Callaway Plant - Response to Notice of Violation (NRC Inspection Report 05000483/2017007)
ML17341B170
Person / Time
Site: Callaway Ameren icon.png
Issue date: 12/07/2017
From: Thomas Farnholtz
Division of Reactor Safety IV
To: Diya F
Ameren Missouri
References
IR 2017007
Download: ML17341B170 (3)


See also: IR 05000483/2017007

Text

December 7, 2017

Mr. Fadi Diya, Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Plant P.O. Box 620 Fulton, MO 65251

SUBJECT: CALLAWAY PLANT - RESPONSE TO NOTICE OF VIOLATION (NRC INSPECTION REPORT 05000483/2017007)

Dear Mr. Diya:

On August 28, 2017, the U.S. Nuclear Regulatory Commission (NRC) cited Union Electric Company for failure to restore compliance for a Technical Specification 5.4.1.a. violation associated with the failure to perform preventative maintenance procedures to verify the operation and timing of the engineered safety feature transformer XNBOl load tap changer at the Callaway Plant. The Notice of Violation (Notice), enclosed within NRC Inspection Report 05000458/2017007 (ML17283A392), required you to respond in writing within 30 days.

You responded to the Notice by letter, dated November 1, 2017 (ML17306A103). In your response, you stated that the timing of engineered safety feature transformer XNBOl load tap changer was successfully tested on October 20, 2017, thus resolving the technical issue associated with the violation for not previously verifying the operation and timing of the load tap changer. You also responded that timing testing of engineered safety feature transformers XNBOl and XNB02 load tap changers will continue to be performed on a routine basis, going forward. The letter also indicated that you are reviewing any NRC violations received since October 2015 for jobs that you are crediting for restoring compliance. The basis for selecting October 2015 was that this was the last time a comprehensive pre-Problem Identification and Resolution (Pl&R) inspection self-assessment was performed. In that assessment, the timeliness of corrective actions for NRC violations prior to October 2015 had been evaluated.

We have reviewed your response letter and find that it meets the requirements of 10 CFR 2.201. The adequacy of your corrective actions to the Notice will be reviewed and, if found acceptable, will be closed in the resident inspector integrated inspection report. This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely,/RA/ Thomas R. Farnholtz, Chief Engineering Branch 1 Division of Reactor Safety Docket No. 50-483 License No. NPF-30 Electronic Distribution for Callaway Plant CALLAWAY PLANT - RESPONSE TO NOTICE OF VIOLATION (NRC INSPECTION REPORT 05000483/2017007) - December 7, 2017

DISTRIBUTION: KKennedy, RA SMorris, DRA TPruett, DRP AVegel, DRS RLantz, DRP JClark, DRS SKirkwood, RC NTaylor, DRP DProulx, DRP JMelfi, DRP DBradley, DRP SJanicki, DRP DYancey, DRP JBowen, RIV/OEDO VDricks, ORA JWeil, OCA JKlos, NRR AMoreno, RIV/CAO BMaier, RSLO THipschman, IPAT EUribe, IPAT MHerrera, DRMA R4Enforcement

DOCUMENT NAME: R:\_REACTORS\_CW\2017\Word Docs\CWY2017007 NOV Acknowledge LTR.docx ADAMS ACCESSION NUMBER: ML17341B170 SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: By: RAK Yes No Publicly Available Sensitive NRC-002 OFFICE SRI/EB1 C/EB1 C/PBB C:EB1 NAME RKopriva TFarnholtz NTaylor TFarnholtz SIGNATURE /RA/ TRF for /RA/ /RA/ /RA/ DATE 12/7/17 12/7/17 12/7/1712/7/17 OFFICIAL RECORD COPY