open Phase Condition Detection Implementation ML20318A3862020-11-13013 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic ML16012A3912016-02-0303 February 2016 Schedule Revision for the Review of the Grand Gulf Nuclear Station, License Renewal Application ML13297A2502013-10-30030 October 2013 Schedule Revision for the Environmental Review of the Grand Gulf Nuclear Station License Renewal Application ML13002A4302013-02-26026 February 2013 Revision of Schedule for the Conduct of a Review of the Grand Gulf Nuclear Station, License Renewal Application ML12242A5452012-09-0707 September 2012 Revision of Schedule for the Conduct of Review of the Grand Gulf Nuclear Station, LRA ML11335A3402011-12-16016 December 2011 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Application from Entergy Operations, Inc. for Renewal of the Operating License for Gulf Nuclear Station, Uni GNRO-2011/00068, Response to NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examination2011-08-17017 August 2011 Response to NRC Regulatory Issue Summary 2011-04, Preparation and Scheduling of Operator Licensing Examination CNRO-2011-00003, Unit 1, Updated Schedule of Submittal of Future License Renewal Applications2011-06-22022 June 2011 Unit 1, Updated Schedule of Submittal of Future License Renewal Applications 2023-05-10
[Table view] |
Text
Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 October 30, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION
Dear Mr. Mulligan:
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 1 0 of the Code of Federal Regulations
( 1 0 CFR) Part 51 and 1 0 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance of the draft supplemental environmental impact statement and subsequent environmental review milestones.
The revised schedule is enclosed.
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@
nrc.qov.
Docket No. 50-416
Enclosure:
Revised Schedule cc: Listserv Sincerely,
\;3---W-:Lub s *,Director Div ic;n of Lie se Renewal Office of Nuclear Reactor Regulation October 30, 2013 Mr. Kevin J. Mulligan Vice President, Site Entergy Operations, Inc. P.O. Box 756 Port Gibson, MS 39150
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION
Dear Mr. Mulligan:
By letter dated October 28, 2011, Entergy Operations, Inc., submitted an application pursuant to Title 10 of the Code of Federal Regulations (1 0 CFR) Part 51 and 10 CFR Part 54, to renew the Grand Gulf Nuclear Station, Unit 1 (GGNS), operating license NPF-29, for review by the U.S. Nuclear Regulatory Commission (NRC). This letter is to inform you of a change in the environmental review schedule for the GGNS license renewal review. Due to the current and projected workload of the NRC's publishing resources, the GGNS environmental review schedule has been updated to reflect a change in the date of the issuance ot the draft supplemental environmental impact statement and subsequent environmental review milestones.
The revised schedule is enclosed.
If you have any questions related to this revised schedule, please contact Mr. David Drucker, senior project manager, for the review of the GGNS license renewal application, by telephone at 301-415-6223 or by e-mail at david.drucker@
nrc.qov.
Docket No. 50-416
Enclosure:
Revised Schedule cc: Listserv DISTRIBUTION:
See next page ADAMS Accession No
- ML 13297 A250 .. OFFICE LA:RPB2:DLR PM: RPB2:DLR NAME I King DDrucker DATE t 0/30/13 t 0/25/13 Sincerely, IRA! John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation
- concurred via email BC:RPB2:DLR D:DLR BWittick Jlubinski 10/28/13 10/30/13 OFFICIAL RECORD COPY GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION SCHEDULE REVISION Milestone Schedule Receive license renewal application (LRA) 11/1/2011 Publish Federal Register notice (FAN) -LRA availability 11/2011 Publish FAN -acceptance/rejection and opportunity for hearing 12/2011 Publish FAN -environmental seeping meeting 12/2011 Audit-Seeping & Screening Methodology 1/9/2012 Audit-Aging Management Programs 1/23/2012 Public Meeting License Renewal Overview and Environmental Seeping 1/3112012 meeting Deadline for filing hearing requests and petitions for intervention 2/2012 Environmental seeping period ends 2/2012 Audit-Environmental 3/26/2012 Inspection-Regional 8/2012 Issue safety evaluation report (SER) with open items 1/2013 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee TBD meetina Issue draft supplemental environmental impact statement (SEIS) 1/2014 U.S. Environmental Protection Agency FRN Published-draft SEIS 2/2014 available for comment Public Meeting-draft SEIS meeting 3/2014 End of draft SEIS comment period 3/2014 Issue final SER TBD ACRS full committee meeting TBD Issue final SEIS 9/2014 U.S. Environmental Protection Agency FRN Published-availability of final 1 0/2014 SEIS Decision-
- Director, Office of Nuclear Reactor Regulation TBD Commission decision (if hearing is granted)
TBD Actual 11/1/2011 11/17/2011 12/27/2011 12/29/2011 1/9/2012 1/23/2012 1/31/2012 2/27/2012 2/27/2012 3/27/2012-3/29/2012 8/6/2012 1/2013 ENCLOSURE Letter to K. Mulligan From J. Lubinski dated October 30, 2013
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE GRAND GULF NUCLEAR STATION LICENSE RENEWAL APPLICATION DISTRIBUTION:
HARD COPY: DLR RF E-MAIL: PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRapb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource JDaily DDrucker OW rona BMizuno, OGC AWang, DORL RSmith, RIV BRice, RIV DAIIen, RIV DMclntyre, OPA