MONTHYEARML1130814412011-11-0303 November 2011 License Amendment Request - Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Request ML1134003382011-12-0606 December 2011 Supplemental Information Required for Peach Bottom November 3, 2011, Submittal (TAC Nos. ME7538 & ME7539) Project stage: Other ML1132602952011-12-14014 December 2011 Supplemental Information Needed for Acceptance of Requested Licensing Action Use of Neutron Absorbing Inserts in Units 2 and 3 Spent Fuel Pool Storage Racks Project stage: Acceptance Review ML1135702082011-12-22022 December 2011 Response to License Amendment Request - Use of Neutron Absorbing Inserts in Units 2 & 3 Spent Fuel Pool Storage Racks Project stage: Request ML12096A0522012-04-0404 April 2012 Response to Request for Additional Information - License Amendment Request for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Response to RAI ML1208702032012-04-18018 April 2012 Request for Additional Information Regarding License Amendment Request for Use of Neutron Absorbing Inserts in Units 2 and 3 Spent Fuel Pool Storage Racks Project stage: RAI ML1212202712012-05-16016 May 2012 Request for Withholding Information from Public Disclosure for Peach Bottom Atomic Power Station, Unit Nos. 2 and 3 Project stage: Withholding Request Acceptance ML1212202552012-05-16016 May 2012 Request for Withholding Information from Public Disclosure for Peach Bottom Atomic Power Station, Unit Nos. 2 and 3 Project stage: Withholding Request Acceptance ML12139A4042012-05-17017 May 2012 Response to Request for Additional Information - License Amendment Request for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Response to RAI ML1212505692012-05-22022 May 2012 Request for Additional Information Regarding License Amendment Request for Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: RAI ML12188A0942012-06-21021 June 2012 Response to Request for Additional Information - License Amendment Request for Use of Neutron Absorbing Inserts in Units 2 and 3 Spent Fuel Pool Storage Racks Project stage: Response to RAI ML12194A6082012-07-12012 July 2012 Draft Request for Additional Information Project stage: Draft RAI ML12192A3532012-07-19019 July 2012 Request for Withholding Information from Public Disclosure for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Withholding Request Acceptance ML12228A4742012-08-15015 August 2012 Response to Request for Additional Information - License Amendment Request for Use of Neutron Absorbing Inserts in Units 2 and 3 Spent Fuel Pool Storage Racks Project stage: Response to RAI ML12319A2302012-11-13013 November 2012 Response to Request for Additional Information - License Amendment Request for Use of Neutron Absorbing Inserts in Units 2 and 3 Spent Fuel Pool Storage Racks Project stage: Response to RAI ML13063A3372013-03-0404 March 2013 Draft Request for Additional Information Project stage: Draft RAI ML13112A8572013-05-0202 May 2013 Request for Withholding Information from Public Disclosure for Peach Bottom Atomic Power Station, Unit Nos. 2 and 3 Project stage: Withholding Request Acceptance ML13121A2882013-05-13013 May 2013 Transmittal of Draft Safety Evaluation for Proposed Amendment Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Draft Approval ML13114A9292013-05-21021 May 2013 Issuance of Amendments Use of Neutron Absorbing Inserts in Spent Fuel Pool Storage Racks Project stage: Approval 2012-05-17
[Table View] |
|
---|
Category:Letter
MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 ML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ML23150A2052023-05-30030 May 2023 Independent Spent Fuel Storage Installation (Isfsi), Annual Radiological Environmental Operating Report 80 January 1, 2022 Through December 31, 2022 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A1582023-05-18018 May 2023 Correction to Technical Specification 3.4.7 (Page 3.4-16) Issued in Amendment No. 337 ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI 2024-01-05
[Table view] |
Text
UNITED NUCLEAR REGULATORY WASHINGTON, D.C. 20555-0001 July 19, 2012 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR PEACH BOTTOM ATOMIC POWER STATION, UNIT NOS. 2 AND 3 (TAC NOS. ME7538 AND ME7539)
Dear Mr. Pacilio:
By Exelon Generation Company, LLC (Exelon) letter to the Nuclear Regulatory Commission (NRC) dated June 21, 2012, and three Global Nuclear Fuel -Americas, LLC (GNF-A) affidavits each dated June 15, 2012, executed by Mr. Andrew A. Lingenfelter, Exelon requested that the information contained in Attachments 7, 8, and 9 to its letter be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390. Specifically, Exelon requested that the following documents be withheld: Enclosure 7 of GNF-A letter CFL-EXN-HEO-12-080 to Exelon, "GNF Response to NRC RAls 19-22" and Enclosure 9 of GNF-A letter CFL-EXN-HEO-12-080 to Exelon, "Supporting Information for RAI-23 Response" (Attachment 7 to Exelon's letter) GNF-A proprietary report NEDC-33672P, "Peach Bottom Atomic Power Station: Fuel Storage Criticality Safety Analysis of Spent Fuel Storage Racks with Rack Inserts," Revision 1, dated June 2012 (Attachment 8 to Exelon's letter) GNF-A proprietary report NEDC-33686P, "Peach Bottom Atomic Power Station: Fuel Storage Criticality Safety Analysis of Spent Fuel Storage Racks with Boraflex," Revision 1 dated, June 2012 (Attachment 9 to Exelon's letter) A non-proprietary copy of the documents (Attachments 10, 11, and 12 to Exelon's letter) has been placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room. The affidavits stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons: Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies; and Information which, if used by a competitor, would reduce [its] expenditure of resources or improve [its] competitive position in the deSign, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.
M. -2 We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavits, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 1 03(b) of the Atomic Energy Act of 1954, as amended. Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the document. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information. If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure. If you have any questions regarding this matter, I may be reached at 301-415-1420. Sincerely, Richard B. Ennis, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278 Mr. Andrew A Lingenfelter Vice President, Fuel Engineering Global Nuclear Fuel -Americas, LLC 3901 Castle Hayne Road Wilmington, NC 28401 Additional Distribution via Listserv M. Pacilio -2 We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavits, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 1 03(b) of the Atomic Energy Act of 1954, as amended. Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the document. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information. If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure. If you have any questions regarding this matter, I may be reached at 301-415-1420. Sincerely, Iral Richard B. Ennis, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278 cc: Mr. Andrew A. Lingenfelter Vice President, Fuel Engineering Global Nuclear Fuel -Americas, LLC 3901 Castle Hayne Road Wilmington, NC 28401 Additional Distribution via Listserv DISTRIBUTION: PUBLIC RidsOgcMailCenter Resource LPL 1-2 RIF RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpl1-2 Resource RidsRgn 1 MailCenter Resource RidsNrrLAABaxter Resource RidsNrrDssSrxb Resource RidsNrrPMPeachBottom Resource ADAMS Accession No.: ML 12192A353 II OFFICE I LPL1-2/PM I LPL 1-2/LA I SRXB/BC (A) LPL1-2/BC ! I NAME REnnis ABaxter SMiranda MKhanna DATE 7/18/12 7/18/12 7/18/12 7/19/12 OFFICIAL RECORD COpy