RBS 2014 Annual Assessment Letter
ML15063A562
Person / Time
Site: River Bend Entergy icon.png
Issue date: 03/04/2015
From: Pruett T W
NRC/RGN-IV/DRP
To: Olson E W
Entergy Operations
R. Azua
References
IR 20144001
Download: ML15063A562 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011

-4511 March 4, 2015 Mr. Eric W. Olson, Site Vice President Entergy Operations, Inc.

River Bend Station 5485 U.S. Highway 61N St. Francisville, LA 70775

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2014001) Dear Mr. Olson

On February 19, 2015, the Nuclear Regulatory Commission (

NRC) completed its end

-of-cycle performance review of the River Bend Station

. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRC's assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at the River Bend Station during the most recent quarter was within the Regulatory Response Column of the NRC

's Reactor Oversight Process (ROP) Action Matrix. On October 23, 2014, the NRC issued an Assessment Follow

-up Letter for the River Bend Station (ML14296A082) which stated that based on the issuance of a Greater-than-Green inspection finding in the Security Cornerstone, the NRC determined the performance at River Bend Station to be in the Regulatory Response Column of the NRC's Reactor Oversight Process Action Matrix, beginning in the second quarter of 2014. Therefore, the NRC plans to conduct a supplemental inspection. In addition, the River Bend Station

's safety-significant performance indicator (PI) for Unplanned Scrams with Complications, crossed the Green-White threshold during the 4th Quarter 2014. This was due to two unplanned scrams the River Bend Station experienced in the 4 th Quarter of 2014. Therefore, the NRC plans to conduct Inspection Procedure 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area."

The NRC requests that your staff provide notification of your readiness for the NRC to conduct this supplemental inspection. Because, this White input is not in the same strategic performance area as the finding in the Security Cornerstone described above, the River Bend Station remains in the Regulatory Response Column.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid

-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security

-related inspections, which will be sent via separate, non

-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC

's "Rules of Practice,

" a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Please contact Greg Warnick, Chief, Project Branch C, at 817-200-1144 with any questions you have regarding this letter

. Sincerely, /RA/ Troy W. Pruett, Director Division of Reactor Projects Docket: 50-458 License:

NPF-47

Enclosure:

River Bend Station Inspection Plan

Page 1 of 2 02/26/2015 19:47:10Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteRiver BendInspection / Activity Plan 03/01/2015

-06/30/201671111.08-INSERVICE INSPECTION 11 IPInservice Inspection Activities - BWR7111108G02/23/2015 03/06/2015 RS 12 PI-RADIATION SAFETY 21 IPRadiological Hazard Assessment and Exposure Controls71124.0103/02/2015 03/06/2015 1 IPOccupational ALARA Planning and Controls71124.0203/02/2015 03/06/2015 1 IPOccupational Exposure Control Effectiveness71151-OR01 03/02/2015 03/06/2015 1 IPRETS/ODCM Radiological Effluent Occurrences71151-PR01 03/02/2015 03/06/2015TSB 52B-BIENNIAL PI&R INSPECTION 41 IPProblem Identification and Resolution71152B06/08/2015 06/12/2015 1 IPProblem Identification and Resolution71152B06/29/2015 07/02/2015 EP-1-BIENNAIL EP PROGRAM INSPECTION 11 IPAlert and Notification System Testing711140208/17/2015 08/21/2015 1 IPEmergency Preparedness Organization Staffing and Augmentation System711140308/17/2015 08/21/2015 1 IPEmergency Action Level and Emergency Plan Changes711140408/17/2015 08/21/2015 1 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140508/17/2015 08/21/2015 EP-2-EP PERFORMANCE INDICATORS 11 IPDrill/Exercise Performance71151-EP01 08/17/2015 08/21/2015 1 IPERO Readiness71151-EP02 08/17/2015 08/21/2015 1 IPAlert & Notification System Reliability71151-EP03 08/17/2015 08/21/2015 EB1-17T-RBS PERMANENT PLANT MODS & 50.59 61 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T09/21/2015 10/09/2015 RS 5678-RADIATION SAFETY - TEAM 41 IPRadiation Monitoring Instrumentation71124.0512/07/201512/11/2015 1 IPRadioactive Gaseous and Liquid Effluent Treatment71124.0612/07/201512/11/2015 1 IPRadiological Environmental Monitoring Program71124.0712/07/201512/11/2015 1 IPRadioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.0812/07/201512/11/2015 RS 24-RADIATION SAFETY 21 IPOccupational ALARA Planning and Controls71124.0201/18/2016 01/22/2016 1 IPOccupational Dose Assessment71124.0401/18/2016 01/22/2016 EB2-05T-TRIENNIAL FIRE PROTECTION INSPECTION 41 IPFire Protection [Triennial]7111105T04/11/2016 04/15/2016 1 IPFire Protection [Triennial]7111105T04/25/2016 04/29/2016 RS 13 PI-RADIATION SAFETY 21 IPRadiological Hazard Assessment and Exposure Controls71124.0105/09/2016 05/13/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Page 2 of 2 02/26/2015 19:47:10Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteRiver BendInspection / Activity Plan 03/01/2015

-06/30/2016 RS 13 PI-RADIATION SAFETY 21 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0305/09/2016 05/13/2016 1 IPOccupational Exposure Control Effectiveness71151-OR01 05/09/2016 05/13/2016 1 IPRETS/ODCM Radiological Effluent Occurrences71151-PR01 05/09/2016 05/13/2016 ISFSI-ROUTINE LOADING INSPECTION (ONE WEEK) 11 IPOperation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.106/01/2016 06/01/2016 EP-2-EP PERFORMANCE INDICATORS 21 IPDrill/Exercise Performance71151-EP01 06/27/2016 07/01/2016 1 IPERO Readiness71151-EP02 06/27/2016 07/01/2016 1 IPAlert & Notification System Reliability71151-EP03 06/27/2016 07/01/2016 EP-3-BIENNIAL EXERCISE INSPECTION 41 IPExercise Evaluation711140106/27/2016 07/01/2016 1 IPEmergency Action Level and Emergency Plan Changes711140406/27/2016 07/01/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

This inspection plan does not include security

-related inspections, which will be sent via separate, non

-publicly available correspondence.

In accordance with 10 CFR 2.390 of the NRC

's "Rules of Practice,

" a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Please contact Greg Warnick, Chief, Project Branch C, at 817-200-1144 with any questions you have regarding this letter.

Sincerely, /RA/ Troy W. Pruett, Director Division of Reactor Projects Docket: 50-458 License: NPF-47

Enclosure:

River Bend Station Inspection Plan DISTRIBUTION See next page RBS 2014 EOC Ltr.

ML15063A562 SUNSI Review By: RA ADAMS: Yes No Sensitive Non-Sensitive Non-Publicly Available Publicly Available Keyword RGN-002 OFFICE DRP BC-C DRS/DIR DRP/DIR NAME GWarnick: tk AVegel TPruett SIGNATURE

/RA/ /RA/ /RA/ DATE 2/27/15 2/27/15 3/4/15 OFFICIAL RECORD COPY

Letter to Eric Olson from Troy Pruett

, dated March 4, 2015

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR RIVER BEND STATION (REPORT 05000458/2014001)

DISTRIBUTION

Regional Administrator (Marc.Dapas@nrc.gov)

Deputy Regional Administrator (Kriss.Kennedy@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

Acting DRP Deputy Director (Thomas.Farnholtz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Jeff.Sowa@nrc.gov)

Resident Inspector (Andy.Barrett@nrc.gov)

Site Administrative Assistant (Lisa.Day@nrc.gov)

Branch Chief, DRP (Greg.Warnick@nrc.gov)

Senior Project Engineer, DRP (Ray.Azua@nrc.gov)

Project Engineer, DRP (Paul.Nizov@nrc.gov)

Project Engineer, DRP (Michael.Stafford@nrc.gov

) Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

RIV State Liaison Officer (Bill.Maier@nrc.gov)

Project Manager (Alan.Wang@nrc.gov)

DRP Branch Chiefs (R4DRP-BC1@nrc.gov

) DRS Branch Chiefs (R4DRS-BC1@nrc.gov) Director, DIRS, NRR (Scott.Morris@nrc.gov)

Deputy Director, DIRS, NRR (Allen.Howe@nrc.gov)

Director, DORL, NRR (Michele.Evans@nrc.gov)

Deputy Director, DORL, NRR (George.Wilson@nrc.gov)

Chief, PLB IV

-2, DORL, NRR (Doug.Broaddus@nrc.gov

) Director, NSIR/DPR (Robert.Lewis@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA:

OEDO (Michael.Waters@nrc.gov)

ROPassessment.Resource@nrc.gov ROPreports.Resources@nrc.gov OEMail.Resource@nrc.gov