Locking of Radiography Exposure DevicesML031080041 |
Person / Time |
---|
Site: |
Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Three Mile Island, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, Fort Saint Vrain, Shoreham, Satsop, Trojan, Atlantic Nuclear Power Plant |
---|
Issue date: |
01/14/1993 |
---|
From: |
Cunningham R E NRC/NMSS/IMNS |
---|
To: |
|
---|
References |
---|
FOIA/PA-2015-0150 IN-93-005, NUDOCS 9301080120 |
Download: ML031080041 (9) |
|
Similar Documents at Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Three Mile Island, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, Fort Saint Vrain, Shoreham, Satsop, Trojan, Atlantic Nuclear Power Plant |
---|
Category:NRC Information Notice
MONTHYEARInformation Notice 2020-02, Flex Diesel Generator Operational Challenges2020-09-15015 September 2020 Flex Diesel Generator Operational Challenges ML20225A0322020-09-0303 September 2020 NRC Choice Letter to NAC International with Attached Safety Inspection Report, IR 0721015/2020201, February 24-27, 2020 and July 22, 2020, Inspection of NAC International in Norcross, Georgia Information Notice 2012-09, PWROG-16043-NP-A, Revision 2, PWROG Program to Address NRC Information Notice 2012-09: Irradiation Effects on Fuel Assembly Spacer Grid Crush Strength for Westinghouse and CE PWR Fuel Designs.2019-11-30030 November 2019 PWROG-16043-NP-A, Revision 2, PWROG Program to Address NRC Information Notice 2012-09: Irradiation Effects on Fuel Assembly Spacer Grid Crush Strength for Westinghouse and CE PWR Fuel Designs. Information Notice 2011-20, NRC060 - NRC Information Notice 2011-20: Concrete Degradation by Alkali-Silica Reaction (Nov. 18, 2011)2019-07-24024 July 2019 NRC060 - NRC Information Notice 2011-20: Concrete Degradation by Alkali-Silica Reaction (Nov. 18, 2011) ML19196A2452019-07-15015 July 2019 Public Notice - Sequoyah Nuclear Plant, Unit 2 - Exigent Amendment to Facility Operating License Information Notice 2019-01, Inadequate Evaluation of Temporary Alterations2019-03-12012 March 2019 Inadequate Evaluation of Temporary Alterations ML16028A3082016-04-27027 April 2016 NRC Information Notice; IN 2016-05: Operating Experience Regarding Complications From a Loss of Instrumentation Air Information Notice 2015-05, Inoperability of Auxiliary and Emergency Feedwater Auto Start Circuits on Loss of Main Feedwater Pumps2015-05-12012 May 2015 Inoperability of Auxiliary and Emergency Feedwater Auto Start Circuits on Loss of Main Feedwater Pumps Information Notice 2015-05, Inoperability Of Auxiliary And Emergency Feedwater Auto Start Circuits On Loss Of Main Feedwater Pumps2015-05-12012 May 2015 Inoperability Of Auxiliary And Emergency Feedwater Auto Start Circuits On Loss Of Main Feedwater Pumps Information Notice 2013-20, OFFICIAL EXHIBIT - NYS000538-00-BD01 - NRC Information Notice 2013-20: Steam Generator Channel Head and Tubesheet Degradation (October 3, 2013) (ML13204A143)2013-10-0303 October 2013 OFFICIAL EXHIBIT - NYS000538-00-BD01 - NRC Information Notice 2013-20: Steam Generator Channel Head and Tubesheet Degradation (October 3, 2013) (ML13204A143) Information Notice 2013-20, Official Exhibit - NYS000538-00-BD01 - NRC Information Notice 2013-20: Steam Generator Channel Head and Tubesheet Degradation (October 3, 2013) (ML13204A143)2013-10-0303 October 2013 Official Exhibit - NYS000538-00-BD01 - NRC Information Notice 2013-20: Steam Generator Channel Head and Tubesheet Degradation (October 3, 2013) (ML13204A143) Information Notice 2013-11, OFFICIAL EXHIBIT - NYS000551-00-BD01 - NRC Information Notice 2013-11: Crack-Like Indication at Dents/Dings and in the Freespan Region of Thermally Treated Alloy 600 Steam Generator Tubes (July 3, 2013)2013-07-0303 July 2013 OFFICIAL EXHIBIT - NYS000551-00-BD01 - NRC Information Notice 2013-11: Crack-Like Indication at Dents/Dings and in the Freespan Region of Thermally Treated Alloy 600 Steam Generator Tubes (July 3, 2013) Information Notice 2013-11, Official Exhibit - NYS000551-00-BD01 - NRC Information Notice 2013-11: Crack-Like Indication at Dents/Dings and in the Freespan Region of Thermally Treated Alloy 600 Steam Generator Tubes (July 3, 2013)2013-07-0303 July 2013 Official Exhibit - NYS000551-00-BD01 - NRC Information Notice 2013-11: Crack-Like Indication at Dents/Dings and in the Freespan Region of Thermally Treated Alloy 600 Steam Generator Tubes (July 3, 2013) Information Notice 2010-12, Intervenors' Fifth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notice 2010-12: Contain2012-08-17017 August 2012 Intervenors' Fifth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notice 2010-12: Containment Liner Cor Information Notice 2010-12, Intervenors' Fifth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notice 2010-12: Con2012-08-17017 August 2012 Intervenors' Fifth Motion to Amend and/or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notice 2010-12: Containment Liner Cor Information Notice 2010-12, Intervenors' Fifth Motion to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notic2012-08-17017 August 2012 Intervenors' Fifth Motion to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking). Appendix VI: NRC FOIA Responses (B-51 Through B-53); Turkey Point Event Report; NRC Information Notice 2010-12: Containment Liner Cor Information Notice 2012-13, Boraflex Degradation Surveillance Programs and Corrective Actions in the Spent Fuel Pool2012-08-10010 August 2012 Boraflex Degradation Surveillance Programs and Corrective Actions in the Spent Fuel Pool Information Notice 2012-13, Boraflex Degradation Surveillance Programs And Corrective Actions In The Spent Fuel Pool2012-08-10010 August 2012 Boraflex Degradation Surveillance Programs And Corrective Actions In The Spent Fuel Pool Information Notice 2012-11, Age Related Capacitor Degradation2012-07-23023 July 2012 Age Related Capacitor Degradation ML12031A0132012-02-0606 February 2012 U.S. Nuclear Regulatory Commission Investigation Report No. 2-2010-058, Cpn International, Inc Information Notice 2011-19, Licensee Event Reports Containing Information Pertaining to Defects to Basic Components2011-09-26026 September 2011 Licensee Event Reports Containing Information Pertaining to Defects to Basic Components Information Notice 2011-15, Steel Containment Degradation and Associated License Renewal Aging Management Issues2011-08-0101 August 2011 Steel Containment Degradation and Associated License Renewal Aging Management Issues Information Notice 2011-17, Calculation Methodologies for Operability Determinations of Gas Voids in Nuclear Power Plant Piping2011-07-26026 July 2011 Calculation Methodologies for Operability Determinations of Gas Voids in Nuclear Power Plant Piping Information Notice 2011-13, Official Exhibit - NYS000329-00-BD01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (NRC in 2011-13)2011-06-29029 June 2011 Official Exhibit - NYS000329-00-BD01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (NRC in 2011-13) Information Notice 2011-13, Official Exhibit - Nys000329-00-Bd01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (Nrc in 2011-13)2011-06-29029 June 2011 Official Exhibit - Nys000329-00-Bd01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (Nrc in 2011-13) Information Notice 2011-13, OFFICIAL EXHIBIT - NYS000329-00-BD01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (NRC in 2011-13)2011-06-29029 June 2011 OFFICIAL EXHIBIT - NYS000329-00-BD01 - NRC Information Notice 2011-13, Control Rod Blade Cracking Resulting in Reduced Design Lifetime (Jun 29, 2011) (NRC in 2011-13) Information Notice 2011-04, IN: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors2011-02-23023 February 2011 IN: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors Information Notice 2011-04, In: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors2011-02-23023 February 2011 In: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors Information Notice 2011-04, in: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors2011-02-23023 February 2011 in: Contaminants and Stagnant Conditions Affecting Stress Corrosion Cracking in Stainless Steel Piping in Pressurized Water Reactors Information Notice 2010-26, New England Coalition'S Motion for Leave to Reply to NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-26 and Entergy'S Response to the Supplement to Nec'S Petition for Commission Review of LBP-10-2010-12-30030 December 2010 New England Coalition'S Motion for Leave to Reply to NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-26 and Entergy'S Response to the Supplement to Nec'S Petition for Commission Review of LBP-10-19 Information Notice 2010-26, New England Coalition'S Motion for Leave to Reply to NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-26 and Entergy'S Response to the Supplement to Nec'S Petition for Commission Review2010-12-30030 December 2010 New England Coalition'S Motion for Leave to Reply to NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-26 and Entergy'S Response to the Supplement to Nec'S Petition for Commission Review of LBP-10-19 Information Notice 2010-26, 2010/12/21-NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-262010-12-21021 December 2010 2010/12/21-NRC Staff'S Objection to Nec'S Notification of Information Notice 2010-26 ML13066A1872009-12-16016 December 2009 Draft NRC Information Notice 2009-xx - Underestimate of Dam Failure Frequency Used in Probabilistic Risk Assessments ML1007804482009-11-23023 November 2009 Email from Peter Bamford, NRR to Pamela Cowan, Exelon on TMI Contamination Control Event Information Notice 2009-11, NSP000059-Revised Prefiled Testimony of Northard/Petersen/Peterson-NRC Information Notice 2009-112009-07-0707 July 2009 NSP000059-Revised Prefiled Testimony of Northard/Petersen/Peterson-NRC Information Notice 2009-11 Information Notice 2009-10, Official Exhibit - NYS000019-00-BD01- NRC Information Notice 2009-10, Transformers Failures - Recent Operating Experience (Jul. 7, 2009) (NRC in 2009-10)2009-07-0707 July 2009 Official Exhibit - NYS000019-00-BD01- NRC Information Notice 2009-10, Transformers Failures - Recent Operating Experience (Jul. 7, 2009) (NRC in 2009-10) Information Notice 2009-09, Improper Flow Controller Settings Renders Injection Systems Inoperable and Surveillance Did Not Identify2009-06-19019 June 2009 Improper Flow Controller Settings Renders Injection Systems Inoperable and Surveillance Did Not Identify Information Notice 2008-12, Reactor Trip Due to Off-Site Power Fluctuation2008-07-0707 July 2008 Reactor Trip Due to Off-Site Power Fluctuation Information Notice 2008-11, Service Water System Degradation at Brunswicksteam Electric Plant Unit 12008-06-18018 June 2008 Service Water System Degradation at Brunswicksteam Electric Plant Unit 1 Information Notice 2008-04, Counterfeit Parts Supplied to Nuclear Power Plants2008-04-0707 April 2008 Counterfeit Parts Supplied to Nuclear Power Plants Information Notice 1991-09, Counterfeiting of Crane Valves2007-09-25025 September 2007 Counterfeiting of Crane Valves Information Notice 2007-28, Potential Common Cause Vulnerabilities in Essential Service Water Systems Due to Inadequate Chemistry Controls2007-09-19019 September 2007 Potential Common Cause Vulnerabilities in Essential Service Water Systems Due to Inadequate Chemistry Controls Information Notice 2007-29, Temporary Scaffolding Affects Operability of Safety-Related Equipment2007-09-17017 September 2007 Temporary Scaffolding Affects Operability of Safety-Related Equipment Information Notice 2007-14, Loss of Offsite Power and Dual-Unit Trip at Catawba Nuclear Generating Station2007-03-30030 March 2007 Loss of Offsite Power and Dual-Unit Trip at Catawba Nuclear Generating Station Information Notice 2007-06, Potential Common Cause Vulnerabilities in Essential Service Water Systems2007-02-0909 February 2007 Potential Common Cause Vulnerabilities in Essential Service Water Systems Information Notice 2007-05, Vertical Deep Draft Pump Shaft and Coupling Failures2007-02-0909 February 2007 Vertical Deep Draft Pump Shaft and Coupling Failures Information Notice 2006-31, Inadequate Fault Interrupting Rating of Breakers2006-12-26026 December 2006 Inadequate Fault Interrupting Rating of Breakers Information Notice 2006-29, Potential Common Cause Failure of Motor-operated Valves as a Result of Stem Nut Wear2006-12-14014 December 2006 Potential Common Cause Failure of Motor-operated Valves as a Result of Stem Nut Wear Information Notice 2006-29, Potential Common Cause Failure of Motor-operated Valves As a Result of Stem Nut Wear2006-12-14014 December 2006 Potential Common Cause Failure of Motor-operated Valves As a Result of Stem Nut Wear Information Notice 2006-13, E-mail from M. Mclaughlin on NRC, Regarding NRC Information Notice 2006-13: Groundwater Contamination2006-07-13013 July 2006 E-mail from M. Mclaughlin on NRC, Regarding NRC Information Notice 2006-13: Groundwater Contamination 2020-09-03 The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Hatch]] OR [[:Monticello]] OR [[:Calvert Cliffs]] OR [[:Dresden]] OR [[:Davis Besse]] OR [[:Peach Bottom]] OR [[:Browns Ferry]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Nine Mile Point]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Perry]] OR [[:Indian Point]] OR [[:Fermi]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Oyster Creek]] OR [[:Watts Bar]] OR [[:Hope Creek]] OR [[:Grand Gulf]] OR [[:Cooper]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Pilgrim]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Susquehanna]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Columbia]] OR [[:Seabrook]] OR [[:Brunswick]] OR [[:Surry]] OR [[:Limerick]] OR [[:North Anna]] OR [[:Turkey Point]] OR [[:River Bend]] OR [[:Vermont Yankee]] OR [[:Crystal River]] OR [[:Haddam Neck]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Duane Arnold]] OR [[:Farley]] OR [[:Robinson]] OR [[:Clinton]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Yankee Rowe]] OR [[:Maine Yankee]] OR [[:Quad Cities]] OR [[:Humboldt Bay]] OR [[:La Crosse]] OR [[:Big Rock Point]] OR [[:Rancho Seco]] OR [[:Zion]] OR [[:Midland]] OR [[:Bellefonte]] OR [[:Fort Calhoun]] OR [[:FitzPatrick]] OR [[:McGuire]] OR [[:LaSalle]] OR [[:Fort Saint Vrain]] OR [[:Shoreham]] OR [[:Satsop]] OR [[:Trojan]] OR [[:Atlantic Nuclear Power Plant]] </code>.
[Table view]The following query condition could not be considered due to this wiki's restrictions on query size or depth: <code> [[:Beaver Valley]] OR [[:Millstone]] OR [[:Hatch]] OR [[:Monticello]] OR [[:Calvert Cliffs]] OR [[:Dresden]] OR [[:Davis Besse]] OR [[:Peach Bottom]] OR [[:Browns Ferry]] OR [[:Salem]] OR [[:Oconee]] OR [[:Mcguire]] OR [[:Nine Mile Point]] OR [[:Palisades]] OR [[:Palo Verde]] OR [[:Perry]] OR [[:Indian Point]] OR [[:Fermi]] OR [[:Kewaunee]] OR [[:Catawba]] OR [[:Harris]] OR [[:Wolf Creek]] OR [[:Saint Lucie]] OR [[:Point Beach]] OR [[:Oyster Creek]] OR [[:Watts Bar]] OR [[:Hope Creek]] OR [[:Grand Gulf]] OR [[:Cooper]] OR [[:Sequoyah]] OR [[:Byron]] OR [[:Pilgrim]] OR [[:Arkansas Nuclear]] OR [[:Three Mile Island]] OR [[:Braidwood]] OR [[:Susquehanna]] OR [[:Summer]] OR [[:Prairie Island]] OR [[:Columbia]] OR [[:Seabrook]] OR [[:Brunswick]] OR [[:Surry]] OR [[:Limerick]] OR [[:North Anna]] OR [[:Turkey Point]] OR [[:River Bend]] OR [[:Vermont Yankee]] OR [[:Crystal River]] OR [[:Haddam Neck]] OR [[:Ginna]] OR [[:Diablo Canyon]] OR [[:Callaway]] OR [[:Vogtle]] OR [[:Waterford]] OR [[:Duane Arnold]] OR [[:Farley]] OR [[:Robinson]] OR [[:Clinton]] OR [[:South Texas]] OR [[:San Onofre]] OR [[:Cook]] OR [[:Comanche Peak]] OR [[:Yankee Rowe]] OR [[:Maine Yankee]] OR [[:Quad Cities]] OR [[:Humboldt Bay]] OR [[:La Crosse]] OR [[:Big Rock Point]] OR [[:Rancho Seco]] OR [[:Zion]] OR [[:Midland]] OR [[:Bellefonte]] OR [[:Fort Calhoun]] OR [[:FitzPatrick]] OR [[:McGuire]] OR [[:LaSalle]] OR [[:Fort Saint Vrain]] OR [[:Shoreham]] OR [[:Satsop]] OR [[:Trojan]] OR [[:Atlantic Nuclear Power Plant]] </code>. |
UNITED STATESNUCLEAR REGULATORY COMMISSIONOFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDSWASHINGTON, D.C. 20555January 14, 1993NRC INFORMATION NOTICE NO. 93-05: LOCKING OF RADIOGRAPHY EXPOSUREDEVICES
Addressees
- All Nuclear Regulatory Commission industrial radiography licensees
Purpose
This information notice is intended to: (a) alert licensees that the lockingmechanisms on certain industrial radiography exposure devices can be lockedwith the sealed source in the exposed position; and (b) emphasize theimportance of ensuring that the source is secure in a shielded position beforemoving the device. We expect that licensees will review this notice,distribute it to responsible staff, and consider actions, if appropriate, toverify that the source is properly secured at the conclusion of radiographicoperations. However, suggestions contained in this notice do not constituteany new NRC requirements, and no written response is required.
Description of Circumstances
Case 1: A radiographer was overexposed in an incident involving adisconnected source when he failed to conduct a survey after each exposure.After investigating the incident, it was discovered that the radiographer hadapproached the device without a survey instrument, locked the device,disassembled the source guide tube, and left the drive controls connectedbefore moving the device from one location to another. The radiographer hadincorrectly assumed that in locking the exposure device, he had secured thesource in a shielded position. In fact, the sealed source remained in theguide tube because the pigtail had disconnected from the drive cable. Theradiographer's error was further compounded when the drive cable was notremoved before moving the device, which would have allowed him to identify theabsence of the source pigtail within the shielded assembly.Case 2: A radiographer was performing radiographic exposures of welds on aseries of pipelines that were located approximately 6.1 meters (20 feet) aboveground. The radiographer used a 1.8-meter (6-foot) guide tube with collimatorand a 7.6-meter (25-foot) control cable. The radiographer hung the devicefrom the pipeline to perform the work with the control cables hanging down tothe ground. After an exposure, the radiographer retracted the source, placedthe control cables on the ground, and used a hydraulic lift to get to thecamera.9301080120 L4'6 fD C fe -2?- 0AIkCct IN 93-05January 14, 1993 Because the camera was suspended above the lift, the radiographer had to movethe camera to reach the locking mechanism. He moved the camera by graspingthe control cables with his right hand and locking the camera with his lefthand. He continued with his left hand to disconnect the guide tube from thecamera. At this point, he noticed that the sealed source was protrudingapproximately 10 centimeters (4 inches) from the camera port. (Note: Hisalarming ratemeter did not sound because it was not turned on. This violationof 10 CFR 34.33, which can result in a civil penalty, is addressed inInformation Notice 91-49: "Enforcement of Safety Requirements forRadiographers").Reenactments of the incident showed that when the radiographer turned thedevice, the crank handle could drag on the ground, exposing the sealed source.The radiographer was then able to lock the device over the drive cable, withthe sealed source protruding approximately 10 centimeters (4 inches).Analysis of the locking mechanism after the event did not identify any obviousdefects with the mechanism. Tests performed showed that the device couldstill be locked with the source in the exposed position.NRC Evaluation:The findings in both of these cases raised concern among NRC staff that, undercertain conditions, radiographers could have false confidence in the lockingmechanisms. If exposure devices can lock when the source is outside of theshielded position, then radiographers could incorrectly believe that they areprotected from exposure when, in fact, the source is not in its fully shieldedposition. We are also concerned that exposure devices are moved while thedrive cables are still connected.To evaluate the effectiveness of the locking mechanism on radiography exposuredevices and to determine whether radiographers commonly move the devices withdrive cables still connected, NRC inspectors observed licensee equipment testsand interviewed radiography personnel. From the data collected, we determinedthat a majority of exposure devices can be locked when the source is in avariety of positions, rather than only when the source pigtail is properlyseated, with the source in the fully shielded position. Many source pigtailsinclude a "locking ball," designed to prevent the source from moving forwardwhen the lock is engaged; however, our observations show that some exposuredevices may be locked both when the source is not fully retracted and whilethe drive cable is seated under the locking pin, thereby circumventing thelocking-ball feature. This may result in a source being positioned where itis not fully shielded.Many radiographers acknowledged to NRC inspectors that they often leave drivecables connected when moving an exposure device from one location to anotherat temporary job sites. In addition, some acknowledged leaving the guide tubeconnected. One licensee stated that this practice had resulted in a sourcebeing forced out of the exposure device while the device was carried to a newlocation at a temporary job site. This licensee noted that the device waslocked at the time, but the source had not been fully retracted before lockingthe devic Attachment 1IN 93-05January 14, 1993 LIST OF RECENTLY ISSUEDNMSS INFORMATION NOTICESInformation Date ofNotice No. Subject Issuance Issued to93-0493-0392-8492-72Investigation and Re-porting of Misadministra-tions by the RadiationSafety OfficerRecent Revision to10 CFR Part 20 andChange of Implementa-tion Date toJanuary 1, 1994Release of PatientsTreated with TemporaryImplantsEmployee Trainingand Shipper Registra-tion Requirements forTransporting RadioactiveMaterialsEmergency ResponseInformation Require-ments for RadioactiveMaterial ShipmentsUranium HexafluorideCylinders -Deviationsin Coupling WeldsImplementation Date forthe Revision to the EPAManual of ProtectiveAction Guides and Pro-tective Actions forNuclear IncidentsImplementation of theDeliberate Misconduct Rule01/07/9301/05/9312/17/9210/18/9208/24/9208/12/9205/12/9205/08/9292-62All U.S. Nuclear RegulatoryCommission medicallicensees.All byproduct, source, andspecial nuclear materiallicensees.All Nuclear Regulatory Com-mission Medical Licensees.All U.S. Nuclear RegulatoryCommission Licensees.All U.S. Nuclear RegulatoryCommission Licensees.All fuel cycle licensees.All holders of OLs or CPsfor nuclear power reactors,non-power reactors andmaterials licensees author-ized to possess largequantities of radioactivematerial.All Nuclear RegulatoryCommission Licensees.92-5892-3892-37 Attachment 2IN 93-05January 14, 1993 LIST OF RECENTLY ISSUEDNRC INFORMATION NOTICESInformation Date ofNotice No. Subject Issuance Issued to93-0493-0393-02Investigation and Re-porting of Misadministra-tions by the RadiationSafety OfficerRecent Revision to10 CFR Part 20 andChange of Implementa-tion Date toJanuary 1, 1994Malfunction of A Pres-surizer Code SafetyValveAccuracy of Motor-Operated Valve DiagnosticEquipment Manufacturesby Liberty TechnologiesUnexpected Restrictionto Thermal Growth ofReactor Coolant PipingPotential Failures ofEmergency Core CoolingSystems Caused byForeign Material Blockage93-0101/07/9301/05/9301/04/9301/04/9312/24/9212/23/9212/17/9212/18/92All U.S. Nuclear RegulatoryCommission medicallicensees.All byproduct, source, andspecial nuclear materiallicensees.All holders of OLs or CPsfor nuclear power reactors.All holders of OLs or CPsfor nuclear power reactors.All holders of OLs or CPsfor nuclear power reactors.All holders of OLs or CPsfor nuclear power reactors.All Nuclear RegulatoryCommission Medical LicenseesAll holders of OLs or CPsfor nuclear power reactors.92-8692-8592-84Release of PatientsTreated with TemporaryImplants88-23,Supp. 4Potential for GasBinding of High-Pres-sure Safety InjectionPumps during A DesignBasis AccidentOL = Operating LicenseCP = Construction Permit K)IN 93-05January 14, 1993 Discussion:All licensees are reminded of the importance of ensuring that the sources usedin radiography exposure devices are properly secured and fully shielded beforemoving the device. Radiographic exposure devices manufactured and newequipment acquired by licensees after January 10, 1992, must meet new designrequirements in 10 CFR 34.20. These require that, among other safetyfeatures, the device must automatically secure the source assembly when it iscranked back into the fully shielded position within the device. However,many radiographic exposure devices currently in use do not include the newersafety features, and licensees are not required to use devices that complywith 10 CFR 34.20 requirements until after January 10, 1996. Certaihradiogiraphv exposure devices still in use today may be able to be locked withthe source in the exposed position.Experience has shown that when an older exposure device is in use, the lockingmechanism is not an indicator that the source is fully retracted and secured.The use of engineered safety features, like the lock mechanism, MUST BEcoupled with a proper survey (10 CFR 34.43) AND use of an alarm ratemeter(10 CFR 34.33), to prevent the unintentional exposure of personnel. Surveysmust be sufficient to detect a change in exposure readings taken at the sourcetube outlet, to determine whether the source is fully retracted to a shieldedposition (10 CFR 34.43). Alarm ratemeters serve as an additional warningmethod. Additionally, it is recommended that radiographers disassemble thesource guide tube, remove the drive controls, and install the safety plugs orcovers, before moving the radiography exposure device to another location.The failure to do so has been identified as a contributing factor in theunintended exposure of personnel, as well as in incidents where radiographersfailed to notice that the source was not retracted into the device.Sealed sources for radiography are capable of delivering significant exposuresto radiography personnel and to members of the general public, when handled byindividuals who are inattentive to radiation safety procedures. It isrecommended that all workers understand the consequences of improperlyhandling radiographic devices, and that workers be encouraged to use necessaryprecautions when working with these device IN 93-05January 14, 993No written response is required by this information notice.questions about this matter, please contact the appropriateoffice or the personnel listed below.If you have anyNRC regional( Richard E. Cunningham, DirectorDivision Industrial andMedical Nuclear Safety, NMSSGary Shear, Region III(708) 790-5620Technical contacts:Charles Cain, Region IV(817) 860-8186Scott Moore, NMSS(301) 504-2514
Attachments:
.1. List of Recently2. List of RecentlyIssued NMSS Information NoticesIssued NRC Information Notices IN 93-05January 14, 1993 No written response is required by this information notice. If you have anyquestions about this matter, please contact the appropriate NRC regionaloffice or the personnel listed below.Richard E. Cunningham, DirectorDivision Industrial andMedical Nuclear Safety, NMSSTechnical contacts:Gary Shear, Region III(708) 790-5620Charles Cain, Region IV(817) 860-8186Scott Moore, NMSS(301) 504-2514
Attachments:
1. List of Recently2. List of RecentlyIssued NMSS Information NoticesIssued NRC Information Notices* = see Drevious concurrenceOFC IMOB I E NMSS I N IMOB EIMABe nNAME *SMoore/sm/11 *EKraus *CJones *JGlennDATE11/30/9210/19/9212/08/9212/09/92OFC SCDB I E IMOB IMOB l El IMNS IMNSNAME *CHaughney *KRamsey *FCombs *JGreeves *RECunninghamDATE 12/10/92 1 01/05/93 1 12/08/92 01/06/93 01/07/93C: COVERE: COVER & ENCL.N: NO COPYOFFICIAL RECORD COPY:93-05.INDOCUMENT NAME:
IN 93-January , 1993 No written response is required by this information notice. If you have anyquestions about this matter, please contact the appropriate NRC regionaloffice or the personnel listed below.Richard E. Cunningham, DirectorDivision Industrial andMedical Nuclear Safety, NMSSTechnical Contacts:Gary Shear,708-790-562CRegion IIICharles Cain, Region IV817-860-8186Scott Moore, NMSS301-504-2514
Attachments:
1. List of Recently2. List of RecentlyIssued NMSS Information NoticesIssued NRC Information Notices* -caP nyVauiniiC anlnlnrranra-Fe F 9- y ... _OFC IMOB I E NMSS I Nj IMOB I E IMAB lNAME *SMoore/sm/l1 *EKraus *CJones *JGlennnATrIllnQ/I21 1 12n iog12/08/9212/09/92Unsu I II-IU ---v -S ~ ~ ~ ~ --r~OFC SCDB I E IMOB , IM0B I E IMNS _ NSNAME *CHaughney KRamsey K 4 *FCombs y Aves hamDATE 12/10/92 I/ E 91q3,f 12/8/92 I / ____ 3 I_ _ / __ __ a :_ IC: COVERE: COVER & LNCL.N: NU WLIOFFICIAL RECORD COPY: G:LOCKING.SWM IN 92-December , 1992 No written response is required by this information notice.questions about this matter, please contact the appropriateoffice or the personnel listed below.If you have anyNRC regionalRichard E. Cunningham, DirectorDivision Industrial andMedical Nuclear Safety, NMSSTechnical Contacts: Gary Shear, Region III708-790-5620\m Charles Cain, Region IV817-860-8186cott Moore, NMSS01-504-2514
Attachments:
1. List of Recently Issued NHSS Information Notices2. List of Recently Issued NR nformation NoticesOFC HQ IEI M A INI -AIEI AB IANAME ro I _I ______I____/_ I_____DATEii /o30/9210/19/92/A/ I/92\6 I,9I1/92OFC SCDB IM Io IIi I MNS IMNSNAME CH ge KRamsey = Uo X xJGreeves RECunninghimDATE It/la /92 j9/ /92 81I _2 /_/92 //92_C: COVERE: COVER & ENCL.N: NO COPYOFFICIAL RECORD COPY: G:LOCKING.SWM
|
---|
|
list | - Information Notice 1993-01, Accuracy of Motor-Operated Valve Diagnostic Equipment Manufactured by Liberty Technologies (4 January 1993)
- Information Notice 1993-02, Malfunction of a Pressurizer Code Safety Valve (4 January 1993, Topic: Loop seal)
- Information Notice 1993-04, Investigation and Reporting of Misadministrations by the Radiation Safety Officer (7 January 1993)
- Information Notice 1993-05, Locking of Radiography Exposure Devices (14 January 1993, Topic: Uranium Hexafluoride)
- Information Notice 1993-06, Potential Bypass Leakage Paths Around Filters Installed in Ventilation Systems (22 January 1993)
- Information Notice 1993-07, Classification of Transportation Emergencies (1 February 1993)
- Information Notice 1993-08, Failure of Residual Heat Removal Pump Bearings Due to High Thrust Loading (1 February 1993, Topic: Probabilistic Risk Assessment)
- Information Notice 1993-09, Failure of Undervoltage Trip Attachment on Westinghouse Model DB-50 Reactor Trip Breaker (2 February 1993)
- Information Notice 1993-10, Dose Calibrator Quality Control (2 February 1993)
- Information Notice 1993-11, Single Failure Vulnerability of Engineered Safety Features Actuation Systems (4 February 1993)
- Information Notice 1993-12, Off-Gassing in Auxiliary Feedwater System Raw Water Sources (11 February 1993)
- Information Notice 1993-13, Undetected Modification of Flow Characteristics in High Pressure Safety Injection System (16 February 1993)
- Information Notice 1993-14, Clarification of 10 CFR 40.22, Small Quantities of Source Material (18 February 1993)
- Information Notice 1993-15, Failure to Verify the Continuity of Shunt Trip Attachment Contacts in Manual Safety Injection and Reactor Trip Switches (18 February 1993)
- Information Notice 1993-16, Failures of Not-Locking Devices in Check Valves (19 February 1993, Topic: Anchor Darling, Flow Induced Vibration)
- Information Notice 1993-17, Safety Systems Response to Loss of Coolant and Loss of Offsite Power (25 March 1994, Topic: Fire Barrier, Backfit)
- Information Notice 1993-18, Portable Moisture-Density Gauge User Responsibilities During Field Operations (10 March 1993, Topic: Moisture Density Gauge, Moisture-Density Gauge, Stolen)
- Information Notice 1993-19, Slab Hopper Bulging (17 March 1993, Topic: Hydrostatic)
- Information Notice 1993-20, Thermal Fatigue Cracking of Feedwater Piping to Steam Generators (24 March 1993)
- Information Notice 1993-21, Summary of NRC Staff Observations Compiled During Engineering Audits or Inspections of Licensee Erosion/Corrosion Programs (25 March 1993, Topic: Weld Overlay)
- Information Notice 1993-22, Tripping of Klockner-Moeller Molded-Case Circuit Breakers Due to Support Lever Failure (26 March 1993)
- Information Notice 1993-23, Weschler Instruments Model 252 Switchboard Meters (31 March 1993)
- Information Notice 1993-24, Distribution of Revision 7 of NUREG-1021, Operation Licensing Examiner Standards (31 March 1993, Topic: Job Performance Measure)
- Information Notice 1993-25, Electrical Penetration Assembly Degradation (1 April 1993)
- Information Notice 1993-26, Grease Soldification Causes Molded-Case Circuit Breaker Failure to Close (31 January 1994)
- Information Notice 1993-27, Level Instrumentation Inaccuracies Observed During Normal Plant Depressurization (8 April 1993, Topic: Reactor Vessel Water Level)
- Information Notice 1993-28, Failure to Consider Loss of DC Bus in the Emergency Core Cooling System Evaluation May Lead to Nonconservative Analysis (9 April 1993, Topic: Fuel cladding)
- Information Notice 1993-29, Problems with the Use of Unshielded Test Leads in Reactor Protection System Circuitry (12 April 1993)
- Information Notice 1993-30, NRC Requirements for Evaluation of Wipe Test Results; Calibration of Count Rate Survey Instruments (12 April 1993)
- Information Notice 1993-31, Training of Nurses Responsible for the Care of Patients with Brachytherapy Implants (13 April 1993, Topic: Brachytherapy)
- Information Notice 1993-32, Nonconservative Inputs for Boron Dilution Events Analysis (21 April 1993, Topic: Shutdown Margin)
- Information Notice 1993-33, Potential Deficiency of Certain Class Ie Instrumental and Control Cables (28 April 1993)
- Information Notice 1993-33, Potential Deficiency of Certain Class IE Instrumental and Control Cables (28 April 1993, Topic: Brachytherapy)
- Information Notice 1993-34, Potential for Loss of Emergency Cooling Function Due to a Combination of Operational and Post-LOCA Debris in Containment (6 May 1993, Topic: Brachytherapy)
- Information Notice 1993-35, Insights from Common-Cause Failure Events (12 May 1993, Topic: Brachytherapy)
- Information Notice 1993-36, Notifications, Reports, and Records of Misadministrations (7 May 1993, Topic: Brachytherapy)
- Information Notice 1993-37, Eyebolts with Indeterminate Properties Installed in Limitorque Valve Operator Housing Covers (19 May 1993, Topic: Brachytherapy)
- Information Notice 1993-38, Inadequate Testing of Engineered Safety Features Actuation Systems (24 May 1993)
- Information Notice 1993-39, Radiation Beams From Power Reactor Biological Shields (25 May 1993)
- Information Notice 1993-39, Radiation Beams from Power Reactor Biological Shields (25 May 1993)
- Information Notice 1993-40, Fire Endurance Test Results for Thermal Ceramics FP-60 Fire Barrier Material (26 May 1993, Topic: Safe Shutdown, Fire Barrier, Fire Protection Program)
- Information Notice 1993-41, One Hour Fire Endurance Test Results for Thermal Ceramics Kaowool, 3M Company FS-195 and 3M Company Interam E-50 Fire Barrier Systems (28 May 1993, Topic: Safe Shutdown, Fire Barrier)
- Information Notice 1993-42, Failure of Anti-Rotation Keys in Motor-Operated Valves Manufactured by Yelan (9 June 1993)
- Information Notice 1993-43, Use of Inappropriate Lubrication Oils in Satety-Related Applications (10 June 1993)
- Information Notice 1993-44, Operational Challenges During a Dual-Unit Transient (15 June 1993)
- Information Notice 1993-45, Degradation of Shutdown Cooling System Performance (16 June 1993)
- Information Notice 1993-46, Potential Problem with Westinghouse Rod Control System and Inadvertent Withdrawal of Single Rod Control Cluster Assembly (10 June 1993)
- Information Notice 1993-47, Unrecognized Loss of Control Room Annunciators (18 June 1993)
- Information Notice 1993-48, Failure of Turbine-Driven Main Feedwater Pump to Trip Because of Contaminated Oil (6 July 1993)
- Information Notice 1993-49, Improper Integration of Software Into Operating Practices (8 July 1993)
... further results |
---|