IR 05000445/1980015
| ML19343A499 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 06/23/1980 |
| From: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | Gary R TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| Shared Package | |
| ML19343A500 | List: |
| References | |
| NUDOCS 8009180095 | |
| Preceding documents: |
|
| Download: ML19343A499 (2) | |
Text
.
.
.
_
_.
_
. - _ _
,
..
[4 m c,
UNITED STATES
o o
NUCLEAR REGULATORY COMMISSION PDR t,'
4 {[
.
REGloN lv LPDR E9 o
611 RYAN PLAZA DRIVE, SUITE 1000 TIC OC ARLINGTON, TEXAS 76012
" j-
,
o,
.
/j
<
%, %"
CENTRAL FILES
June 23, 1980
-
In Reply Refer To:
RIV Docket No. 50-445/80-15 50-446/80-15 f
Texas Utilities Generating Company
,
ATTN:
Mr. R. J. Gary, Executive Vice
'
President and Geneal Manager 2001 Bryan Tower Dallas, Texas 75201
Gentlemen:
This refers to the inspection activities performed by our Resident Inspector, Mr. R. G. Taylor, of activities authorized by NRC Construction Permits No.
CPPR-126 and 127 for the Comanche Peak Steam Electric Station, Units No. 1 and 2, and to the discussion of the findings by the inspector with members of your staff on June 17, 1980.
j During the inspection, it was found that certain activities under your license appear to be in noncompliance vita Part 50, Title 10, of the Code of Federal Regulations. The item of noncompliance and references to the pertinent j
requirements are identified in the enclosed Notice of Violation. Details of i
i this item will be included in an inspection report to be issued in the near
}
future and identified as Inspection Report No. 50-445/80-15; 50-446/80-15.
!
This notice is sent to you pursuant to the provisions of Section 2.201 of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within M days of your receipt of this notice, a written statement or explanation in reply including:
(1) corrective steps which have been taken by you, and the results achieved;
,
(2) corrective steps which will be taken to avoid further noncompliance; and (3)-the date when full compliance will be achieved.
,
,
>
%
'
.
,
8 0 09180Df5
.
..
,,
..
-
.-
.
. -.
.
.
,
a Texas Utilities Generating Company-2-June 23, 1980 Should you have ar.y questions concerning this inspection, we will be pleased to discuss them with you.
Sincerely,
-l I6_.
,-
W. C. Seidle, Chief Reactor Construction and Engineering Support Branch Enclosure:
Appendix A, Notice of Violation ec: w/ enclosure Texas Utilities Generating Company ATTN:
Mr. H. C. Schmidt, Project Manager 2001 Bryan Tower Dallas, Texas 75201
,